    2020 - 2049

  • Abbreviations

    AAS Australian Accounting Standard

    ADWG Australian Drinking Water Guidelines

    AHD Australian Height Datum

    BOD Biological Oxygen Demand

    BPM Best-Practice Management (NSW Department of Industry (Water) Planning Framework for LWUs)

    CCTV Closed Circuit TeleVision

    CWP Capital Works Program

    DCP Development Control Plan

    DSP Development Servicing Plan

    EP Equivalent Population

    EPA NSW Environmental Protection Agency

    ET Equivalent Tenement

    FINMOD NSW Financial Planning Model (developed by NSW Department of Industry (Water))

    I/I Inflow and Infiltration

    IPART NSW Independent Pricing and Regulatory Tribunal

    IWCM Integrated Water Cycle Management

    kL Kilolitre (1,000 litres)

    LOS Levels of Service

    LTW Liquid Trade Waste

    LWU Local Water Utility

    ML Megalitre (1,000,000 litres)

    OCC Orange City Council

    p.a. per annum

    SBP Strategic Business Plan

    SPS Sewage Pump Station

    TBL Triple Bottom Line

    TRB Typical Residential Bill

    WHS Work Health and Safety

    WTP Water Treatment Plant (also: Water Filtration Plant)

    WWTP Wastewater Treatment Plant (also: STP – Sewage Treatment Plant)

  • TABLE OF CONTENTS

    1 Executive Summary ......................................................................................................................... 2

    2 Strategic Objectives ......................................................................................................................... 4

    3 Services Provided ............................................................................................................................. 6

    3.1 Orange Sewerage Scheme ..................................................................................................... 6

    3.2 Spring Hill and Lucknow Sewerage Scheme ........................................................................... 7

    3.3 Recycled Water Scheme ......................................................................................................... 8

    4 Levels of Service ............................................................................................................................. 10

    5 Condition of Our Assets ................................................................................................................. 13

    6 Operational Plan ............................................................................................................................ 16

    7 Maintenance Plan .......................................................................................................................... 19

    8 Capital Renewal Plan ..................................................................................................................... 21

    9 Capital Upgrade & Expansion Plan ................................................................................................ 25

    10 Asset Rationalisation and Disposal Plan ........................................................................................ 27

    11 Financial Plan ................................................................................................................................. 28

    11.1 Summary of Model Inputs.................................................................................................... 29

    11.2 Sewer Fund Model Results ................................................................................................... 32

    12 Key Performance Measures ........................................................................................................... 38

    13 Risk Management Plan .................................................................................................................. 39

    14 Performance Review and Proposed Improvement Plan ............................................................... 41

    Appendix A: Operations and Maintenance Programs ........................................................................... 42

    Appendix B: Four Year Renewal Programs 2019-2022 .......................................................................... 46

    Appendix C: 30 Year Capital Works Program ........................................................................................ 51

    Appendix D: 30 Year Financial Plan ....................................................................................................... 53

    Appendix E: Sewerage Performance TBL Report.......................................................................................

    Document Control

    Rev No Date Revision Details Author Verifier Approver

    1 19/03/2020 Draft AMP 2020 SM WB

    Note: All figures expressed in this plan are in 2019/20 real (current) terms and NOT adjusted for inflation unless otherwise stated.

  • Sewerage Asset Management Plan

    Orange City Council Page 2

    1 Executive Summary

    Orange City Council’s intention is to provide the City with a sewerage network that is serviced and maintained

    to a level which reflects the community’s expectations and operates in a manner that is both functional and

    cost effective. The sewerage asset portfolio had a fair value of $236,866,000 at 30 June 2019.

    This plan assists Council in the decision making process and is presented at a high level to provide key

    information that can be used in the determination of levels of service and funding required.

    This plan’s primary objective is to meet the adopted Levels of Service, which cover the following areas:

    Wastewater quality and protection of the environment

    Availability and capacity of wastewater services

    Response times for system failures

    Note that the Levels of Service are the targets which Council aims to meet; they are not intended as a formal

    customer contract. Council’s performance in these areas is also presented in Section 12 – Performance

    Measures.

    Table 1-1 identifies the asset categories in this plan, the thirty year average costs and funding gap if one exists

    between available renewal budget and predicted renewal requirements.

    Table 1-1: Sewerage Asset Portfolio Overview 2020-2049 (30yr Average Annual Costs)

    Asset Renewal Upgrade & New Funding Gap Backlog 2020 Backlog 2049

    Sewer Treatment Plant 765,000 312,000 529,000 -543,000 15,861,000

    Sewer Pump Stations 140,000 121,000 255,000 6,000 7,647,000

    Sewer Rising Mains - - 598,000 745,000 17,945,000

    Sewer Trunk Mains - - 214,000 3,909,000 6,428,000

    Sewer Reticulation Mains 700,000 330,000 -69,000 2,582,000 -2,075,000

    Sewer Vents 8,000 - 15,000 -42,000 450,000

    Other 205,000 110,000 - - -

    Total 1,818,000 873,000 1,542,000 6,657,000 46,256,000

    Negative figures indicate a surplus in the first year, which will be required to fund renewals in subsequent

    years where there is a funding gap. If the programs are flexible this surplus may be able to be used in other

    categories which have a funding gap. The renewal modelling shows that overall, the funding gap is increasing

    over the 30 years towards 2049.

  • Sewerage Asset Management Plan

    Orange City Council Page 3

    Figure 1-1 identifies the proposed expenditure over the next 10 years, with an increasing backlog at current

    levels of funding for all sewerage asset categories. The backlog after 30 years is indicative of current levels of

    renewal funding. The proposed Capital Works Program is detailed in Appendix C, including work for Renewals,

    Upgrades and New Works.

    Alternative funding scenarios are discussed in Section 11 – Financial Plan, including funding the renewal gap.

    Figure 1-1: What will we spend over the next 10 years?

    The current condition of our assets is shown in Figure 1-2 based on the value of each asset in each of 10

    conditions ranging from 1 to 10, with 1 being near new and 10 as a completely failed asset.

    Figure 1-2: What condition are our assets in?

    0

    5

    10

    15

    20

    25

    2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29

    $ (

    Mill

    ion

    s)

    Operations Maintenance Renewal Upgrade / Expansion Rolling Backlog

    0

    10

    20

    30

    40

    50

    60

    70

    1 2 3 4 5 6 7 8 9 10

    $ (

    Mill

    ion

    s)

    Sewer Vents Sewer Treatment Sewer Trunk Mains

    Sewer Pump Stations Sewer Reticulation Mains Sewer Rising Mains

  • Sewerage Asset Management Plan

    Orange City Council Page 4

    2 Strategic Objectives

    Council operates and maintains the sewerage network to achieve the following strategic objectives.

    To satisfy community expectations and regulatory requirements at a reasonable cost.

    To have sufficient capacity for community growth.

    To provide an environmentally and financially sustainable service.

    To develop public confidence in the staff and services..

    Orange City Council developed a comprehensive community engagement strategy to ensure a broad range of

    opinions, ideas and visions were captured to help shape the Orange Community Strategic Plan (CSP). The

    outcomes and strategies supported by that plan are detailed in the Strategic Asset Management Plan,

    Strategic Business Plan (SBP) and Integrated Water Cycle Management (IWCM) Strategy.

    To assist in the delivery of the objectives in this plan, a number of key documents and systems have been

    prepared and should be referred to in considering the findings in Table 2-1.

    Table 2-1: Where can I find additional information?

    Document / System Content

    Annual Systems Performance Report (ASPR)

    Performance of the sewerage system in regards to effluent quality and overflows

    Asset Management Manual (AMM) Documents the procedures and processes for the management of assets

    Asset Management Strategy (AMS) Overall direction of asset management and portfolio summary

    Asset Management System (AIM) Electronic system that contains the asset register, condition ratings and used to model future renewals

    Capital Value Register (CVR) Electronic system that stores the financial information of assets

    Community Strategic Plan (CSP) Outcomes and strategies identified by the community

    Condition Assessment Manual Details on the process of assessing condition, including photographic examples of various conditions

    Council Asset Policy How we manage assets

    Development Servicing Plans (DSP) Developer charges applicable to development for sewerage infrastructure

    Enlighten GIS Geographical information system that produces maps of assets

    Enterprise Risk Management (ERM) The identification and management of risks across Council operations

    Integrated Water Cycle Management Evaluation Study (IWCM)

    Sustainable management strategies for optimal management of all components of the water system (water, sewage and stormwater)

    Liquid Trade Waste Policy (ST046) Identification and monitoring of trade wastes according to NOW and EPA Guidelines

    Pollution Incident Response Management Plan (PIRMP)

    Processes and procedures when we respond to an overflow event

    Pollution Reduction Plan (PRP) Identifies high risk pump stations and overflow points

    Sewer Infrastructure Strategic Policy (ST130)

    Outlines Council’s commitment to sustainable and efficient sewerage services

    Water Supply and Sewerage Strategic Business Plan (SBP)

    Management of water supply and sewerage business

  • Sewerage Asset Management Plan

    Orange City Council Page 5

    Figure 2-1 shows the strategic context for sewerage services. It demonstrates the link between the NSW Best

    Practice Management (BPM) framework for Water Supply & Sewerage and how that integrates with the NSW

    Integrated Planning & Reporting (IPR) framework.

