Page 1: Shell Quest CCS Project

QUEST CCS PROJECT

Stephen Harvey– QUEST Geophysicist

5

CO2 Pipeline

2

1

Amine Unit Compressor

1

Page 2: Shell Quest CCS Project

QUEST - LOCATION

March 19, 2014 Quest Project - MUN 2014, Calgary

Alberta    

Canada    

Quest Fort  Saskatchewan  

Fort  McMurray  

Edmonton  

Calgary  

! Capture  plant  located  near  Fort  Saskatchewan,  approx  60  km  N.E.  of  Edmonton  

2

Page 3: Shell Quest CCS Project

CCS IN ALBERTA

n  CCS is a significant part of GHG mitigation plans for both Canada and Alberta

n  Quest Funding

n  ~1.3 Bln $ project

n  165 MM$ CND, 700 MM$ AB

Source: Alberta 2008 Climate Change Strategy

GHG emissions profile and mitigation options – Alberta

CCS =70%

Materiality: Quest = 1.1 MT/a of

CO2 ~ 175,000 cars

50Mt

BUSINESS AS USUAL

ALBERTA’S PLAN

First CCS project in Alberta Oil Sands and it has massive scalability.

Cost of Project •  ~1.3 Bln $ Quest Funding •  165 MM$ CND, 700

MM$ AB

Page 4: Shell Quest CCS Project

The Athabasca Oil Sand Project (AOSP)

May 2014 4

Peace River

Calgary

Edmonton

Corridor Pipeline

Fort McMurray

Muskeg River Mine

Bitumen

Scotford Upgrader

Bitumen to Synthetic crude (255,000 bpd)

H2

Scotford Refinery

(Shell only)

AOSP - JV among Shell (60%); Chevron (20%); and Marathon (20%) QUEST Update - Pittsburgh CCUS Conference

Page 5: Shell Quest CCS Project

QUEST – Overview

 

SALT SEALS

Cement

SHALE SEALS

TARGET FORMATION

! Capture at the Scotford Upgrader from 3 Hydrogen Manufacturing Units - One million tonnes CO2 per year capacity for 25 years

! CO2 transported by 12 inch pipeline to storage, with 6 inch laterals

! Pipeline to 65 km north of the Upgrader

! Wells : 3 injection wells , 3 Deep Monitoring Wells and 9 Shallow Ground Water monitoring wells

! Execution Phase since Sept 2012

May 2014 5 QUEST Update - Pittsburgh CCUS Conference

Page 6: Shell Quest CCS Project

INTEGRATED CCS PROJECT �Technical aspects: Capture, Pipeline, Storage & MMV

CO2 Pipeline

2

Pipeline to storage site, 65 km

3 CO2 injectors

1

Amine Unit Compressor

1

Up to 1.2 Mtpa from the Scotford Upgrader

o  Commissioning Q1 2015 o  Sustained Injection by end 2015 o  Measurement, Monitoring &

Verification (MMV) o  25 year field life (27 Mt CO2 ) o  10 year closure period

Page 7: Shell Quest CCS Project

n  BCS Storage Complex n  Deep saline aquifer (~2km), porous sandstone (Por~16%, K~ 1D)

n  Multiple continuous seals to minimize containment risk

n  No significant faulting visible from wells or seismic

n  Well below hydrocarbon bearing formations(<1200m) and potable water zones (<200m)

n  Few legacy wells, nearest at ~20 km

QUEST Overview - Storage

34m

84m

44m

41m

Ultimate Seal

Secondary Seal

Primary Seal

Injection Target

Ultimate Seal

BC

S St

orag

e C

ompl

ex

Win

nipe

gosi

s C

ompl

ex

Upper Lotsberg

Lower Lotsberg

MCS – Middle Cambrian Shale

LMS – Lower Marine Sand

PreCambrian Basement BCS – Basal Cambrian Sand

85m

May 2014 7 QUEST Update - Pittsburgh CCUS Conference

Page 8: Shell Quest CCS Project

QUEST - Construction Progress Highlights

8

! All major equipment such as towers and the compressor have been received and on site.

! One HMU set of equipment modules installed.

! Pipeline construction progressing and > 50% welding is complete.

! Wells drilled and 2 injection wells tested in 2013

! Operations readiness activities progressing per plan

! Schedule is tracking on target costs slightly below target

! Public engagement activities continue through start-up.

