september 1, 2021 rehabilitation of the gold star …

137
ADDENDUM NO. 1 SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR MEMORIAL BRIDGE, BRIDGE NO. 03819, CARRYING INTERSTATE 95 NB OVER THE THAMES RIVER, RAILROADS, & LOCAL ROADS FEDERAL AID PROJECT NO. 0953(073) STATE PROJECT NO. 94-256 CITY OF NEW LONDON AND CITY OF GROTON ADDENDUM NO. 1 This Addendum addresses the following questions and answers contained on the CT DOT Questions and Answers Website for Advertised Construction Projects: Question and Answer Nos. 10, 11, 14, 15, 16, 22, 29, 34, 37, and 41. SPECIAL PROVISIONS NEW SPECIAL PROVISIONS The following Special Provisions are hereby added to the Contract: NOTICE TO CONTRACTOR – CONSTRUCTION SEQUENCE AND LIMITATIONS ITEM NO. 1806226A – PRE-WARNING VEHICLE REVISED SPECIAL PROVISIONS The following Special Provisions are hereby deleted in their entirety and replaced with the attached like-named Special Provisions: NOTICE TO CONTRACTOR – PROJECT LABOR AGREEMENT NOTICE TO CONTRACTOR – CONSTRUCTION ACTIVITY CONTACTS SECTION 1.08 – PROSECUTION AND PROGRESS ITEM NO. 0100600A – CONSTRUCTION ACCESS ITEM NO. 0603061A – STRUCTURAL STEEL (SITE NO. 1) ITEM NO. 0603062A – STRUCTURAL STEEL (SITE NO. 2) ITEM NO. 0603923A - ABRASIVE BLAST CLEANING AND FIELD PAINTING OF STRUCTURE (SITE NO. 1) ITEM NO. 0971001A – MAINTENANCE AND PROTECTION OF TRAFFIC

Upload: others

Post on 02-Aug-2022

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

ADDENDUM NO. 1

SEPTEMBER 1, 2021

REHABILITATION OF THE GOLD STAR MEMORIAL BRIDGE, BRIDGE NO. 03819,

CARRYING INTERSTATE 95 NB OVER THE THAMES RIVER,

RAILROADS, & LOCAL ROADS

FEDERAL AID PROJECT NO. 0953(073)

STATE PROJECT NO. 94-256

CITY OF NEW LONDON AND CITY OF GROTON

ADDENDUM NO. 1

This Addendum addresses the following questions and answers contained on the CT DOT

Questions and Answers Website for Advertised Construction Projects:

Question and Answer Nos. 10, 11, 14, 15, 16, 22, 29, 34, 37, and 41.

SPECIAL PROVISIONS

NEW SPECIAL PROVISIONS

The following Special Provisions are hereby added to the Contract:

NOTICE TO CONTRACTOR – CONSTRUCTION SEQUENCE AND LIMITATIONS

ITEM NO. 1806226A – PRE-WARNING VEHICLE

REVISED SPECIAL PROVISIONS

The following Special Provisions are hereby deleted in their entirety and replaced with the

attached like-named Special Provisions:

NOTICE TO CONTRACTOR – PROJECT LABOR AGREEMENT

NOTICE TO CONTRACTOR – CONSTRUCTION ACTIVITY CONTACTS

SECTION 1.08 – PROSECUTION AND PROGRESS

ITEM NO. 0100600A – CONSTRUCTION ACCESS

ITEM NO. 0603061A – STRUCTURAL STEEL (SITE NO. 1)

ITEM NO. 0603062A – STRUCTURAL STEEL (SITE NO. 2)

ITEM NO. 0603923A - ABRASIVE BLAST CLEANING AND FIELD PAINTING OF

STRUCTURE (SITE NO. 1)

ITEM NO. 0971001A – MAINTENANCE AND PROTECTION OF TRAFFIC

Page 2: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

ADDENDUM NO. 1

PERMIT

REVISED PERMIT

The following Permit is hereby deleted in its entirety and replaced with the attached like-named

Permit:

CTDEEP CERTIFICATE OF PERMISSION

AGREEMENT

REVISED AGREEMENT

The following Agreement is hereby deleted in its entirety and replaced with the attached like-named

Agreement:

PROJECT LABOR AGREEMENT

CONTRACT ITEMS

NEW CONTRACT ITEMS

ITEM NO. DESCRIPTION UNIT QUANTITY0970006 TRAFFICPERSON (MUNICIPAL POLICE

OFFICER) (ESTIMATED COST)EST. ESTIMATED

COST0970007 TRAFFICPERSON (UNIFORMED FLAGGER) HR. 120 HR.

0976002 BARRICADE WARNING LIGHTS - HIGH INTENSITY

DAY 6,140 DAY

0978002 TRAFFIC DRUM EA. 132 EA.

0981100 42'' TRAFFIC CONE EA. 132 EA.

1130010 ARROW BOARD DAY 770 DAY

1131002 REMOTE CONTROL CHANGEABLE MESSAGE SIGN

DAY 3,910 DAY

1209114 HOT-APPLIED PAINTED PAVEMENT MARKINGS 4'' YELLOW

L.F. 11,388 L.F.

1209124 HOT-APPLIED PAINTED PAVEMENT MARKINGS 4'' WHITE

L.F. 11,870 L.F.

1209126 HOT-APPLIED PAINTED PAVEMENT MARKINGS 6'' WHITE

L.F. 482 L.F.

1209129 HOT-APPLIED PAINTED PAVEMENT MARKINGS 12'' WHITE

L.F. 1,560 L.F.

1210101 4” WHITE EPOXY RESIN PAVEMENT MARKINGS

L.F. 11,870 L.F.

1210102 4” YELLOW EPOXY RESIN PAVEMENT MARKINGS

L.F. 5,699 L.F.

1210103 6” WHITE EPOXY RESIN PAVEMENT MARKINGS

L.F. 2,980 L.F.

1210106 12” WHITE EPOXY RESIN PAVEMENT MARKINGS

L.F. 1,864 L.F.

1211001 REMOVAL OF PAVEMENT MARKINGS S.F. 13,146 S.F.

1220027 CONSTRUCTION SIGNS S.F. 685 S.F.

1806202 TRUCK-MOUNTED OR TRAILER-MOUNTED IMPACT ATTENUATOR

HR. 178 HR.

1806226A PRE-WARNING VEHICLE HR. 66 HR.

Page 3: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

ADDENDUM NO. 1

PLANS

NEW PLANS

The following Plan Sheets are hereby added to the Contract:

03.11-1.A1

07.01.A1, 07.02.A1, 07.03.A1, 07.04.A1, 07.05.A1, 07.06.A1, 07.07.A1, 07.08.A1,

07.09.A1

TR-STD-INDEX, TR-1208_01, TR-1208_02, TR-1210_04, TR-1210_05, TR-1210_06,

TR-1210_07, TR-1220_01, TR-1220_02

REVISED PLANS

The following Plan Sheets are hereby deleted and replaced with the like-numbered Plan Sheets:

02.01.A1

03.03.A1, 03.05.A1, 03.06.A1, 03.08.A1, 03.09.A1, 03.10.A1, 03.11.A1

04.03.A1, 04.10.A1, 04.12.A1, 04.14.A1, 04.15.A1, 04.17.A1, 04.19.A1, 04.26.A1,

04.37.A1, 04.44.A1, 04.46.A1

The Detailed Estimate Sheets do not reflect these changes.

The Bid Proposal Form has been revised to reflect these changes.

There will be no change in the number of calendar days due to this Addendum.

The foregoing is hereby made a part of the contract.

Page 4: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 1/28/2021

GENERAL

ADDENDUM NO.1

NOTICE TO CONTRACTOR – PROJECT LABOR AGREEMENT

The Contractor is hereby notified that a Project Labor Agreement (PLA) is required as part

of this Contract.

A copy of the PLA signed by the Norwich-New London Building Trades Construction Trades

Council is included in the Contract Documents.

The Contractor will be required to sign the PLA prior to the Award of this Contract. At

Award, the Contractor will be required to sign the “Acceptance of Agreement” form,

acknowledging that the Contractor has received a fully executed copy of the PLA, and

accepts and agrees to be bound by the PLA for Project No. 94-256.

Page 5: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

02/28/2018

GENERAL

ADDENDUM NO. 1

NOTICE TO CONTRACTOR - CONSTRUCTION ACTIVITY CONTACTS

The following project stake holders and contact information are noted below for informational

purposes. Scheduling and performing work that impacts project stake holders shall be coordinated

through the District. Contacting of stake holders shall be performed exclusively by the District.

PROPERTY OWNED BY HOUSING AUTHORITY OF THE CITY OF NEW LONDON

Point of Contact for Advance Notification for Construction Access:

Kolisha Fiore

Executive Director

Housing Authority of the City of New London,

78 Walden Avenue

New London, Connecticut 06320

(860) 443-2851

DEPARTMENT OF PUBLIC WORKS, NEW LONDON

Point of Contact for Advance Notification for Construction Access:

Mr. Brian Sear

Interim Director of Public Works

Public Works Department

111 Union Street

New London, CT 06320

Telephone: (860) 447 5250

[email protected]

CITY OF NEW LONDON

Point of Contact for Coordination of Construction Activity During Local Events:

Ms. Sybil Tetteh

City Planner

City Hall, 2nd Floor

181 State Street

New London, CT 06320

Telephone: (860) 437 6380

[email protected]

FIRE DEPARTMENTS

City of New London City of Groton

Mr. Thomas J. Curcio Mr. Robert Tompkins

Fire Chief Fire Chief

(860) 447-5291 (860) 445-2456

[email protected] [email protected]

Page 6: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

02/28/2018

GENERAL

ADDENDUM NO. 1

Town of Waterford

Mr. Peter Schlink

Fire Marshall

(860) 440-0544

[email protected]

POLICE DEPARTMENTS

City of New London Town of Groton

Mr. Peter Reichard Mr. Louis J. Fusaro, Jr.

Chief of Police Chief of Police

(860) 447-5262 (860) 441-6712

City of Groton Town of Waterford

Mr. Michael Spellman Mr. Brett Mahoney

Chief of Police Chief of Police

(860) 445-2451 (860) 442-9451

[email protected]

DEEP BOAT LAUNCH

Point of Contact for Advance Notification of Temporary Boat Launch Impacts:

Nicole Lugli

Office Director, Land Management and Acquisition

Planning and Program Development

Connecticut Department of Energy and Environmental Protection

79 Elm Street Hartford, CT 06106

(860) 424-3611

[email protected]

City of Groton

Mr. Robert C. Tompkins Captain James Bee

Chief, City of Groton Fire Department Groton Police Department

140 Broad Street Communications Center Director

Groton, CT 68 Groton Long Point Rd

[email protected] Groton, CT 06340

O: (860) 445-2456 [email protected]

C: (860) 885-9541 (860) 441-6757

Page 7: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

02/28/2018

GENERAL

ADDENDUM NO. 1

Edward Sargent, Deputy Chief

City of Groton Fire Dept.

416 Benham Rd.

Groton, CT 06340

[email protected]

Office: 860-446-4106

Cell: 860-287-5761

City of New London

Capt. Matt Galante

Support Services Division Commander

New London Police Dept.

5 Gov. Winthrop Blvd.

New London, CT [email protected]

(860) 437-6373

UNITED STATES NAVY

Point of Contact for Advance Notification of Temporary Boat Launch Impacts:

Primary:

LTJG Jonathan J. Battle

Port Services Officer

SUBASE New London

W - 860 694 2652

C - 860 625 9682

[email protected]

Alternative Contact:

CWO3 Erik E. Allison

NLON Port Operations

W - 860 694 5803

C - 757 286 6153

LCDR M Templar

Officer In Charge

Maritime Expeditionary Security Squadron EIGHT (HVU Det)

Office: 860-694-4284

Page 8: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

02/28/2018

GENERAL

ADDENDUM NO. 1

PROPERTY OWNED BY GENESEE & WYOMING, INC. AND SUBSIDIARIES

Mr. Greg Breaston

MBA Public Projects Manager

13901 Sutton Park Drive South, Suite 330

Jacksonville, FL 32224

PROPERTY OWNED BY CHURCH TOWERS PARTNERSHIP

Point of Contact:

Tenant: Facility Manager:

Mr. Stephen Chickos Mr. Scott Merritt

Leidos 18 Fourth Street 221 Third Street

New London, CT 06320 Newport, RI 02840

860-447-8553 (office) and 916-500-1936 (cell) 401-848-4729 (O) and 401-207-4369 (C)

[email protected] [email protected]

800-268-9655 (Helpdesk)

Owner

Mr. Floran Boland

Bell Pump Service Company

P.O. Box 261567

Hartford, CT 06126-1567

860-525-6678 (office) 860-874-7603 (cell)

[email protected]

PROPERTY OWNED BY CWPM, LLC

Point of Contact for Advance Notification for Construction Access:

Jason Manafort

Generation Four Realty, LLC

P.O. Box 225

Plainville, CT 06062

[email protected]

(860) 798-8107

Page 9: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

08/03/2021

GENERAL

ADDENDUM NO. 1

NOTICE TO CONTRACTOR – CONSTRUCTION SEQUENCE AND

LIMITATIONS

The Contractor is hereby notified that Bridge No. 03819 has load limitations which require that

all rehabilitation included in this project be conducted in strict accordance with the sequence of

work and load restrictions described in the contract plans and these specifications. In addition,

the contractor is required to work within limitations established for site access as described in the

plans and these specifications.

Sequence

The work has been separated into four phases which are shown on the plans. The following is an

overview of each phase and a general description of the sequence of work.

1. Phase A: Gusset Plate Repairs at Nodes U9/U11 and L6/L14 on the South Trusses

a. Set up Maintenance and Protection of Traffic (MPT) to close the shoulder and next

adjacent lane on the south side of the bridge in accordance with the plans.

b. Install work platforms between U9/U11 gussets and the adjacent pier. Concurrent work

on all four approach trusses is allowable.

c. Repair the U9/U11 gussets in accordance with the plans.

d. Install work platforms on the bottom chord between the L6/L14 gussets and the adjacent

pier. Remove the top chord work platform between the pier and the U9/U11 gussets.

e. Repair the L6/L14 gussets in accordance with the plans.

f. Remove the work platform from the bottom chord between the pier and the L6/L14

gussets.

g. Remove the MPT pattern from the south side of the bridge.

2. Phase B: Gusset Plate Repairs at Nodes U9/U11 and L6/L14 on the North Trusses

a. Set up Maintenance and Protection of Traffic (MPT) to close the shoulder and next

adjacent lane on the north side of the bridge in accordance with the plans.

b. Install work platforms between U9/U11 gussets and the adjacent pier. Concurrent work

on all four approach trusses is allowable.

c. Repair the U9/U11 gussets in accordance with the plans.

d. Install work platforms on the bottom chord between the L6/L14 gussets and the adjacent

pier.

e. Repair the L6/L14 gussets in accordance with the plans.

3. Phase C: Gusset Plate Repairs and Member Strengthening - other locations on the North

Trusses

a. Install work platforms for the remaining segments of the top and bottom chords as

needed.

Page 10: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

08/03/2021

GENERAL

ADDENDUM NO. 1

b. Repair the remaining gussets and strengthen the remaining members in accordance with

the sequence indicated on the plans.

c. Complete the stringer repairs which are accessible from the north side of the bridge.

d. Upon completion of all gusset repairs and member strengthening on the north trusses,

remove all work platforms from the north trusses.

e. Remove the MPT pattern from the north side of the bridge.

Phase D: Gusset Plate Repairs and Member Strengthening - other locations on the South Trusses

a. Set up Maintenance and Protection of Traffic (MPT) to close the shoulder and next

adjacent lane on the south side of the bridge.

b. Install work platforms for the top and bottom chords as needed.

c. Repair the remaining gussets and strengthen the remaining members in accordance with

the sequence indicated on the plans.

d. Complete the stringer repairs which are accessible from the south side of the bridge.

e. Upon completion of all gusset repairs and member strengthening on the south trusses,

remove all work platforms from the south trusses.

f. Remove the MPT pattern from the south side of the bridge.

The duration of each phase may conflict with a winter shutdown period. The contractor shall

meet with the Engineer at least 45 days prior to the start of the winter shutdown to establish an

appropriate task where work should be stopped. The MPT pattern shall be removed prior to the

winter shutdown.

Load Restrictions

Due to the critical condition of the bridge structure, the contractor shall conduct his operations in

compliance with all load restrictions during each phase of the work as follows:

1. Vehicular loads on the bridge are restricted to legal vehicles and limited to operating

within the striped lanes as identified in the MPT plans.

2. When the trusses are under reconstruction, the shoulder and the adjacent travel lane shall

be closed to traffic in accordance with the MPT plan.

3. No construction loading will be permitted on the bridge deck except as noted.

4. Stringer repairs on Spans 26-28 shall be completed using a snooper-type vehicle located

in the shoulder of the bridge. The snooper shall be restricted to a single vehicle

complying with legal load limits. Stringer repairs on the remaining spans may be

accessed from snoopers after all Phase C and Phase D truss repairs are completed.

5. Containment for Blast Cleaning and Painting operations – erection of containment

enclosures shall be limited to have the equivalent of one truss panel, or 1,200 s.f.

maximum, of enclosure area erected per span at any one time. As indicated in the

specification for Class 1 Containment, the containment structures shall be

removed/collapsed and tied off when winds are expected to be 40 m.p.h. or greater.

Page 11: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

08/03/2021

GENERAL

ADDENDUM NO. 1

6. For work platform and rigging load restrictions, refer to the notes below and on the plans.

Work Platforms & Rigging Loads

The sequence of installation and loading of work platforms has been established to limit loading

on the bridge until critical repairs are completed during Phase A and Phase B identified on the

plans and it is critical that the sequence of construction indicated on the plans be followed. No

revision of this sequence will be permitted without prior approval of the Engineer.

Work platform loadings shall be limited as indicated on the plans. In addition, support locations

of the platforms shall be in accordance with the restrictions noted on the plans.

A concept for installation of temporary rigging for use in handling equipment and materials has

been shown on the drawings. This concept describes the maximum allowable loads for these

scenarios. Alternative rigging arrangements may be acceptable if they adhere to these maximum

allowable loads subject to the review and approval of the Engineer.

Site Access

Access to the areas below the bridge involves encroachment on leased property, railroad property

and on property designated for public access. The limitations on access to these areas are as

follows and as depicted on the plans.

1. Waste Transfer Station Driveway (Below Span 22): The contractor shall coordinate with

the operator of the waste transfer facility for access to the driveway below Span 22.

Interruption to daytime operation of the driveway shall not exceed 30 calendar days

throughout a construction year nor shall it exceed 60 calendar days throughout the duration

of the project. The days for access do not need to be successive, however, every effort shall

be made to minimize the inconvenience to the operator of the facility. The contractor shall

notify the Engineer at least 14 days prior to the start of work requiring access to the facility.

Access to the facility during nights and weekends, when the facility is not operating, will

be available throughout the duration of the project for work being conducted on the span

over the driveway.

2. Railroad Property (Genesee & Wyoming (G&W)): The contractor shall comply with all

requirements of the Railroad as described in these specifications. The contractor is required

to obtain an entry permit from the Railroad. Access to the property is depicted on the plans

and further described as follows:

a. New London (New England Central Railroad owned by G&W): A gravel access road

currently exists from the boat launch parking lot to the railroad property.

b. Groton (Providence & Worcester Railroad owned by G&W): A gravel access road

currently existing from Fairview Avenue to the railroad property.

c. There are two existing grade crossings, one on each side of the river as indicated on

the plans. If the contractor utilizes these crossings, they shall restore the crossings at

the conclusion of the project to the condition that existed prior to the start of work. If

additional crossings are required, the Contractor shall coordinate approval and

installation with the Railroad.