    Figure 2-1: Strategic Planning Framework for Water Supply & Sewerage

    The Orange Community Strategic Plan outcomes supported by this Sewerage Asset Management Plan include:

    Theme: Preserve | Objective 8: Managing our resources wisely

    o 8.1: Identify and deliver essential water, waste and sewer infrastructure to service the community

    into the future.

    o 8.2: Develop and promote initiatives to reduce water, energy and waste in consultation with the

    community.

  • Sewerage Asset Management Plan

    Orange City Council Page 6

    3 Services Provided

    Orange City Council provides reticulated sewerage to the City of Orange and the villages of Lucknow and

    Spring Hill.

    3.1 Orange Sewerage Scheme

    Orange City Council provides reticulated sewerage services to approximately 17,000 assessments. Sewage

    from this area is collected through approximately 450km of sewer mains and 11 major pump stations. Sewage

    is collected at the Orange Wastewater Treatment Plant (WWTP), which processes 3,000 to 4,000 ML annually

    and has the capacity to service up to 60,000 equivalent population (EP) with capacity to provide full treatment

    up to approximately 43.2 ML/day. The majority of treated effluent from the Orange STP is reused under an

    existing water supply agreement with Cadia Holdings Pty Ltd for mineral processing. The balance of the

    treated effluent is discharged under licence to Blackmans Swamp Creek.

    Figure 3-1: Orange Sewerage Service Area

  • Sewerage Asset Management Plan

    Orange City Council Page 7

    3.2 Spring Hill and Lucknow Sewerage Scheme

    Orange City Council also provides reticulated sewerage to the villages of Lucknow and Spring Hill, serviced

    through approximately 40km of sewer mains and 4 pump stations. Sewage is collected and delivered to the

    Spring Hill Sewage Treatment Plant, which has the capacity to service up to 1,000 EP with capacity to provide

    full treatment up to 2.3ML/day.

    Figure 3-2: Spring Hill and Lucknow Sewerage Service Area

  • Sewerage Asset Management Plan

    Orange City Council Page 8

    3.3 Recycled Water Scheme

    Cadia Valley Operations (CVO) is under contract with Orange City Council to receive recycled water from the

    Orange STP. This agreement currently gives CVO access to a minimum 10 ML/day with the ability to take up to

    13 ML/day.

    The water supply agreement started in December 1997 and was set to continue for the life of the mine.

    Figure 3-3: Orange Effluent Reuse System

    Orange Wastewater treatment plant

    Blackmans Swamp Creek / Summer Hill Creek

    Pump Station Effluent re-use

    Environmental Flows

  • Sewerage Asset Management Plan

    Orange City Council Page 9

    Table 3-1: What is provided? (at 30 June 2019)

    Asset Category Dimension/Capacity Fair Value

    Sewage Treatment 61000 EP -

    Sewage Pump Stations 91 ML/d -

    Sewer Rising Mains 34 km -

    Sewer Gravity Mains 442 km -

    TOTAL

    236,866,000

    The extension of sewerage services to new areas is dependent on a range of factors, detailed in the Integrated

    Water Cycle Management (IWCM) Strategy, the most important of which relate the our Levels of Service:

    Servicing new residential areas

    The impact to existing customers

    The environmental impact of effluent (raw or treated)

    Affordable Typical Residential Bill (TRB)

    Growth and Demand

    In addition to assets constructed by Council, new sewerage assets are also acquired from land developments.

    In the last 5 years (2013/14 to 2018/19 FY):

    Council’s total gravity mains network has grown by 8.6%, from 407km to 442km (1.7% p.a.); and

    The number of residential sewerage assessments has increased 6.7%, from 15,119 to 16,133 (1.3%

    p.a.).

    Acquiring these new assets commits Council to fund the additional operating, maintenance and renewal costs

    associated with the assets.

    Council has undertaken hydraulic modelling to determine what infrastructure would be required in the next 30

    years to service new development and maintain levels of service for existing customers. This analysis was

    collected in the “30 Year Infrastructure Strategy”. The projects included in the Infrastructure Strategy are

    included in the Capital Works Program for growth.

    Opportunities for Non Asset Service Delivery

    Council has pursued a number of non-asset service delivery options which are detailed in the Strategic

    Business Plan and IWCM. These include Trade Waste Policy, Inflow/Infiltration program, and energy efficiency

    programs.

  • Sewerage Asset Management Plan

    Orange City Council Page 10

    4 Levels of Service

    One of the basic principles of sound asset management practice is to provide the level of service the current

    and future community want and are prepared to pay for, in the most cost effective way (NZ NAMS 2007).

    Sewer assets have been categorised into classes to assist in the determination of Levels of Service (LOS) which

    are grouped into:

    Community LOS – relates to how the community receives the service in terms of safety, quality,

    quantity, reliability responsiveness, cost efficiency and legislative compliance; and

    Technical LOS – are the technical measures of performance developed to ensure the minimum

    community levels of service are met.

    Table 4-1 outlines what the community desires for each asset Category and how Orange City Council will

    deliver it. The Community desires have been determined in line with the Community Strategic Planning and

    Strategic Business Plan processes.

    Table 4-1: Customer Service Levels

    CSP Type of Service (Community LOS)

    Level of Service (Technical LOS)

    CUSTOMER ENQUIRIES

    14.2 Adequate response to complaints/enquiries

    Respond to 95% of written complaints/inquiries within 5 working days.

    Respond to 95% of personal/verbal complaints/inquiries within 1 working day.

    WASTEWATER SERVICES

    8.1 Properties are able to connect to the sewerage network

    Connections for domestic sewerage should be provided to all houses, units or businesses within the defined service area.

    Acceptance of commercial and industrial wastes (trade waste) should be in accordance with the approval conditions for each discharger.

    8.1 Service is available to use at all times

    Minimise frequency of overflows, breakdowns and chokes though maintenance and renewal programs.

    WASTEWATER QUALITY

    8.1 Effluent from Treatment Works

    To meet licence regulations set by the Environmental Protection Authority.

  • Sewerage Asset Management Plan

    Orange City Council Page 11

    Table 4-2: Reponse Times

    Response times to System Failures

    8.1 Priority 1 A major failure to contain sewage within the sewer system.

    Typical Causes:

    Main break

    Choke (blockage)

    Overloading of system

    Failure of pumping station

    Typical Effects:

    Personal injury or risk to public health

    Surcharge or overflow in dry weather

    Surcharge or overflow in wet weather

    Surcharge inside building

    Surcharge outside a building, if posing a health risk

    Major property damage, e.g. subsidence

    Major environmental impact

    We will aim to respond within:

    30 min (business hours)

    1 hour (after hours)

    8.1 Priority 2 A minor failure to contain sewage within the sewer system.

    Typical Causes:

    Cracked pipe

    Partial blockage of the sewer

    Typical effects:

    Surcharge outside a building, not posing a health risk

    Minor property damage

    Minor environmental impact, i.e. odour problems

    We will aim to respond within:

    1 hour (business hours)

    1 hour (after hours)

    8.1 Priority 3 A minor failure to contain sewage affecting a single property.

    Typical causes:

    Sudden extra hydraulic load which backs up but then clears itself

    Partial main line choke

    Partial house service choke

    Broken junction connection

    Typical effects:

    Minor surcharge

    Slow-moving toilet flush

    Minimal or no environmental impact

    We will aim to respond within:

    1 hour (business hours)

    2 hours (after hours)

    Any requirements for further community consultations, particularly for Level of Service changes may cause a

    significant impact on costs to deliver the services detailed in this plan. A review of Council’s performance in

    delivering the sewerage service to the community is included in Section 12 – Performance Measures.

  • Sewerage Asset Management Plan

    Orange City Council Page 12

    Table 4-3 provides a brief overview of the legislative framework in which Council operates its sewerage

    network, and the requirements that the network is required to meet.

    Table 4-3: Legislative requirements

    Obligation Implications

    PRICING

    Local Government Act 1993 (and Regulations 2005)

    Determining developer charges: o Provide a source of funding for infrastructure required for new urban

    development o Provide signals regarding costs of urban development and encourage

    less costly forms

    Pricing principles to be adopted by local government authorities for water & sewerage

    Guidelines for a ‘user pays’ charging system

    ENVIRONMENTAL PROTECTION AND LICENCES

    Protection of the Environment Operations Act 1997

    Council holds environmental protection licences for the operation of the Orange and Spring Hill Sewerage Systems

    HEALTH AND SAFETY

    Work Health & Safety Act 2011 (and Regulation 2017)

    Council is required to comply with Work Health and Safety in its sewerage service operations

    Public Health Act 2010 Effluent disposal methods to protect public health

    Prevention of the spread of disease

    CONTRACTUAL ARRANGEMENTS

    Cadia Valley Operations Recycled Water Supply Agreement

    Contractual obligation for delivery of treated effluent to Cadia Valley Operations

  • Sewerage Asset Management Plan

    Orange City Council Page 13

    5 Condition of Our Assets

    Council maintains a Condition Assessment Manual that details the frequency of inspection and condition

    rating to be used for all assets. This data is recorded in the Council Asset Management System and used to

    predict the timing of renewal / maintenance requirements in the Long Term Financial Plan.

    Assets are rated on a 1 (Near New) to 10 (Completely Failed) scale consistent with the Maloney model and

    advanced asset management practices as outlined in the IPWEA International Infrastructure Management

    Manual. Details on how Council assesses condition and further information on the rating scale are contained in

    the Condition Assessment Manual.

    The intent of Council is not to undertake renewal on an asset until it reaches its ‘Intervention Level’, that is the

    condition at which the community has determined renewal is required based on the LOS analysis. Typically

    assets will be renewed by condition 8.

