settlements of an embankment founded on a soft soil … · settlements of an embankment founded on...

6
SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL Pavel Zvanut ZAG - Slovenian National Building and Civil Engineering Institute, Dimiceva 12, 1000 Ljubljana, Slovenia Abstract The construction of a pre-loading embankment was begun in December 2001. The total height of the embankment, which remained in place until March 2002, was 9 m, and it was founded on a marshland soft soil. Because of the nature of the foundation soil, a monitoring system was installed in order to assess the embankment settlements. The measurements of settlements were obtained by field instrumentation, which consisted of ten settlement plates, enabling optical levelling measurements at these points, and one measuring tube, which was installed beneath the embankment and used to assess the settlement profile of the embankment using a hydrostatic profile gauge. The settlements measured by the hydrostatic profile gauge showed a continuous increase in the vertical displacement after the end of construction for approximately half a year. The maximum measured settlement was 43 cm. It was shown that the results are very similar to those observed on settlement plate SP-3, which was located very close to the measuring tube. The use of a measuring tube and a hydrostatic profile gauge, which do not interfere with the construction works, proved to be a very practical solution. 1. Introduction The location of the embankment was on the Barje marshland, just a few kilometres south of the city of Ljubljana (see Figure 1). Because of the nature of the foundation soil, a monitoring system was installed in order to assess the embankment settlements. Settlement measurements indicated the time which needed to elapse before removal of the temporary surcharge load. It was the first time in Slovenia that a hydrostatic profile gauge was used to measure settlements at a selected profile beneath the embankment (the length of the measuring tube was 80 m). Before this, only settlement plates - consisting of a steel square plate, placed on the original ground surface, to which a riser pipe is attached which, in turn, permits optical levelling measurements to be taken - to measure settlements of embankments were used. Figure 1. Location of the pre-loading embankment Proceedings, 11 th FIG Symposium on Deformation Measurements, Santorini, Greece, 2003.

Upload: vuminh

Post on 22-Aug-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL … · SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL Pavel Zvanut ZAG - Slovenian National Building and Civil Engineering

SETTLEMENTS OF AN EMBANKMENTFOUNDED ON A SOFT SOIL

Pavel Zvanut

ZAG - Slovenian National Building and Civil Engineering Institute,Dimiceva 12, 1000 Ljubljana, Slovenia

Abstract

The construction of a pre-loading embankment was begun in December 2001. The total heightof the embankment, which remained in place until March 2002, was 9 m, and it was founded ona marshland soft soil. Because of the nature of the foundation soil, a monitoring system wasinstalled in order to assess the embankment settlements. The measurements of settlements wereobtained by field instrumentation, which consisted of ten settlement plates, enabling opticallevelling measurements at these points, and one measuring tube, which was installed beneaththe embankment and used to assess the settlement profile of the embankment using ahydrostatic profile gauge. The settlements measured by the hydrostatic profile gauge showed acontinuous increase in the vertical displacement after the end of construction for approximatelyhalf a year. The maximum measured settlement was 43 cm. It was shown that the results arevery similar to those observed on settlement plate SP-3, which was located very close to themeasuring tube. The use of a measuring tube and a hydrostatic profile gauge, which do notinterfere with the construction works, proved to be a very practical solution.

1. Introduction

The location of the embankment was on the Barje marshland, just a few kilometres south of thecity of Ljubljana (see Figure 1). Because of the nature of the foundation soil, a monitoringsystem was installed in order to assess the embankment settlements. Settlement measurementsindicated the time which needed to elapse before removal of the temporary surcharge load. Itwas the first time in Slovenia that a hydrostatic profile gauge was used to measure settlements ata selected profile beneath the embankment (the length of the measuring tube was 80 m). Beforethis, only settlement plates - consisting of a steel square plate, placed on the original groundsurface, to which a riser pipe is attached which, in turn, permits optical levelling measurementsto be taken - to measure settlements of embankments were used.

Figure 1. Location of the pre-loading embankment

Proceedings, 11th FIG Symposium on Deformation Measurements, Santorini, Greece, 2003.

Page 2: SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL … · SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL Pavel Zvanut ZAG - Slovenian National Building and Civil Engineering

2. Embankment construction

Construction of the pre-loading embankment, which was founded on a compressible marshlandsoft soil, was begun in December 2001 (see Figure 2). It remained in place until March 2002(see Figure 3). The lower strata of the embankment were 3 m high and made from ash from athermo-electric power plant, whereas the upper strata, made from the crushed stone, were 6 mhigh. The total height of the embankment was thus 9 m.

Figure 2. The embankment at an early stage of construction

Figure 3. The completed embankment

3. Field instrumentation

Settlements were measured by means of field instrumentation, which consisted of 10 steelsettlement plates (SP-1 to SP-10), laid in 3 lines across the embankment, and 1 plasticmeasuring tube (MT-3, length = 80 m), placed at the selected profile (see Figure 4). Thesettlement plates were installed at the bottom of the lower stratum of the embankment, justahead of the start of the construction works. The measuring tube was placed in an ash stratum,

Page 3: SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL … · SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL Pavel Zvanut ZAG - Slovenian National Building and Civil Engineering

about 1.0 m below the crushed stone embankment, after the ash embankment had beencompleted (see Figure 5). Movement of the plates was determined by conventional geometriclevelling, whereas the vertical movement of the tube, at points 0.5 m apart, was monitored usinga hydrostatic profile gauge.