Page 12: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

08/03/2021

GENERAL

ADDENDUM NO. 1

d. Any additional re-grading required to provide access for equipment shall be

completed at no additional cost to the State and shall be restored to the satisfaction of

the Railroad and the Engineer.

3. Boat Launches: There are two boat launches below the bridge which are operated by the

Connecticut DEEP, one on the New London side of the river and one on the Groton side of

the river. The contractor shall be permitted to close one boat launch to allow access for

construction operations and shall maintain the other for public use. Prior to closure of a

boat launch, the contractor shall notify the Engineer who will notify CT DEEP, U.S. Navy

and the emergency service personnel in both New London and Groton in accordance with

the provisions of these specifications. Refer to the Permits for additional information.

Page 13: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 08/11/2021

GENERAL

ADDENDUM NO. 1

SECTION 1.08 - PROSECUTION AND PROGRESS

Article 1.08.04 - Limitation of Operations - Add the following:

In order to provide for traffic operations as outlined in the Special Provision "Maintenance and

Protection of Traffic," the Contractor will not be permitted to perform any work which will interfere

with the described traffic operations on all project roadways as follows:

Route I-95 (US Route 1)

The Contractor shall not perform any work that will interfere with traffic operations during the

below State observed Legal Holidays and Legal Holiday Periods.

A. On the following State observed Legal Holidays:

New Year’s Day Labor Day

Good Friday Thanksgiving Day

Memorial Day Christmas Day

Independence DayB. During the following Legal Holiday Periods:

i. When an above Legal Holiday is celebrated on a Sunday or Monday: From 6:00 a.m. the

immediately preceding Friday to 6:00 a.m. the immediately following Tuesday.

ii. When an above Legal Holiday is celebrated on a Tuesday, Wednesday, or Thursday: From 6:00

a.m. the day before to 6:00 a.m. the day after, except Thanksgiving (see below for Thanksgiving

specific restrictions).

iii. When an above Legal Holiday is celebrated on a Friday or Saturday: From 6:00 a.m. the

immediately preceding Thursday to 6:00 a.m. the immediately following Monday.

iv. Thanksgiving: From 6:00 a.m. the Wednesday before to 6:00 a.m. the Monday after.

During all other times:A. The Contractor shall maintain and protect traffic as shown on the accompanying "Limitation of

Operations" charts, which dictate the maximum number of lanes allowed to be closed and the allowable

hours for implementing a rolling roadblock operation for each day of the week.

B. The Contractor will be allowed to halt traffic for a period not to exceed 10 minutes to actively

perform rehabilitation work on the Gold Star Bridge, as approved by the Engineer, between 12:01

a.m. and 5:00 a.m. during all non-Legal Holiday Periods.

C. The Contractor will be allowed to close a lane of traffic as shown on the Maintenance and

Protection of Traffic plans for Phase A, B, C and D for a duration not to exceed 244 consecutive

days for the 8-month construction season. The intent is for each phase to be left in place until the

phase is complete or winter shuts construction down.

Ramps and Turning Roadways

Monday through Friday between 6:00 a.m. and 9:00 a.m. & between 3:00 p.m. and 6:00 p.m.

Page 14: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 08/11/2021

GENERAL

ADDENDUM NO. 1

Limitation of Operations Chart – Maximum Number of Lanes Allowed to be Closed and Hours

Allowed for a Rolling Roadblock (RRB)

On Legal Holidays and within Legal Holiday Periods, all hours shall be ‘0.’ “0” = No closures allowed = all available travel lanes, including exit only lanes, climbing lanes, gore areas, and all available

shoulder widths shall be open to traffic during this time period.

“S” = Shoulders are allowed to be closed = all available travel lanes, including exit only lanes, climbing lanes, and gore areas

shall be open to traffic during this time period.

“1” = One lane closure is allowed. Adjacent shoulder(s) and/or gore areas may also be closed.

“2” = Two lane closure is allowed. Adjacent shoulder(s) and/or gore areas may also be closed.

“*” = The hours that a rolling roadblock may be implemented with the approval of the Engineer.

Route: I-95 NB (New London/Groton)

Number of Through Lanes: 4

Hour

Beginn-

ing Mon Tue Wed Thu Fri Sat Sun

Mid 2* 2* 2* 2* 2* 2* 2*

1 AM 2* 2* 2* 2* 2* 2* 2*

2 AM 2* 2* 2* 2* 2* 2* 2*

3 AM 2* 2* 2* 2* 2* 2* 2*

4 AM 2* 2* 2* 2* 2* 2* 2*

5 AM 2 2 2 2 2 2* 2*

6 AM 0 0 0 0 0 2 2

7 AM 0 0 0 0 0 2 2

8 AM 0 0 0 0 0 1 2

9 AM 1 1 1 1 0 1 1

10 AM 1 1 1 1 0 0 1

11 AM 1 1 1 1 0 0 1

Noon 1 1 1 1 0 0 1

1 PM 1 1 1 1 0 0 1

2 PM 1 1 1 1 0 0 1

3 PM 0 0 0 0 0 0 1

4 PM 0 0 0 0 0 1 1

5 PM 0 0 0 0 0 1 1

6 PM 2 2 2 2 1 1 1

7 PM 2 2 2 2 2 2 2

8 PM 2 2 2 2 2 2 2

9 PM 2 2 2 2 2 2 2

10 PM 2* 2 2 2 2 2 2

11 PM 2* 2* 2* 2* 2 2* 2*

Page 15: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 08/11/2021

GENERAL

ADDENDUM NO. 1

All Other Roadways

Contractor shall not impact normal traffic operations:

Monday through Friday between 6:00 a.m. and 9:00 a.m. & between 3:00 p.m. and 6:00 p.m.

The Contractor shall maintain and protect a minimum of one lane of traffic in each direction, each

lane on a paved travel path not less than 11 feet in width, unless otherwise noted.

Additional Lane Closed Restrictions

It is anticipated that work on adjacent projects will be ongoing simultaneously with this project. The

Contractor shall be aware of those projects and anticipate that coordination will be required to

maintain proper traffic flow at all times on all project roadways, in a manner consistent with these

specifications and acceptable to the Engineer.

The Contractor will not be allowed to perform any work that will interfere with traffic operations on

a roadway when traffic operations are being restricted on that same roadway, unless there is at least a

one-mile clear area length where the entire roadway is open to traffic or the closures have been

coordinated and are acceptable to the Engineer. The one-mile clear area length shall be measured

from the end of the first work area to the beginning of the signing pattern for the next work area.

Page 16: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date: 07/27/2020

ITEM #0100600A

ADDENDUM NO. 1

ITEM #0100600A - CONSTRUCTION ACCESS

Description: This item shall consist of the design, construction, installation, maintenance, and

subsequent removal of construction access systems that the Contractor elects to use to access the

structure to accomplish and complete the work called out in the Contract. Construction Access

systems are considered to include temporary work platforms, protective debris shields, and

temporary structures to access the platforms. In addition, improvements to and restoration of

access/haul roads below the bridge shall be included with this work.

Construction access shall be made available to the Engineer and other support staff to witness

and inspect the work, and at other times as may be requested.

Materials: Any material or combination of materials may be used to construct the construction

access system provided they are properly designed for the purpose intended. Systems utilizing

different materials shall conform to the manufacturer’s specifications and project specifications.

The parts list shall be furnished for the proprietary system and the Contractor shall provide the

Materials Certificates for the parts.

Construction Methods:

1. Restriction on Bridge Load: The Contractor is hereby notified that at no time during the

installation of construction access and duration of the Project shall materials or equipment be

allowed to be off-loaded, stockpiled or stored on the bridge deck, to avoid overloading the existing

girders and trusses except as noted on the plans. All materials shall be stored in the approved

staging areas.

2. Weight Limitations on Construction Access Systems Supported by the Existing

Superstructure: The Contractor is hereby notified that weight of construction access systems

including work platforms and debris shields supported by the existing superstructure, including

weight of workers, equipment and fabricated material supported prior to being installed, shall not

exceed the allowable load per foot for Construction Access and Attachment loads, as provided on

the Contract plans. Working Drawings and Calculations shall be provided to document proposed

systems to be used, and their maximum load per linear foot and attachment point loads which shall

not exceed the allowable loads provided on the Contract plans.

3. Design of Construction Access, Work Platforms and Debris Shields: The design of these

systems is the responsibility of the Contractor. The design shall conform to the latest edition of the

AASHTO "Guide Design Specification for Bridge Temporary Works", the AASHTO Construction

Handbook for Bridge Temporary Works, and applicable OSHA requirements including OSHA

Safety and Health Requirements, 29 CFR 1926. Platform design shall be required to accommodate

anticipated bridge expansion and contraction. Design shall also consider the coincident use of the

construction access system with the containment system required for abrasive blast cleaning and

field painting of the structure. Construction access/haul roads below the bridge shall be designed

to accommodate the equipment proposed for the work.

Page 17: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date: 07/27/2020

ITEM #0100600A

ADDENDUM NO. 1

4. Submittals: Working drawings and design calculations for construction access, work platforms

and debris shield shall be submitted in accordance with the requirements of Section 1.05.02 within

these special provisions. Working drawings and design calculations for work platforms and debris

shield shall be prepared by a licensed Professional Engineer registered in the State of Connecticut

and submitted to the Engineer for review at least 30 days prior to construction of platforms. No

platform construction shall be done until the Engineer's review has been made and all deficiencies

have been addressed. The review of the platform plans by the Engineer shall not relieve the

Contractor of any responsibility for safely and adequately designing and constructing platforms.

The working drawings shall include design and details of the debris shield and/or platform, and

any temporary structures to access the platform including all connections, brackets, fasteners, and

force gauges. The various components of the debris shield and/or platform shall be designed for

the anticipated weight of all personnel, material, equipment, and debris to be supported, based on

the Contractor’s method and sequence of work, but in no case shall be designed for less than 50

pounds per square foot. Vertical elements of the debris shield and/or platform shall be designed

for anticipated loads including wind, or a minimum of 30 pounds per square foot, whichever is

higher. The calculations shall consider the loading effects from the debris shield and/or platform

on the bridge structure in addition to the design of the debris shield and/or platform itself. The

furnishing of such plans shall not serve to relieve the Contractor of any responsibility for the safety

of the work or for the successful completion of the project.

The Construction Access plan shall also include a description of the methods to provide access

to the platform, and the procedures and equipment that will be used to protect Contract

Representatives including the Engineer and additional staff as needed during inspections. The

system shall also include breathable side tarps and side walls as required for protection from

inclement weather. Side tarps shall be disassembled if the wind velocity is greater than 40 miles

per hour, if it is forecast to be higher, or when directed by the Engineer.

The construction access/haul roads below the bridge shall be detailed as necessary for any

proposed improvements to accommodate construction of the project.

5. Safety: The Contractor shall provide personal safety equipment (including personal safety

harnesses, hard hats, safety glasses and vests, etc.) that may be needed by Contract Representatives

including the Engineer and CTDOT inspection staff when accessing temporary platforms during

inspections.

6. Construction of Construction Access: Work platforms shall be constructed in accordance with

the reviewed platform/debris shield working drawings. If during platform construction, site

conditions are such that changes to the platforms are required, new platform working drawings

shall be submitted to the Engineer for review prior to continuing construction of the platforms. If,

in the opinion of the Engineer, the shields are not secure, the Contractor shall remove and install

them to the satisfaction of the Engineer. Construction access/haul roads below the bridge shall be

constructed in accordance with the working drawings.

Page 18: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date: 07/27/2020

ITEM #0100600A

ADDENDUM NO. 1

7. Use of Work Platforms: Work platforms shall be erected in accordance with the sequence

identified on the plans. To minimize impacts on the truss, live loading on the platforms between

adjacent truss panels shall be limited as shown on the plans. Repair of the existing superstructure

and use of the work platforms shall proceed based on the sequence of construction described on

the contract plans.

The Contractor shall monitor live loads applied to the work platforms where construction

operations are occurring. In order to monitor the live loading, the Contractor shall install force

gauges or load cells on the wire ropes or chains which suspend the work platforms. The force

gauges will be used to monitor loads and assist the Contractor in not exceeding the allowable load

per foot for construction access and attachment loads, as provided on the Contract plans.

8. Removal of Construction Access: Unless otherwise specified on the plans or approved by the

Engineer, all temporary platforms shall be removed upon completion of repairs and post-

installation inspections. The removal of work platforms and access/haul roads below the bridge

shall be done in such a manner that no damage occurs to the structure and/or the area below the

bridge.

Method of Measurement: This work, being paid for on a Lump Sum basis, will not be measured

for payment.

Basis of Payment: This work will be paid for at the contract lump sum price for "Construction

Access”, which shall include the design, construction, maintenance, installation, removal and re-

installation for phased construction, and subsequent removal of temporary construction access

including work platforms and associated debris shielding and tarps; providing access to the

platforms and personal safety equipment during inspections and at other times when accessing the

platform; monitoring of live loads; and all equipment, material, tools and labor incidental thereto.

This work shall also include construction, maintenance, removal and restoration of access/haul

roads below the bridge including all equipment, material, tools and labor incidental thereto.

Pay Item Pay Unit

Construction Access l.s.

Page 19: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

03/19/2020

ITEM #0603061AITEM #0603062A

ADDENDUM NO. 1

ITEM #0603061A – STRUCTURAL STEEL (SITE NO. 1)

ITEM #0603062A – STRUCTURAL STEEL (SITE NO. 2)

Work under this item shall conform to the requirements of Section 6.03- Structural Steel of

the Standard Specifications as amended and supplemented herein.

6.03.01 – Description:

Supplement this article to include the following:

Work shall also include all field drilling and reaming of holes in existing steel, field reaming of

holes in the new structural steel, removal of existing rivets, removal of existing rivet heads,

removal of existing bolts, installation of high strength bolts, field wielding as called for on the

plans and as may be required for the installation of new structural steel.

Structural Steel Site Numbers: All work and material furnished and installed shall be paid for

under its Site Number and associated location, as noted below:

Site No. 1: Spans 22-32 as noted below:

All work and material to strengthen steel truss members, truss gusset plates and their

connections as called for in Subset 4 “Truss Rehabilitation”, except as otherwise noted and

included in other items.

Site No. 2: Spans 22-32 as noted below:

All work and material to strengthen Stringers as noted in Subset 3 “Structure General”, except

as otherwise called for and included in other items.

6.03.02 – Materials:

Materials shall conform to the requirements of Section M.06

Supplement this article to include the following:

Structural steel plate and shapes shall conform to the requirements of AASHTO M270 Grade

50, unless otherwise noted.

Structural steel plates, shapes, high strength bolts, nuts and washers shall be galvanized in

accordance with the special provision “Galvanizing Structural Steel (Site No. 1)” and

“Galvanizing Structural Steel (Site No. 2),” except as noted herein.

Bolts shall be high strength ASTM F3125, Grade A325, Type 1 galvanized, unless otherwise

noted.

Page 20: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

03/19/2020

ITEM #0603061AITEM #0603062A

ADDENDUM NO. 1

Nuts shall conform to ASTM A563 Grade DH.

Washers shall conform to ASTM F436, Type 1.

ASTM F3125 Grade A490, Type 1 bolts shall not be galvanized and shall have Zinc/Aluminum

Corrosion Protection Coatings per ASTM F1136 Grade 3.

Bolts designated as ASTM A449 shall be Type 1, galvanized.

6.03.03 – Construction Methods:

Supplement this article to include the following:

Bridge Load Restrictions: The Contractor is hereby notified that at no time during the

installation of temporary construction access, and for the duration of the Project, shall materials or

equipment be allowed to be off-loaded, stockpiled or stored on the bridge, to avoid overloading

the existing girders and trusses except in accordance with the guidance shown on the Contract

plans. All materials shall be stored in the approved staging areas.

Limitations on Construction Access: The Contractor is hereby notified that weight of

temporary construction access and platforms suspended from the existing bridge, including

workers and fabricated material to be installed, shall not exceed the allowable load, and localized

attachment loads for construction access, as provided on the Contract plans. The installation and

use of temporary construction access and work platforms shall be staged to control their limits and

location to not exceed the allowable loads.

Sequencing of Work: All plate strengthening and connections work in the gusset plates shall

be completed in accordance with the sequence shown on the plans. No change to the sequence will

be permitted without prior approval of the Engineer.

1. Shop Prequalification:

Delete subarticle (a) and replace with the following:

(a) Fabricators: Fabricators producing material under these items are required to have as a

minimum, an active AISC Certification for Certified Bridge Fabricator – Intermediate (Major)

(IBR). Fabricators producing material to be installed in fracture critical members shall also

have an AISC endorsement for fabrication of fracture critical members (FCE).

Add the following after subarticle (b):

(c) Field Erectors: Field erectors are required to have as a minimum, an active AISC

Certification for Steel Erector (Advanced) with Bridge Erection Endorsement.

Page 21: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

03/19/2020

ITEM #0603061AITEM #0603062A

ADDENDUM NO. 1

3. Submittals:

(a) Shop Drawings:

Supplement this subarticle to include the following:

Existing Dimensions: Dimensions of the existing structure shown on the Contract plans

have been taken from the original bridge construction plans and subsequent rehabilitation

projects.

Existing Shop Drawings: Shop drawings from the original bridge construction and

subsequent rehabilitation projects have been included for the Contractor’s reference and use as

a basis for the development of shop drawings for this project.

Field Measurements: The Contractor shall take field measurements of the existing

structure to verify and supplement existing shop drawing information, to provide information

for fabrication of new material and to allow proper installation of the finished work. Field

measurements shall be submitted with shop drawings.

Rivet Removal Methods: The Contractor shall submit proposed method of rivet removal

and rivet head removal for review and acceptance by the Engineer. Appropriate methods and

caution shall be used during rivet removals to avoid damaging existing structure.

(d) Working Drawings for Falsework and Erection of Structural Steel:

Supplement this subarticle to include the following:

Working drawings for falsework and erection of structural steel shall also consider the

coincident use of the construction access system. See Item #0100600A "Construction Access”

for limitations on “Use of Work Platforms.”

4. Shop Fabrication:

Supplement the article to include the following:

The structural steel shall be fabricated to comply with the following requirements. The latest

edition of the code or standard shall govern:

ASTM A123 – Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products

ASTM A143 – Safeguarding Against Embrittlement of Hot-Dipped Galvanized Structural Steel

Products and Procedures for Detecting Embrittlement

ASTM A153 – Zinc Coating (Hot-Dip) on Iron and Steel Hardware

ASTM A384 – Safeguarding Against Warpage and Distortion during Hot-Dip Galvanizing of Steel

Articles

ASTM A385 – Providing High-Quality Zinc Coatings (Hot-Dip)

ASTM A780 – Repair of Damaged Hot-Dip Galvanized Coatings

Page 22: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

03/19/2020

ITEM #0603061AITEM #0603062A

ADDENDUM NO. 1

(e) Inspection:

Supplement this subarticle to include the following:

Inspections of the hot-dip galvanized coatings shall be done in accordance with ASTM A123,

A767 or A153, as applicable.

(f) Nondestructive Testing:

Supplement this subarticle to include the following:

Testing of the hot-dip galvanized coatings shall be done in accordance with ASTM A123, A767

or A153, as applicable.