    Asset Deterioration

    Deterioration profiles have been developed that track the rate of deterioration expected over time for each

    material type in each asset group. This information is used in our models to determine when an asset is

    expected to be due for renewal, noting that assets will only be renewed when they reach their intervention

    condition, not based on their age.

    Figure 5-1 provides examples of several deterioration profiles used with the vertical column showing the years

    remaining at a particular condition. For example, a VC main at condition 3 will last 85 years until complete

    failure at condition 10.

    Figure 5-1: At what rate do we expect our assets to deteriorate?

    021426384

    105

    1 2 3 4 5 6 7 8 9 10

    Sewer Reticulation Mains

    Relined Mains AC, VCConcrete UPVC, PECast Iron, DICL

    0

    13

    26

    39

    52

    65

    1 2 3 4 5 6 7 8 9 10

    Mechanical Assets

    20 year life 30 year life

    40 year life 60 year life

    0

    9

    18

    27

    36

    45

    1 2 3 4 5 6 7 8 9 10

    Electrical Assets

    15 year life 20 year life

    30 year life 40 year life

    0

    17

    34

    51

    68

    85

    1 2 3 4 5 6 7 8 9 10

    Civil Assets

    30 year life 40 year life

    60 year life 80 year life

  • Sewerage Asset Management Plan

    Orange City Council Page 14

    Asset Condition Assessment

    Using the information from the deterioration profiles and the intervention level set for the class of an asset we

    can determine the expected useful lives of our assets as detailed in Table 5-1.

    Table 5-1: What are our Intervention Levels to Renew an Asset?

    Category Component Intervention Level Useful Life

    Trunk Mains Sewer Mains – Metallic (DICL, CI) 8 40 years

    Sewer Mains – Concrete 8 100 years

    Sewer Mains – AC 8 70 years

    Sewer Mains – Earthenware (VC) 8 70 years

    Sewer Mains – Plastic (UPVC, PE) 8 70 years

    Sewer Mains – Relined 8 50 years

    Reticulation System (Gravity & Pressure mains)

    Sewer Mains – Metallic (DICL, CI) 8 40 years

    Sewer Mains – Concrete 8 100 years

    Sewer Mains – AC 8 70 years

    Sewer Mains – Earthenware (VC) 8 70 years

    Sewer Mains – Plastic (UPVC, PE) 8 70 years

    Sewer Mains – Relined 8 50 years

    Pump Stations Structures 8 20-80 years

    Electrical 8 15-40 years

    Mechanical 8 20-60 years

    Treatment Plants Structures 8 20-80 years

    Electrical 8 15-40 years

    Mechanical 8 10-60 years

    Condition inspections for above ground assets are conducted annually by competent operational staff who

    maintain the assets being inspected, with a member of the asset team to determine the condition of the asset

    being inspected. The method of condition assessment for underground sewerage assets is detailed in the

    Condition Assessment Manual and is broken up as follows:

    Level 1 assessment – a preliminary condition rating based on the asset age, material and pipe

    diameter where no other information is available

    Level 2 assessment – utilising operation and maintenance records (e.g. sewer choke information) to

    gain an understanding of asset condition. Assets that are identified in a condition close to or exceeding

    the intervention level are scheduled for a Level 3 assessment.

    Level 3 assessment – formalised condition assessment, e.g. CCTV. Inspections are undertaken by

    competent operational staff who are qualified to conduct CCTV inspection in accordance with WSAA

    Conduit Inspection Code.

  • Sewerage Asset Management Plan

    Orange City Council Page 15

    Asset Register

    The asset register captures the asset data and condition data in a hierarchical structure. The adequacy of the

    data and information captured is comprehensive, although is due to be reviewed to ensure the relevance of

    the data captured. This includes making sure that data is not captured for data’s sake, and that resources are

    available to keep the data up to date. The review of the data is included as an action in Section 13 –

    Improvement Plan.

    Each asset’s condition is maintained in the Asset Register and Figure 5-2 gives the condition profile based on

    the dollar value of the top 4 valued assets in each condition.

    An overview of the assets that are recorded in the Asset Register is provided in Table 3-1.

    Figure 5-2: What Condition are our assets in?

    0

    5

    10

    15

    1 2 3 4 5 6 7 8 9 10

    $ (

    Mill

    ion

    s)

    Sewer Treatment

    0

    5

    10

    1 2 3 4 5 6 7 8 9 10

    $ (

    Mill

    ion

    s)

    Sewer Pump Stations

    0

    5

    10

    15

    1 2 3 4 5 6 7 8 9 10

    $ (

    Mill

    ion

    s)

    Sewer Trunk Mains

    0

    10

    20

    30

    1 2 3 4 5 6 7 8 9 10

    $ (

    Mill

    ion

    s)

    Sewer Reticulation Mains

  • Sewerage Asset Management Plan

    Orange City Council Page 16

    6 Operational Plan

    The purpose of the Operational Plan is to ensure that service objectives (Levels of Service, statutory &

    regulatory requirements and obligations) are achieved at the least cost and that the impact of any breakdowns

    or outages is minimised. Operational Performance Indicators are shown in Section 12.

    The operations plan is based on knowledge of the system assets and as such, there are ongoing requirements

    for maintaining an appropriate asset register and for investigating the condition of key elements of the

    systems that affect the ability to deliver the desired level of service. Contingency operations plans (emergency

    response plans and business continuity plans) are being developed where the consequence of failure is

    significant.

    Existing operational systems, processes and procedures routinely deliver services that comply with levels of

    service and regulatory requirements. Rapid changes in the operating environment in terms of customer

    expectations, improved environmental outcomes, resource conservation and higher regulatory standards will

    require commensurate improvements in operations.

    Key operation issues include the following:

    Asset condition and monitoring program.

    Monitoring of operational performance.

    Review and documenting of operating procedures.

    Ongoing review of energy usage and reduction opportunities.

    Operational activities are those regular activities that are required to continuously provide the service

    including asset inspection, electricity costs, plant and overheads. Table 6-1 outlines the split of our operational

    costs on an annual basis.

    Table 6-1: What are our annual Operational Costs?

    Item 30 yr Avg Annual Cost

    Administration 2,849,000

    Engineering 1,406,000

    Operations 3,519,000

    Energy 1,004,000

    Depreciation 3,956,000

    Interest 4,000

    Total 12,739,000

  • Sewerage Asset Management Plan

    Orange City Council Page 17

    Figure 6-1: What is the breakup of our Operational Costs?

    Routine Operations

    Normal operational procedures are undertaken in accordance with the Environmental Protection Licences for

    each sewerage scheme and specify the level of service to be maintained.

    It is recognised that monitoring telemetry and SCADA systems leads to best operating efficiency and improves

    resource utilisation.

    As well as ongoing operations, annual returns required for Environmental Protection Licences (EPL) through

    the Environmental Protection Authority for the sewerage treatment system provides further opportunity for

    performance review and if any issues may be present. The Spring Hill EPL only requires the annual return,

    whereas the Orange STP EPL includes a further assessment with the Annual Systems Performance Report.

    The operation of the treated effluent reuse system is documented in Council’s Recycled Water Management

    System.

    Emergency Response

    Council has documented procedures in place in the Pollution Incident Response Management Plan. The

    response plan includes actions in relation to pollution incidents including sewer overflows, treatment bypasses

    and water quality results exceeding EPL limits.

    Business Continuity

    Emergency operational procedures are being developed by Council into a suite of Business Continuity Plans

    where service fails at critical facilities. There are currently no Sewerage facilities that are being considered for

    Business Continuity Planning.

    Administration22%

    Engineering11%

    Operations28%

    Energy8%

    Depreciation31%

    Interest0%

    Administration

    Engineering

    Operations

    Energy

    Depreciation

    Interest

  • Sewerage Asset Management Plan

    Orange City Council Page 18

    Future Operational Expenditure

    Increases to operations and maintenance expenditure occur when new assets are acquired through new works

    and developer contributions. These extra costs would be identified at the project stage when undertaking a

    life-cycle cost analysis of the asset to be built and included operational budgets. For example:

    New sewer pump stations in new development areas, electricity and operational costs.

    New reticulation mains in new areas adding to the overall network requiring inspection and flushing.

    More sewage being treated at the sewer treatment plants, resulting in more chemical use and

    electricity use.

    Impact of Inflow/Infiltration Programs being implemented reducing the volume of sewage pumped

    and sewage treated at the sewerage treatment plants.

    Impact of demand management strategies on indoor water use reducing volume of sewage pumped

    and sewage treated at treatment plants.

    Future operational expenditure is forecast to trend in line with the growth in the sewerage network. Forecast

    operational expenditure levels are detailed in Section 12 – Financial Plan.

  • Sewerage Asset Management Plan

    Orange City Council Page 19

    7 Maintenance Plan

    The purpose of the Maintenance Plan is to support the Operation Plan by ensuring that the actual outputs,

    reliability and availability of the sewer systems, facilities and components, as specified in the Operation Plan,

    are achieved in the most cost effective manner.

    Maintenance is the on-going work that is necessary to keep assets operating to ensure they reach their useful

    life. It includes work on an asset where a portion may fail and need immediate repair to make it operational

    again. It may be either planned where works are programmed in, cyclic in nature or reactive in response to

    storm damage, vandalism etc.

    Planned or scheduled maintenance is normally used for critical items where a breakdown would be

    costly and would cause large interruptions to service. Scheduled maintenance can be fixed-time

    interval or condition-based interval (e.g. every 10,000 pump run hours). These programs should be

    documented in a Scheduled Maintenance Plan.

