serbia's activities in the field of res - unece · 2011 - the law on energy sector (ii package and...
TRANSCRIPT
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Serbia's activities in the field of RES
Miloš Banjac, Ph.D., Assistant Minister
The Ministry of Mining and Energy of the Republic of Serbia
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
1. Commitments in the field of RES
2. Efforts of MME
3. Key obstacles for implementation of RES projects
4. Achieved results
5. Additional efforts – projects
Contents
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Decision of the Council ofMinisters D/2012/04/MC-EnC, of9 July 2012 – Transposition ofDirective 2009/28/EC onrenewable energy sources
• Increase the share of RES in consumption from 21.2% in 2009 to 27 % by 2020 (5.8%)
• Increase the share of fuel of bio orign in the transport sector from 0% in 2009 to 10 % in 2020.
Commitments in the field of RES
The commitments result from membership in the Energy Community
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Commitments
0
10
20
30
40
50
60
Comparison % RES relative to EU members states
EU target for 2020
20% RES
EU target for 2030
27% RES
Commitments in the field of RES
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Steps undertaken for fulfilment of commitments
2004 – The Law on Energy Sector (I package)
For RES
2009 - „Feed-in“ tariff system and status of privileged electricity producer, definition of free capacities for the use of „wind“ and „solar“
2010 – Action Plan for Biomass adopted
2011 - The Law on Energy Sector (II package and the minor part of III package)
Directive on RES - partially
2013 – National Action Plan for RES of the Republic of Serbia
2014 - The Energy Law (the whole III package)
Directive on RES - fully
2015 – National Strategy of Development of the Energy Sector by 2025 with projections until 2030
2016 - New Regulations on incentives for privileged power producer
Commitments in the field of RES
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
New Decree on Incentives for Electricity Production
7.58.22
15 15
8.449.2 9
8.2
12,613,26
18,33 18,33
14,6
0
5
10
15
20
25
Hydro powerplant
Biomass powerplant
Biogas powerplant
Plant fired bybiogas from
animal originwaste
Landfill andsewage gas power
plant
Wind powerplants
Solar power plant Geothermalpower plants
c€/k
Wh
„Feed-in tariff“ systems
Efforts by the Ministry
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
1. Decree on power purchase agreements („Official Gazette RSˮ, No. 56/16) New Models of Power Purchase Agreement
2. Decree on incentives for electricity production from renewable energy sources and high-efficiency power and heat co-generation („ Official Gazette RSˮ, No. 56/16)
3. Decree on requirements and procedure for acquiring the status of privileged electricity producer, preliminary privileged electricity producer and producer of electricity from RES („ Official Gazette RSˮ, No. 56/16)
4. Decree on guaranteeing origin ("Official Gazette of RS", No. 82/17)) - "Green certificates"
New efforts by the Ministry
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
WIND POWER MONTHLY
First due diligence assessment very positive by C.M.S
“ It was worth the wait!!!”“ The result is a consistent, comprehensive and, at least on the face of it, bankable set of regulations to govern the renewable sector in Serbia in a manner which appears to be unmatched in the entire Western Balkan region in terms of both the quality of drafting and the completeness of the solutions implemented. ”“ Overall, the newly adopted PPA Package is a great step forward for renewables in Serbia.”http://balkangreenenergynews.com/long-awaited-ppa-package-finally-adopted-in-serbia/
"You can clearly see they are the result of lengthy discussions with the international financial institutions, which is important, but something you don't see very often.“
http://www.windpowermonthly.com/article/1403500/new-legislation-paves-500mw-wind-farms?utm_source=Viber&utm_medium=Chat&utm_campaign=Private
Efforts by the Ministry
http://balkangreenenergynews.com/long-awaited-ppa-package-finally-adopted-in-serbia/
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
0
10000
20000
30000
40000
50000
60000
70000
80000
90000
EU
R
GDP per capita in EUR (2012) Eurostat
Average in EU 27 500 EUR
Serbia 4 100 EUR
Key obstacles to implementation of RES projects
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
29,46 c€/kWh
6,54 c€/kWh
19,58 c€/kWh
5,65,13 c€/kWh
2500 – 5000 kWh/year
500 – 2000 MWh/year
Price of electricity 2016
Key obstacles to implementation of RES projects
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Lack of reliable data
– on where are and how big are economically viable RES potential.