5. Field Erection:

(d) Field Assembly: Supplement this subarticle with the following:

Field Drilled Holes and Removal of Rivets: Field assembly and installation of the work

will require field drilling of holes in existing steel, removal of existing rivets, removal of

existing rivet heads, and removal of existing bolts, as called for on the plans and as may be

required for the installation of new structural steel.

Sequencing the removal and replacement of rivets with high strength bolts one-at-a-time, will

be required for field assembly and installation of certain proposed work as noted on the plans.

Close Tolerance Holes: The installation of structural steel at some locations will require

drilling and reaming holes to close tolerances, and “transfer” drilling thru fabricated steel

elements into existing bridge members, to ensure a close tolerance fit of high strength bolts, as

called for at certain locations on the plans. Bolts installed in close-tolerance holes shall be

installed in holes with a clearance tolerance of between +0.0313 inches and +0.005 inches

between hole I.D. and galvanized bolt shank diameter.

(f) High Strength Bolted Connections: Supplement this sub-article with the following:

The installation of high strength bolted connections for this contract will, in many

instances, require removing existing rivets “one at a time” and replacing with high strength

bolts, as noted and called for on the plans. Drilling and reaming close tolerance holes at some

locations will also be required, as noted on the plans.

Supplement “Surface Conditions” to include the following:

Surface Preparation of New Steel: All new structural steel shall be hot-dipped galvanized and

the surface preparation of the steel shall be in accordance with accepted methods to produce

an acceptable surface for quality hot-dip galvanizing.

Surface Preparation of Existing Steel: Faying surfaces of existing steel interfacing with

proposed connections shall undergo surface preparation per the item “Abrasive Blast Cleaning

Page 23: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

03/19/2020

ITEM #0603061AITEM #0603062A

ADDENDUM NO. 1

and Field Painting of Structure (Site No. 1)”.

6.03.04 - Method of Measurement: Revise this article as follows:

This work, being paid for on a lump sum basis, will not be measured for payment.

6.03.05 - Basis of Payment: Supplement this article by replacing the first paragraph with the

following two paragraphs:

The structural steel, incorporated in the completed and accepted structure, will be paid for at the

contract unit lump sum price for "Structural Steel (Site No. 1)”, as indicated in the accepted bid

proposal.

Prior to beginning the work, the Contractor shall submit a proposed schedule of values for review

and concurrence by the Engineer.

The lump sum price shall also include all field drilling and reaming new and existing holes in

existing and proposed structural steel, removal of rivets and rivet heads, associated bolts, nuts, and

washers, welding and weld inspection, and all other materials, equipment, tools, labor and work

incidental thereto.

The blast cleaning and surface preparation of existing steel faying surfaces interfacing with

proposed steel connections and field painting of the exposed portions of the blast cleaned existing

steel after the installation of the new structural steel, shall be paid for under the item “Abrasive

Blast Cleaning and Field Painting of Structure (Site No. 1),” as applicable. Surface preparation

and field painting of stringer repairs shall be paid for under the item “Localized Paint Removal

and Field Painting of Beam Ends (Site No. 2). Galvanizing of new steel shall be paid for under the

item “Galvanizing Structural Steel (Site No. 1)” and “Galvanizing Structural Steel (Site No. 2).”

Pay Item Pay Unit

Structural Steel (Site No. 1) LS

Structural Steel (Site No. 2) LS

Page 24: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

ITEM #0603923A - ABRASIVE BLAST CLEANING AND FIELD

PAINTING OF STRUCTURE (SITE NO. 1)

Description: Work under this item shall consist of surface preparation and field painting of the

steel components of structures as shown on the plans and as directed by the Engineer.

All structural steel, except those specific components listed below or on the plans, shall be

abrasive blast cleaned and painted with a 3-coat system.

Site No.1 is noted to be truss members, truss gusset plates and their connections in Spans 22-32.

Components to be blast cleaned and painted include, but are not limited to:

The faying surfaces of existing steel interfacing with new steel and at modified

connections. The surface to be blast cleaned shall extend one-inch (1”) minimum beyond

the edge of the new steel or connections, unless noted otherwise on the plans, and then

shall be coated with a primer. After the installation of the new steel, the exposed portions

of the primed steel shall be field painted with the intermediate and top coats of this 3-coat

system, and paid for under these items, as applicable.

The interior and exterior surfaces of existing steel at strengthened truss verticals and

diagonals shall be painted full length. The interior and exterior surfaces of existing steel at

gussets shall be painted to the limits shown on the plans.

Privately-owned utilities, bridge rails, stay-in-place forms, fences, elastomeric bearing pads and

bronze components shall be protected from damage by surface preparation and painting operations

and shall not be painted.

Tabulated data for the structure(s), including the Federal Standard 595 Color Number for the top

coat, are listed in tables on the plans. The estimated surface area of structural steel to be painted

on each structure is given as a guide only, and is not guaranteed to be accurate. Bidders shall

examine the listed structures and shall make their own determinations as to the work involved and

conditions to be encountered.

Submittals: A minimum of 20 calendar days before starting any surface preparation and coating

application work, the painting firm shall submit the following to the Engineer for acceptance:

1. A copy of the firm’s written Quality Control Program used to control the quality of surface

preparation and coating application including, but not limited to, ambient conditions, surface

cleanliness and profile, coating mixing, dry film thickness, and final film continuity.

2. A copy of the firm’s written surface preparation and application procedures. This written

program must contain a description of the equipment that will be used for removal of laminar

and stratified rust, for surface preparation, including the remediation of soluble salts, and for

paint mixing and application, including stripe coating. Coating repair procedures shall be

Page 25: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

included.

3. The qualifications, references and documentation of the personnel managing and performing

the Quality Control Program, including a detailed description of the firm’s enforcement

procedures and the authority of personnel.

4. Containment plans (paint removal/collection of debris, surface preparation, coating

applications with heat)

5. If the application of heat is proposed for coating application purposes, provide information on

the heat containment and procedures that will be used, with data sheets for the equipment.

Note: If heat is used for coating operations, the heat and containment must be maintained to

provide the required temperatures for the duration of the cure period.

6. Proof of SSPC-QP1 qualifications, CAS-certification(s) and QP2 qualifications, as applicable.

7. Proof that the finish coat complies with the color and gloss retention performance criteria of

SSPC Paint 36, Level 3, for accelerated weathering.

8. Coating product information, including coating manufacturer, product name, application

instructions, technical data, MSDS and color chips.

9. Abrasive product information, including abrasive manufacturer, product name, technical data,

and MSDS.

10. Touch-up and repair procedures, including methods and materials.

The Contractor shall not begin any paint removal Work until the Engineer has accepted the

submittals. The Contractor shall not construe Engineer acceptance of the submittals to imply

approval of any particular method or sequence for conducting the Work, or for addressing health

and safety concerns. Acceptance of the programs does not relieve the Contractor from the

responsibility to conduct the Work in strict accordance with the requirements of Federal, State, or

local regulations, this specification, or to adequately protect the health and safety of all workers

involved in the Project and any members of the public who may be affected by the Project. The

Contractor remains solely responsible for the adequacy and completeness of the programs and

work practices, and adherence to them.

Materials: The materials for the coating system for this work shall meet the requirements of

Section M07.02 and the following:

The coating system shall be a 3-coat system selected by the Contractor and accepted by the

Engineer. The system shall be on the NEPCOAT Qualified Products List B (Organic Zinc Rich

Primer / Epoxy or Urethane Intermediate / Aliphatic Urethane Finish) for Protective Coatings for

New and 100% Bare Existing Steel for Bridges.

All materials for the complete coating system shall be furnished by the same coating material

manufacturer with no subcontracted manufacturing allowed. Intermixing of materials within and

between coating systems will not be permitted. Thinning of paint shall conform to the

manufacturer's written recommendations. All components of the coating system and the mixed

paint shall comply with the Volatile Organic Compounds (VOC) Content Limits and Emission

Standards stated in the Connecticut Department of Energy and Environmental Protection's

Administration Regulation for the Abatement of Air Pollution, Sections 22a-174-41 through 41a

and 22a-174-20(s), respectively.

Page 26: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

The top coat shall meet the color and gloss retention performance criteria of SSPC Paint 36, Level

3, for accelerated weathering. After 2000 hours of accelerated weathering in accordance with

ASTM D4587, the color change (ASTM D2244) shall be less than 2.0 E* with a loss of gloss

(ASTM D523) less than 30. With the submittals, the Contractor shall provide the Engineer with

proof that the finish coat complies with the above criteria.

The abrasive media for blast cleaning shall be recyclable steel grit.

Control of Materials: A Materials Certificate will be required for the selected paint system in

accordance with Article 1.06.07, confirming that the paint meets the requirements set forth in these

specifications.

Note: If any of the above or following stipulated Contract specifications differ from those of the

manufacturer’s recommended procedures or ranges, the more restrictive of the requirements shall

be adhered to unless directed by the Engineer in writing.

Construction Methods:

Contractor - Subcontractor Qualifications: Contractors and subcontractors doing this work are

required to be certified by the SSPC Painting Contractor Certification Program (PCCP) to QP-1

entitled “Standard Procedure for Evaluating Qualifications of Painting Contractors: Field

Application to Complex Structures.” When the work involves the disturbance of lead-containing

paint, the Contractor and subcontractor are also required to be certified to SSPC QP-2 “Standard

Procedure for Evaluating the Qualifications of Painting Contractors to Remove Hazardous Paint.”

Contractors and subcontractors are required to have at least one (1) Coating Application

Specialist (CAS) (SSPC ACS/NACE No. 13)-certified (Level II-Interim Status-Minimal) craft-

worker. CAS-certified (Level II-Interim Status-Minimal) craft-worker(s) are required for all

crews/craft-workers up to four (4) crew members. For each crew larger than four (4), an additional

CAS-certified (Level II-Interim Status-Minimal) craft-worker shall be present on each

painting/blasting crew during blast cleaning and spray application (Atmospheric and Immersion

Service) operations. A crew-member is a person who is on the job performing hand-held nozzle

blast cleaning and/or spray application of protective coatings on a steel structure. The

certification(s) must be kept current for the duration of the Project work. If a Contractor’s,

subcontractor’s or any craft-worker’s certification expires, the firm will not be allowed to do any

work on this item until the certification is reissued.

Requests for extension of time for any delay to the completion of the Project due to an inactive

certification will not be considered, and liquidated damages will apply. In addition, if any recoat

times are exceeded, the affected areas shall be abrasive blast cleaned to SSPC-SP 10 and coatings

reapplied in accordance with these specifications at no additional cost to the State. At the option

of the Engineer, if such a delay will adversely impact the successful and timely completion of the

Project, the Department may require the Contractor to engage another SSPC-certified firm to do

the painting work at the Contractor’s expense.

Page 27: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

Quality Control Inspections: The Contractor shall perform first line, in-process Quality Control

(QC) inspections. The Contractor shall implement a Quality Control Program accepted by the

Engineer, including written daily reports, that ensures that the work accomplished complies with

these specifications. Copies of these reports shall be provided daily to the Engineer. Contractor

QC inspections shall include, but not be limited to the following:

Suitability of protective coverings and containments

Ambient conditions

Surface preparation (solvent cleaning, hand/power tool or abrasive blast cleaning)

Coating application (mixing, thinning, and wet/dry film thickness)

Recoat times and cleanliness between coats

Coating continuity (freedom from runs, sags, overspray, dryspray, pinholes, shadow-through,

skips, misses)

Final film acceptance

The personnel managing and performing the quality control program shall be NACE Certified

Coating Inspector(s) (successfully completed Sessions I, II, III and Peer Review) or shall provide

evidence of successful inspection of three projects of similar size and scope that have been

completed in the last two years. References shall include the name, address, and telephone number

of a contact person employed by the bridge owner. The personnel performing the quality control

tests shall be trained in the use of the quality control instruments. Documentation of training shall

be provided. These personnel shall not perform surface preparation and painting.

Test Equipment and Materials: The Contractor shall furnish the following new test equipment

and materials for use by the QC Inspector:

1. Two (2) PTC Surface Temperature Thermometers

2. Psychron 566 Psychrometer (Battery Operated) with two (2) sets of batteries or a Bacharach

Sling Psychrometer

3. U.S. Weather Bureau Psychrometric Tables

4. Hypodermic Needle Pressure Gage for nozzle pressure tests.

5. SSPC Visual Standards VIS 1, VIS 3, and/or VIS 4, as applicable.

6. Testex Spring Micrometer

7. Testex Press-O-Film Replica Tape, one (1) roll, 100 pieces each, of coarse and extra-coarse

per bridge span, or as specified by the Engineer.

8. Wet film thickness gage

9. PosiTest, Mikrotest or Elcometer Dry Film Thickness Gauge (FM)

10. SSPC Type 2 Dry Film Thickness Gauge per PA2

11. NIST (NBS) Calibration Standards Range: 0 – 39 mils

Quality Assurance Inspections: The Engineer may conduct Quality Assurance (QA) observations

of any or all phases of the work. The presence or activity of Engineer inspections in no way

relieves the Contractor of the responsibility to provide all necessary daily Quality Control

inspections of its own and to comply with all requirements of this Specification.

Page 28: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

The Contractor shall facilitate the Engineer’s inspections as required, including allowing ample

time for the inspections and providing suitable lighting (50-foot candles minimum at the surface

as defined later in this specification). The Contractor shall furnish, erect and move scaffolding or

other mechanical equipment to permit inspection and close observation of all surfaces to be cleaned

and painted. This equipment shall be provided during all phases of the work. The Contractor shall

notify the Engineer in advance of plans to remove staging used in cleaning and painting operations

in order to allow for inspection. The QA inspection will be performed with the QA inspector’s

equipment when verifying the Contractor’s test results in the field.

Safety: All Contractor activities associated with the coating work described and specified herein

shall be conducted in accordance with all applicable Federal (OSHA) and State of Connecticut

safety regulations, and SSPC-PA Guide 3 entitled “A Guide to Safety in Paint Application.”

Ambient Conditions: Surface preparation and coating application work shall only be done inside

a containment enclosure as specified herein. Surface preparation or coating work shall be

performed inside the containment enclosure meeting the following:

The relative humidity is at or below 90%.

The substrate is not damp, or covered by frost or ice.

The surface temperature and air temperature are between 50°F and 100°F.

The surface temperatures of the steel and air are more than 5°F above the dew point

temperature, as determined by a surface temperature thermometer and electric or sling

psychrometer.

If the requirements of the coating manufacturer differ from the ranges provided above, comply

with the most restrictive requirements unless directed otherwise by the Engineer in writing.

Protective Coverings: The Contractor shall protect property, pedestrians, vehicular, and other

traffic upon, underneath, or near the bridge, and all portions of the bridge superstructure and

substructure against abrasive blast cleaning damage or disfigurement from splatters, splashes, or

spray of paint or paint materials. All coating overspray, drips and spills shall be contained.

Maintain the integrity and security of all protective coverings and containment materials

throughout the entire Project.

Any paint chips, paint removal media (e.g., abrasives), coating or solvent that has escaped the

Contractor’s containment enclosure shall be cleaned up immediately. For bridges over water, the

Contractor shall have on Site a sufficient quantity of spill containment boom and pads to contain

a spill. The length of containment boom on Site shall be at least equal to twice the length of the

active work Site over the water.

Observed Steel Defects: If significant deficiencies, such as cracks or section losses, are found

during cleaning or coating operations, the Contractor shall immediately notify the Engineer as to

their extent. Significant deficiencies include the following:

a) Cracks in any part of the superstructure

Page 29: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

b) Section loss more than 1/8 inch or section loss equal to or greater than 5% of flange thickness

in the maximum moment areas (i.e. Section loss in the middle 1/2 of a single span structure.)

c) Section loss more than 1/4 inch or section loss equal to or greater than 25% of the flange

thickness in other than the maximum moment areas (i.e. Section loss up to 1/4 points of the

middle 1/2 of a single span structure.)

d) Section loss more than 1/8 inch or section loss equal to or greater than 15% of web thickness

in the maximum shear areas (i.e. Section loss within 5 feet of the bearing center line.)

e) Section loss more than 1/8 inch or section loss equal to or greater than 25% of web thickness

in other than the maximum shear areas (i.e. Section loss found a minimum of 5 feet beyond

the bearing center line.)

Heating Devices: The Contractor may use heating devices to obtain and maintain a condition

within the containment enclosure that is suitable for surface preparation and painting application.

For painting applications, the required conditions must be maintained for the duration of the cure

period. Heating devices shall be limited to gas- or oil-fired indirect air heaters in which the

combustion products are discharged separately from the forced airstream to an area outside the

containment enclosure. The heating devices must be configured so as not to form condensation

on cold surfaces or cause rust-back and must be automatically controlled. Information describing

the proposed heating devices and the proposed heating procedures shall be provided a minimum

of 20 days in advance for Engineer acceptance.

Lighting Requirements: A minimum illumination level of 20 foot-candles shall be provided

throughout the inside of the containment enclosure during surface preparation and coating

application work. A minimum illumination level of 50 foot-candles shall be provided at the

location of the specific work task and for inspection. All lighting fixtures and related connectors

located inside the containment enclosure must be explosion proof and shall be UL listed.

Material Storage: The Contractor shall provide a suitable facility for the storage of paint that

complies with all Federal and State laws and regulations.

This facility shall provide protection from the elements and ensure that the paint is stored at

temperatures within the more stringent of (1) the manufacturer's written recommended

temperatures, or (2) between 40°F and 100°F. If paint application takes place in conditions that

require heating of the containment, then the temperature of the stored paint shall be maintained at

a similar temperature. Storage of paint shall be in reasonable proximity to the painting location(s).

The Engineer shall be provided access to the stored paint for inspection and to witness removal of

the materials. The Contractor's facility for the storage of paint shall be subject to the approval of

the Engineer.

Equipment: All equipment used in surface preparation and removal of debris, such as hoses,

hoppers, recycling and vacuum machines, that the Contractor brings to the Site shall be clean and

free of any prior debris.

Spray equipment, brushes and rollers used in application of coatings shall be sized sufficiently

and be in proper working order to accomplish the work according to the manufacturer's written

Page 30: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

recommendations.

Compressed Air: All compressed air sources shall have oil and moisture separators, attached and

functional, and properly designed and sized. The compressed air sources shall deliver air to the

blast nozzle, for blowing down the surfaces, or for conventional spray application that is free of

oil and moisture and of sufficient pressure to accomplish the associated work efficiently and

effectively. The tanks on the air compressor and moisture separator shall be drained at the end of

each workday. The compressed air source shall produce a minimum pressure of 90 psi at the

nozzle during abrasive blast cleaning.

The Contractor shall verify that the compressed air is free of moisture and oil contamination in

accordance with the requirements of ASTM D4285. The tests shall be conducted at least once

every 4 hours for each compressor system in operation. Sufficient freedom from oil and moisture

is confirmed if soiling or discoloration is not visible on the paper. If air contamination is

evidenced, the Contractor shall change filters, clean traps, add moisture separations or filters, or

make other adjustments as necessary to achieve clean, dry, air.

Test Sections: Prior to surface preparation, the Contractor shall prepare a test section(s) on each

structure to be painted in a location(s) that the Engineer considers to be representative of the

existing surface condition and steel type for the structure as a whole. The test section(s) shall be

prepared using the same equipment, materials and procedures as the production operations. The

Contractor shall prepare the test section(s) to the specified level according to the appropriate SSPC

written specifications and visual standards. The written requirements of the specification prevail

in the event of a conflict with the SSPC visual standards. Only after a test section area has been

approved shall the Contractor proceed with surface preparation operations. The test section(s)

shall cover approximately 10 square feet each. Additional compensation will not be allowed the

Contractor for preparation of test sections.