MT 3

MT - 3L= 80 m

SP 3 - SETTLEMENT PLATE- MEASURING TUBE

A

SP 1

SP3

SP 8SP 2

SP 7

SP 4

SP 5

SP 6

SP 10

SP 9

A

LINE 1

LINE 2

LINE 3

Figure 4. Field instrumentation of the embankment – plan

m a.s.l.

300

299

298

297

296

295

294

293

292

291

290

CRUSHEDSTONEEMBANKMENT

ASH EMBANKMENT

MT - 3 L = 80 m

FILTER STRATUM

MARSHLAND SOFT SOIL

SP 10 SP 2 SP 7SP 4 SP 6SP 5 SP 3

0 10 m

CRUSHED STONEEMBANKMENT

H = 6 m

Figure 5. Field instrumentation of the embankment – cross section A-A

Page 4: SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL … · SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL Pavel Zvanut ZAG - Slovenian National Building and Civil Engineering

3.1 The hydrostatic profile gauge

The hydrostatic profile gauge consisted of a control unit, a readout unit and a length of tripletubing connected to a settlement probe, which can be pushed (with aluminium rods) or pulled(with a draw-cord) through the access tube (see Figures 6 and 7). Two of three small tubes arefilled with water and are constantly back-pressurized in order to overcome surface tensioneffects, and to prevent the formation of bubbles. Measurements of elevation are taken at regularintervals in an access tube, which is laid in a sand-filled trench. The hydrostatic head at theprobe 'H' is measured with the aid of a differential pressure transducer. These readings arerelated to a reference pin outside the tube and in this manner a complete profile of the tube canbe established. By comparing profiles taken at different times, the vertical displacement of thetube can be determined to an accuracy of ± 1.0 cm, which is excellent for this application.

Figure 6. Schematic arrangement of the hydrostatic profile gauge

Figure 7. Measurement using the hydrostatic profile gauge (the probe is being pushed)

Page 5: SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL … · SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL Pavel Zvanut ZAG - Slovenian National Building and Civil Engineering

4. Results

4.1 Settlement profiles at different times along the measuring tube

Figure 8 shows the settlements measured using the hydrostatic profile gauge along themeasuring tube MT-3, at points 0.5 m apart, at different times since the 1st measurement. Thesettlements showed a continuous increase in vertical displacement after the end of constructionfor approximately half a year. It can be seen that, 256 days after the 1st measurement, themaximum measured settlement was 43 cm.

80706020 30Distance (m)

40 50

end of construction

256 days

135 days

95 days

78 days

57 days

11 days

0

0

-1010

50

20

30

10

40

Se

ttle

ment

(c

m)

Figure 8. Settlement profiles at different times (since the 1st measurement) along the measuringtube MT-3

4.2 Comparison of settlement development measured using 2 different methods

Figure 9 shows a comparison of settlement development measured in the measuring tube MT-3with the settlements observed on plate SP-3, which was located very close to the tube (seeFigure 4), and progress of the embankment construction. The measurements were not all carriedout at the same time, and the measuring tube was installed about 2 m above the mentionedsettlement plate (see Figure 5), which had problems connected with the attachment of riser pipesand also with movements due to the effect of site transport. In spite of all this a comparison ofthe two different methods shows that the magnitude of the measured settlements and thesettlement development are very similar.

Page 6: SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL … · SETTLEMENTS OF AN EMBANKMENT FOUNDED ON A SOFT SOIL Pavel Zvanut ZAG - Slovenian National Building and Civil Engineering

0

5

10

15

20

25

30

35

40

45

50

dec-01 feb-02 apr-02 jun-02 avg-02 okt-02Date

Se

ttle

me

nt

(cm

)

0

1

2

3

4

5

6

7

8

9

10

He

igh

t o

f th

e e

mb

an

kme

nt

(m

)

Measuring tube (MT-3)

Settlement plate (SP-3)

Construction of embankment

Figure 9. Settlement development measured using 2 different methods, compared to theprogress of embankment construction

5. Conclusions

The use of a measuring tube and a hydrostatic profile gauge, which do not interfere with theconstruction works, proved to be a very practical solution. The result is not only a singlesettlement (like that measured using a settlement plate), but also the settlement profile, obtainedusing a measuring tube. There were some difficulties connected with the settlement plates (theattachment of riser pipes, movement because of the effect of site transport, etc.). In future, themonitoring system for embankment settlements will be improved with the replacement ofsettlement plates by measuring tubes monitored using a hydrostatic profile gauge.

References

Fahel, A.R.S., Palmeira, E.M. and Ortigao, J.A.R. (2000). Behaviour of geogrid reinforcedabutments on soft soil in the BR 101-SC Highway, Brazil. GeoDenver 2000, Advances inTransportation and Geoenvironmental Systems Using Geosynthetics, Denver, USA, 257-270.

Herle, I. and Herle, V. (2001). Road construction on a soft organic subsoil. XVth InternationalConference on Soil Mechanics and Geotechnical Engineering, Istanbul, Turkey, 2081-2084.

Steenfelt, J.S., Jorgensen, M.B. and Jorgensen, P.O. (1999). Preloaded motorway embankments– an environmentally sound solution for soft soil areas. XIIth European Conference onSoil Mechanics and Geotechnical Engineering, Amsterdam, The Netherlands, 1583-1592.

Zvanut, P. (2002). Report No. P74/02-730-1 on settlement measurements using a hydrostaticprofile gauge on the Barje marshland. ZAG, Ljubljana, Slovenia (in Slovenian).