serving the armed forces and the nation minersville ......huntington district one team—relevant,...

28
Serving the Armed Forces and the Nation Minersville Ohio Minersville Ohio Minersville, Ohio Riverbank Stabilization Minersville, Ohio Riverbank Stabilization A C Hi t A C Hi t A Case History A Case History Lisa Gatens E I Lisa Gatens, E.I. Seth Lyle, P.E. U.S. Army Corps of Engineers Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch Huntington, West Virginia

Upload: others

Post on 14-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Minersville OhioMinersville OhioMinersville, OhioRiverbank Stabilization

Minersville, OhioRiverbank Stabilization

A C Hi tA C Hi tA Case HistoryA Case History

Lisa Gatens E ILisa Gatens, E.I.Seth Lyle, P.E.

U.S. Army Corps of EngineersHuntington District

One Team—Relevant, Ready, Responsive, Reliable

Geotechnical BranchHuntington, West Virginia

Page 2: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Presentation OutlinePresentation Outline

1. Background2 Ch ll2. Challenges3. Investigations4. Remedial Measures5. Summary6. Recommendations7. Questions7. Questions

One Team—Relevant, Ready, Responsive, Reliable

Page 3: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

WHAT?WHAT?Section 14 of the 1946 Flood Control Act Section 14 of the 1946 Flood Control Act

(Public Law 79-526)• Authority for USACE to plan and construct flood Authority for USACE to plan and construct flood

damage related emergency streambank and shoreline protection projects.

• Critically essential public facilities (highways • Critically essential public facilities (highways, sewer lines, schools, etc.)

• Federal costs limited to $1.5M for each project.• Projects accepted after an investigation of

relocation alternatives, engineering feasibility, environmental acceptability, and economic

One Team—Relevant, Ready, Responsive, Reliable

justification.

Page 4: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

WHO?WHO?

♦ USACE (federal goverment)♦ ODOT (non-federal sponsor)♦ ODOT (non federal sponsor)

● First $100K of study funds are 100% federally funded.100% federally funded.

● Remainder is 65% federally funded and 35% sponsor funded, not to % p ,exceed $1.5M.

One Team—Relevant, Ready, Responsive, Reliable

Page 5: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

WHERE?WHERE?WHERE?WHERE?

- Upper right descending bank of Ohio River (River Mile 248.5)

One Team—Relevant, Ready, Responsive, Reliable

- Upstream of Pomeroy, OH.

- 2400 LF reach along State Route 124 (Mile 23).

Page 6: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

WHY?WHY?Constructed to address retaining wall collapse, Constructed to address retaining wall collapse, top-of-bank retreat, and related roadway failures.

One Team—Relevant, Ready, Responsive, Reliable

Page 7: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

WHEN?WHEN?

Construction commenced in September 2003 and was completed in October 2004.

One Team—Relevant, Ready, Responsive, Reliable

Page 8: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

P j t S ifiP j t S ifiProject SpecificsProject Specifics♦ Total Cost: $2.5 M♦ Length: 2400 ft.♦ Bank Height: 30 ft.♦ Total Stone: 80,000 tons♦ Stone Grad.: 24” top size♦ Excavation: 20,000 CY♦ Excavation: 20,000 CY♦ SSP thickness: 6 to 20 ft.♦ SSP riverward slope: 1.5H:1V ♦ Toe key: Avg. 5 – 15 ft. wide

B Wid h 20 30 f♦ Base Width: 20 – 30 ft.

One Team—Relevant, Ready, Responsive, Reliable

Page 9: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Ohi Ri R ilOhi Ri R ilOhio River RailwayOhio River Railway

Railway car system extended 12 miles along the Ohio River . Built in 1900.g

Failed stone wall & exposed

RR ties

Photo from

One Team—Relevant, Ready, Responsive, Reliable

downtown Pomeroy, Ohio

Page 10: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Ab d d C l MiAb d d C l MiAbandoned Coal MinesAbandoned Coal Mines

Overview of Abandoned Underground Coal Mines, Meigs County, Ohio

Abandoned Underground Mines, Minersville, OH= underground mines

= underground mine extent partially unknown

, g y,

Project

ProjectLocation(2400 LF)

Project Location

Drift Entry

Air Shaftf

One Team—Relevant, Ready, Responsive, Reliable

More than 40,000 acres of abandoned underground coal mines located up dip of project. 14 separate mines. Some sealed during the WPA days.

