sgp4813 measurement of quantities

43
www.utm.my innovative entrepreneurial global 1 MEASUREMENT OF QUANTITIES Mat Naim bin Abdullah @ Mohd Asmoni Diploma QS (UTM), BSc. QS (Glasgow Caledonian University), M.Eng. Construction (UTM), PhD Facilities Management (UTM) matnaim @utm.my [email protected] C04-308 019-7573760

Upload: alanchong88

Post on 06-May-2015

618 views

Category:

Business


2 download

TRANSCRIPT

Page 1: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 1

MEASUREMENT OF QUANTITIES

● Mat Naim bin Abdullah @ Mohd Asmoni● Diploma QS (UTM), BSc. QS (Glasgow

Caledonian University), M.Eng. Construction (UTM), PhD Facilities Management (UTM)

[email protected][email protected]● C04-308● 019-7573760

Page 2: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 2

MEASUREMENT OF QUANTITIES

Assumption No. 1: Total land area = 10m x 10m

Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron

Page 3: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 3

MEASUREMENT OF QUANTITIES

Page 4: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 4

MEASUREMENT OF QUANTITIES

Construction Method

1. Preliminaries (Initial site works) - % of total cost2. Site clearance and earthwork3. Foundation construction (E.g. Piling and footing)4. Work below lowest floor finish5. Frame6. Staircase7. Upper Floor8. Roof9. Wall and partition10. Door and window11. Finishes12. Sundries (Built-in furniture)13. Building services (M&E, ICT etc)14. External works (Water reticulation, landscape etc)

Page 5: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 5

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

1) Site clearance

1.1) Clear the site including grubbing of trees, shrubs and demolish any existing structure and cart away and dump to the specified location.

10.00 10.00 ---------- 100.00 100 m2 ----------

Area of the site:10 x 10 = 100m2

Page 6: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 6

MEASUREMENT OF QUANTITIES

Page 7: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 7

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.1) Piling including all related works

6.10 6.10 ---------- 37.21 37 m2 ----------

Area of the building:Length = 3048 + 3048 = 6096Width = 3048 + 3048 = 6096

Page 8: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 8

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.2) Excavation for pile cap

9/1.22 1.22 1.57 ---------- 21.03 21 m3 ----------

Size of pile cap = 1219 x 1219Depth of excavation: 1524 + 50 (lean concrete) = 1574

Excavation and Lean concrete as base for pile cap

Page 9: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 9

MEASUREMENT OF QUANTITIES

Page 10: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 10

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.3) Reinforced concrete Grade 30 for pile cap

9/1.22 1.22 0.31 ---------- 4.15 4 m3 ----------

Size of pile cap:Length = 1219 Width = 1219Thickness = 305

Concrete for pile cap

Page 11: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 11

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.4) 50mm thick lean concrete Grade 15 for pile cap

9 / 1.22 1.22 ---------- 13.40 13 m2 ----------

Size of pile cap:Length = 1219 Width = 1219

Excavation and Lean concrete as base for pile cap

Page 12: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 12

MEASUREMENT OF QUANTITIES

Page 13: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 13

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation

2.5) Formwork for pile cap

9 / 4 /1.22 0.31 ---------- 13.62 14 m2 ----------

Size of pile cap:Length = 1219 Width = 1219Thickness = 305

9/2/1.22 0.31 6.81

9/2/1.50 0.31 8.37

15.18 15m2

Formwork for pile cap

Page 14: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 14

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

2) Foundation2.6) Reinforcement bar Y12 for pile cap

9/2/ 12/ 1.53 ---------- 330.48m x 0.89 kg/m = 294.13kg ----------

= 294 kg

Length:

= a + b + c – cover = 305 + 1219 + 305 – 6(50)= 1829 – 300= 1529

No. of bars:= (b/100) + 1= ((1219 – 2(50)cover )/100 )+1 = 12 nos.

