september 26, 2002
DESCRIPTION
Process–Product Integrity Audit (PPIA) NASA Engineering Quality Audit (NEQA) Update. Presented by:. Ralph Kolts. September 26, 2002. Agenda. Some Background The Genesis of PPIAs PPIA Observations, Purpose, and Scope ATK Thiokol Propulsion’s PPIA and NEQA Experience - PowerPoint PPT PresentationTRANSCRIPT
September 26, 2002
Ralph KoltsPresented by:
Process–Product Integrity Audit (PPIA)NASA Engineering Quality Audit (NEQA)
Update
ATK THIOKOL PROPULSION
2
Agenda
Some Background The Genesis of PPIAs PPIA Observations, Purpose, and Scope
ATK Thiokol Propulsion’s PPIA and NEQA Experience Lessons Learned/Enhancements NEQA Results and Recommendations
Supplier PPIAs Experience Challenges and Action Plan
ATK THIOKOL PROPULSION
3
Background
During disassembly operations of a critical Space Shuttle component, it was discovered that some of the sub-assemblies were either missing or the wrong configuration
The part had gone through six different verification inspections without detection
Launch delays resulted while other units were disassembled and inspected
A “stand down” was ordered while a joint contractor/NASA team performed a line-by-line review of all production planning and related documents
Two problems surfaced: Planning documents did not always reflect actual shop practices or
engineering requirements Operators and inspectors did not view their stamps as a personal
warranty that the planning instructions had been followed
ATK THIOKOL PROPULSION
4
Stand Down / PPIA Observations
People perform tasks in a manner “they believe” makes sense and they are aware of things “they believe” are important.
Technicians performed tasks to the best of their ability, but they had given up on the change process Is the change request system responsive and timely?
Work instructions too detailed for craftsmen Techniques based on tradition, handed down from craftsman to craftsman Stamps and signatures used primarily as place-holders
How strong is “Stamp Warranty” awareness? Do people really feel free to stop because they can’t perform to literal text?
In-process redlines not incorporated Large number of sequence changes identified How often does Engineering review the process with performing personnel?
Are new tasks proofed? Do reworks/inserts get the same type of review and proofing?
ATK THIOKOL PROPULSION
5
Stand Down / PPIA Observations
Keys to a robust process: Pay attention to the changes – both intentional and unintentional Engineering must work closely with operators and be responsive to
problems and ideas High potential opportunities:
Repetitive tasks involving large number of small pieces New tasks inserted into a standard set of tasks (especially time,
temperature, pressure, materials) Long time span between repeat application of task High level of task variation permitted Limited direct interface between personnel setting requirements and
personnel performing tasks High dependence on inspection control of the task Low perceived consequences of not following literal text
ATK THIOKOL PROPULSION
6
Purpose of a PPIA
Match paperwork and practices – no disconnects Involves the people writing the planning and doing the
work A structured approach
Table top Process review Periodic validation and systems assessment
Reinforces stamp warranty
ATK THIOKOL PROPULSION
7
Scope of a PPIA
Processand Product
Integrity
Facilities andTooling
Equipment
SupportMaterials andDocuments
Drawingsand Specs
RawMaterials
Components
People
Work Instructions
ATK THIOKOL PROPULSION
8
ATK Thiokol Propulsion’sPPIA and NEQA Experience
ATK THIOKOL PROPULSION
9
PPIAs at ATK Thiokol Propulsion
PPIA program in place since 1993. Target is to audit 25% of RSRM processes each year.