    Reactive or breakdown maintenance is generally reserved for less critical assets, or for situations

    where scheduled maintenance is not possible. These are usually carried out in response to service

    requests.

    Maintenance Programs

    Current maintenance programs are designed to maintain sewer assets at their target levels of service and

    minimise risk of future failure. Maintenance expenditure levels are considered to be adequate to meet

    required service levels.

    Future revision of this asset management plan will include linking required maintenance expenditures with

    required service levels in the Community Strategic Plan. The level of service and standards of care for

    maintenance is carried out in accordance with Council’s Asset Management Policy.

    The proposed maintenance programs are detailed in Appendix A, with costs identified in Table 7-1.

    Table 7-1: What are our annual maintenance costs?

    Item 30 yr Avg Annual Cost

    453 Sewerage Treatment $ 644,000

    456 Sewage Pumping $ 202,000

    458 Sewer Reticulation $ 364,000

    Total $ 1,210,000

  • Sewerage Asset Management Plan

    Orange City Council Page 20

    Figure 7-1: What is the breakup of our Maintenance Costs?

    Future Maintenance Expenditure

    Increases to operations and maintenance expenditure occur when new assets are acquired through capital

    works and developer contributions. These extra costs are identified at the project stage when undertaking a

    life-cycle cost analysis of the asset to be built and included operational budgets. For example:

    Maintenance of new sewer pump stations in new development areas

    New reticulation mains in new areas adding to the overall network requiring response when

    choked/blocked.

    Future maintenance expenditure is forecast to trend in line with the growth in the sewerage network. Forecast

    maintenance expenditure levels are detailed in Appendix D.

    Deferred maintenance, i.e. works that are identified for maintenance and unable to be funded, present a

    higher likelihood of failure.This can happen if maintenance budgets do not increase in line with asset growth.

    453 Sewerage Treatment

    53%

    456 Sewage Pumping17%

    458 Sewer Reticulation

    30%

    453 Sewerage Treatment

    456 Sewage Pumping

    458 Sewer Reticulation

  • Sewerage Asset Management Plan

    Orange City Council Page 21

    8 Capital Renewal Plan

    Renewal works are Capital Work on an existing asset to replace or rehabilitate it to a condition that restores

    the capability of the asset back to an acceptable level of service. The intervention level and estimated useful

    lives are contained in Table 5-1.

    Renewal will be undertaken using ‘low-cost’ renewal methods where practical. The aim of ‘low-cost’ renewals

    is to restore the service potential or future economic benefits of the asset by renewing the assets at a cost less

    than the full replacement cost. For example, re-lining sewer mains instead of re-construction.

    This Asset Management Plan contains an analysis based on broad assumptions and best available knowledge

    to date. Modelling is not an exact science so we deal with long term averages across the entire asset stock.

    Work will continue on improving the quality of our asset registers and systems to increase the accuracy of our

    renewal models.

    Details of planned renewal activities proposed over the next four years are contained in Appendix B for each

    asset category. The first year of the program will be considered in the development of the next Operational

    Plan and the remaining three years of work will be assessed each year to confirm that the asset has reached its

    intervention level prior to the work being scheduled.

    Prioritising Renewals

    Assets requiring renewal will be generally identified from estimates of remaining life and condition

    assessments obtained from the asset register and models. Candidate proposals will be inspected to verify the

    accuracy of the remaining life estimate and to develop a preliminary renewal estimate.Verified proposals are

    ranked by priority and available funds and scheduled in future works programs.

    Assets were identified for the renewal program based on the following criteria:

    Not meeting the level of service (e.g. sewer overflows)

    Poor condition/performance resulting in high risk to leave in service (identified from asset register)

    from assets that have a level 2 assessment level

    Assets that have been identified in poor condition/performance rating from a level 1 assessment have

    been identified to undertake a level 2 assessment (e.g. Sewer mains that have been assessed to be in

    poor condition are included in the upcoming CCTV program to confirm their condition before being

    included in a renewal program).

    Any other specialist evaluation study commissioned by Council (e.g. Treatment Plant Capacity Studies,

    Pump station specialist inspections and studies)

    A backlog of works (works that have been identified as required, but not able to be funded), may result in

    reduced performance, e.g. overflows and odour problems.

    This risk may be acceptable for some assets, but not for others. A criticality assessment has been undertaken

    for these assets included in the Sewerage Asset Management Plan, and prioritise renewals based on their

    consequence of failure. Assets that have a low consequence of failure that are a low risk to remain in service

    are not included in Special Schedule 7 financial reports.

  • Sewerage Asset Management Plan

    Orange City Council Page 22

    Renewal Expenditure

    The costs presented in Table 8-1 identify the current level of funding for the required renewal programs and

    the funding required to maintain the asset to what is considered an appropriate standard. The required

    funding in that table is based on the intervention specified in Section 5.

    For sewerage assets, an analysis has been undertaken to determine assets that are already at or above

    intervention level that are not able to be funded in the next Operational Plan. This work is quantified in the

    ‘Backlog’ column.

    Negative figures (in red) indicate a surplus for that particular category, however if the programs are flexible

    this surplus may be able to be used in other categories which have a funding gap. Overall, however there is no

    surplus in renewal funding.

    Appendix B details the renewal programs over the next 4 years.

    Table 8-1: What are our Renewal Costs, Gap and Backlog?

    Activity Budget Required Gap Backlog 2019 Backlog 2048

    Sewer Treatment 765,000 1,293,000 529,000 -543,000 15,861,000

    Sewer Pump Stations 140,000 395,000 255,000 6,000 7,647,000

    Sewer Rising Mains - 598,000 598,000 745,000 17,945,000

    Sewer Trunk Mains - 214,000 214,000 3,909,000 6,428,000

    Sewer Reticulation Mains 700,000 631,000 -69,000 2,582,000 -2,075,000

    Sewer Vents 8,000 23,000 15,000 -42,000 450,000

    Other 205,000 - - - -

    Total 1,818,000 3,155,000 1,542,000 6,657,000 46,256,000

    Figure 8-1: What will we spend over the next 10 years on Renewal?

    0

    1

    2

    3

    4

    5

    6

    7

    8

    9

    2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29

    $ (

    Mill

    ion

    s)

    Sewer Treatment Sewer Pump Stations Sewer Rising Mains

    Sewer Trunk Mains Sewer Reticulation Mains Sewer Vents

    Other Rolling Backlog

  • Sewerage Asset Management Plan

    Orange City Council Page 23

    Figure 8-2: Rolling Backlog Split

    Lifecycle costs

    The lifecycle costs are determined based on the total cost of ownership of each asset including operations,

    maintenance, renewal and disposal costs. The thirty year average annualised lifecycle costs for each

    component is presented in Table 8-2.

    Table 8-2: What are our Lifecycle Costs?

    Category Units Rate Annual Average

    Sewer Reticulation /km $ 19,034 $ 8,565,151

    Sewage Treatment /1000 EP $ 29,353 $ 1,790,524

    Sewer Pump Stations /ML $ 10,196 $ 919,720

    0

    1

    2

    3

    4

    5

    6

    7

    8

    2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29

    $ (

    Mill

    ion

    s)

    Sewer Treatment Sewer Pump Stations Sewer Rising Mains

    Sewer Trunk Mains Sewer Reticulation Mains Sewer Vents

    Other

  • Sewerage Asset Management Plan

    Orange City Council Page 24

    8.1 Intervention Levels – Phase Up/Phase Down

    For each asset type, the “intervention level” condition is the condition at which renewal of the asset proposed

    to be undertaken. Minimising the life cycle cost and indications of the desired level of service obtained

    through community engagement have been considered in setting intervention level conditions.

    As an example, the intervention level adopted for trunk mains (condition 7) is higher than the level adopted

    for reticulation mains (condition 8) as it is a more critical asset type. Refer to Section 5 - Condition of Our

    Assets for more details.

    Evaluating “phase up” and “phase down” scenarios provides information on costs or savings and other impacts

    to the community based on higher and lower Levels of Service (LOS) options.

    A phase up scenario may mean that mains are renewed at condition level 6 for trunk mains and condition 7 for

    reticulation mains, and a phase ramp down scenario could be where mains renewed at condition level 8 for

    trunk mains and at condition 9 for retic mains.

    The average annual renewal costs under each of the scenarios modelled are listed in Table 4.2 below.

    Table 8-3: What is the cost of increasing intervention levels by 1 condition point?

    Asset Category Scenario 30yr Avg Ann Cost

    Base Case Movement

    Sewer Rising Mains Phase Up $ 641,000 $ 598,000 $ 43,000

    Sewer Reticulation Mains Phase Up $ 334,000 $ 631,000 $ 295,000

    Sewer Trunk Mains Phase Up $ 269,000 $ 214,000 $ 55,000

    Sewer Pump Stations Phase Up $ 600,000 $ 395,000 $ 205,000

    Sewer Treatment Phase Up $ 2,165,000 $ 1,293,000 $ 871,000

    Sewer Vents Phase Up $ 27,000 $ 23,000 $ 4,000

    Table 8-4: What is the cost of decreasing intervention levels by 1 condition point?