a

b

c

Page 15: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 15

MEASUREMENT OF QUANTITIES

@100 c/c

Page 16: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 16

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF Taker off : Checked by:3.1) Column stump3.1.1) Reinforced concrete Grade 30 for

column stump

9/0.23 0.23 1.04 ---------- 0.50 1 m3 ----------

Size of column stump:Length = 229Width = 229Height = 1524 – 305 thickness of pile

cap – (351/2) Half of beam’s thickness

= 1043.50

Page 17: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 17

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.1) Column stump3.1.2) Formwork for column stump

9/4/0.23 1.04 ---------- 8.61 9 m2 ----------

Size of column stump:Length = 229Width = 229Height = 1524 – 305 thickness of pile

cap – (351/2) Half of beam’s thickness

= 1043.50

Page 18: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 18

MEASUREMENT OF QUANTITIES

@100 c/c

Height of column stump

Page 19: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 19

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.1) Column stump3.1.3) Reinforcement bar Y12 for

column stump

9/4/2.97 ---------- 106.92m x 0.89kg/m = 95.16kg ----------

95kg

Length = a + half beam’s thickness – cover + 2 laps

= 1524 + (351/2) – 50 + (660x2)= 2969.50

lap

a

lap

Page 20: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 20

MEASUREMENT OF QUANTITIES

General Notes

Page 21: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 21

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.1) Column stump3.1.4) R6 link in for column stump

9/6/0.62 ---------- 33.48m x 0.22kg/m = 7.36kg ----------

7kg

Length of link: (length of CS– 2cover) x 4 +hook

=(229-100)+(229-100)+(229-100)+(229-100)+100=616

No. of link:Height of column stump = 1043.50=(1043.50/229)+1= 6 nos.

Hook

Page 22: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 22

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.2) Ground beam3.2.1) Excavation for ground beam

2/3/6.10 0.23 0.35 ---------- 2.95m3 ----------

3m3

Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351

Excavation for ground beam

Page 23: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 23

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.2) Ground beam3.2.2) Reinforced concrete Grade 30 for

ground beam

2/3/6.10 0.23 0.35 ---------- 2.95m3 ----------

3m3

Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351

RC for ground beam

Page 24: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 24

MEASUREMENT OF QUANTITIES

Assumption No. 1: Total land area = 10m x 10m

Project Title: Construction and completion of guard houseOwner: Panicsonic Sdn BhdArchitect: A to Z Sdn BhdDrawing Title: Ground beam and foundation plan-------------------------------------------------------------------------Drawn by: SheilaChecked by: Aaron

Page 25: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 25

MEASUREMENT OF QUANTITIES

@100 c/c

Height of column stump

Page 26: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 26

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.2) Ground beam3.2.3) Formwork for ground beam

2/3/2/6.10 0.35 ---------- 25.62 26m2 ----------

Size of ground beam:Length=3048+3048=6096Width = 229Thickness = 351

Installation of reinforcement bar and formwork for ground beam

Page 27: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 27

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.2) Ground beam3.2.4) Reinforcement bar Y10 for

ground beam

2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ----------

97kg

Length = (length–2cover)+(2bend-2cover)=(6096-(2x50))+(2x351)-(4x50)= 6498

Page 28: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 28

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.2) Ground beam3.2.5) R6 stirrup for ground beam

2/3/28/0.86 ---------- 144.48m x 0.22kg/m = 31.79kg ----------

32kg

Length of stirrup:

=(229-100)+(351-100)+(229-100)+(351-100)+100=860

No. of stirrup:Length of grd beam= 6096=(6096/229)+1= 28 nos.