Page 11: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Ab d d C l Mi & R l t d D iAb d d C l Mi & R l t d D iAbandoned Coal Mines & Related DrainageAbandoned Coal Mines & Related Drainage

Top of coal unit (Pomeroy Seam ~ 4 to 5 ft. thick) beneath Pomeroy SandstoneSandstone

- Relic drainage features noted landward of project reach.

- Collapsed vault structure noted on landward side of SR 124 in displaced reach.

One Team—Relevant, Ready, Responsive, Reliable

- Cross drains through roadway were not functional.

Page 12: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Construction ChallengesConstruction Challenges

S Ohi Ri fl d♦ Seven Ohio River flood events inundated the roadway during construction.

♦ Barges got loose from tow and ran up on roadway damaging shoulder.

One Team—Relevant, Ready, Responsive, Reliable

Page 13: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Sta 13+50

Displaced ReachDisplaced Reach

Sta. 13+50Sta. 16+00

One Team—Relevant, Ready, Responsive, Reliable

Page 14: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Investigations♦ Post construction surveys

- As-Built (April 2004) - 10 June 2004- 10 June 2004- 15 June 2004- 16 July 2004- 3 Jan. 2005

8 A 2006

ODOTBORING

- 8 Aug. 2006

♦ ODOT borings (Nov. 04)

B-4

♦ USACE borings (July 06)

♦ Bathymetric surveys (2002 and July 2006)(Note: 2002 bathymetric survey data limited; sections taken every 500’ along

One Team—Relevant, Ready, Responsive, Reliable

♦ Review of Historic Mapping

( y y ; y griver; only one x-section within study reach at approx. Sta. 15+60)

Page 15: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Typical Section

One Team—Relevant, Ready, Responsive, Reliable

Page 16: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Section including July 2006 Bathymetric Survey

EL. 520

thalweg

- Survey sections at 25 to 50 ft. increments from station 12+50 to 17+00.

One Team—Relevant, Ready, Responsive, Reliable

y

- Bathymetric survey performed at same sections as bank sections and at upstream and downstream limits of project, as well as parallel to bank for length of project.

Page 17: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation1911-1914 Ohio River Survey

N

ROCK WALL 530

PROJECT LOCATIONOHIO RIVER ELECTRIC RAILWAY

SAILING LINE

L&D No. 25 Pool = 528.5’ m.s.l.

One Team—Relevant, Ready, Responsive, ReliableRock outcrop

“ROCK 520”

R.C. Byrd L&D Pool = 538.0’ m.s.l(1937 to present)

Page 18: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Pre (2002) vs. Post (2006) ConstructionBathymetric Surfaces Sta. 15+70

2002 surface

2006 surface

- 2002 survey sections performed in 500 ft increments along entire reach of RCB L&D pool

One Team—Relevant, Ready, Responsive, Reliable

- 2002 survey sections performed in 500 ft. increments along entire reach of RCB L&D pool.

- Survey sections within project reach are located at approximately Sta. 4+50, 10+00, 15+70, and 21+50.

Page 19: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Former Tipple Location in Project Reach

1935 Ohio River Navigation Chart

Former tipple location &displaced reach of project

~ Ohio River Mile 248.3

-Note:“In the nineteen twenties, Grant Hood build a large coal tipple in the west end of town (Minersville). . . . Later the tipple was moved down river a short distance beside the Pomeroy Water Works.”

One Team—Relevant, Ready, Responsive, Reliable

Reference:Meigs County Historical SocietyMeigs County History Volume IPg. 18, Minersville History

Page 20: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Relic Coal Transfer Points

Relic transfer pointsRelic transfer points(displaced SSP located between these points)

One Team—Relevant, Ready, Responsive, Reliable

Page 21: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

SELECTED ALTERNATIVE

Treatment Alternatives

♦ Excavation and Reconstruction : did not adequately address probable failure mechanism; costly temporary shoring and sheeting required

Sheet Pile Wall w/King Piles:Cost effective; Reduces risk related to inability of driving sheet piling due to subsurface obstructions.

costly temporary shoring and sheeting required during excavation due to risk of failure of roadway.