May 2014 QUEST Update - Pittsburgh CCUS Conference

Page 9: Shell Quest CCS Project

QUEST - Amine Stripper Vessel lift – March, 2014 �

May 2014 9 QUEST Update - Pittsburgh CCUS Conference

Page 10: Shell Quest CCS Project

QUEST - 2013 Well Test Results - Injectivity

10

W ell  N am e Ra te D elta P In jectiv itym 3 / d k Pa m 3 / d /MPa

Ra dw a y  8 -­‐1 9 3 6 0 0 .9 5 3 7 9Redw a ter  1 1 -­‐3 2 4 9 2 1 2 .1 3 4 1Tho rh ild  5 -­‐3 5 3 4 2 0 .3 3 1 0 3 6Ra dw a y  7 -­‐1 1 3 9 6 0 .1 9 2 0 8 5

0

10000

20000

30000

40000

50000

60000

70000

3  Well  Avg  PI                            Water  Injection  Rates

Water  Injection            Potential

Estimated  CO2                    Injection  Potential

Quest  CO2  injection  requirement

Injection  Ra

te,  [reservoir  m

3/d]

Water  PICO2  UncertaintyQuest  Requirement

Linear  adjustmentto  FBHP  of  26  MPa

CO2/waterinjectivityratio  of  1.5  -­‐ 3

Quest  Initial  Rate=  900  -­‐ 1800  %  

May 2014 QUEST Update - Pittsburgh CCUS Conference

Regulatory Constraint Ø  30 Mpa Ø Fracture pressure 40Mpa

WATER INJECTIVITY / TEST RESULTS

CO2 INJECTION CAPABILITY

Page 11: Shell Quest CCS Project

Pressure and CO2 Plume Propagation

2015 - Start 2015 - Start 2016 – 1 Year Injection 2025 2025 – 10 Year Injeciton 2040 – Shut-in 2045 – Shut-in 5 years

2055 – Shut-in 15 years

MPa

2016 – 1 Year

2025 – 10 Years

2040 – Shut-in 2050 – 10 Years Shut-in 2085 – 45 Years Shut-in

Expectation delta Pressure

Expectation CO2 @ 8-19

Page 12: Shell Quest CCS Project

Heavy Oil Shell Canada

QUEST - New Well Results - Containment

May 2014 12 QUEST Update - Pittsburgh CCUS Conference

Gen-4- Pressure Distribution after 25 Years of Injection in the Mid Property / Mid Connectivity Case with an analytical aquifer extension

Gen -4- 25 Year FBHP Forecast for the mid property, mid connectivity case with analytic aquifer

n  Capacity very large compared to injected volume

n  Elevated pressure is very low - no risk of brine leakage n  Expected to be considerably less then Gen-4 – mid case

Page 13: Shell Quest CCS Project

QUEST IN-WELL MONITORING

Lotsberg

LMS

BCS

MCS UMS

Colorado

PreCambrian

Upper

Lower

CKLK

Quest Storage Complex

Freshwater

Geophone array (1 well only)

450m

1750m 5 ½”

8 ¾”

30m DEEP MONITORING WELL (DMW)

40m

180m 5 9/16”

Datalogger (pH, Eh)

GROUNDWATER MONITORING WELL (GWM)

DTS/DAS

13 3/8”

9 5/8”

4 ½

” Tu

bing

7“

Downhole P/T Gauge

450m

2000m

2150m

INJECTION WELL (IW)

Page 14: Shell Quest CCS Project

QUEST - New Well Results - Injection Performance Modelling

14 May 2014 QUEST Update - Pittsburgh CCUS Conference

5 Generations of Models

Ø  Substantial reduction in range of uncertainty after appraisal/injection wells in 2012/13

! !

Identify Risks &

Uncertainties

Appraisal

Strategy

Data Evaluation

Integrated Reservoir Modeling

1)FPP

SDP & MMV Plans

2) Lease App.