    Asset Category Scenario 30yr Avg Ann Cost

    Base Case Movement

    Sewer Rising Mains Phase Down $ 597,000 $ 598,000 $ -2,000

    Sewer Reticulation Mains Phase Down $ 926,000 $ 631,000 $ -297,000

    Sewer Trunk Mains Phase Down $ 170,000 $ 214,000 $ -44,000

    Sewer Pump Stations Phase Down $ 318,000 $ 395,000 $ -77,000

    Sewer Treatment Phase Down $ 811,000 $ 1,293,000 $ -483,000

    Sewer Vents Phase Down $ 19,000 $ 23,000 $ -4,000

    The average annual renewal costs are identified in Table 8.3 and 8.4, however the extra maintenance costs

    that would be required because of renewal delay under the phase down option have not been captured. More

    sewer chokes, equipment breakdown or other issues could occur due to a decline in the average condition of

    the sewerage network.

  • Sewerage Asset Management Plan

    Orange City Council Page 25

    9 Capital Upgrade & Expansion Plan

    Upgrade and expansion works are those capital works that create a new asset that did not previously exist, or

    works which upgrade or improve an existing asset’s capacity.

    Upgrades enhance an existing asset to provide a higher level of service, for example improving capacity in an

    area, and improving wastewater quality (identified in the Capital Works Program as Level of Service works).

    New assets are those created to meet an additional service level requirement or increase the size of a

    network, for example, servicing new development areas.

    Works for growth may be funded in part through developer contributions in the form of Section 64

    contributions, a Voluntary Planning Agreement, or as part of a subdivision development. These works are

    identified in the Capital Works Program for ‘Future Growth’. They are usually not eligible for grant funding

    Upgrade works (Level of Service works) need to be funded from within the existing revenue stream of the

    Sewer Fund. Upgrade works may also be eligible for grant funding.

    Project Identification and Strategies

    New assets and upgrade/expansion of assets are identified from studies completed by Council. These will be

    included into Integrated Water Cycle Management (IWCM) Plan scenarios. The current capital works projects

    have been identified from the following sources:

    Orange STP Capacity Study 2015

    Spring Hill STP Capacity Study 2015

    30 year Infrastructure Strategy 2014

    IWCM Evaluation Study , May 2013

    Interim Sewer Development Servicing Plan, November 2012 – currently under review

    Council has an adopted strategy for the expansion of sewerage network with the following new / upgraded

    assets proposed over the next 30 years to meet demand and levels of service.

  • Sewerage Asset Management Plan

    Orange City Council Page 26

    Capital Expenditure

    Table 9-1 indicates the major projects and groups of new and upgraded assets proposed, a complete list is

    contained in Appendix C.

    Table 9-1: What are the major projects proposed over the next 10 years?

    Project Reason Year(s) Total Budget

    Orange STP – Inlet Works Upgrade LOS 2019/20 – 2020/21

    4,850,000

    Orange STP – UV Design, construction and dechlorination

    LOS 2022/23 – 2023/24

    4,350,000

    Orange STP – Digestor Upgrade LOS 2026/27 – 2029/30

    2,700,000

    Orange STP – Aeration Upgrade LOS 2020/21 – 2022/23

    1,900,000

    SPS – Leeds Parade Rural Residential New SPSs Growth 2020/21 – 2025/26

    1,648,000

    SPS – Clergate Road/Leeds Parade New SPSs Growth 2023/24 – 2024/25

    1,119,000

    North Orange Sewer Strategy Growth 2020/21 – 2021/22

    3,234,000

    Spring Hill / lUkcnow Sewer Strategy LOS 2020/21 – 2025/26

    2,800,000

    Figure 9-1: What will we spend over the next 10 years on Upgraded and New Assets?

    0

    1

    2

    3

    4

    5

    6

    2019/20 2020/21 2021/22 2022/23 2023/24 2024/25 2025/26 2026/27 2027/28 2028/29

    $ (

    Mill

    ion

    s)

    451 Sewer Administration 453 Sewer Treatment 456 Sewage Pumping 458 Sewer Reticulation

  • Sewerage Asset Management Plan

    Orange City Council Page 27

    10 Asset Rationalisation and Disposal Plan

    Disposal is any activity associated with disposal of a decommissioned asset including sale, demolition or

    relocation. Assets with a condition rating of 9 (poor condition), where Council has received no contact through

    the Customer Request System indicating that the community don’t require the asset (as they have raised

    concerns or complaints about the asset condition) may be considered to be a redundant asset or not utilised

    and therefore decommissioned and disposed unless it is considered critical infrastructure

    Table 10-1: What assets are we planning to dispose of?

    Asset Reason Year Cost

    Spring Hill Wastewater Treatment Plant

    Asset is to be replaced with a new Sewer Pump Station to enable treatment of all wastewater at the Orange Wastewater Treatment Plant

    2025/26 (part of Spring Hill-Lucknow Sewer Strategy)

    2,000,000

    Turner Crescent SPS Asset is currently non-operational (no power connected & no pumps in well)

    Asset is no longer required (further development has removed the need for this pump station – connected now via gravity sewer to North Orange 1 SPS)

    Asset is located on residential block that might be able to be sold for development should the pump station be fully decommissioned.

    UNSCHEDULED 40,000

    Orange Wastewater Treatment Plant – Trickling Filters

    Asset no longer required 2028/29 1,850,000

  • Sewerage Asset Management Plan

    Orange City Council Page 28

    11 Financial Plan

    This financial plan is based on Orange City Council’s financial statements from 2017/18 (Special Schedule 5 and

    6), which are a key component of Council’s strategic business plans for water supply and sewerage.

    A 30-year financial plan has been prepared for Council’s Sewerage business. The NSW Financial Planning

    Model (FINMOD) has been used for preparing this Financial Plan.

    This Financial Plan sets out the long term price path (Typical Residential Bills) Council will need to levy in order

    to fund the recurrent cost and capital investment required for delivering the levels of service set out in this

    Asset Management Plan.

    A summary of the expenditure projected over the next 30 years is included in Appendix D. Funding for

    management of assets can come in a variety of sources as detailed in the table below.

    Table 11-1: Where does our Income come from?

    Item 30yr Avg Annual Income

    Fees & Charges 13,748,000

    Interest 1,011,000

    Other 559,000

    Grants 161,000

    Contributions 2,138,000

    Total 17,617,000

    Figure 11-1: What is the breakup of our income streams?

    Fees & Charges-78%

    Interest-6%

    Other-3%

    Grants-1%

    Contributions-12%

    Fees & Charges

    Interest

    Other

    Grants

    Contributions

  • Sewerage Asset Management Plan

    Orange City Council Page 29

    11.1 Summary of Model Inputs

    Historical Financial Data

    Historical financial data was obtained from Special Schedules 5 & 6 of Council’s 2017/18 annual financial

    statements.

    Initial Data

    Data used in the modelling is shown in Table 11-2. The values are those recommended by Orange City

    Council’s Finance Department.

    Table 11-2: Initial Data

    Parameter Value

    Inflation Rate 2.5%

    Borrowing Interest Rate 3.0%

    Deposit Interest Rate 1.75%

    Term of new loan 10

    Average life of new system assets 70

    Assessments and Growth Projections

    The figures used for the existing number of assessments and the projected growth are given in Table 11-3.

    Table 11-3: Sewer Assessments

    Item Exiting Assessments (June 2019)

    Growth Projection

    Residential Assessments 16133 0.9%

    Non-Residential Assessments 1235 0.9%

    Typical Developer Charges

    Developer charges, together with the annual charges, are Council’s two sustainable sources of income. In

    order to project the annual charges, the income from developer charges needs to be estimated.

    For assessing the developer charges for new development, it was assumed that each new residential

    assessment will be 1 ET (Equivalent Tenement) and on average, each non-residential assessment will also be 1

    ET.

    Table 11-4: Sewer Developer Charges per Assessment

    Item Developer Charge

    Residential Development 4948

    Non-Residential Development 4948

  • Sewerage Asset Management Plan

    Orange City Council Page 30

    Operation, Maintenance and Administration Costs

    As a default, FINMOD assumes no change in the real operation, maintenance and administration (OMA)

    historical costs per assessment, and increases the total annual OMA expenditure in line with growth. These

    costs are adjusted annually for inflation.

    Additional OMA costs to the sewer fund have been considered in this financial plan, as detailed in Table 11-5.

    Table 11-5: Additional OMA costs to the sewer fund

    Item Additional OMA costs to Sewer Fund

    Energy Costs

    Adjustment to Electricity Contract -$53k from 2019/20, adjusted annually for CPI

    Other Revenue

    Internal loan incomes – loans to the Water Fund and General Fund from the Sewer Fund1

    $ 8.66M @ 2% interest only over 20 years until 2034/35

    $ 3.3M @ 2% interest over 24 years until 2040/41

    $ 2.493M @ 2% interest over 10 years until 2026/27

    Non-Residential Income

    One of the inputs to FINMOD is the proportion of income from annual charges that will be provided from

    residential customers. This input variable has a significant impact on the outcomes, as typical residential bills

    are affected by the contribution of non-residential customers to the total income from annual charges.

    For the sewerage scheme, the historical split between residential and non-residential customers has been

    assumed to continue for the next 30 years.

    Table 11-6: Sewer Income Split

    Item User Charges

    Residential Assessments – Service Availability 76.44 %

    Non-Residential Assessments – Trade Waste 23.56 %

    Total 100 %

    1 Annual Financial Statements June 2018 – Note 22

  • Sewerage Asset Management Plan

    Orange City Council Page 31

    Capital Works Program

    The sewerage business is a highly capital-intensive service, with capital costs representing about 70% of the

    cost of providing the sewerage service.

    Council’s capital works program is divided into three categories:

    New Assets for improved standards (e.g. improvements to wastewater effluent quality).