♦ Drilled Shaft Wall : uncertainties related to soil arching effect of slag/cinders/refuse between shafts; estimated cost greater than sheet pile wallshafts; estimated cost greater than sheet pile wall

♦ Post and Panel Wall : prohibitively expensive due to excavation and backfill costs (double handling of stone); would require temporary shoring measures during excavation.g g

♦ Sheet Pile Wall : Cost effective alternative; some risk involved with potential subsurface obstructions (boulders, relic stone wall) and vibration related concerns. Detail taken from: www.lbfoster.com/

One Team—Relevant, Ready, Responsive, Reliable

Page 22: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Sheet Pile WallTypical Section

One Team—Relevant, Ready, Responsive, Reliable

Page 23: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Pile Driving

3 vibratory hammers used during driving (2 failed during driving)

Initially unable to driveInitially unable to drive 7 sheets to required depth; encountered large boulders (sandstone blocks); Able to re drive sheetsAble to re-drive sheets with larger hammer

Drove sheet thru areas of N=50+ blow counts to top of sandstone bedrock.

One Team—Relevant, Ready, Responsive, Reliable

Page 24: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Vibration Monitoring

♦ Vibration related concerns♦ Vibration related concerns stemming from prior litigation following original Sec. 14 project construction.

♦ Pre and post inspection surveys l d ll dj icompleted on all adjacent properties

by private contractor specialist.♦ Glass rods installed on foundation

blocks.

♦ Ground vibration monitoring throughout construction via seismic instruments.

♦ Ground vibrations never exceeded♦ Ground vibrations never exceeded 10% of allowable horizontal accelerations.

♦ No structural changes from ground vibrations as the results of the

One Team—Relevant, Ready, Responsive, Reliable

project. No complaints from residents.

Page 25: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Drainage Interception and Control

♦ >40,000 acres of abandoned coal mines up dip of SR 124.

♦ Mine discharge storm event runoff and♦ Mine discharge, storm event runoff, and Ohio R. inundation cannot be fully addressed by sizing collection structures and cross drains.

♦ Collapse of an adjacent collection vault (20 x 6 x 4 ft.) and blockage of cross drains was the most significant cause of displacement of SSP.displacement of SSP.

♦ ODOT completed repairs of the vault cover.

USACE C d d

One Team—Relevant, Ready, Responsive, Reliable

♦ USACE Contractor reconstructed drop inlets and cross drains.

Page 26: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Project Summary♦ 2400 LF of bank stabilization complete for $2.5 million; ~80,000 tons of stone, 30

ft. high bank g

♦ 280 LF reach of project failed prior to final inspection and was subsequently repaired by installation of a sheet pile wall and reconstruction of drainage interception and control features; work funded entirely by ODOT ($1.2 million)

♦ Complete project is functioning as designed. Numerous storm and high water events have occurred since completion.

One Team—Relevant, Ready, Responsive, Reliable

Page 27: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

General Recommendations♦ Perform comprehensive evaluation of site

diti i l di li t t dcondition including relic structures and history of land use and failures.

♦ Subsurface explorations are necessary to properly characterize the site.

♦ Establish foundation requirements; Key-in SSP treatment & place on suitable filter and/or in-place soils.

♦ Review hydrometerological data and♦ Review hydrometerological data and perform construction during historical low water/rainfall periods.

Conclusions♦ Riverbank projects are complex. There

are inherent risks building along rivers.

♦ Retain a team of experienced f i l f d i d t ti

Conclusions

One Team—Relevant, Ready, Responsive, Reliable

professionals for design and construction.

♦ Use an experienced contractor with supervisory and inspection staff.

Page 28: Serving the Armed Forces and the Nation Minersville ......Huntington District One Team—Relevant, Ready, Responsive, Reliable Geotechnical Branch ... First $100K of study funds are

Serving the Armed Forces and the Nation

Questions??Questions??

Credits

♦ Ohio Department of Transportation (ODOT) District 10

Credits

District 10

♦ Madison Coal & Supply (Construction Contractor)

♦ Michael F. Spoor (USACE Lead Engineer)

USACE C t ti♦ USACE Construction Division

One Team—Relevant, Ready, Responsive, Reliable