For the production cleaning operations, the specifications and written definitions, the test

section(s), and the SSPC visual standards shall be used in that order for determining compliance

with the Contract requirements.

Surface Preparation:

1 – Laminar and Stratified Rust: All laminar and stratified rust or corrosion products that have

formed on any area of the existing steel surfaces and accessible rust formed along edges of

connected plates or shapes of structural steel shall be removed. The tools used to remove these

corrosion products shall be identified in the submittals and accepted by the Engineer. If the surface

preparation or removal of rust results in nicks or gouges, the work will be suspended. The

Contractor shall demonstrate that the necessary adjustments have been made to prevent a

recurrence of the damage prior to resuming work.

2 – Near White Metal Blast Cleaning (SSPC-SP10): Steel surfaces shall be cleaned by the

specified methods described in the SSPC Steel Structures Painting Manual, Volume 2 - Systems

and Specifications, latest edition. The structural steel shall be abrasive blast cleaned according to

Page 31: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

SSPC-SP 10 “Near White Blast Cleaning.” Before and after blast cleaning, all dissolvable foreign

matter, such as oil, grease, and dust shall be removed by wiping or scrubbing the surface with rags

or brushes wetted with solvent in accordance with the provisions of SSPC-SP 1 “Solvent

Cleaning.” Clean solvent and clean rags or brushes shall be used for the final wiping.

All foreign materials such as dirt, dust, rust scale, sand, bird droppings, and all materials loosened

by abrasive blasting operations shall be completely removed by vacuuming before any painting

operations are begun.

The cleaned surface shall be accepted by the Engineer before any painting. If the surface is

determined to meet the requirements of SSPC-SP 10, painting operations can commence. The

prime coat shall be applied to the steel before the end of the day that preparation was performed

and before the formation of any flash rusting or rerusting of the steel. Flash rusting or rerusting of

the surface is unacceptable and requires additional blast cleaning prior to painting.

Failure of the Contractor to prepare and clean the surfaces to be painted according to these

specifications shall be cause for rejection by the Engineer. All surfaces that are rejected shall be

recleaned to the satisfaction of the Engineer in accordance with these specifications, at no

additional cost to the State.

3 – Steel Grit Abrasive Mix: The recyclable steel grit abrasive mix shall be maintained and

monitored such that the final surface profile is within the range specified elsewhere in these

specifications.

Before each reuse, the recyclable steel grit abrasive shall be cleaned of millscale, rust, paint, and

other contaminants by an abrasive reclaimer.

On a weekly basis during blast cleaning operations, the Contractor shall verify that the recycled

steel grit abrasives meet the requirements of SSPC-AB2. If the abrasive fails the testing, all

abrasive blast cleaning operations shall be suspended. The abrasive reclaimer shall be repaired

and another abrasive sample will be required for testing after grit recovery and reclassification.

For test results within the acceptable limits, abrasive blast cleaning may resume. Test results

outside of the acceptable limits will require additional equipment repairs or replacement at no cost

to the State. If additional repairs were performed, another sample will be required for testing after

grit recovery and reclassification. It the test results continue to remain outside of the acceptable

limits, the Contractor shall replace the abrasive reclaimer at no cost to the State.

4 - Surface Profile: The specified height of the steel surface profile is 1-3 mils and shall be

uniform. Verification of the profile height will be done with Testex Replica Tape. A surface

profile correction factor will be measured according to SSPC-PA 2, Section 2.2.4 with the dry film

thickness gauge.

Note: Chemical Stripping will not be permitted.

Painting Operation:

Page 32: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

1 - General: All coatings shall be supplied in sealed containers bearing the manufacturer’s name,

product designation, batch number and mixing/thinning instructions. Leaking containers shall not

be used. Storage, opening, mixing, thinning and application of coating materials shall be

accomplished in strict accordance with the written requirements and procedures published by the

respective coating material manufacturer and supplier. In the event of a conflict, the Contractor

shall notify the Engineer in writing, and unless directed otherwise in writing, the requirements of

this specification shall prevail. The Contractor shall always have, at the Project Site, the current

copies of all material safety data sheets (MSDS), technical data, recommendations and procedures

published by the coating manufacturer for the coating materials.

2 - Paint Mixing and Thinning: Thinning shall be performed only to the extent allowed by the

manufacturer’s written instructions, and only with the manufacturer’s approved thinner. In no case

shall thinning be permitted that would cause the coating to exceed the local VOC restrictions. For

multiple component paints, only complete kits shall be mixed and used. Partial mixing is not

allowed.

The ingredients in the containers of paint shall be thoroughly mixed by mechanical power mixers

in the original containers, or as directed by the manufacturer, before use or mixing with other

containers of paint. The paint shall be mixed in a manner that will break up all lumps, completely

disperse pigment and result in a uniform composition. Paint shall be carefully examined after

mixing for uniformity and to verify that no unmixed pigment remains on the bottom of the

container. Excessive skinning or partial hardening due to improper or prolonged storage will be

cause for rejection of the paint, even though it may have been previously inspected and accepted.

Multiple component coatings shall be discarded after the expiration of the pot life. Single

component paint shall not remain in spray pots, painter’s buckets, or similar containers overnight.

It shall be stored in a covered container and remixed before use.

The Engineer reserves the right to sample field paint (individual components or mixed material)

and have it analyzed. If the paint does not meet the product requirements due to excessive thinning

or because of other field problems, the coating shall be removed from that section of the structure

and replaced as directed by the Engineer.

3 – Methods of Application: All applicators of the specified coating material shall show

proficiency on a test panel, or a portion of the structure as selected by the Engineer, to the

satisfaction of the Engineer before commencing full-scale application.

The preferred method for coating application shall be by airless spray equipment. For stripping

and for application in areas where complex shapes or tight clearances will not allow spray

application, the Contractor shall apply the coating material by appropriately designed and

constructed rollers and brushes.

4 – Recoat Times: The recoat time of the primer, intermediate and top coat shall not deviate from

the written recommendation of the manufacturer or the times specified in these specifications,

Page 33: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

complying with the most restrictive requirements unless directed otherwise by the Engineer in

writing. If any individual time is exceeded, the affected areas shall be abrasive blast cleaned to

SSPC-SP 10 and coatings reapplied in accordance with these specifications at no additional cost

to the State.

5 – Film Continuity: All applied coatings shall exhibit no running, streaking, sagging, wrinkling,

holidays, pinholes, top coat color or gloss variation, or other film defects. Failure of the Contractor

to apply coatings that are free of film defects shall be cause for rejection by the Engineer. All

coatings rejected shall be repaired to the satisfaction of the Engineer, at no additional cost to the

State. Before doing any coating repair work, the Contractor shall submit to the Engineer for

approval the procedures that will be used to repair the coating.

6 - Technical Advisor: It is mandatory that the Contractor obtain the services of a qualified

technical advisor employed by the coating manufacturer. This advisor shall be familiar with the

technical properties of the coating products and proper application methods. The technical advisor

shall assist the Engineer and the Contractor in establishing correct application methods for the

complete coating system. They shall be present at the work Site before the opening of the material

containers and shall remain at the Site until the Engineer is satisfied that the Contractor's personnel

have mastered the proper handling, mixing and application of the material. The Engineer may call

the technical advisor back to the Site if there are concerns that the Contractor is not handling,

mixing or applying the material correctly.

7 - Containment Plan: For each individual Site, the Contractor shall submit a plan of containment

to the Engineer for acceptance. The plan, as outlined in other Contract item special provisions,

shall be submitted 20 days before commencing painting operations. The prime coat shall be

applied within the same containment used for abrasive blast cleaning. After prime coat

application, the minimum containment enclosure for the intermediate and top coat shall conform

to the requirements of SSPC Guide 6, Class 3A and the following:

Components of the containment system must be made from flame retardant materials.

Tarpaulin material shall be clean and impermeable to air and water.

Joints shall be fully sealed except for entryways.

Entryways shall use multiple flap overlapping door tarps to minimize dust escape through the

entryway.

All mists or dust shall be filtered with collection equipment.

For truss bridges, a ceiling shall also be included.

8 - Prime Coat Application: All prepared surfaces shall be cleaned by vacuuming to remove dust,

remaining debris, and other surface contaminants before coating. Such surfaces shall then be

sprayed, brushed or rolled within the specified abrasive blast cleaning containment enclosure with

the specified primer material before the end of the day or before any visible rust-back occurs. If

rust-back occurs, affected surfaces shall be recleaned to the satisfaction of the Engineer in

accordance with these specifications, at no additional cost to the State.

Page 34: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

All plate and shape edges, plate seams, back-to-back angle seams, pitted steel, and other sharp

discontinuities shall be hand-striped with a brush in the longitudinal direction with the primer.

Bolted connections shall also have all bolt heads and nuts hand-striped in a circular brush motion

with the primer material. Stripe coats shall be applied before or after the full prime coat

application. The prime coat material used for hand-striping shall be tinted to distinguish it from

material used for full prime coat application.

The zinc-rich primer shall be applied to dry surfaces within the more restrictive temperature range

(both steel and air) as specified in the manufacturer’s written application instructions or between

50°F and 100°F, unless directed otherwise by the Engineer in writing. The dry film thickness shall

be according to the manufacturer's written instructions in effect at the time that the product was

tested for NEPCOAT. The dry film thickness will be checked for compliance by measuring above

the peaks of the substrate profile per the guidelines of SSPC-PA 2.

The dry primer shall be free of all surface and embedded contamination and dry spray.

9 - Intermediate Coat Application: When the primer has cured per the manufacturer's

recommendations (not to exceed 30 days), all previously coated surfaces shall receive the

intermediate coat. The cured and dry primer coat shall be clean and free of all surface and

embedded contamination and dry-spray. If it is not clean and free of all contamination, and dry-

spray, the surfaces shall be cleaned by using clean rags or brushes to water wipe, solvent wipe, or

detergent wash and rinse. Power washing is not allowed. Temperature ranges (both steel and air)

shall be the more restrictive of that specified in the manufacturer’s written application instructions

or between 50°F and 100°F, unless directed otherwise by the Engineer in writing. The dry film

thickness shall be according to the manufacturer's written instructions in effect at the time that the

product was tested for NEPCOAT. The intermediate coat shall be of a contrasting color to the

prime and topcoat colors. The dry film thickness will be checked for compliance per the guidelines

of SSPC-PA 2.

10 - Top Coat Application: When the intermediate coat has cured per the manufacturer's written

recommendations (not to exceed 10 days), all previously coated surfaces shall receive the top coat.

The cured and dry intermediate coat shall be clean and free of all surface and embedded

contamination and dry-spray. If it is not clean and free of all contamination, and dry-spray, the

surfaces shall be cleaned by using clean rags or brushes to water wipe, solvent wipe, or detergent

wash and rinse. Power washing is not allowed. Temperature ranges (both steel and air) shall be

the more restrictive of that specified in the manufacturer’s written application instructions or

between 50°F and 100°F, unless directed otherwise by the Engineer in writing. The dry film

thickness shall be according to the manufacturer's written instructions in effect at the time that the

product was tested for NEPCOAT.

11 - Date of Completion: The word “PAINTED” followed by the month and year the painting

of each structure was completed, along with the manufacturer’s abbreviations for each of the 3

coats, shall be stenciled on the inside of a fascia girder at mid-depth of the girder in three (3) inch

high block letters near each abutment, to be clearly visible from the ground below. In order to

ensure uniformity, abbreviations shall be approved by the Engineer prior to application of the

Page 35: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. 3/19/2020

ITEM #0603923A

ADDENDUM NO. 1

stenciled information.

Method of Measurement: This item, being paid for on a lump sum basis for each site number,

will not be measured for payment.

Basis of Payment: This work will be paid for at the Contract lump sum price for “Abrasive Blast

Cleaning and Field Painting of Structure (Site No. 1),” which price shall include all materials,

equipment, painting overspray containment enclosure, heating devices, tools, labor, and services

of the technical advisor. No direct payment will be made for the cost of storage or hauling the

paint and other materials to and from the bridge site(s), but the cost thereof shall be included in

the lump sum price as noted above.

Pay Item Pay Unit

Abrasive Blast Cleaning and Field Painting

of Structure (Site No. 1) l.s.

Page 36: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

ITEM # 0971001A – MAINTENANCE AND PROTECTION OF TRAFFIC

Article 9.71.01 – Description is supplemented by the following:

The Contractor shall maintain and protect traffic as described by the following and as limited in the

Special Provision "Prosecution and Progress":

Route I-95 (US Route 1)

The Contractor shall maintain and protect the minimum number of through lanes and shoulders

on a paved travel path not less than 12 feet in width per lane during the hours dictated in the special

provision for Article 1.08.04 – Limitation of Operations.

The Contractor will be permitted to halt traffic during the allowable periods. If more than one 10-

minute period is required, then the Contractor shall allow all stored vehicles to proceed through the

work area prior to the next stoppage.

The Contractor will be permitted to close a lane of traffic as shown on the Maintenance and

Protection of Traffic plans for Phase A, B, C and D; during the time periods allowed in the special

provision for Article 1.08.04 – Limitations of Operations.

Ramps and Turning Roadways

The Contractor shall maintain and protect existing traffic operations, with the following

exceptions:

1. During the allowable periods and when the Contractor is actively working, the Contractor

will be permitted to maintain and protect a minimum of 1 lane of traffic on a paved travel

path not less than 12 feet in width.

All Other Roadways

The Contractor shall maintain and protect a minimum of one lane of traffic in each direction, each

lane on a paved travel path not less than 11 feet in width, unless otherwise noted.

Closure of Local Streets:

Contractor shall provide at least 2 weeks advance notice to the Engineer for any requests to

temporarily impact normal traffic operations. The Engineer will then notify the municipalities and

all emergency services as required.

Groton:

Alternating one-way traffic or short-term 20-minute maximum closures controlled by a Municipal

Police Officer shall be provided when the Contractor is actively performing work over local roads

which present hazards to the motoring public.

Page 37: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Commercial and Residential Driveways

The Contractor shall maintain access to and egress from all commercial and residential driveways

throughout the project limits. The Contractor will be allowed to close said driveways to perform

the required work during those periods when the businesses are closed, unless permission is

granted from the business owner to close the driveway during business hours. If a temporary

closure of a residential driveway is necessary, the Contractor shall coordinate with the owner to

determine the time period of the closure.

Article 9.71.03 - Construction Methods is supplemented as follows:

General

Unpaved travel paths will only be permitted for areas requiring full depth and full width

reconstruction. The unpaved section shall be the full width of the road and shall be perpendicular to

the travel lanes. The Contractor will be allowed to maintain traffic on processed aggregate for a

duration not to exceed 10 calendar days and opposing traffic lane dividers shall be used as a

centerline.

The Contractor is required to delineate any raised structures within the travel lanes, so that the

structures are visible day and night, unless there are specific Contract plans and provisions to

temporarily lower these structures prior to the completion of work.

The Contractor shall schedule operations so that pavement removal and roadway resurfacing shall

be completed full width across a roadway or bridge section by the end of a work shift, or as directed

by the Engineer.

When the installation of all intermediate courses of bituminous concrete pavement is completed

for the entire roadway, the Contractor shall then install the final course of bituminous concrete

pavement.

When the Contractor is excavating adjacent to the roadway, the Contractor shall provide a 3-foot

shoulder between the work area and travel lanes, with traffic drums spaced every 50 feet. At the end

of the work shift if the vertical drop-off exceeds 3 inches, the Contractor shall provide a temporary

bituminous concrete traversable slope of 4:1 or flatter that is acceptable to the Engineer.

The Contractor, during the course of any active overhead construction work, shall close the lanes

directly below the work area for the entire length of time overhead work is being undertaken.

At no time shall an overhead sign be left partially removed or installed.

When an existing sign is to be relocated or replaced, the work shall be completed during the same

work shift.

The field installation of a signing pattern shall constitute interference with existing traffic operations

and shall not be allowed, except during the allowable periods.

On limited-access highways, construction vehicles entering travel lanes shall not be allowed without

a lane closure. The lane closure shall be of sufficient length to allow vehicles to enter or exit the work

area at the posted speed limit, in order to merge with existing traffic.

Existing Signing

The Contractor shall maintain all existing overhead and side-mounted signs within the Project

limits throughout the duration of the project. The Contractor shall temporarily relocate signs and

Page 38: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

sign supports as many times as deemed necessary, and shall install temporary sign supports if

necessary and as directed by the Engineer.

Requirements for Winter

The Contractor shall schedule a meeting with representatives of the Department including the

offices of Maintenance and Traffic, and the Town/City to determine any interim traffic control

measures the Contractor shall accomplish prior to winter to provide safety to motorists and permit

adequate snow removal procedures. This meeting shall be held prior to October 31 of each year

and will include, but not be limited to, discussion of the status and schedule of the following items:

lane and shoulder widths, pavement restoration, traffic signal work, pavement markings, and

signing.

Signing Patterns

The Contractor shall erect and maintain all signing patterns in accordance with the traffic control

plans contained herein. Proper distances between advance warning signs and proper taper lengths

are mandatory.

Pavement Markings - Limited Access Highways, Turning Roadways and Ramps

During construction, the Contractor shall maintain all pavement markings throughout the limits

of the Project, except those that conflict with the temporary hot-applied painted pavement

markings.

Temporary pavement markings shall be installed on each intermediate course of bituminous

concrete pavement and on any milled surface by the end of the work shift.

Permanent Epoxy Resin Pavement Markings shall be installed on the final course of bituminous

concrete pavement within 10 calendar days of the final pavement installation if no Pavement

Marking Grooves are proposed.

Temporary Pavement Markings

Temporary pavement markings shall consist of temporary painted pavement markings and shall

be installed in accordance with Section 12.09. The markings shall include 6-inch-wide white

dotted lane lines, 4 inch wide edge lines, and chevron markings.

In Phase A, the conflicting pavement markings along the right shoulder and lane closure shall be

removed and restriped according to the Contract plans. The Phase A traffic pattern shall then be

implemented and upon completion of the phase, the striping shall be restored to the original

condition with Permanent Epoxy Resin Pavement Markings. In Phase B, the conflicting pavement

markings along the left shoulder and lane closure shall be removed and restriped according to the

Contract plans. The Phase B and C traffic pattern shall then be implemented. Upon completion of

Phase C, the striping shall be restored to the original condition with Permanent Epoxy Resin

Pavement Markings. In Phase D, the conflicting pavement markings along the right shoulder and

lane closure shall be removed and restriped according to the Contract plans. The Phase D traffic

Page 39: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

pattern shall then be implemented and upon completion of the phase, the striping shall be restored

to the original condition with Permanent Epoxy Resin Pavement Markings.

All temporary pavement markings exposed throughout the winter shall be Epoxy Resin Pavement

Markings, unless directed otherwise by the Engineer.

Temporary pavement markings, as described above, shall be maintained until the permanent

pavement markings are installed.

Final Pavement Markings

Permanent epoxy resin pavement markings shall be installed in accordance with Section 12.10

and the applicable Traffic Engineering Standard Drawings.

TRAFFIC CONTROL DURING CONSTRUCTION OPERATIONS

The following guidelines shall assist field personnel in determining when and what type of traffic

control patterns to use for various situations. These guidelines shall provide for a safer and more

efficient movement of traffic through work zones and enhance the safety of work forces in the

work area.