    New Assets for growth.

    Renewals – replacement of assets that have reached the end of their useful life.

    The 30 Year Capital Works Program is included in Appendix C. A summary is shown in Table 11-7

    Table 11-7: 30 Year Sewer Capital Works Program

    Category 30 Year Total Capital Works

    New Assets for Improved Standards $ 8,535,000

    New Assets for growth $ 16,389,000

    Renewals $ 55,222,000

    Total $ 80,146,000

  • Sewerage Asset Management Plan

    Orange City Council Page 32

    11.2 Sewer Fund Model Results

    The main output parameter of this financial plan is the Typical Residential Bill (TRB) in current (2019/20 $)

    dollars over the next 30 years. The TRB is the annual bill paid by a non-pensioner2 resident.

    The purpose of the financial modelling is to identify the lowest TRB that will enable Council to fund the

    operation, maintenance and development of the system. The TRB is a measure of affordability, and sets the

    price path Council needs to set in order to meet the proposed levels of service.

    It is important to note that the financial outcomes (e.g. TRB, cash and investments) are shown in 2019/20

    dollars. CPI adjustments are required annually.

    Financial Data

    The Sewerage Fund at 30 June 2019 had cash and investments totalling $47,234,000 and borrowings of

    $995,000. According to Council’s loan repayment schedule, the existing loans will be repaid over the next 20

    years.

    The minimum Cash and Investments modelled in the sensitivity analysis has been kept above approximately

    10% of business income in the first few years, or $6,500,000.

    Capital Works and Growth

    The capital works and growth projectsions are shown graphically in Figure 11-2.

    Figure 11-2: Sewerage Capital Works and Growth

    2 Pensioners receive a $87.50 pensioner rebate for each of water supply and sewerage

  • Sewerage Asset Management Plan

    Orange City Council Page 33

    Typical Residential Bill

    Council levies a uniform residential sewerage charge of $523 in 2019/20. Over the next 4 years, this represents

    a Typical Residential Bill of (adjusted annually for CPI of 2.5%):

    2019/20 - $523

    2020/21 - $536

    2021/22 - $549

    2022/23 - $563

    Results Summary & Recommendations

    The results are summarised in Figure 11-3. The main output parameters shown in the figure are all in 2020/21

    dollars:

    Typical Residential Bill:

    The modelling indicates that the current TRB is sufficient to fund the operation and development of the

    sewerage network identified in the current Capital Works Program (Appendix C), without the need for

    borrowing.

    There is provision to reduce the current TRB – refer to the sensitivity analysis for the minimum TRB

    required for each scenario.

    Cash and Investments:

    The cash grows over the modelled years. It accumulates in periods when capital investment is low, and

    then the reserves are reduced as money is invested in new assets and renewals but is overall increasing

    towards 2049.

    Borrowings:

    Loans are required when accumulated cash and investments are insufficient to fund capital works. The

    base case includes all new works are funded through accumulated cash and investments, and no

    borrowing is used.

  • Sewerage Asset Management Plan

    Orange City Council Page 34

    Figure 11-3: Sewer Fund Base Case Results (2020/21 $)

  • Sewerage Asset Management Plan

    Orange City Council Page 35

    Sewer Fund Model Sensitivity Analysis

    A sensitivity analysis was carried out in order to assess the sensitivity of results to the input parameters. The

    results of the sensitivity analysis are shown in Table 11-8. Four additional cases were modelled, as described

    below:

    Minimum Required TRB: the TRB was reduced until the minimum Cash and Investments over the 30

    Year model was at $6.5M. The following scenarios also used this threshold to calculate the TRB.

    Slow growth: The growth projections were modified from the figures in Table 11-3, to a growth rate of

    0.5% p.a. over the 30 year planning period.

    The Cash & Investments at year 30 was modelled to be the same as current 2020 levels ($47 million).

    Fully funding the renewal gap: the capital works program was increased to fully fund the renewal gap

    identified in Section 8 through accumulated surpluses.

    Table 11-8: Sewer Fund Sensitivity Analysis

    Scenario Assessment Growth Rate Total Capital Works

    C&I Final Year ($M)

    TRB 2020$

    BASE CASE Status Quo (Existing TRB)

    0.9 $80,146,000 128 523

    1. Status Quo (Minimum TRB)

    0.9 $80,146,000 6.8 315

    2. No net decrease in Cash and Investments

    0.9 $80,146,000 50.5 390

    3. Slow growth (Minimum TRB)

    0.5 $80,146,000 6.9 337

    4. Increased Total Renewals (Minimum TRB)

    0.9 123,900,000 6.5 377

    The sensitivity analysis indicates that the minimum TRB for sewerage is highly sensitive maintaining the

    reserves of Cash & Investments at current levels, which shows the highest TRB, increasing the total capital

    works program, which shows the next highest TRB.

    However, both scenarios have significantly less TRBs than the base case (current TRB) of $523p.a.

    The sensitivity analysis also indicates that the lowest TRB is found in Case 1, where the renewal program is

    kept at current funding levels (and the renewal gap as demonstrated in Section 8 exists), and the reserves are

    used to fund the capital works program.

    The following figures show a comparison of the cases.

  • Sewerage Asset Management Plan

    Orange City Council Page 36

    Figure 11-4: Sewer Fund Sensitivity Analysis – TRB

  • Sewerage Asset Management Plan

    Orange City Council Page 37

    Figure 11-5: Sewer Fund Sensitivity Analysis – Cash and Investments

    Figure 11-6: Sewer Fund Sensitivity Analysis – Borrowing

  • Sewerage Asset Management Plan

    Orange City Council Page 38

    12 Key Performance Measures

    Department of Industry (Water) publishes the NSW Benchmarking Report in May each year for the previous

    financial year. Orange City Council’s performance as a sewerage utility is also reported via the Triple Bottom

    Line (TBL) report each year. The 2018/19 TBL Report is due to be published in May 2020. Table 12-1 shows a

    summary of the performance indicators included in the annual TBL Report.

    Those areas where current performance has not met target performance are addressed in the Water and

    Sewer Annual Report.

    Table 12-1: How did we perform in 2018/19? – TO BE PROVIDED WB

    Category Key Performance Measure

    2017/ 2018

    2018/ 2019

    Target 3 National Average4

    Pricing Typical Residential Bill $/assessment 498 - ●

    Residential Access Charge $/assessment 498 - ●

    Non-residential sewer charge

    c/kL 234 - ●

    Finance Operating Cost per property

    $/property 389 - ●

    Economic Real Rate of Return

    ratio 1.7 - ●

    Customer Average Sewerage Interruption

    mins 75

  • Sewerage Asset Management Plan

    Orange City Council Page 39

    13 Risk Management Plan

    Council is committed to the identification and elimination or reduction of risks associated with hazards that

    arise throughout Council operations as far as reasonably practicable. To facilitate this process an Enterprise

    Risk Management Plan has been developed which includes the management of risks for each of its assets.

    From this Plan the key Risks have been identified in Table 13-1.

    Table 13-1: Critical Risks and Treatment Plans

    Asset at Risk What can Happen Risk Rating

    Risk Treatment Plan

    All Assets Ageing asset failure impacting ability to provide services

    Moderate Undertake criticality assessment, ensure implementation of CCTV inspection process

    Sewage Treatment

    Mechanical/Electrical failure affecting effluent quality

    Major Operational procedures and BCPs.

    Sewage Treatment

    Extra Costs incurred to treat sewage in wet weather flows

    Moderate Inflow/Infiltration Program

    New Developments

    Failure to adequately service new areas

    Moderate Infrastructure modelling, Development Control Plan

    Pump Stations Mechanical/Electrical failure affecting service

    Moderate Pump maintenance program

    Reticulation Effluent quality degradation in reticulation below standards

    Minor Flushing Maintenance Program

    One of the outcomes of this assessment is the determination of Critical Assets. Critical Assets are specific

    assets which have a high consequence of failure but not necessarily a high likelihood of failure. By identifying

    critical assets and critical failure modes, Council can appropriately target and refine inspection regimes,

    maintenance plans and capital expenditure plans.

  • Sewerage Asset Management Plan

    Orange City Council Page 40

    Operations and maintenance activities may also be targeted to mitigate critical assets failure and maintain

    service levels. These activities may include increased inspection frequency, higher maintenance intervention

    levels, etc.

    Pumping stations where there is a potential for failure to risk public safety, public health or property have

    been identified as critical, as has the Sewage Treatment Plants.