PPIA effort offers intangible benefits Team building Re-enforces values Identifies and corrects system weaknesses Reduces process creep
Six steps to accomplish a PPIA review: Kickoff meeting Paper review Live review Table top with other affected team members Management review Incorporate changes/improvements
ATK THIOKOL PROPULSION
10
ATK Thiokol Propulsion’s PPIA History
YearProcesses
AuditedFindings
Cat 1 Cat 2 Cat 3 Totals
1994 61 0 115 3,785 3,900
1995 120 0 67 6,026 6,093
1996 69 0 56 3,336 3,392
1997 81 0 25 3,251 3,276
1998 67 0 37 2,222 2,259
1999 28 0 20 925 945
2000 86 0 43 3,259 3,302
2001 70 0 19 3,951 3,970
2002 63 0 18 1,680 1,698
Totals 645 0 400 28,435 28,835
ATK THIOKOL PROPULSION
11
Lessons Learned - Enhancements
Need to periodically reinvigorate PPIA efforts Ensure personnel are given the time and priority to
perform PPIAs Recent enhancements:
Leadership is now a required team member Strengthened involvement of operators (minimum of 2) Included an independent team facilitator Added a minimum quorum for team to proceed Strengthened work team involvement by convening a table
top review of the findings with other affected crew members Updated training for all PPIA team members
ATK THIOKOL PROPULSION
12
NEQA Results
0
10
20
30
40
50
60
Num
ber o
f Fin
ding
s
'94 '96 '97 '98 '99 '00 '01 '02Year
ATK THIOKOL PROPULSION
13
NEQA Systemic Recommendations
PPIA culture is alive and well – but: Operators/teams too close to processes to recognize that
specifics in planning are missed Categorization of findings has become too controversial,
emotionalizes the process, and dilutes overall objective Conversion of automated shop planning appears to create
opportunity for errors On-floor opportunities difficult to sync with NEQA week Support materials lack specifics in planning
ATK THIOKOL PROPULSION
14
Supplier PPIA Experience
ATK THIOKOL PROPULSION
15
Conducting a Supplier PPIA
ATK Thiokol Propulsion PPIA Mentor assigned Supplier Orientation Supplier Implementation Plan Assignment of Redline Teams and Redline Team
Training Phase I – Conducting the Audit
Table Top Review Process Review
Findings, Categories, and Corrective Action Phase II Final Report
ATK THIOKOL PROPULSION
16
Supplier PPIA Experience
There have been very effective and successful supplier PPIA results: 19 suppliers completed PPIAs (see following pages for details) A total of 86 different processes audited Over 1500 findings identified and fixed – an average of 83 potential
problems corrected 83% of the findings are Category 3 (minor) and 17% are Category 2
(fix before next use); no Category 1 findings (flight safety) Overall, these PPIAs were extremely successful with significant
results: many disconnects found and fixed, process ownership strengthened, communication improved, greater consistency achieved, and process repeatability enhanced
In other cases, various challenges have resulted in half hearted commitments, false starts, and missed schedules
ATK THIOKOL PROPULSION
17
ICI FiberiteASRCGSATParkerEatonAMPACRobradTaycoCourtauldsDodge RegupolALCOANylokAccurate Cal DoranKirkhillSTADCOCytec FiberiteAMPACGlenairTOTAL
Carbon ClothPolymerFastenersSeals/GasketsArming MonitorOxidizerVent Port PlugHeater/SensorPolysulfideCork SheetAluminum PowderNylon FastenerLSCHeat TreatRubberMachiningGlass ClothOxidizerHeater Cables
6295272259615149663
86
127293266290
3145289307331216414363850
1617
1578
NUMBER OFPROCESSES
NUMBER OFFINDINGSPRODUCTSUPPLIER
Supplier PPIA History
ATK THIOKOL PROPULSION
18
Categories of Supplier PPIA Findings
Category 10%
Category 217%
Category 383%
ATK THIOKOL PROPULSION
19
Challenges
There have been missed or slipped PPIA commitments and schedules. A number of factors contribute to this: Contracts are being completed, materials are being phased out,
new equipment/facilities/processes are being qualified, key personnel have changed
In some cases we have not received the full commitment by the supplier. Many suppliers are going lean – they don’t have the time or people to commit to the PPIA. In other cases, we’re a very small percent of the suppliers’ sales
The PPIA is a considerable commitment of resources for the supplier, including time, people, and . . . money
ATK THIOKOL PROPULSION
20
Supplier PPIA Action Plan
Actions have been taken to re-energize: Benefits discussed at Supplier Symposiums PPIA mentor training class PPIA web page Suppliers identified and targeted for PPIAs Quarterly status review meetings
Further actions: Keep awareness, visibility, and commitment high PPIAs will be a component of overall supplier management plans
We are looking for a good opportunity to pursue funding options or other incentives to assist the supplier in offsetting costs