– the lack of planning documents determined the mode how to use of land
(Spatial Plan of the Republic of Serbia, Regional Spatial Plans, Spatial
Plans of the unit of local administration, General Urban Plan, General
Regulation Plan).
Key obstacles to implementation of RES projects
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
• Inadequate credit rating (2016: Moody's B1 - positive, Fitch: BB - stable) macroeconomic indicators, political stability, stability of the banking sector (SPECULATIVE GRADE – ability to achieve financial obligations, risk of change in the business environment and economic conditions, considerable credit risk)
• Insufficient trust of IFI’s (banks) and investors in the national legal system and legal protection
Uncertainty of investment
Key obstacles to implementation of RES projects
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Temporaray status of PP483 MW (16,6 mil EUR)
Energy permits80 MW
Plan and implementation for electricity
Results achieved
Action plan Constructed
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Large jumps and achievements of goals are largely based on the construction of
500 MW wind farms, from which already Kula 9.9 MW and La Piccolina 6.6 MW,
MalibuNar, 8 MW have already been played, and the remaining ones are to be
built:
1. Alibunar, 42 MW
2. Plandište 1, 102 MW
3. Kovačica 104.5 MW
4. Cibuk 1, 158.5 MW
5. Kosava, 68 MW
6. Wind farm in Kostolac (EPS) 66 MW
Results achieved
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Power plants on RES constructed
Type of power
plant
2014 2015 2016 2017
[number] [MW] [number] [MW] [number] [MW] [number] [MW]
HPP 0 0 0 0 0 0 0 0
SHPP up to 10
MW
46 35 54 38 65 43,567 78 45,7
Biomass 0 0 0 0 0 0 0 0
Biogas 5 4,9 5 4,9 9 10,332 10 12,2
Wind 1 1 1 1 3 17 4 25
Solar 86 7,2 97 8,6 106 8,786 106 8,786
Results achieved
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
"Development of biomass energy market for energy production" (2014-2018)
funded by the Global Environment Fund (GEF) and UNDP in the amount of
3,15 mil. USA $.
Additionally subsidized construction of six biogas plants
Additional effort
Изаграђена постројења
1 БГС ГАМА БП ДОО Бач 0,65 MW
2 БГС БЕТА БП ДОО Бач 0,65 MW
3 Биогас Енергy доо Село Иланџа, општина Алибунар 3,57 MW
4 Биоелектра доо Ботош, Зрењанин 0,60 MW
У изградњи
5 БГС АЛФА БП ДОО (у изградњи) Бач 0,65 MW
6 ФОРКОМ ДОО,БЕОГРАД Алексинац 0,2 MW
Укупна снага 6,32 MW
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
The first phase of the project will include the municipalities of Mali Zvornik,
Nova Varos, Novi Pazar, Prijepolje, Bajina Basta, Valjevo, Priboj, Kladovo
and Majdanpek and Bečej
Project: „Promotion of Renewable Energies: Developing the Biomass
Market in the Republic of Serbia“ KfW, SECO, I phase 27 mil EUR
Additional effort
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
• Efficient use of wood for heating in households
• Promotion of small energy cooperatives (community) in villages
• Construction of mini boiler rooms in schools
„Project: „Promotion of Renewable Energies: Developing the Biomass
Market in the Republic of Serbia“, GIZ
Additional effort
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Project: Cadastre of small hydropower plants IPA 2013 (EUR 1.6 million)
Additional effort
Expected results:• clearly defined locations with energy
potential and technology for the best use of each location in terms of energy efficiency and environmental protection for HPPs between 100 kV and 10 MW
• Web application Cadastre MHE
-
Ministry of Mining and Energy of the Republic of Serbia September 2017
Thank you for your [email protected]
mailto:[email protected]