Hook

Page 29: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 29

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF

3.3) Ground slab3.3.1) Excavation for ground slab

6.10 6.10 0.50 ---------- 18.61m3 19 m3 ----------

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Installation of formwork,Damp Proof Membrane (DPM) and BRC wire mesh for ground slab

Page 30: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 30

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.2) Reinforced concrete G30 in

ground slab

6.10 6.10 0.15 ---------- 5.58m3 ---------- 6 m3

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 31: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 31

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.3) Formwork for ground slab

4/6.10 0.15 ---------- 3.66m2 ----------

4 m2

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 32: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 32

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd3) WBLFF3.3) Ground slab3.3.4) BRC A8 for ground slab

6.10 6.10 ---------- 37.21m2 ----------

37 m2

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 33: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 33

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd3) WBLFF3.3) Ground slab3.3.5) DPM for ground slab

6.10 6.10 ---------- 37.21m2 ----------

37 m2

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 34: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 34

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.6) 50mm sand blinding for ground

slab

6.10 6.10 ---------- 37.21m2 ----------

37 m2

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 35: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 35

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

3) WBLFF3.3) Ground slab3.3.7) Hardcore for ground slab

6.10 6.10 0.30 ---------- 11.16m3 ----------

11 m3

Area of slab = length x widthDepth of excavation = 500mm

300mm thick hardcore

BRC A8 150mm thick concrete slab

DPM

50mm thick sand

Page 36: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 36

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME Taker off : Checked by:

4.1) Column4.1.1) Reinforced concrete Grade 30 for

column

9/0.23 0.23 3.00 ---------- 1.43 1 m3 ----------

Size of column:Length = 229Width = 229Height = Height of the wall = 3000mm

Installation of reinforcement bar and formwork for column

Page 37: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 37

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.1) Column4.1.2) Formwork for column

9/4/0.23 3.00 ---------- 24.84 25 m2 ----------

Size of column:Length = 229Width = 229Height = 3000

Page 38: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 38

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.1) Column4.1.3) Reinforcement bar Y12 for

column

9/4/4.50 ---------- 162.00m x 0.89kg/m = 144.18kg ----------

144kg

Length = height of column + half of roof beam + 1 lap + bend

= 3000+ (0.5x351) + 660 + 660= 4495.5

bend

Height of wall

lap

Page 39: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 39

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.1) Column4.1.4) R6 link in for column

9/14/0.82 ---------- 103.32m x 0.22kg/m = 22.73kg ----------

23kg

Length of link: (length of CS– 2cover) x 4 +hook

=(229-50)+(229-50)+(229-50)+(229-50)+100=816

No. of link:Height of column = 3000=(3000/229)+1= 14 nos.

Hook

Page 40: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 40

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME

4.2) Roof beam4.2.1) Reinforced concrete Grade 30 for

roof beam

2/3/6.10 0.23 0.35 ---------- 2.95m3 ----------

3m3

Size of roof beam:Length=3048+3048=6096Width = 229Thickness = 351

Page 41: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 41

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME

4.2) Roof beam4.2.2) Formwork for roof beam

2/3/6.10 0.93 ---------- 34.04 34m2 ----------

Size of roof beam:Length=3048+3048=6096Width = 229Thickness = 351

= 351 + 229 + 351= 931

Side

Soffit

Page 42: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 42

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME4.2) Roof beam4.2.3) Reinforcement bar Y10 for roof

beam

2/3/4/6.50 ---------- 156.00m x 0.62kg/m = 96.72kg ----------

97kg

Length = (length–2cover)+(2bend-2cover)=(6096-(2x50))+(2x351)-(4x50)= 6498

Page 43: Sgp4813 measurement of quantities

www.utm.my innovative ● entrepreneurial ● global 43

MEASUREMENT OF QUANTITIES

Project: Construction and completion of Guard House for Panicsonic Sdn Bhd

4) FRAME3.2) Roof beam3.2.5) R6 stirrup for roof beam

2/3/28/1.06 ---------- 178.08m x 0.22kg/m = 39.18kg ----------

39kg

Length of stirrup:

=(229-50)+(351-50)+(229-50)+(351-50)+100=1060

No. of stirrup:Length of beam= 6096=(6096/229)+1= 28 nos.

Hook