    Table 13-2: Critical Assets

    Critical Assets Critical Failure Mode Treatment Plan

    Orange Sewerage Treatment Plant

    Mechanical/Electrical Assets:

    Reduced flow output

    Excessive or unusual vibration

    Excessive or unusual noise

    Excessive or unusual temperature increase

    Leakage from seals

    External corrosion

    Oil or grease leaks

    Pollution Incident Response Management Plan

    Spring Hill Sewerage Treatment Plant

    Mechanical/Electrical Assets:

    Reduced flow output

    Excessive or unusual vibration

    Excessive or unusual noise

    Excessive or unusual temperature increase

    Leakage from seals

    External corrosion

    Oil or grease leaks

    Pollution Incident Response Management Plan

    North Orange 1 Pump Station North Orange 2 Pump Station March Road Pump Station Beer Road Pump Station Lucknow 1 Pump Station

    Reduced flow output

    Excessive or unusual vibration

    Excessive or unusual noise

    Excessive or unusual temperature increase

    Leakage from seals

    External corrosion

    Oil or grease leaks

    Pollution Incident Response Management Plan

    Lucknow 1 Rising Main Beer Rd Rising Main North Orange 1 Rising Main North Orange 2 Rising Main March Rd Rising Main

    Corrosion

    Joint leakage

    Biofilms

    Fracture

    Longitudinal split

    Circumferential break

    Leaching of lime and calcium silicate hydrates

    Pollution Incident Response Management Plan

  • Sewerage Asset Management Plan

    Orange City Council Page 41

    14 Performance Review and Proposed Improvement Plan

    Achievements

    The following actions have been completed since the development of the last Sewerage Asset Management

    Plan:

    Annual budgets have been updated

    Complete condition rating of all above-ground assets

    Asset data hierarchy reviewed

    Risk Assessment completed for sewerage service through Enterprise Risk Management System

    Review of Customer Request Management system reporting categories for Water & Sewer

    Improvement Plan

    Asset Management improvements pertaining to the asset management system, or Council’s approach to asset

    management, are identified in the Asset Management Strategy. The improvements in Table 14-1 are

    specifically to improve the asset management of the sewerage network only.

    Table 14-1: Improvement Plan

    Action Responsibility Target Progress

    Implement Maintenance Scheduling Work Orders System

    AE, WE, WTS December 2016

    ON HOLD – to be implemented with AMG Working Group

    Develop an Inflow/infiltration Management Plan

    AE, WE FY2020 In progress – sewer flow gauging program

    Review CRM categories CS FY2020 In progress

  • Sewerage Asset Management Plan

    Orange City Council Page 42

    Appendix A: Operations and Maintenance Programs

    458 Sewerage Reticulation

    Reoccurrence per year Task

    Nu

    mb

    er

    Ora

    nge

    Re

    ticu

    lati

    on

    Spri

    ng

    Hill

    Re

    ticu

    lati

    on

    Cad

    ia E

    fflu

    en

    t

    Activity Type

    z46

    5

    z46

    5

    -

    OPERATIONS

    No programs

    MAINTENANCE

    Cleaning – Chokes Unplanned – Locate fault & repair .0024 1 1

    Cleaning – Flushing Planned – Frequency based 1 1 1

    Inspections – CCTV Planned – Frequency based .0654 1 1

    Inspections – Manholes Planned – Frequency based .0673 1 1

    Mains Repair Unplanned – Locate fault & repair .0024 1 1 1

    Root Foaming Planned – Frequency based 1 1

    Sewer Reconstruction Planned – Condition based 1 1

  • Sewerage Asset Management Plan

    Orange City Council Page 43

    453 Sewage Treatment

    Reoccurrence per year Task

    Nu

    mb

    er

    Ora

    nge

    STP

    Spri

    ng

    Hill

    STP

    Activity Type

    z46

    5

    z46

    9

    OPERATIONS

    EPA Testing Planned – Compliance based .0649 12 12

    Sampling Planned – Compliance based .0871 12 12

    Operations Planned – Frequency based .0622 365 52

    Sludge Transport Planned – Frequency based .0872 1 -

    Trade Waste Monitoring Planned – Frequency based .0603 1 -

    Trade Waste Operations Planned – Frequency based .0603 1 -

    Electrical Testing & Tagging Planned – Frequency based .0626 1 1

    Confined Space Equipment Inspections Planned – Frequency based .0628 1 -

    Gas Monitor Inspections Planned – Frequency based .0628 1 -

    MAINTENANCE

    Flowmeter Calibration Planned – Frequency based .0024 1 1

    Instrument Calibration Planned – Frequency based .0024 1 1

    Lab gear servicing Planned – Frequency based .0024 1 1

    Cleaning – Clarifiers Planned – Frequency based .0622 1/7 -

    Cleaning – Lagoons Planned – Frequency based .0623 - 1

    Gantry Inspections Planned – Frequency based .0622 4 -

    Servicing – Aerators Planned – Frequency based .0024 1 1

    Servicing – Blowers Planned – Frequency based .0024 2 -

    Servicing – Boilers Planned – Frequency based .0024 2 -

    Servicing – Centrifuge Planned – Frequency based .0024 1 -

    Servicing – Compressors Planned – Frequency based .0024 4 -

    Servicing – Pumps Planned – Frequency based .0531 1 1

    Electrical Repair Unplanned – Locate fault & repair .0626 1 1

    Mechanical Repair Unplanned – Locate fault & repair .0024 1 1

  • Sewerage Asset Management Plan

    Orange City Council Page 44

    456 Sewage Pumping – Major Pump Stations

    Reoccurrence per year Task

    Nu

    mb

    er

    Air

    po

    rt S

    PS

    Bee

    r R

    oad

    SP

    S

    Dea

    n D

    rive

    SP

    S

    Lake

    Can

    ob

    ola

    s SP

    S

    Leec

    hat

    e SP

    S

    Luck

    no

    w N

    o 1

    SP

    S

    Luck

    no

    w N

    o 2

    SP

    S

    Mal

    lee

    Pla

    ce S

    PS

    Mar

    ch R

    oad

    SP

    S

    Mit

    chel

    l Hw

    y SP

    S

    No

    rth

    Ora

    nge

    1 S

    PS

    No

    rth

    Ora

    nge

    2 S

    PS

    No

    rth

    po

    int

    SPS

    Ph

    illip

    Str

    eet

    SPS

    Sieb

    en D

    rive

    SP

    S

    Shir

    alee

    No

    1 S

    PS

    Shir

    alee

    No

    2 S

    PS

    Sop

    hie

    Pla

    ce S

    PS

    Spri

    ng

    Hill

    No

    1

    Spri

    ng

    Hill

    No

    2

    Turn

    er C

    res

    SPS

    Wo

    od

    war

    d S

    tree

    t

    SPS

    Activity Type

    Z46

    3

    Z10

    56

    9

    Z46

    1

    - - Z46

    3

    Z46

    3

    Z46

    1

    Z10

    57

    0

    Z46

    1

    Z18

    84

    4

    Z18

    84

    5

    Z46

    1

    Z46

    1

    Z46

    1

    Z46

    1

    Z46

    1

    Z46

    1

    Z46

    3

    Z46

    3

    Z46

    1

    Z46

    1

    OPERATIONS

    Operations Planned – Frequency based .0062 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52 52

    Confined Space Equipment Inspections Planned – Frequency based .0683 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

    Gas Monitor Inspections Planned – Frequency based .0683 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

    Electrical testing & tagging Planned – Frequency based .0626 1 1 1 1 1

    MAINTENANCE

    Lagoon cleaning Planned – Frequency based .0623 1

    Gantry Inspections Planned – Frequency based .0622 1 1 1 1 1 1

    Servicing – Generators Planned – Frequency based .0024 1

    Servicing – Pumps Planned – Frequency based .0531 1/2 1 1/2 1/2 1 1/2 1 1/2 1 1 1/2 1/2 1/2 1/2 1/2 1/2 1/2

    Electrical Repairs Unplanned – Locate fault & repair .0626 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

    Mechanical Repairs Unplanned – Locate fault & repair .0024 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1

    Pump Well wash downs Planned – Frequency based .0024 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12 12

    Rising Main inspections Planned – Frequency based .0024 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4 4

  • Sewerage Asset Management Plan

    Orange City Council Page 45

    456 Sewage Pumping – Single Pump Units

    Reoccurrence per year Task

    Nu

    mb

    er

    Air

    po

    rt E

    ast

    SPS

    Bla

    cket

    t P

    lace

    SP

    S

    Bo

    tan

    ic G

    ard

    ens

    Caf

    é SP

    S

    Bu

    sh F

    ire

    Shed

    Mo

    lon

    g SP

    S

    Car

    eflig

    ht

    SPS

    Clin

    ton

    Str

    eet

    SPS

    Oly

    mp

    ic P

    oo

    l SP

    S

    Fore

    st R

    oad

    Pre

    ssu

    re

    Sew

    er

    Ree

    ce S

    PS

    Shep

    her

    ds

    Lan

    e P

    ress

    ure

    Sew

    er

    Activity Type

    Z46

    3

    Z46

    1z

    Z46

    1

    Z14

    40

    9

    Z46

    1

    Z46

    1

    - Z46

    1

    Z46

    1

    Z46

    1

    OPERATIONS

    Nil

    MAINTENANCE

    Electrical Repairs Unplanned – Locate fault & repair .0626 1 1 1 1 1 1 1 1 1 1

    Mechanical Repairs Unplanned – Locate fault & repair .0024 1 1 1 1 1 1 1 1 1 1

    Rising Main inspections Planned – Frequency based .0024 4 4

  • Sewerage Asset Management Plan

    Orange City Council Page 46

    Appendix B: Four Year Renewal Programs

    The following programs are based on best available information with the first year of works expected to be

    delivered within budgetary constraints. The following years will be validated each year with a review of the

    condition so that assets are only renewed at the intervention level. Works that can’t be funded within the 4

    years but which are expected to be due based on modelling are grouped as ‘unfunded works’.