TRAFFIC CONTROL PATTERNS

Traffic control patterns shall be used when a work operation requires that all or part of any vehicle

or work area protrudes onto any part of a travel lane or shoulder or is within the clear zone. For

each situation, the installation of traffic control devices shall be based on the following:

Speed and volume of traffic.

Duration of operation.

Exposure to hazards.

Traffic control patterns shall be uniform, neat, and orderly in order to command respect from the

motorist.

Lane reduction tapers should be placed so that the entire length of the taper is installed on a

tangent section of roadway and the entire taper area can be seen by the motorist.

All existing conflicting signs shall be removed, covered with an opaque material, or turned so

that they are not legible to oncoming traffic prior to implementing a traffic control pattern. The

existing signs shall be uncovered or reinstalled once the pattern is removed.

A buffer area should be provided during installation of a traffic control pattern and maintained

for the duration of the work. The buffer area shall be free of any equipment, workers, materials,

and parked vehicles.

Construction Traffic Control Plans 19 through 25 should be used for moving operations such as

line striping, rumble strips, pothole patching, mowing, or sweeping when it is necessary for

equipment to occupy a travel lane.

Traffic control patterns are not required for vehicles on an emergency patrol type activity or for

a short duration stop of up to one hour, as long as the equipment is contained within the shoulder.

Page 40: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Flashing lights, arrow boards, truck-mounted or trailer-mounted impact attenuators, and

appropriate Trafficperson(s) shall be used when required.

In a situation not adequately covered by the Construction Traffic Control Plans, the Contractor

shall contact the Engineer for assistance prior to setting up a traffic control pattern.

PLACEMENT OF SIGNS

Signs shall be placed in a position that allows motorists the opportunity to reduce their speed

prior to the work area. Signs shall be installed on the same side of the roadway as the work area.

On multi-lane divided highways, advance warning signs shall be installed on both sides of the

highway. On directional roadways (on-ramps, off-ramps, one-way roads), where the sight distance

to signs is restricted, these signs should be installed on both sides of the roadway.

ALLOWABLE ADJUSTMENT OF SIGNS AND DEVICES SHOWN ON THE TRAFFIC

CONTROL PLANS

The Construction Traffic Control Plans contained herein show the location and spacing of signs

and devices under ideal conditions. Signs and devices should be installed as shown on these plans.

The proper application of the Construction Traffic Control Plans and installation of traffic control

devices is dependent upon actual field conditions.

In the case of a horizontal or vertical sight restriction in advance of the work area, the traffic

control pattern shall be extended to provide adequate sight distance for approaching traffic.

Adjustments to the Construction Traffic Control Plans shall only be made at the direction of the

Engineer.

Table 1 indicates the minimum taper lengths required for a lane closure based on the posted speed

limit and lane width of the roadway. These taper lengths shall only be used when the recommended

taper lengths shown on the Construction Traffic Control Plans cannot be achieved.

TABLE I – MINIMUM TAPER LENGTHS

MINIMUM TAPER LENGTH

FOR A SINGLE LANE CLOSURE (FEET)

POSTED SPEED

LIMIT

(MPH) FREEWAYS SECONDARY ROADS

30 OR LESS

35

40

45

50

55

65

180

245

320

540

600

660

780

165

225

295

495

550

605

715

Page 41: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

1. Work Zone Safety Meetings

1.a) Prior to the commencement of work, a Work Zone Safety Meeting shall be conducted with

representatives from DOT Construction, Connecticut State Police (Local Barracks),

Municipal Police, the Contractor (Project Superintendent) and the Traffic Control

Subcontractor (if different than the prime Contractor) to review the traffic operations, lines

of responsibility, and operating guidelines which will be used on the Project. DOT Traffic

Engineering shall be invited to the Work Zone Safety Meeting. Other Work Zone Safety

Meetings during the course of the Project should be scheduled as needed.

1.b) A Work Zone Safety Meeting Agenda shall be developed and used at the Meeting to outline

the anticipated traffic control issues during the construction of this Project. Any issues that

can’t be resolved at these Meetings will be brought to the attention of the District Engineer

and the Office of Construction. The agenda shall include:

i. Review Project scope of work and time;

ii. Review Section 1.08, Prosecution and Progress;

iii. Review Section 9.70, Trafficpersons;

iv. Review Section 9.71, Maintenance and Protection of Traffic;

v. Review Contractor’s schedule and method of operations;

vi. Review special concern areas: ramps, turning roadways, medians, lane drops, etc.;

vii. Open discussion of work zone questions and issues;

viii. Discussion of review and approval process for changes in Contract requirements as

they relate to work zone areas.

2. General

2.a) Traffic control patterns shall only be installed if the required minimum number of signs,

traffic cones, traffic drums, and other equipment (i.e. one Arrow Board for each lane

closed, two Truck-Mounted or Trailer-Mounted Attenuators (TMAs), Changeable

Message Sign, etc.) are on Site.

2.b) The Contractor shall have spare maintenance and protection of traffic equipment (TMAs,

Arrow Board, Changeable Message Sign(s), construction signs, traffic cones, traffic drums,

etc.) available at all times in case of mechanical failures, etc. Spare maintenance and

protection of traffic equipment installed as a result of a sudden equipment breakdown shall

be replaced by the Contractor within 24 hours.

2.c) Failure of the Contractor to have the required minimum number of signs, personnel, and

equipment, which results in the pattern not being installed, shall not be a reason for a time

extension or claim for lost time.

2.d) In cases of differences of opinion between the Contractor and the Inspection staff, the

Contractor shall follow the directions of the Engineer. The matter shall be brought to the

District Office for resolution immediately or, in the case of work after regular business

hours, on the next business day.

Page 42: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

3. Installing and Removing Traffic Control Patterns

3.a) Lane closures shall be installed beginning with the advance warning signs and proceeding

forward toward the work area.

3.b) Lane closures shall be removed in the reverse order, beginning at the end of the work area,

or traffic control pattern, and proceeding back toward the advance warning signs.

3.c) Stopping traffic may be allowed within the allowable hours stated in Section 1.08.04:

i. For those activities stated within the Contract.

ii. During paving, milling operations, or similar activities where, in the middle of the

operation, it is necessary to flip the pattern to complete the operation on the other

half of the roadway so traffic does not travel across the longitudinal joint or

difference in roadway elevation.

iii. To move slow moving equipment across live traffic lanes into the work area.

3.d) The Contractor shall adhere to using the proper signs, placing the signs correctly, and

ensuring the proper spacing of signs.

3.e) Additional devices are required on entrance ramps, exit ramps, and intersecting roads to

warn and/or move traffic into the proper travel path prior to merging with or exiting from

the mainline traffic. This shall be completed before installing the mainline pattern past the

ramp or intersecting roadway.

3.f) Workers are prohibited from crossing the travel lanes on limited access roadways to install

and remove signs or other devices on the opposite side of the roadway. Any signs or

devices on the opposite side of the roadway shall be installed and removed separately.

4. Implementation of Rolling Road Block (RRB)

4.a) Temporary road closures using a RRB may be allowed on limited access highways for

operations associated with the installation and removal of temporary lane closures. RRB

may be allowed for the installation and removal of lead signs and lane tapers only and shall

meet the following requirements:

i. Refer to the Limitation of Operations Chart provided in Section 1.08.04 for the

hours allowed for implementing a RRB operation. The Contractor shall only

implement a RRB operation within the hours shown in the Chart.

ii. In areas with good sight lines and full shoulders, signs on the side of the road

opposite the traffic pattern should be installed in a separate operation.

iii. TMAs equipped with Arrow Boards shall be used to slow traffic to implement the

RRB. State Police Officers in marked vehicles may be used to support the

implementation of the RRB. The RRB shall start by having all vehicles, including

TMAs and police vehicles, leave the shoulder or on-ramp and accelerate to normal

Page 43: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

roadway speeds in each lane. The vehicles will then position themselves side by

side and decelerate to the RRB speed on the highway.

iv. A Pre-Warning Vehicle, as specified elsewhere in the Contract, shall be used to

advise the motorists that sign pattern installation or removal is underway.

v. The RRB duration shall not exceed 15 minutes from the start of the traffic block

until all lanes are opened as designated in the Limitation of Operations chart. If the

RRB duration exceeds 15 minutes on 2 successive shifts, no further RRB will be

allowed until the Contractor obtains approval for a revised installation procedure

from the District.

vi. RRB shall not be used to expand a lane closure pattern to an additional lane during

the shift. The workers and equipment required to implement the additional lane

closure should be staged from within the closed lane. TMAs (and State Police if

available) shall be used to protect the workers installing the taper in the additional

lane.

vii. Exceptions to these work procedures may be submitted to the District Office for

consideration. A minimum of 2 business days shall be allowed for review and

comment by the District.

viii. The Engineer and the Contractor will review and discuss the RRB procedures

(including any revisions) in advance of the work. The implementation of the agreed

upon plan will be reviewed with the State Police during the Work Zone Safety

Meeting held before each shift involving temporary lane closures. If the State

Police determine that alternative procedures should be implemented for traffic

control during the work shift, the Department and Contractor will attempt to resolve

any discrepancies with the duty sergeant at the Troop. If the discrepancies are

unable to be resolved prior to the start of the shift, then the work will proceed as

recommended by the Department. Any unresolved issues shall be addressed the

following day.

5. Use of Arrow Boards

5.a) On limited access roadways, one Arrow Board shall be used for each lane that is closed.

The Arrow Board shall be installed concurrently with the installation of the traffic control

pattern and its placement shall be as shown on the Construction Traffic Control Plans.

Additional Arrow Boards shall be deployed if sight distances are limited.

5.b) On non-limited access roadways, the use of an Arrow Board for lane closures is optional.

The roadway geometry, sight distance, and traffic volume shall be considered in the

decision to use the Arrow Board.

5.c) A vehicle displaying an arrow board shall be equipped with high-intensity rotating,

flashing, oscillating, or strobe lights.

5.d) The flashing arrow mode shall be used for lane closure (merge) tapers.

Page 44: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

5.e) The flashing arrow mode shall not be used for temporary alternating one-way traffic

operations or to laterally shift lanes of traffic.

5.f) The flashing double arrow mode shall only be used for closing a center lane on a multilane

roadway where adjacent left and right lanes remain open.

5.g) For shoulder work or roadside work near the shoulder, the Arrow Board shall be positioned

in the shoulder and the flashing alternating diamond mode should be used.

5.h) The flashing alternating diamond caution mode should also be used when supplemental

Arrow Boards are positioned in an already closed lane.

6. Use of Truck-Mounted or Trailer-Mounted Impact Attenuators (TMAs)

6.a) On limited access roadways, lane closures shall use a minimum of two TMAs to install and

remove traffic control patterns. If two TMAs are not available, then the pattern shall not

be installed.

6.b) On non-limited access roadways, the use of TMAs to install and remove patterns closing a

lane(s) is optional. The roadway geometry, sight line distance, and traffic volume shall be

considered in the decision to utilize the TMAs.

6.c) On limited access roadways, one TMA shall be placed on the shoulder and the second

TMA shall be approximately 1,000 feet ahead blocking the lane to establish the advance

and transition signing. The Arrow Board mounted on the TMA shall be in the arrow mode

when taking the lane. The sign truck and workers shall be at sufficient distance ahead of

the second TMA. In no case shall the TMA be used as the sign truck or a work truck. Once

the transition is in place, the TMAs shall travel in the closed lane until all Portable

Changeable Message Signs, signs, Arrow Boards, and cones/drums are installed. The

Arrow Board mounted on the TMA should be in the flashing alternating diamond caution

mode when traveling in the closed lane.

6.d) A TMA shall be placed prior to the first work area in the pattern. If there are multiple work

areas within the same pattern, then additional TMAs shall be positioned at each additional

work area as needed. The Arrow Board mounted on the TMA should be in the flashing

alternating diamond caution mode when in the closed lane.

6.e) TMAs shall be positioned a sufficient distance prior to the workers or equipment being

protected to allow for appropriate vehicle roll-ahead in the event that the TMA is hit, but

not so far that an errant vehicle could travel around the TMA and into the work area. For

additional placement and use details, refer to Section 18.06. Some operations, such as

paving and concrete repairs, do not allow for placement of the TMA(s) within the specified

distances. In these situations, the TMA(s) shall be placed at the beginning of the work area

and shall be advanced as the paving or concrete operations proceed.

Page 45: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

6.f) TMAs will be paid for in accordance with how the unit is used. If it is used as a TMA and

is in the proper location as specified, then it will be paid for at the specified hourly rate for

Truck-Mounted or Trailer-Mounted Impact Attenuator. When the TMA is used as an

Arrow Board, it will be paid for at the daily rate for Arrow Board. If a TMA is used to

install and remove a pattern and is also used as an Arrow Board in the same day, then the

unit will be paid for as a Truck-Mounted or Trailer-Mounted Impact Attenuator for the

hours used to install and remove the pattern, typically 2 hours (1 hour to install and 1 hour

to remove). If the TMA is also used as an Arrow Board during the same day, then the unit

will only be paid for at the daily rate as an Arrow Board.

7. Use of Traffic Drums and Traffic Cones

7.a) On limited-access highways, ramps, and turning roadways:

i. Traffic drums shall be used for taper channelization.

ii. Traffic drums shall be used to delineate raised catch basins and other hazards.

iii. Traffic cones with a minimum height of 42 inches may be used in place of drums

in the tangent section of a closed lane or shoulder.

iv. Traffic cones less than 42 inches in height shall not be used.

7.b) On all roadways:

i. Traffic drums shall be used in place of traffic cones in traffic control patterns that

are in effect for more than a 36-hour duration.

ii. Traffic cones shall not be left unattended.

iii. Traffic cones with a minimum height of 42 inches shall be used when the posted

speed limit is 45 MPH or above.

7.c) Typical spacing of traffic drums and/or cones shown on the Construction Traffic Control

Plans in the Contract are maximum spacings and may be reduced to meet actual field

conditions as required.

8. Use of Barricade Warning Lights

8.a) Barricade Warning Lights shall be installed on channelizing devices when used in a merge

taper. The Barricade Warning Lights shall flash in a sequential pattern when used in a

merge taper. The successive flashing shall occur from the upstream end (beginning) of the

merge taper to the downstream end (end) of the merge taper.

8.b) Type C Barricade Warning Lights may be used at night to delineate the edge of the travel

way.

8.c) Type B Barricade Warning Lights shall be used on post-mounted advanced warning signs.

Page 46: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

9. Use of Portable Changeable Message Signs (PCMS)

9.a) On limited access roadways, one PCMS shall be used in advance of the traffic control

pattern for all lane closures. Prior to installing the pattern, the PCMS shall be installed and

in operation, displaying the appropriate lane closure information. The PCMS shall be

positioned ½ to 1 mile ahead of the start of the lane closure taper. If the distance to the

nearest exit ramp is greater than the specified ½ to 1 mile distance, then an additional

PCMS shall be positioned a sufficient distance ahead of the exit ramp (and before the

previous on-ramp where practical) to alert motorists to the work and therefore offer them

an opportunity to take the exit.

9.b) On non-limited access roadways, the use of PCMS for lane closures is optional. The

roadway geometry, sight line distance, and traffic volume shall be considered in the

decision to use the PCMS.

9.c) PCMS should be placed off the shoulder of the roadway and behind a traffic barrier, if

practical. Where a traffic barrier is not available to shield the PCMS, it should be placed

off the shoulder and outside of the clear zone. If a PCMS has to be placed on the shoulder

of the roadway or within the clear zone, it should be placed on the paved shoulder with a

minimum of five traffic drums placed in a taper in front of it to delineate its position. The

taper shall meet minimum distance requirements for a shoulder closure. The PCMS shall

be protected if it is used for a continuous duration of 36 hours or more.

9.d) The PCMS shall be removed from the clear zone and have the display screen cleared and

turned 90 degrees away from the roadway when the PCMS is no longer required.

9.e) The PCMS should not be used within 1,000 feet of an existing PCMS or Variable Message

Sign (VMS).

9.f) A PCMS message shall:

i. consist of no more than two phases;

ii. contain no more than three lines of text per phase;

iii. have no more than eight characters per line, including spaces.

9.g) The PCMS should be used for specific situations that need to command the motorist’s

attention which cannot be conveyed with standard construction signs. The PCMS should

not be used for generic messages (ex.: Road Work Ahead, Bump Ahead, Gravel Road, etc.)

or for messages that need to be displayed for long periods of time, such as during stage

construction. These types of messages should be displayed with construction signs.

Special signs shall be coordinated with the Office of Construction and the Division of

Traffic Engineering for the proper layout/dimensions required.

9.h) Typical messages that are allowed on the PCMS are shown below. Approval must be

received from the Office of Construction for any message(s) different than the typical

messages shown in Figure 1.

Page 47: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

9.i) All messages shall comply with the information provided in Tables 2 and 3.

Message No.

Phase 1 Phase 2 Message No. Phase 1 Phase 2

1 LEFT

LANE

CLOSED

MERGE

RIGHT

9 LANES

CLOSED

AHEAD

REDUCE

SPEED

2 2 LEFT

LANES

CLOSED

MERGE

RIGHT

10 LANES

CLOSED

AHEAD

USE

CAUTION

3 LEFT

LANE

CLOSED

REDUCE

SPEED

11 EXIT XX

CLOSED

USE

EXIT YY

4 2 LEFT

LANES

CLOSED

REDUCE

SPEED

12 EXIT XX

CLOSED

USE YY

FOLLOW

DETOUR

5 RIGHT

LANE

CLOSED

MERGE

LEFT

13 2 LANES

SHIFT

AHEAD

USE

CAUTION

6 2 RIGHT

LANES

CLOSED

MERGE

LEFT

14 3 LANES

SHIFT

AHEAD

USE

CAUTION

7 RIGHT

LANE

CLOSED

REDUCE

SPEED

8 2 RIGHT

LANES

CLOSED

REDUCE

SPEED

Figure 1: Typical PCMS Messages

Page 48: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Table 2: Acceptable Abbreviations

Word Message Standard

Abbreviation

Word Message Standard

Abbreviation

Access ACCS Minimum MIN

Afternoon / Evening PM Minor MNR

Ahead AHD Minute(s) MIN

Alternate ALT Monday MON

Avenue AVE, AV Morning / Late Night AM

Bicycle BIKE Mount MT

Blocked BLKD Mountain MTN

Boulevard BLVD National NATL

Bridge BR Normal NORM

CB Radio CB North N

Center CTR Northbound NBND

Center CNTR Oversized OVRSZ

Chemical CHEM Parking PKING

Circle CIR Parkway PKWY

Compressed Natural

Gas

CNG Pavement PVMT

Condition COND Pedestrian PED

Congested CONG Place PL

Construction CONST Pounds LBS

Court CT Prepare PREP

Crossing XING Quality QLTY

Crossing (other than

highway-rail)

XING Right RT

Downtown DWNTN Road RD

Drive DR Roadwork RDWK

East E Route RT, RTE

Eastbound EBND Saint ST

Electric Vehicle EV Saturday SAT

Emergency EMER Service SERV

Entrance, Enter ENT Shoulder SHLDR

Exit EX Slippery SLIP

Express EXP South S

Expressway EXPWY Southbound SBND

Feet FT Speed SPD

Freeway FRWY, FWY State, county, or other

non-US or non-

Interstate numbered

route

[Route Abbreviation

determined by highway

agency]**

Friday FRI Street ST

Frontage FRNTG Sunday SUN

Hazardous HAZ Telephone PHONE

Hazardous Material HAZMAT Temporary TEMP

High Occupancy

Vehicle

HOV Terrace TER

Page 49: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Highway HWY Thruway THWY

Highway-Rail Grade

Crossing

RR XING Thursday THURS

Hospital HOSP Tons of Weight T

Hour(s) HR, HRS Traffic TRAF

Information INFO Trail TR

International INTL Travelers TRVLRS

Interstate I- Tuesday TUES

Junction / Intersection JCT Turnpike TPK

Lane LN Two-Way Intersection 2-WAY

Left LFT Two-Wheeled Vehicles CYCLES

Liquid Propane Gas LP-GAS Upper UPR

Local LOC US Numbered Route US

Lower LWR Vehicle(s) VEH, VEHS

Maintenance MAINT Warning WARN

Major MAJ Wednesday WED

Maximum MAX West W

Mile(s) MI Westbound WBND

Miles Per Hour MPH

** A space and no dash shall be placed between the abbreviation and the number of the route.

Table 3: Unacceptable Abbreviations

Unacceptable Abbreviation Intended Word Common Misinterpretation

ACC Accident Access (Road)

CLRS Clears Colors

DLY Delay Daily

FDR Feeder Federal

L Left Lane (Merge)

LT Light (Traffic) Left

PARK Parking Park

POLL Pollution (Index) Poll

RED Reduce Red

STAD Stadium Standard

WRNG Warning Wrong

Page 50: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

10. Use of State Police Officers

10.a) State Police may be used only on limited access highways and secondary roadways that

are under their primary jurisdiction. A minimum of one Officer may be used per critical

sign pattern; however, a State Police presence is not required. Shoulder closures and right

lane closures can generally be implemented without the presence of a State Police

Officer. Left lane closures may also be implemented without State Police presence in areas

with only moderate traffic and wide, unobstructed medians. It may be desirable to have a

State Police presence, when available, under specific situations, such as nighttime lane

closures; left lane closures with minimal width for setting up advance signs and staging;

lane and shoulder closures on turning roadways/ramps or mainline where sight distance is

minimal; and closures where extensive turning movements or traffic congestion regularly

occur; however, they are not required.