3) Reg. Submission

4) SDP n  Status n  BCS Static model update

complete

n  Cooking Lake static modeling ongoing

n  Leak path model update ongoing

n  Results in Q3 2014 n  CO2 plume and pressure

predictions

- Sequestration Lease area

- Timing of VSP vs 4D seismic

- MMV coverage

n  Leakage risk

n  Pressure Monitoring Thresholds

Iterative Workflow

! 5) MMV

Page 15: Shell Quest CCS Project

Heavy Oil Shell Canada

MONITORING PLAN OVERVIEW

Atmosphere LightSource CO2 Monitoring

Biosphere Remote Sensing (Brine & NDVI), CO2 Natural and Artificial Tracer Monitoring,

Hydrosphere Private Landowner Groundwater wells (Chemistry and Isotopes on water and wellhead gas

Deep Monitoring

Wells

Down-Hole Pressure & Temperature (DHPT) above Storage Complex Down-Hole Microseismic Monitoring

BCS Observation Well: DHPT

Injection Wells

Injection Rate Metering, PFC Tracer Injection?

Geosphere

InSAR

Time-Lapse 3D VSP Time-Lapse 3D Surface Seismic

DHPT, Distributed Temperature and Acoustic Sensing, Annulus Pressure Monitoring, WHPT, Wellhead CO2 Sensor, Mechanical Well Integrity

Testing, Operational Integrity Assurance

Time (years)

Baseline Injection Closure

CBL, USIT

Shell Groundwater Wells: Continuous EC, pH, T, P & ORP, Discrete Chemical and Isotopic Analysis on water and WHG,

2010 2015 2020 2025 2030 2035 2040 2045 2050

CO2 Flux & Soil Gas

Page 16: Shell Quest CCS Project

Heavy Oil Shell Canada

MMV baselining Activities – HBMP progress

May 2014 16 QUEST Update - Pittsburgh CCUS Conference

a)Discrete  GW  well  sampling  (Landowner  &  Project  Wells)

Sampling  event Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Q4-­‐2012

Q1-­‐2013

Q2-­‐2013

Q3-­‐2013

Q4-­‐2013 b)

Continuous  GW  well  sampling  (Project  Wells  only)Sampling  event Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

2013 c)

Soil  Gas/Flux  Sampling  &  Remote  Sensing  Calibration  Data  AcquisitionSampling  event Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec

Q4-­‐2012

Q1-­‐2013

Q2-­‐2013

Q3-­‐2013

Q4-­‐2013

no soil  gas

n  Ground Water and Biosphere Baseline Data acquisition progressing as planned n  Golder Report at end of 2013 summaries all data to date.

n  “Sample Manager” implementation ongoing for Data Management

Page 17: Shell Quest CCS Project

Heavy Oil Shell Canada

MMV Baselining Activities – Pressure Monitoring

May 2014 17 QUEST Update - Pittsburgh CCUS Conference

n  Pressure Monitoring Zone changed to Cooking Lake n  Shallowest zone with high enough permeability

n  Depleted by production from the Leduc Reef

n  Commenced Feasibility Study n  Pressure gauges installed in DMW 5-35 and DMW 7-11 to measure pressure variability

n  Some fit for purpose dynamic modeling indicates monitoring at Redwater 3-4 would be beneficial

n  Planning for gauge installation in Redwater 3-4 and building a more detailed Cooking Lake static model.

Page 18: Shell Quest CCS Project

MMV baselining – 2014/15 Activities

May 2014

18

QUEST Update - Pittsburgh CCUS Conference

RADAR REMOTE SENSING for Salinity (SAR) & Surface Deformation (INSAR) - Complete SAR Feasibility Study - Q2 2014 - Update INSAR capability Dec 2014

OPTICAL REMOTE SENSING for Plant Health Feasibility Ongoing – Complete in 2014

BCS Formation

Injector Observation Well Geophones

Seismic wave

Microseismic event

Fracture opening or fault slip

BCS Storage Comple

x

Micro Seismic – Installation Q3 2014

Surface Seismic

3D VSP

3D VSP Baseline –Q1 2015

Page 19: Shell Quest CCS Project

March 19, 2014 Quest Project - MUN 2014, Calgary

BCS Formation

Injector Observation Well Geophones

Seismic wave

Microseismic event

BCS Storage Comple

x

§   Time  Lapse  3D  Surface  Seismic                            (&  Time  Lapse  3D  VSP)  Ex:  Sleipner/Norway,  CO2  injecMon  into  saline  aquifer  (started  1996)                      (source:  Chadwick  et  al.,  2009,  Energy  Procedia  1,  2103–2110)  

§   Micro  Seismic              Fracture opening or fault slip

19

QUEST - MMV ACTIVITIES: GEOSPHERE §   Remote  Sensing  (InSAR)  

Surface displacement

Page 20: Shell Quest CCS Project

Heavy Oil Shell Canada

MMV Activities - Sensor Hook Up / Data Transmission �

20

Storage �(Well sites)

LOS CO2 DAS …

Continuous MMV data

(WPH, WEC, BHP, DMWP.)