    456 Sewage Pumping – Sewage Pump Stations

    Pump Station Asset / Project Renewal Year Renewal Cost

    Blackett Place – eone Electrical - Blackett Place 2020 $ 5,594

    Leechate SPS - 10L/s Electrical - Leechate SPS 2020 $ 123,524

    March Rd SPS - 165L/s Ventilation System - March Road SPS 2020 $ 16,848

    TOTAL 2020 $ 145,966

    Nil - - -

    TOTAL 2021 $

    Nil - - -

    TOTAL 2022 $

    March Rd SPS - 165L/s Wet Well Lid - March Road SPS 2023 $ 9,126

    TOTAL 2023 $ 9,126

    March Rd SPS - 165L/s Old Wet Well Lid - March Road SPS 2024 $ 9,126

    March Rd SPS - 165L/s Telemetry - March Road SPS 2024 $ 16,848

    TOTAL 2024 $ 25,974

  • Sewerage Asset Management Plan

    Orange City Council Page 47

    453 Sewage Treatment – Sewage Treatment Plants

    Plant Treatment Unit Asset / Project Renewal Year

    Renewal Cost

    Orange 400 Activated Sludge (Secondary Sedimentation)

    Clarifier 7 Chain Scraper MF2.2 2020 $ 98,280

    Orange 400 Activated Sludge (Secondary Sedimentation)

    Clarifier 7 Chain Scraper MF2.2 Motor 2020 $ 11,340

    Orange 500 Chlorination Plant Turbidity Analyzer - Chlorine Room 2020 $ 10,800

    TOTAL 2020 $120,420

    Nil - - - -

    TOTAL 2021 $

    Orange 700 Anaerobic Digestion Plant (Sludge Treatment)

    Sludge Circulation Pump P7509 Motor

    - Heat Exchange

    2022 $ 6,048

    TOTAL 2022 $6,048

    Orange 000 Site Works & Process Control

    Telemetry MTU - Wastewater Plant 2023 $ 113,400

    Orange 400 Activated Sludge (Aeration & Anoxic)

    Redox Sensor Probe - Anoxic Tank 2023 $ 22,680

    Orange 400 Activated Sludge (Aeration & Anoxic)

    Combined Amonia/Nitrate Probe - Anoxic Tank

    2023 $ 22,680

    Orange 400 Activated Sludge (Secondary Sedimentation)

    Scum Pump P4901 Motor - Secondary Clarifiers

    2023 $ 1,512

    TOTAL 2023 $160,272

    Orange 700 Anaerobic Digestion Plant (Sludge Treatment)

    Mixer M7514 - Secondary Digestor $ 22,680

    Spring Hill

    Effluent Pump Station Effleunt Pump 8011 $ 4,914

    Spring Hill

    Effluent Pump Station Effluent Pump 8012 $ 4,914

    TOTAL 2024 $ 32,508

  • Sewerage Asset Management Plan

    Orange City Council Page 48

    456 Sewage Pumping – Sewer Rising Mains

  • Sewerage Asset Management Plan

    Orange City Council Page 49

    458 Sewer Reticulation – Sewer Gravity Trunk Mains (CCTV)

  • Sewerage Asset Management Plan

    Orange City Council Page 50

    458 Sewer Reticulation – Sewer Gravity Reticulation Mains

  • Sewerage Asset Management Plan

    Orange City Council Page 51

    Appendix C: 30 Year Capital Works Program

    $’000

    Re

    ne

    wal

    Ne

    w A

    sse

    ts f

    or

    Gro

    wth

    Ne

    w A

    sse

    ts f

    or

    Imp

    rove

    d S

    tan

    dar

    ds 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    PROJECT DESCRIPTION

    20

    19

    /20

    20

    20

    /21

    20

    21

    /22

    20

    22

    /23

    20

    23

    /24

    20

    24

    /25

    20

    25

    /26

    20

    26

    /27

    20

    27

    /28

    20

    28

    /29

    20

    29

    /30

    20

    30

    /31

    20

    31

    /32

    20

    32

    /33

    20

    33

    /34

    20

    34

    /35

    20

    35

    /36

    20

    36

    /37

    20

    37

    /38

    20

    38

    /39

    20

    39

    /40

    20

    40

    /41

    20

    41

    /42

    20

    42

    /43

    20

    43

    /44

    20

    44

    /45

    20

    45

    /46

    20

    46

    /47

    20

    47

    /48

    20

    48

    /49

    CAPITAL WORKS PROGRAM

    Total New Assets for Improved Standards 100% 255 1,495 0 550 4,550 1,435 250 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

    Total New System Assets for Growth 100% 812 3,007 1,767 1,065 605 1,549 3,623 432 45 135 45 2,045 45 135 45 45 45 135 45 45 45 135 45 45 45 135 45 45 45 135

    Total Renewals 100% 1,745 6,145 1,425 3,195 1,395 1,405 1,463 1,493 1,363 3,213 3,963 3,463 1,393 1,363 1,363 1,363 1,463 1,393 1,363 1,363 1,363 1,463 1,393 1,363 1,363 1,363 1,463 1,393 1,363 1,363

    TOTAL CAPITAL WORKS 2,812 10,647

    3,192 4,810 6,550 4,389 5,336 1,925 1,408 3,348 4,008 5,508 1,438 1,498 1,408 1,408 1,508 1,528 1,408 1,408 1,408 1,598 1,438 1,408 1,408 1,498 1,508 1,438 1,408 1,498

    451 SEWAGE ADMINISTRATION

    Sewer Temporary Flow Survey 100% 0 200

    Sewer Model Update 100% 0 90 0 0 0 90 0 0 0 90 0 0 0 90 0 0 0 90 0 0 0 90 0 0 0 90 0 0 0 90

    CCTV (Centroc) - 900mm C6 Trunk Main 100% 0 50

    CCTV (Centroc) - Sample of Sewer Mains for Reval

    100% 0 100 0 0 0 0 100 0 0 0 0 100 0 0 0 0 100 0 0 0 0 100 0 0 0 0 100 0 0 0

    Water & Sewer Revaluation (50% Sewer Fund)

    100% 0 0 30 0 0 0 0 30 0 0 0 0 30 0 0 0 0 30 0 0 0 0 30 0 0 0 0 30 0 0

    TOTAL 451 SEWER ADMINISTRATION 0 440 30 0 0 90 100 30 0 90 0 100 30 90 0 0 100 120 0 0 0 190 30 0 0 90 100 30 0 90

    453 SEWAGE TREATMENT

    Sewer Treatment Renewals 100% 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213 213

    Primary No 2 Coating 100% 0 0 0 0 0 0 250

    Carbon dosing 100% 0 75 0 0 0 845

    Secondary Clarifier Upgrade 100% 100 100 100 100 100 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110 110

    Cadia Tank 1 Roofing 100% 0 0 0 0 0 90

    Cadia Tank 2 Chlorine Booster 100% 0 0 0 0 0 500

    Cadia UV design, construction and dechlorination

    100% 0 0 0 250 4,100

    Sewage Treatment Plant Inlet Works Upgrade

    100% 350 4,500

    Aeration Upgrade 100% 0 100 0 1,800

    Orange STP Dechlorination (Effluent) 100% 0 0

    Orange STP Biosolids Handling 100% 0 0 0 0 450

    Back-Up Diesel Generator 100% 0 0 0 300

    Orange STP Digestor Upgrade 100% 0 0 0 0 0 0 0 100 0 0 2,600

    Concept Design - Water infrastructure 100% 25

    STP Process Water Upgrade 100% 0 470

  • Sewerage Asset Management Plan

    Orange City Council Page 52

    $’000

    Re

    ne

    wal

    Ne

    w A

    sse

    ts f

    or

    Gro

    wth

    Ne

    w A

    sse

    ts f

    or

    Imp

    rove

    d S

    tan

    dar

    ds 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30

    PROJECT DESCRIPTION

    20

    19

    /20

    20

    20

    /21

    20

    21

    /22

    20

    22

    /23

    20

    23

    /24

    20

    24

    /25

    20

    25

    /26

    20

    26

    /27

    20

    27

    /28

    20

    28

    /29

    20

    29

    /30

    20

    30

    /31

    20

    31

    /32

    20

    32

    /33

    20

    33

    /34

    20

    34

    /35

    20

    35

    /36

    20

    36

    /37

    20

    37

    /38

    20

    38

    /39

    20

    39

    /40

    20

    40

    /41

    20

    41

    /42

    20

    42

    /43

    20

    43

    /44

    20

    44

    /45

    20

    45

    /46

    20

    46

    /47

    20

    47

    /48

    20

    48

    /49

    Decommission Trickling Filters 100% 0 0 0 0 0 0 0 0 0 1,850

    Orange STP Upgrade 50% 50% 0 0 0 0 0 0 0 0 0 0 0 4,000

    TOTAL 453 SEWER TREATMENT 688 5,458 313 2,663 4,863 1,758 573 423 323 2,173 2,923 4,323 323 323 323 323 323 323 323 323 323 323 323 323 323 323 323 323 323 323

    456 SEWAGE PUMPING

    Sewer Pump Station Renewals 100% 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140

    Lake Canobolas Sewer Upgrade 100% 0 800

    Burrendong Way Rural Residential 100% 0 50 0 0 0 854

    Leeds Parade Rural Residential 100% 0 50 0 20 0 0 1,578

    Bloomfield Servicing Strategy 100% 0 50

    Burrendong Way Pump Station Access Road

    100% 30

    Operations Shed 100% 200

    TOTAL 456 SEWAGE PUMPING 370 1,090 140 160 140 994 1,718 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140 140

    458 SEWER RETICULATION

    Sewer Reconstructions 100% 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100

    Vent Conversions CVR 11599 100% 42 42 42 42 42 42

    Sewer CCTV - Unit 969 100% 0 150

    Flow Gauges / Modelling 100% 45 150 150 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45 45

    Manholes 100% 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100 100

    Sewer Main Relining Program 100% 70