10.b) If a State Police presence is provided, once the pattern is in place, the State Police Officer

should be positioned in a non- hazardous location in advance of the pattern to provide

advance warning to the motorist. If traffic backs up beyond the beginning of the pattern,

then the State Police Officer shall reposition so that they are located prior to the

backup. The State Police Officer should not be located immediately behind or within the

roll ahead area of any TMA or within the work zone buffer area. The State Police Officer

shall not be positioned in such a way that the State Police Officer obstructs any construction

warning signs or PCMS from view of the motorist.

10.c) Other functions of the State Police Officer(s) may include:

i. Assisting construction vehicles entering and exiting the work area.

ii. Enforcement of motor vehicle laws within the work area, if specifically requested

by the Engineer.

10.d) State Police Officers assigned to a work site shall take direction from the Engineer.

Page 51: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 52: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 53: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 54: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 55: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 56: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 57: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 58: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 59: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 60: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 61: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 62: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 63: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 64: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 65: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Page 66: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 8/11/2021

ITEM #0971001A

ADDENDUM NO. 1

Article 9.71.05 – Basis of Payment is supplemented by the following:

The temporary relocation of signs and supports, and the furnishing, installation and removal of

any temporary supports shall be paid for under the item “Maintenance and Protection of Traffic”.

Temporary overhead sign supports and foundations shall be paid for under the appropriate item(s).

The cost of furnishing, installing, and removing the material for the 4H:1V traversable slope shall

be paid for under the item “Maintenance and Protection of Traffic”.

Page 67: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 10/22/2018

ITEM #1806226A

ADDENDUM NO. 1

ITEM #1806226A – PRE-WARNING VEHICLE

Description: Work under this item shall include furnishing, deploying and maintaining a Truck-

Mounted Impact Attenuator equipped with a changeable message sign (CMS) for use as a Pre-

Warning Vehicle (PWV) in a rolling road block operation on limited access highways. Impact

attenuators shall only be truck-mounted. The message on the sign shall warn motorists of slow or

stopped traffic conditions.

Materials: The Truck-Mounted Impact Attenuator shall meet the requirements of Article

18.06.02, except replace all instances of “flashing arrow,” “arrow sign,” and “arrow” with “CMS”.

The CMS shall meet the requirements of Article 11.31.02, with the following amendments:

1. Physical Characteristics of the CMS

a) Mounting – The CMS shall be truck mounted only

b) Sign Display Dimensions – Width of 6 feet, height of 4 feet

2. Visual Characteristics of the CMS Display

a) Sign Type – CMS shall have a LED display only

b) Color – CMS shall have black background with orange, yellow, or amber legend

c) Characters – Letter height shall be 13 inches; Single stroke

d) Visibility– CMS brightness must provide for visibility at 1/2 mile

e) Message – The message shall read as follows, or shall be as directed by the Engineer:

Frame 1: SLOWED TRAFFIC AHEAD

Frame 2: BE PREPARED TO STOP

Or

Frame 1: STOPPED TRAFFIC AHEAD

Frame 2: BE PREPARED TO STOP

Construction Methods: The PWV shall be initially positioned in the right shoulder ½ mile prior

to the rolling road block operation.

If a traffic queue reaches the PWV’s initial location, the Contractor shall slowly reverse the PWV

along the shoulder to position itself prior to the new back of queue.

The Contractor shall meet the requirements of Article 18.06.03.

Method of Measurement: This work will be measured for payment by the actual number of

hours that the Pre-Warning Vehicle is used in a rolling road block operation.

Basis of Payment: This work will be paid for at the Contract unit price per hour for “Pre-

Warning Vehicle,” which shall include the furnishing and use of the pre-warning vehicle and a

driver, attenuator reflector, flashing lights, changeable message sign, and all equipment, materials,

Page 68: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

Rev. Date 10/22/2018

ITEM #1806226A

ADDENDUM NO. 1

tools, labor, disposal of damaged Truck-Mounted Impact Attenuator components and work

incidental thereto.

Pay Item Pay Unit

Pre-warning Vehicle hr

Page 69: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 70: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 71: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 72: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 73: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 74: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 75: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 76: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 77: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 78: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 79: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 80: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 81: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 82: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 83: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 84: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 85: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 86: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 87: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 88: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 89: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 90: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 91: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 92: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 93: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 94: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 95: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 96: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 97: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 98: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 99: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 100: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 101: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …
Page 102: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

1

REHABILITATION OF GOLD STAR BRIDGE

STEEL STRUCTURAL STRENGTHENING

State Project No. 94-256

PROJECT LABOR AGREEMENT BETWEEN

_________________________ Prime Contractor

AND

NORWICH-NEW LONDON BUILDING TRADES

CONSTRUCTION TRADES COUNCIL

AND

SIGNATORY UNIONS

_____________, 2021

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 103: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

2

PROJECT LABOR AGREEMENT

This Project Labor Agreement (hereinafter referred to as the “Agreement”) is entered into

this __ day of __________________, 2021, by and between the _______________________ as

Prime Contractor (hereinafter referred to as the “Prime Contractor”) and the Norwich-New

London Building and Construction Trades Council (hereinafter referred to as the “Council”) and

each of the seven (7) affiliated Local Unions signatory hereto (hereinafter individually and

collectively referred to as “Union” or “Unions” or “Local Unions”), with respect to the site

preparation, demolition and rehabilitation of Gold Star Bridge, New London, Connecticut, State

Project No. 94-256 (hereinafter referred to as the “Project”).

It is understood by the parties (collectively “Parties”; individually “Party”) that this

Agreement is in accordance with §31-56b of the Connecticut General Statutes and it is the intention

of the Project owner, the Connecticut Department of Transportation (the “Owner”), that work

within the scope of the Agreement shall be performed by Contractors (hereinafter referred to as

“Contractors” and as more particularly described in the next paragraph) who agree to execute and

be bound by the terms of this Agreement. Therefore, the Unions agree that Contractors may

execute an Acceptance of Agreement in the form attached to this Agreement as Exhibit A, which

Exhibit is incorporated herein, for the purpose of performing work on the Project. The Prime

Contractor for the Owner shall monitor and enforce compliance with this Agreement by the Unions

and by all Contractors who, through their execution of the Acceptance of Agreement, together with

their subcontractors, have become bound hereto.

The term “Contractors” shall include the Prime Contractor, all subcontractors and sub-

subcontractors of whatever tier engaged in on-site construction work or dedicated off-site

construction work within the scope of this Agreement. The Unions, the Prime Contractor and all

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 104: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

3

the Contractors agree to abide by the terms and conditions contained in this Agreement with

respect to the administration of the Agreement by the Prime Contractor and the performance of all

Contractors on the Project. All Contractors shall become parties to this Agreement whether or not

they operate their businesses as union or non-union companies on work not covered by this

Agreement. The Unions, the Prime Contractor and all other Contractors agree that this Agreement

applies only to this Project and nothing in this Agreement requires either the Owner or any

Contractor to become party to or to be required to sign any collective bargaining agreement as a

condition of performing work within the scope of this Agreement. This Agreement and the local

collective bargaining agreements attached as Schedule A represent the complete understanding of

the Parties.

ARTICLE I.

PURPOSE

The timely and successful completion of the Project is of paramount importance to the

Owner. Therefore, it is essential that the Project work be done in an efficient and economical

manner in order to secure optimum productivity and to eliminate any delays in the work. In

recognition of the needs of this Project and to maintain a spirit of harmony, labor-management

peace, and stability during the term of this Agreement, the Parties agree to binding methods for

the settlement of all misunderstandings, disputes or grievances which may arise as set forth in

Articles VII and VIII of this Agreement. This Agreement will foster the achievement of these

goals by: (1) prohibiting strikes, sympathy strikes, slowdowns, walkouts, lockouts, picketing and

other interruptions or disruptions and delays arising from work disputes, and promoting labor

harmony and peace for the duration of the Project; (2) standardizing and stabilizing certain basic

terms and conditions governing the employment of hourly craft employees on the Project, and

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 105: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

4

thereby promoting labor harmony and peace for the duration of the Project; (3) permitting

flexibility in scheduling work and shift hours and times to enhance coordination of work among

the various crafts on the Project and to promote efficiency and economy of operations; (4)

adjusting work rules and staffing requirements from those which otherwise might pertain to

enhanced coordination of the work among the various crafts on the Project, and to promote

efficiency and economy of operations; (5) providing comprehensive and standardized mechanisms

for the settlement of disputes that can be implemented without delay, including those relating to

grievances, job disputes and trade jurisdiction; (6) ensuring a reliable source of skilled and

experienced labor, whether unionized or non-unionized; (7) encouraging the use of local residents

by Contractors; (8) establishing goals for and encouraging the use of apprentices by all

Contractors, whenever and wherever possible and feasible; (9) expediting the Project work and

otherwise minimizing potential disruptions for the duration of the Project; (10) inviting all

Contractors to bid on the Project without regard to whether the employees are members of a labor

organization as defined in section 31-101 of the Connecticut General Statutes; (11) permitting the

selection of the lowest responsible bidder without regard to labor organization affiliation; (12) not

requiring compulsory labor organization membership of employees working on the Project; and

(13) binding all Contractors to the terms of the Agreement.

ARTICLE II.

SCOPE OF THE AGREEMENT

SECTION 1. This Agreement shall apply and is limited to all site preparation, demolition,

construction, and dedicated off-site work as defined in Article III, Section 5 within the scope of

the Project under the direction of the Contractors who have contracts awarded for such work by

the Prime Contractor or other Contractors on and after the effective date of this Agreement.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 106: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

5

SECTION 2. (a) The Prime Contractor has the absolute right to award sub-contracts on

this Project without reference to the existence or non-existence of any collective bargaining

agreements between such Contractor and any signatory Union to this Agreement; provided that

such Contractor is willing, ready and able to execute the attached Acceptance of Agreement and

comply with this Agreement.

(b) It is agreed that no Contractor shall be awarded contracts for work covered by this

Agreement until such Contractor has duly executed the attached Acceptance of Agreement,

thereby becoming bound by the terms and conditions of this Agreement. All Contractors shall

promptly provide copies of all executed Acceptance of Agreement forms to the Prime Contractor.

SECTION 3. (a) Incorporated into this Agreement by reference are the local collective

bargaining agreements or standard agreements between the Unions and their respective employer

associations and any successor local collective bargaining agreements (hereinafter referred to as

“Schedule A’s”).

The provisions of this Agreement (including the Schedule A’s) shall apply to the

construction of the Project, notwithstanding the provisions of any local, area and/or national

bargaining or standard agreements which may conflict or differ from the terms of this Agreement.

Where a subject covered by the provisions of this Agreement is also covered by provisions of one

of the Schedule A’s, the provisions of this Agreement shall prevail. Where a subject is covered

by the provisions of one of the Schedule A’s and not covered by this Agreement, the Schedule A’s

provisions shall apply.

(b) Any dispute as to whether this Agreement or the applicable Schedule A determines

the wages, hours and working conditions of employees on the Project shall be resolved pursuant

to Article VIII of this Agreement by an Arbitrator selected by the Parties at the time of signing the

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 107: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

6

PLA in accordance with the procedures of the American Dispute Resolution Center (ADRC). A

Party invoking such arbitration shall notify the Arbitrator by written notice delivered via hand

delivery or UPS overnight delivery with a copy to the other Party or Parties to such dispute

delivered via hand delivery or UPS overnight delivery. In the event the Arbitrator is unable to

hear any such dispute within ten (10) days of receipt of notice, the Parties to such dispute shall

choose an alternative Arbitrator. It is understood that this Agreement, together with the attached

Schedule A’s, constitutes a self-contained, standalone agreement and that by virtue of having

become bound to this Agreement, the Contractor will not be obligated to sign or in any way be

bound by any other Local, Area or National Agreement.

SECTION 4. This Agreement shall only be binding on the Parties hereto and shall not

apply to the parents, affiliates, subsidiaries, or other ventures of any such Party.

SECTION 5. This Agreement shall be limited to work customarily recognized as

construction work including, specifically, the site preparation and related demolition work

necessary to prepare the site for construction and dedicated off-site work as is directed by the

Prime Contractor. “Dedicated off-site work” shall be defined as work done at a facility or location

established exclusively for the Project which work is performed outside of the geographic footprint

of the Project. Contractor’s yards or fabrication sites which include other operations are excluded

from the Project.

SECTION 6. It is understood that the liability of any individual Contractor and the

liability of the separate Unions under this Agreement shall be several and not joint. The Unions

agree that this Agreement does not have the effect of creating any joint employment status between

or among the Owner, the Prime Contractor, and/or any other Contractor.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 108: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

7

SECTION 7. Items specifically excluded from the scope of this Agreement include, but

are not limited to, the following:

(a) Work of non-manual employees including, but not limited to, superintendents,

supervisors, staff engineers, surveyors, (except where expressly covered by a Schedule A to this

Agreement), inspectors, quality control personnel, quality assurance personnel, timekeepers, mail

carriers, clerks, office workers, including messengers, guards, emergency medical and first aid

technicians, and other professional, engineering, administrative, supervisory and management

employees.

(b) Equipment and machinery owned or controlled and operated by the Owner.

(c) All off-site fabrication, assembly, and handling of materials, equipment or

machinery; and all deliveries of those items with the exception of concrete, to and from the Project

site.

(d) All employees of the Owner or their representative not a party to this agreement,

and all employees of the Contractor not performing manual labor.

(e) Any work performed on or near, or leading to or into, the Project site by state,

county, municipal or other governmental bodies, or their contractors; or by public utilities, or their

contractors, and/or by the Owner, or its contractors (for work which is not part of the Project).

(f) Off-site maintenance on leased equipment and on-site supervision of such work.

(g) Off-site warranty functions and warranty work, on-site supervision of such work.

SECTION 8. None of the provisions of this Agreement shall apply to the Owner and

nothing contained herein shall be construed to prohibit or restrict the Owner or its employees or

contractors from performing work not covered by the Agreement on the Project site. As areas and

systems of the Project are inspected and construction tested by the applicable Contractor and

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 109: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

8

accepted by the Prime Contractor, the Agreement shall not have further force and effect on such

items or areas, except when the Contractor is directed by the Prime Contractor to engage in repairs,

modifications, check-out, and/or warranty functions required by the contract(s) with the Owner.

ARTICLE III.

UNION RECOGNITION AND EMPLOYMENT

SECTION 1. The Prime Contractor and other Contractors recognize the Unions as the

sole and exclusive bargaining representative for all craft employees within their respective

jurisdictions working within the scope of this Agreement.

SECTION 2. Applicants for various job classifications covered by the Agreement

required by the Contractors on the Project shall be referred to the Contractors by the Local Union.

Each Contractor shall have the right to determine the competency of its employees, the right to

determine the number of employees required, and shall have the sole responsibility for selecting

the employees to be laid off consistent with Article IV of this Agreement and the attached Schedule

A’s. Each Contractor shall also have the right to reject any applicant referred by the Local Union,

subject to the show-up payments required in the applicable Schedule A.

SECTION 3. (a) Recognizing that this is a publicly financed and supported Project for

the benefit of the residents of the State of Connecticut, the Parties agree that any special conditions

required of the Contractors by the Owner will be observed and accepted for the performance of

Project work, including but not limited to:

(i) payment of wages and benefits at least equal to those established by the

applicable prevailing wage statute and regulations;

(ii) the encouragement of employment of minorities, women, veterans, and

residents of the labor market within which the Project is located;

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 110: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

9

(iii) the participation in Project work of certified Disadvantaged Business

Enterprises (DBE); and

(iv) the encouragement of the utilization of properly trained and qualified

apprentices.

Nothing in this Section 3 shall require Contractors to hire workers that such Contractors believe

are not qualified for the available work.

(b) The Prime Contractor and the Council acknowledge that this Project is subject to

the Federal DBE Program and the Prime Contractor will make good faith efforts to meet or exceed

the Project goals for DBE participation contained in the bid requirements.

SECTION 4. For a Local Union having a job referral system in its Schedule A, for the

purpose of initial employment only, the Contractor agrees to make use of such system. There shall

be no discrimination against any employee or applicant for employment because of his or her

membership or non-membership in the Union. Such job referral system must be operated in a non-

discriminatory manner and in full compliance with federal, state and local laws and regulations

which require equal employment opportunities and non-discrimination, and referrals shall not be

affected in any way by the rules, regulations, by-laws, constitutional provisions or any other

aspects or obligations of union membership, policies or requirements and shall be subject to such

other conditions as established in this Article.

SECTION 5. All Union employees now in the employ of any Contractor shall remain

members in good standing in the Union during the term of this Agreement to the extent permitted

by law. All other employees hereinafter employed by a Contractor may elect to become members

of the Union, or if they do not desire to become members, they shall not be required to join a Union

but may pay the hourly agency fee and shall not be required to pay monthly Union dues. Each

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 111: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

10

Union shall ensure that the union security requirement in this Article shall be in compliance with

all applicable federal and state laws, and each Union shall remain solely responsible for any non-

compliance therewith.

SECTION 6. In the event that any Union is unable to fill any requisition for employees

within a forty-eight (48) hour period after such requisition is made by the Contractor (Saturdays,

Sundays and Holidays excepted), the Contractor may employ applicants from any other available

source.

SECTION 7. In the event that the Local Union does not have a job referral system as set

forth in Section 2 of this Article, the Local Union shall refer qualified applicants pursuant to a non-

discriminatory job referral procedure, subject to the provisions of Section 4 of this Article. The

Contractor shall notify the Union of employees hired from any source other than referral by the

Union.

SECTION 8. The Local Union shall not knowingly refer to a Contractor under this

Agreement employees currently employed by another Contractor working under this Agreement.

SECTION 9. (a) The Unions will exert their utmost efforts to recruit and refer sufficient

numbers of skilled craftsmen to fulfill the manpower requirements of the Contractors, including

any specific employment conditions to which the Contractor is obligated pursuant to the provisions

of the statutes and regulations governing development of the Project. Where employees require

Occupational Safety and Health Administration-approved hazardous materials training, the Unions

agree to provide such training at no additional cost to the Contractor.

(b) Further, the Parties recognize the level of activity in the construction industry

within the area and the State of Connecticut at the time of the execution of this Agreement. Each

Contractor shall have the ability to bring a reasonable number of its key employees to work on the

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 112: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

11

Project provided that (i) as a general rule such employee complement does not exceed thirty

percent (30%) of its workforce in any given month, and (ii) such employee complement is

consistent with Federal Equal Employment Opportunity requirements and affirmative action goals

contained in the bid specifications. Notwithstanding the above requirements, DBE certified

Contractors will be allowed to bring up to fifty percent (50%) of their workforce to work on the

Project, and their numbers will be included in the 30% goal calculation. The Prime Contractor

and the Council will work together to implement procedures and advise the Unions of reasonable

means to effectuate the intent of this provision.

SECTION 10. The selection of non-working foremen and/or general foremen and the

number of non-working foremen required shall be entirely the responsibility of each Contractor.

All employees shall take orders from his or her designated Contractor representative.

SECTION 11. Except as provided in Article IV, Section 3, individual seniority shall be

recognized and applied to employees working on the Project as set forth in the attached Schedule

A’s.

SECTION 12. Helmets to Hardhats.

(a) The Contractors and the Union recognize a desire to facilitate the entry into the building

and construction trades of military veterans interested in careers in the building and construction

industry. The Contractors and Unions agree to utilize the Connecticut Department of Labor’s Jobs

Funnel Initiative, the services of the Center for Military Recruitment, Assessment and Veterans

Employment (hereinafter "Center") and the Center’s Helmets to Hardhats program to serve as a

resource for preliminary orientation, assessment of construction aptitude, referral to apprenticeship

programs or hiring halls, counseling and mentoring, support network, employment opportunities

and other needs as identified by the Parties.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 113: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

12

(b) The Union and Contractors agree to coordinate with the Center to create and maintain

an integrated database of veterans interested in working on this Project and of apprenticeship and

employment opportunities for this Project. To the extent permitted by law, the Unions will give

credit to such veterans for bona fide, provable past experience.

ARTICLE IV.

UNION REPRESENTATION

SECTION 1. Authorized representatives of the Union shall have access to the Project,

provided they do not interfere with the work of employees and further provided that such

representatives comply with safety rules of the Project.

SECTION 2. Stewards.

(a) Each signatory Local Union shall have the right to designate a working journeyman

as a steward, and shall notify the Contractor in writing of the identity of the designated steward

prior to the assumption of his or her duties as steward. Such designated steward shall not exercise

any supervisory functions. Stewards will be allowed to devote a reasonable amount of time to

discharge their responsibilities as stewards; however, there will be no non-working stewards.

Stewards will receive the regular rate of pay of their respective crafts.

(b) In addition to his or her work as an employee, the steward shall have the right to

receive, but not solicit, complaints or grievances and to discuss and assist in the resolution of the

same with the employee’s appropriate supervisor. Each steward shall be concerned with the

employees of the steward’s Contractor and not with the employees of any other Contractor.

Contractors will not discriminate against the steward in the proper performance of his/her Union

duties.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 114: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

13

(c) The stewards shall not have the right to determine when overtime shall be worked

or who shall work overtime; provided that this subsection shall not be construed to supersede the

provisions of any applicable Schedule A, which contains a procedure for establishing equitable

distribution of overtime.

SECTION 3. The Contractor agrees to notify the appropriate Union twenty-four (24)

hours prior to the layoff of a steward, except in the case of discipline or discharge for just cause.

If a steward is protected against such layoff by the provisions of the applicable Schedule A, such

provisions shall be recognized to the extent that the steward possesses the necessary qualifications

to perform the work remaining. In any case in which a steward is discharged or disciplined for

just cause, the appropriate Union shall be notified immediately by the directly employing

Contractor which imposed such discharge or discipline.

ARTICLE V.

MANAGEMENT RIGHTS

SECTION 1. The Contractor retains full and exclusive authority for the management of

its operation(s). Except as expressly limited by other provisions of this Agreement, the Contractor

retains the right to direct the workforce, including the hiring, promotion, transfer, lay-off,

discipline or discharge for just cause of its employees; the selection of foremen; the assignment

and scheduling of work; the requirement of overtime work, the determination of when it shall be

worked, and the number of employees who shall be engaged for such work. No rules, customs, or

practices which limit or restrict productivity, efficiency or the individual and/or joint working

efforts of employees shall be permitted or observed. The Contractor may utilize any customary,

industry-recognized methods or techniques of construction. Nothing herein shall affect the role

and responsibility of the Prime Contractor on this Project.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 115: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

14

SECTION 2. Except as otherwise expressly stated in this Agreement, there shall be no

limitation or restriction upon the Contractor’s choice of materials or design or its choice of

methodologies for the installation or use of materials, supplies or equipment. The Contractor may

install or otherwise use materials, supplies or equipment according to the Schedule A’s or as

customarily performed in this area. The on-site installation or application of such items shall be

performed by the Union trade having jurisdiction over such work.

SECTION 3. The use of new technology, equipment, machinery, tools and/or labor-

saving devices and methods of performing work may be initiated by the Contractor from time to

time during the Project. The Unions agree that they will not in any way restrict the implementation

of such new devices or work methods and there shall be no limit on production by workers or

restrictions on the full use of tools and equipment. If there is any disagreement between a

Contractor and the Union concerning the manner or implementation of such devices or method of

work, the implementation shall proceed as directed by the Contractor, and the Union shall have

the right to initiate a dispute as set forth in Article VIII of this Agreement.

ARTICLE VI.

PRE-JOB CONFERENCE

SECTION 1. There shall be a mandatory pre-job conference initiated by the Prime

Contractor which shall address all the specific and substantial issues affecting the Project at a

time and location to be determined by the Prime Contractor. The Parties agree to use such

conference to its fullest to avoid unforeseen conflicts which may affect job assignments,

productivity, costs, or the Project schedule. Architects and design professionals may be involved

in the pre-job conference to ensure that the Project is fully understood by all Parties involved. A

well-planned pre-job conference with labor and management can result in substantial cost

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 116: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

15

savings.

Further, each subcontractor to the Prime Contractor shall conduct a pre-job conference with

the appropriate signatory Union(s) prior to commencing work. The Prime Contractor and the

Council shall be advised in advance of all such conferences and may participate if they wish.

SECTION 2. A Steering Committee consisting of the President of the Norwich New

London Building and Construction Trades Council, the Owner or its designee and the Prime

Contractor shall be established to ensure smooth implementation of this Agreement. The

Committee shall meet on a designated day on a monthly basis, provided nothing herein shall

prevent such Committee for meeting more often, as may be necessary. The Steering Committee

shall have the authority to recommend amendments to this Agreement for consideration by the

Union, the Prime Contractor and the Owner.

ARTICLE VII.

WORK STOPPAGES AND LOCKOUTS

SECTION 1. There shall be no strikes, sympathy strikes, walkouts, picketing (including

but not limited to economic, area standards, or informational), work stoppages, slowdowns,

interruptions or other disruptive activity for any reason by any Union or employees against any

Contractor covered under this Agreement or which otherwise disrupts Project work, and there shall

be no lockout by any Contractor. Failure of any Union or employee to cross any picket line

established by any Union, signatory or non-signatory, or any other organizations, at or in proximity

to the Project site is a violation of this Article.

SECTION 2. Any Contractor may discharge any of its employees for violating Section 1

of this Article, and any such employee will not be eligible for employment under this Agreement

for a period of ninety (90) working days from the date of his or her discharge. Each Contractor

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 117: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

16

and each Union shall take all steps necessary to obtain compliance with this Article, and neither

shall be held liable for conduct for which it is not responsible.

SECTION 3. Any Party may institute the following procedure in lieu of, or in addition to,

any other action at law or equity, when a breach of Section 1 of this Article is alleged:

(a) A Party invoking this procedure shall immediately notify the subject Contractor or

Union, as applicable. These Parties shall, within two (2) days, agree to a permanent Arbitrator

(“Arbitrator”) for the subject dispute. Notice to the Arbitrator shall be by telephone and fax and/or

e-mail with notices by telephone, fax and/or e-mail, or UPS overnight delivery to the Party alleged

to be in violation. The Party invoking this procedure shall also give notice to the Prime Contractor.

(b) Upon receipt of said notice, the Arbitrator selected by the Parties to the contract or

his or her alternate shall sit and hold a hearing within twenty-four (24) hours if it is contended that

the violations still exist.

(c) The Arbitrator shall notify the subject Parties by telephone and fax and/or e-mail

of the reasonable place and time he or she has chosen for this hearing. Said hearing shall be

completed in one session which, with appropriate recesses at the Arbitrator’s discretion, shall not

exceed twenty-four (24) hours unless otherwise agreed upon by the subject Parties. A failure of

any such Party or Parties to attend said hearing shall not delay the hearing of evidence or the

issuance of any decision by the Arbitrator. The Arbitrator shall provide all notifications and

decisions made pursuant to this subsection to the Prime Contractor at the same time as the same

are provide to the Parties to the dispute.

(d) The sole issue at the hearing shall be whether or not a violation of Section 1 of this

Article has occurred, and the Arbitrator shall have no authority to consider any matter in

justification, explanation or mitigation of such violations or to award damages, which issue is

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 118: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

17

reserved for court proceedings, if any. The Arbitrator’s decision shall be issued in writing within

three (3) hours after the close of the hearing, and may be issued without an opinion. If any Party

to the dispute desires an opinion, one shall be issued within fifteen (15) days, but its issuance shall

not delay compliance with, or enforcement of, the Arbitrator’s decision. The Arbitrator may order

cessation of the violation of Section 1 of this Article and other appropriate relief, and such decision

shall be served on all Parties to the dispute and the Prime Contractor by hand or fax and/or e-mail

and by certified mail, return receipt requested, upon issuance. No Party may authorize an

Arbitrator to consider any matter in justification, explanation or mitigation of such violations or to

award damages.

(e) The Arbitrator’s decision may be enforced by any Court of competent jurisdiction

upon the filing of the Arbitrator’s decision and all other relevant documents referred to hereinabove

in the following manner. Telephonic and fax and/or e-mail notice of the filing of such enforcement

proceeding shall be given to the other Parties to the dispute and the Prime Contractor. In the

proceeding to obtain a temporary order enforcing the Arbitrator’s decision as issued under

subsection (d) of this Article, all Parties to the dispute waive the right to a hearing and agree that

such proceedings may be ex parte. Such agreement does not waive any such Party’s right to

participate in the hearing for a final order of enforcement.

(f) Any rights created by statute or law governing arbitration proceedings inconsistent

with the above procedure or which interfere with compliance hereto are, to the extent possible,

hereby waived by the Parties to whom they accrue.

(g) The fees and expenses of the Arbitrator shall be borne by the Party or Parties found

in violation, or in the event no violation is found, such fees and expenses shall be borne by the

Party who invokes the arbitration.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 119: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

18

(h) It is the responsibility of each Local Union and Contractor to keep on file with the

Owner and the Prime Contractor a current address or operating fax number and/or e-mail address

to which notices and notifications under this Article may be sent. Any Local Union or Contractor

failing to do so hereby waives its rights to claim that it did not receive proper or timely notice or

notification of any action taken by a Party or Arbitrator pursuant to this Article.

(i) If the Arbitrator determines that a violation has occurred in accordance with

subsection 3(d) of this Article VII, the violating Party(ies) shall, within eight (8) hours of receipt

of the Arbitrator’s decision, direct a cessation of such activity held to be in violation. If such

violation has not ceased and/or work recommenced consistent with the Arbitrator’s decision and

this Agreement by the beginning of the next regularly scheduled shift following the expiration of

the eight (8) hours, and the violating Union(s) or Contractor(s) has not made all good faith efforts

available to comply with the Arbitrator’s decision, then the violating Party shall pay the sum of

five thousand dollars ($5,000.00) as liquidated damages to the Owner and shall pay, as liquidated

damages, an additional five thousand dollars ($5,000.00) per shift for each shift thereafter on which

the violation is not ceased and/or work is not recommenced. The liquidated damages contained in

this Article are limited solely to the failure of a signatory Union to direct its members to cease

engaging in a work stoppage following an Arbitrator’s decision. The Arbitrator shall retain

jurisdiction to determine compliance with this Section.

SECTION 4. Procedures contained in Article VIII of this Agreement shall not be

applicable to any alleged violations of this Article, with the single exception that any employee

discharged for violation of Section 1 of this Article VII may resort to the procedures of Article

VIII to determine only if he or she was engaged in that violation. Further, disputes alleging a

violation of any other provision of this Agreement, including any underlying dispute(s) alleged to

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 120: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

19

be in justification, explanation or mitigation of any violation of Section 1 of this Article VII, shall

be resolved under the procedures of Article VIII of this Agreement.

SECTION 5. In the event of any work stoppage, strike, sympathy strikes, slowdowns,

picketing, interruptions or any other disruptive activity in violation of Section 1 of this Article, the

Prime Contractor may suspend all or any portion of Project work affected by such activity at the

Prime Contractor’s discretion and without penalty or consequence.

SECTION 6. At its option, the Owner may participate in any proceedings initiated under

this Article, and may receive copies of notifications through its Prime Contractor, and no rights or

liabilities shall accrue against the Owner pursuant to this Agreement.

ARTICLE VIII.

GRIEVANCES

SECTION 1. This Agreement is intended to provide close cooperation between

management and labor. The Prime Contractor and the Council shall each assign a representative

to this Project for the purpose of assisting the Unions, together with the Contractors, to complete

the Project economically, efficiently, continuously and without interruption, delays or work

stoppages.

SECTION 2. The Contractors and Unions agree to resolve issues of dispute in accordance

with the arbitration provisions set forth in this Article, except as otherwise set forth in Article VII

of this Agreement. The Unions and Contractors, by signing this Agreement, shall similarly bind

employees to such provisions.

SECTION 3. Any question or dispute arising out of and during the term of this Agreement

involving its interpretation and application (other than trade jurisdictional disputes or alleged

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 121: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

20

violations of Article VII, Section 1) shall be considered a grievance and subject to resolution under

the following procedures:

Step 1. (a) When any employee subject to the provisions of this Agreement feels he or

she is aggrieved by a violation of this Agreement, he or she must, to pursue the grievances, shall,

through his or her Local Union business representative or job steward, within seven (7) working

days after the individual knew or reasonably should have known of the occurrence of the alleged

violation, give notice to the work site representative of the involved Contractor and the work site

representative and Prime Contractor stating the provision(s) alleged to have been violated. The

business representative of the Local Union or the job steward and the work site representative of

the involved Contractor shall meet and endeavor to resolve the matter within seven (7) days after

timely notice has been given. If those parties fail to resolve the matter within the prescribed period,

the grieving party may, within seven (7) days thereafter, pursue Step 2 of this grievance procedure

provided the grievance is reduced to writing setting forth the relevant information concerning the

alleged grievance, including a short description thereof, the date on which the grievance allegedly

occurred, and the provision(s) of the Agreement alleged to have been violated. Grievances settled

at Step 1 of this Section shall be non-precedential except as to the parties directly involved unless

endorsed by the Owner through its Prime Contractor within seven (7) days after resolution has

been reached and the terms of the resolution are set forth in writing to the subject Union and the

subject Contractor.

(b) Should the Local Union(s) or any Contractor have a grievance with the other party

and, if after conferring, a settlement is not reached within seven (7) days, the grievance shall be

reduced to writing and proceed to Step 2 of this section in the same manner as Step 1(a) above, for

the resolution of an employee complaint.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 122: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

21

Step 2. The designee of the involved Local Union, together with the International Union

representative of that Union, the representative of the involved Contractor, and the a representative

of the Prime Contractor (or his designee) shall meet within seven (7) days of the referral of the

grievance to this second step to attempt to arrive at a satisfactory settlement thereof. If such parties

fail to reach an agreement, the grievance may be appealed in writing in accordance with the

provisions of Step 3 of this Section within fourteen (14) calendar days after the initial meeting at

Step 2.

Step 3. (a) If the grievance shall have been submitted, but not resolved pursuant to Step 2,

any party to the grievance may request, in writing, within fourteen (14) calendar days after the

initial Step 2 meeting, that the grievance be submitted to an Arbitrator selected by mutual

agreement of the parties, but if they are unable to do so within fourteen (14) days after referral to

them for arbitration, they shall request the American Dispute Resolution Center (ADRC) to

provide them with a list of Arbitrators from which the Arbitrator shall be selected. The then-

current Labor Arbitration Rules of the American Arbitration Association shall govern the conduct

of the arbitration hearing. The decision of the Arbitrator shall be final and binding on all parties

to the grievance and the fees and expenses of such arbitrations shall be borne equally by the

involved Contractor and the involved Union(s).

(b) Failure of the party raising the grievance to adhere to the time limits established

herein shall render the grievance null and void. The time limits established herein may be extended

only by written consent of the parties to the grievance involved at the particular step where the

extension is agreed upon. The Arbitrator referenced in Step 3 shall have the authority to make

decisions only on issues presented to him or her and he or she shall not have the authority to

change, amend, add to or subtract or detract from any of the provisions of this Agreement. No

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 123: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

22

Party may authorize an Arbitrator to consider any issue other than an issue raised pursuant to

Section 3, Step 1(a) of this Article.

SECTION 4. No adjustment or decision may provide retroactivity exceeding thirty (30)

days prior to the date of the filing of a written grievance.

SECTION 5. The Prime Contractor shall be notified by the involved Contractor of all

actions at Steps 2 and 3 and shall, upon its request, be permitted to participate in full in all

proceedings at these steps.

SECTION 6. To encourage the resolution of disputes and grievances at Steps 1 and 2 of

this procedure, the Parties agree that settlements reached at such Steps shall not be precedent

setting; and, further, recognizing the unique provisions of this Agreement, any decision issued by

an Arbitrator pursuant to Step 3 shall be applicable to work covered by this Agreement only, and

may not be used for any purpose regarding works not so covered.

ARTICLE IX.

JURISDICTIONAL DISPUTES

SECTION 1. Work shall be assigned by each Contractor in accordance with area practice

and such assignments shall be disclosed by each Contractor at a pre-job conference. All

Contractors involved, and representatives of the appropriate Unions shall be invited to attend such

conference.

There will be no strikes, sympathy strikes, work stoppages, picketing, slowdowns,

interruptions or other disruptive activity arising out of any jurisdictional dispute. Pending the

resolution of such dispute pursuant to Article VII of this Agreement, the construction work shall

continue in accordance with Section 1 of Article VII.

SECTION 2. In the event of a jurisdictional dispute, an aggrieved signatory Local Union

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 124: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

23

may request the Council to convene a committee comprised of the five (5) signatory Unions

uninvolved in the jurisdictional dispute (“Committee”) and attempt to make a resolution of the

assignment of work in dispute within forty-eight (48) hours of being contacted by the grieving

signatory Local Union. Any resolution must be acceptable to all Parties and will be reduced to

writing and will affect this Project only and will not be precedent setting. The Contractor that

assigned the work at issue may present any evidence or material to the Committee that the

Contractor used to make its assignment within this time period. If the Committee of the uninvolved

signatory Unions fails to reach a settlement on the matter within the prescribed period, any affected

Party may proceed to invoke the jurisdictional dispute procedure set forth in Section 3(a) or 3(b),

as applicable, of this Article within forty-eight (48) hours thereafter.

SECTION 3. (a) All jurisdictional disputes between or among Unions who have agreed

to be bound to the procedures provided in the Plan for the Settlement of Jurisdictional Disputes in

the Construction Industry (the “Plan”) shall be resolved under the Plan and shall be settled and

resolved according to the Procedural Rules and Regulations as set forth in the Plan. The

assignments of the Contractor(s) shall be followed until the dispute is resolved in accordance with

the Plan. Decisions rendered under the Plan shall be final, binding and conclusive on the affected

Contractor or Contractors and the Union or Unions.

(b) For all Unions and Contractors who have not agreed to be bound to provisions of the

Plan, all jurisdictional disputes between those Unions or Contractors and any other Union(s) or

Contractors shall be settled through arbitration where the Arbitrator shall be bound by area practice

regarding the assignment of the work. The assignments of the Contactor(s) shall be followed and

work shall continue until the dispute is resolved. Decisions rendered by the Arbitrator shall be

final, binding, and conclusive on the affected Contractor or Contractors and the Union or Unions.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 125: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

24

The Parties hereby appoint an Arbitrator selected in accordance with the rules and regulations of

the ADRC to serve as the Arbitrator for all disputes under this subsection (b).

SECTION 4. There shall be no authority to assign work to a double crew, that is, to more

employees than the minimum required to perform the work involved, or to assign the work to

employees who are not qualified to perform the work involved. This does not prohibit agreement

by the Parties to any dispute, including the involved Contractor, to establish composite crews

where more than one (1) employee is needed for the job, or an Arbitrator from ordering such when

appropriate under the Plan. The aforesaid determinations shall decide only to whom the disputed

work belongs.

SECTION 5. There shall be no strike, work stoppages, slowdown, picketing, interruption

or other disruptive activity while any jurisdictional dispute is being resolved. The work shall

proceed as assigned by the involved Contractor until finally resolved. The award or resolution

shall be confirmed in writing to the involved Parties. There shall be no strike, work stoppage,

slowdown, picketing, interruption or other disruptive activity in protest of any such award or

resolution. The involved Parties shall timely provide the Prime Contractor with a copy of the

Arbitrator’s decision.

ARTICLE X.

WAGES AND BENEFITS

SECTION 1. All employees covered by this Agreement shall be classified in accordance

with work performed and paid the base hourly wage rates for those classifications as specified in

the appropriate Schedule A; but in no event will such wage rates be less than those established

under the provisions of any prevailing wage statute or regulation applicable to the Project.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 126: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

25

SECTION 2. Each Contractor agrees to pay contributions to the established employee

benefit funds and industry promotion funds and other funds and programs in the amounts

designated in the appropriate Schedule A. Bona fide jointly trusteed fringe benefit plans

established or negotiated through collective bargaining during the life of this Agreement may be

added only at the time a segment of the Project is put out to bid and will not apply to any segments

previously put out to bid.

SECTION 3. Each Contractor shall adopt and agree to be bound by the written terms of

the legally-established trust agreements specifying the detailed basis on which payments are to be

made into, the benefits paid out of, such trust funds; provided, however, that any Contractor that

has posted payment and performance bonds for the full value of its work shall not be required to

post additional payment bonds pursuant to the Trust Agreements. Each Contractor shall authorize

the parties to such Trust Agreements to appoint trustees and successor trustees to administer the

Trust Funds and hereby ratifies and accepts the trustees so appointed as if made by the Contractor.

Employees not previously participants in the Taft-Hartley pension fund shall have the option to

divert pension hourly contributions made on their behalf to the appropriate annuity fund. Such

election by the employee must be done in writing on a form provided by the Council and shall be

effective for the duration of the Project.

SECTION 4. (a) Upon written notice from a benefit fund to which Contractors are required

to make contributions pursuant to this Agreement (or from the Union co-sponsoring such Benefit

Fund), to the Prime Contractor that a Contractor is in arrears on payments of benefit contributions

for work performed on this Project, which notice specifies the amount owed by the Contractor for

this Project by month, the Prime Contractor will immediately direct the Contractor, in writing, to

comply with its contractual obligations. Should the Contractor not provide the Benefit Fund with

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 127: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

26

payment, or a legally enforceable procedure for payment (or enforceable escrow procedure),

within five (5) working days after receipt of the written notice from the Prime Contractor, the

affected Union(s) may direct employees of such Contractor to engage in work stoppage (provided,

however, that such stoppage will not include picketing or otherwise disrupt the work on the Project

and provided that any such stoppage will cease upon payment (without violation of Section 1 of

Article VII). If the correct payments are not made within thirty (30) days of such notice, the Prime

Contractor will withhold moneys owed from its payments to its subject subcontractor sufficient to

satisfy the outstanding debt to the benefit fund and/or shall issue joint checks payable to the

involved subcontractor and the involved benefit fund. Upon receipt of any such joint check, the

involved Benefit Fund agrees to execute the Prime Contractor’s partial lien waiver and release.

ARTICLE XI.

HOURS OF WORK, OVERTIME SHIFTS AND HOLIDAYS

SECTION 1. Work Week and Work Day. The standard work week shall consist of forty

(40) hours Monday through Friday. The standard work day shall consist of eight (8) hours of work

commencing at 7:00 a.m. and ending at 3:30 p.m., with a one-half (1/2) hour unpaid lunch period

to commence between the fourth and fifth hours of work. The standard work day may be changed

within a two-hour window to accommodate job conditions or the needs of the Project as

determined by the Prime Contractor. Starting time shall commence and quitting time shall occur

at the employee’s designated work area. The Parties affirm their policy of a fair day’s work for a

fair day’s wage, and the Union Parties agree to cooperate in the implementation and application of

reasonable work rules intended to enforce this commitment.

SECTION 2. Overtime. Overtime pay at a rate of time and one-half shall be paid for all

work performed after ten (10) hours in a shift, forty (40) hours in a work week or any work

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 128: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

27

performed on Saturdays (unless it is a make-up day), Sundays or holidays. There will be no

restriction upon the non-discriminatory designation of employees who shall work the overtime.

There shall be no pyramiding of overtime pay under any circumstances. Any abuse of this

provision will be referred to the dispute/grievance procedure set forth in Article VIII of this

Agreement for resolution.

SECTION 3. It shall not be a violation of this Agreement if the Prime Contractor

considers it necessary to suspend all or a portion of the job to protect the life and safety of an

employee. In such cases, employees will be compensated only for the actual time worked;

provided, however, that where the Contractor requests employees to remain at the site and

available for work, the employees will be compensated for the standby time at their base hourly

rate of pay.

SECTION 4. Shifts. Scheduling of shifts by the Prime Contractor shall remain flexible

in order to meet the Project schedules and existing Project conditions including the minimization

of interference with traffic. It is not necessary to work a day shift in order to schedule a second

or third shift. Shifts must work a minimum of five (5) consecutive work days and must be

scheduled with not less than five (5) days’ notice to the Unions. There will be no premiums paid

for shift work.

SECTION 5.

(a) Holidays. Recognized holidays on this Project shall be those set forth below:

New Year’s Day Christmas Day Memorial Day

Labor Day Independence Day

Thanksgiving Day

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 129: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

28

b) Holiday pay shall be paid only as set forth in the Schedule A’s. Holidays shall be

observed on the dates established by the state and federal government.

SECTION 6. Reporting Pay. Reporting pay shall be paid in the manner set forth in the

Schedule A’s.

SECTION 7. Meal Period. Each Contractor will schedule a meal period of not more

than one-half hour’s duration at the work location at approximately four (4) hours into the

scheduled work shift, consistent with Section 1 of this Article. If an employee is required to

work through his or her meal period, he/she shall be compensated.

SECTION 8. (a) If the Prime Contractor determines that it would be beneficial to the

Project, the Contractor may, with the consent of the Union, implement a four (4) day-ten (10) hours

per day work week (as more fully described in this subsection), after providing a five (5) day notice

to the affected Union(s). The standard four (4) day-ten (10) hours per day work week shall consist

of ten (10) hours of work (plus one-half (1/2) hour unpaid lunch at approximately the mid-point of

the shift), between the hours of 6:00 a.m. and 4:30 p.m., Monday through Thursday. The standard

ten (10) hour work day may be changed to accommodate conditions on five (5) days’ notice from

the Prime Contractor or less notice as is mutually agreed upon.

(b) Should a 4 day-10 hour per day work week schedule be implemented, overtime

shall be paid after ten (10) hours of work during a work day within the normal work week. Should

five (5) or more hours of a normal ten (10) hour day be lost due to weather or other conditions

beyond the control of the Contractor, the Contractor may schedule a Friday make-up day, in the

same calendar week, with a minimum of eight (8) hours scheduled and straight time to be paid

until the schedule of work exceeds the time lost, after which overtime shall be paid.

SECTION 9. If a day during the normal five (5) day work week or two (2) days during

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 130: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

29

a four (4) day ten (10) hour work week is lost as a result of circumstances beyond the control of

the Contractor including severe weather, fire, power failure, or natural disaster, a Saturday make-

up day at straight time for all shifts may be scheduled.

ARTICLE XII.

CLEAN UP

All trades will clean up their own work area. The removal of debris from the designated

work area will be the work of the laborer.

ARTICLE XIII.

APPRENTICES

SECTION 1. The Contractor is encouraged to utilize apprentices and such other

appropriate classifications as are contained in the applicable Schedule A. Apprentices and such

other classifications as are appropriate shall be employed by the Unions utilizing a maximum

permissible ratio of 1:1 or 1:3, depending upon the craft.

SECTION 2. The Parties recognize the need to maintain continuing support of programs

designed to develop adequate numbers of competent workers in the construction industry

(“Apprentice Program”). To these ends, each Contractor will employ apprentices in their

respective crafts to perform such work as is within their capabilities and which is customarily

performed by the craft in which they are indentured.

SECTION 3. The Parties are made aware that the contract between the Prime Contractor

and the Owner requires an On-The–Job (OJT) Training Workforce Development Pilot.

Apprentices in the subject Apprentice Program are encouraged to participate in the OJT Pilot.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 131: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

30

ARTICLE XIV.

SAFETY, PROTECTION OF PERSON AND PROPERTY

SECTION 1. In accordance with the requirements of the Occupational Safety and Health

Act, it shall be the exclusive responsibility of each Contractor on the job site to ensure safe working

conditions for its employees and their compliance with any safety rules contained herein or

established by the Contractor, and/or Prime Contractor; provided, however, it is understood that

the employees have an obligation as set forth in Section 2 of this Article below.

SECTION 2. Employees use diligent care to perform their work in a safe manner and to

protect themselves and the property of the Contractor and the Owner. The Contractors and the

Unions agree that the failure of employees to do so will be grounds for discipline, including

discharge.

SECTION 3. The Contractors and Unions acknowledge that employees covered by the

terms of this Agreement shall at all times while in the employ of the Contractor be bound by the

reasonable safety, security, and visitor rules as established by the Contractor with the consent of

the Union and with applicable state and federal safety and health statutes and regulations. These

rules will be published and posted in conspicuous places throughout the Project.

SECTION 4. For the purpose of providing maximum safety for all concerned, the Prime

Contractor may establish and implement, after consultation with the Council, reasonable substance

abuse testing procedures and regulations, which may include pre-hire and reasonable cause testing,

to the extent permitted or otherwise required by federal and state law.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 132: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

31

ARTICLE XV.

SECURITY OF MATERIAL, EQUIPMENT AND TOOLS

The inspection of incoming shipments of equipment, apparatus, machinery and

construction materials of every kind shall be performed by individuals selected by the Contractor,

at his or her discretion. All employees shall comply with the reasonable security procedures

established by the Prime Contractor and/or Contractor.

ARTICLE XVI.

NO DISCRIMINATION

SECTION 1. Each Contractor and Union agrees that they will not discriminate against

any employee or applicant for employment because of race, color, religious creed, age, sex, sexual

orientation, marital status, national origin, ancestry, gender identity or expression, present or past

history of physical or mental or intellectual disability or handicap, or veteran’s status in any manner

prohibited by law or regulation.

SECTION 2. Any complaints regarding application of the provisions of Section 1 of this

Article should be brought to the immediate attention of the involved Contractor for consideration

and resolution.

SECTION 3. The Contractors and the Unions agree to provide a workforce that complies

with all state and federal guidelines regarding minority hiring. Further, it is recognized that the

State of Connecticut has certain policies and commitments for the utilization of business

enterprises owned and/or controlled by minorities, women, the disadvantaged or others. The

Parties shall jointly endeavor to assure that these commitments are fully met and that any

provisions of this Agreement which may appear to interfere with any minority, women, or

disadvantaged owned business enterprise successfully bidding or subcontracting for work within

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 133: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

32

the scope of this Agreement shall be carefully reviewed, and adjustments made as may be

appropriate and agreed upon among the Parties to assure full compliance with the spirit and letter

of the policies and commitments of the State of Connecticut and all applicable federal, state and

Local rules and regulations relating to employment and utilization of such businesses.

SECTION 4. The use of the masculine or feminine gender in this Agreement shall be

construed as including both genders.

ARTICLE XVII.

WORKING CONDITIONS

SECTION 1. With the exception of one organized coffee break per day, there will be no

rest periods except when necessary for health and safety reasons. Individual coffee containers will

be permitted at the employee’s work location.

SECTION 2. There shall be no restrictions on the emergency use of any tools or

equipment by any qualified employee.

SECTION 3. The Contractor shall provide hard hats, safety glasses, foul weather gear and

other required personal protective equipment (PPE). The Unions shall ensure that employees will

exercise diligence in the care and custody of such safety gear provided.

SECTION 4. Employees engaging in willful or negligent acts that result in damage to any

property or facilities or injury to other employees will be subject to immediate termination.

ARTICLE XVIII.

SAVINGS AND SEPARABILITY

SECTION 1. It is not the intention of the Prime Contractor, any of the other Contractors

or the Unions to violate any laws governing the subject matter of this Agreement. The Parties

hereto agree that in the event any provisions of the Agreement are finally held or determined to be

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 134: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

33

illegal or void by order of any court of competent jurisdiction as being in contravention of any

applicable law, the remainder of the Agreement shall remain in full force and effect to the

maximum extent legally possible. Further, the Prime Contractor, all other Contractors and the

Unions agree that if and when any and all provisions of this Agreement are finally held or

determined to be illegal or void by a court of competent jurisdiction, the Parties will promptly

enter into negotiations in which the Owner may participate concerning the substance affected by

such decision for the purpose of achieving conformity with the requirements of an applicable law

and the intent of the Parties hereto.

SECTION 2. The Parties recognize the right of the Prime Contractor to withdraw, at its

absolute discretion, the utilization of this Agreement as part of any bid specification should a court

of competent jurisdiction issue any order, or any applicable statute be invoked which contains any

self-applying provision, either of which could result, temporarily or permanently, in delay of the

bidding, awarding and/or constructing of work on the Project. The Parties further recognize the

right of the Prime Contractor to terminate this Agreement at the direction of the State of

Connecticut or the Owner. Notwithstanding such action by the State of Connecticut, the Owner,

or such court order or statutory provision, the Parties agree that the Agreement shall remain in full

force and effect on the Project, to the maximum extent legally possible.

SECTION 3. The occurrence of events covered by Sections l and 2 of this Article shall

not be construed to waive the prohibitions of Article VII.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 135: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

34

ARTICLE XIX.

DURATION OF THE AGREEMENT

SECTION 1. This Agreement shall be effective on the date executed by the Parties and

shall continue in effect for the duration of the Project site preparation, demolition, dedicated off

site work and construction described in Article II hereof. Site preparation, demolition, dedicated

off site work and construction of any phase, portion, section or segment of the Project shall be

deemed complete when such phase, portion, section or segment has been turned over to the Owner

and has received the final acceptance from the appropriate Owner representative as designated by

Owner.

SECTION 2. The Schedule A’s incorporated into this Agreement shall continue in full

force and effect until the Prime Contractor and/or Union Parties to this Agreement and to the

Schedule A’s notify the Owner of the mutually agreed upon changes in those provisions of such

Schedule A’s which are applicable to the Project and their effective date(s), which shall become

the effective date(s) under this Agreement.

SECTION 3. Notwithstanding Section 2 of this Article, the Parties agree that any

provisions negotiated into said collective bargaining agreements will not apply to work on this

Project if such provisions are less favorable to the Contractor than those uniformly required of

contractors for construction work normally covered by those agreements; nor shall any provision

be recognized or applied on this Project if it may be construed to apply exclusively or

predominantly to work covered by this Agreement. Any disagreement between the Parties on this

issue shall be referred to an Arbitrator as provided in Article VIII, hereof.

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 136: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

35

SECTION 4. This Agreement may be amended or supplemented only by the mutual

consent of the Council, the Prime Contractor and the Unions, reduced to writing and duly signed

by each.

SECTION 5. The Union agrees that there will be no strikes, work stoppages, walkouts,

sympathy strikes, picketing, slowdowns or other interruptions or disruptive activity affecting the

Project by any Union involved in the negotiation of the subject Schedule A’s, nor shall there be

any lock-out on this Project affecting the Union during the course of such negotiations. Each

Contractor agrees to implement all applicable changes as negotiated in the Schedule A’s, except

as provided in Section 3 of this Article.

IN WITNESS WHEREOF the parties have caused this Agreement to be executed and

effective as of the ______day of ________________, 2021.

PRIME CONTRACTOR

__________________________________

Authorized Representative

THE NORWICH-NEW LONDON BCTC

By. �-=�-- Keith Brothers, President

ing andConstruction Norwich-New

Trades London

CouncilBuild

FINAL PLA GOLD STAR MEMORIAL BRIDGE

Page 137: SEPTEMBER 1, 2021 REHABILITATION OF THE GOLD STAR …

36

REHABILITATION OF GOLD STAR BRIDGE

STEEL STRUCTURAL STRENGTHENING

STATE PROJECT NO. 94-256 PROJECT LABOR AGREEMENT

ACCEPTANCE OF AGREEMENT

The undersigned Contractor who has been awarded work for State Project No. 94-256,

acknowledges that it has received and hereby accepts and agrees to be bound by the Project Labor

Agreement for the Rehabilitation of Gold Star Bridge, New London, Connecticut, State Project

No. 94-256 between ___________________ in its capacity as the Prime Contractor for the

Department of Transportation, the Norwich-New London Building & Construction Trades Council

and the individual signatory unions.

NAME OF EMPLOYER _________________________________________________________

ADDRESS ____________________________________________________________________

CITY, STATE, ZIP CODE _______________________________________________________

______________________________________________________________________________

Name and Title of Authorized Representative

______________________________________________________________________________

Signature of Authorized Representative Date

______________________________________________________________________________

Telephone number ______________________________________________________________

Fax Number ___________________________________________________________________

E-mail ________________________________________________________________________

FINAL PLA GOLD STAR MEMORIAL BRIDGE