LOS CO2 DAS …

MMV data (MS data, DAS/

DTS Lightsource

LOS CO2 DAS …

Continuous Process Control

(WHPT, WHCO2, APM,DHPT)

Capture (Scotford)

Transport (Pipeline)

Well pads

Private wireless

CO2

ß 67 km pipeline à

P&C Signals, Alarms

MMV Measurements

LBV’s

#1

X

P&C data

Scotford Control Room

Scotford Control Rooms

#2

X #3

X #4

X #5

X

Storage Mgt Team

WRFM TOOLKIT

SHELL NETWOR

K

PI

May 2014 QUEST Update - Pittsburgh CCUS Conference

Page 21: Shell Quest CCS Project

Heavy Oil Shell Canada

MMV Activities - Technology Development

May 2014 21 QUEST Update - Pittsburgh CCUS Conference

n  Tracer Feasibility Studies n  PFC Experimental work progressed in 2013 and ongoing until March 2014

n C13 Studies progressing

- CO2 Gas sampling at Scotford

-  Research (phases 1 to 3) completed and reports received from the Uni. of Calgary

-  C13 Data collection in as part of the HBMP baselining

n Decision on Tracers postponed to June 2014 – AER special report #3

n  Lightsource Feasibility n Controlled release test at IW 8-19 in Sept. 2013

n  Further work on algorithm development

n New Boreal digital laser tested.

n Agreed workplan with U of Vic & BC on EC for background

n  Report Expected May 2nd - Milestone meeting /Decision

Page 22: Shell Quest CCS Project

Heavy Oil Shell Canada

April 11, 2014 22 Quest CCS Project - 2nd AER Annual Status Report

Stakeholder Engagements n  Status

n  Local community events in summer 2013 (Thorhild Sunflower Festival)

n Open Houses conducted in October 2013:

n  Thorhild, Radway and Bruderheim

n  Town, City and Council updates provided annually to:

n  Thorhild, Lamont, Bruderheim, Fort Saskatchewan, Strathcona, Lamont, Sturgeon

n Community Advisory Panel (CAP) formed and kicked off in 2012 for MMV program- met 6 times in 2013- including touring the upgrader and pipeline construction

n Community newsletters - 2 in 2013

n HBMP GW sampling brochure for landowners issued in Q1 2014

n  Upcoming work in 2014 n Continue CAP meetings (quarterly), annual Council

updates , Open Houses (Oct. 2014) and Newsletters

n Community survey on Quest (completed bi-annually)

Page 23: Shell Quest CCS Project

n  Well Program n Hook up and testing of wellpad MMV

sensors by Q4 2014

n  MMV program

n Baseline sampling program complete Q1 2015

n  Capture & Pipeline n Module fabrication – Last module

installation targeted for summer 2014

n Pipeline mechanical completion expected fall 2014

n Mechanical completion of capture facility by Q1 2015

n  Operations Handover Q3 2015

n  Full production Q4 2015

May 2014 23

QUEST - Project Timeline to Operations  

QUEST Update - Pittsburgh CCUS Conference

Page 24: Shell Quest CCS Project

Thank You

Page 25: Shell Quest CCS Project

QUEST - 2013 Well Test Results - Injectivity

25

W ell  N am e Ra te D elta P In jectiv itym 3 / d k Pa m 3 / d /MPa

Ra dw a y  8 -­‐1 9 3 6 0 0 .9 5 3 7 9Redw a ter  1 1 -­‐3 2 4 9 2 1 2 .1 3 4 1Tho rh ild  5 -­‐3 5 3 4 2 0 .3 3 1 0 3 6Ra dw a y  7 -­‐1 1 3 9 6 0 .1 9 2 0 8 5

0

10000

20000

30000

40000

50000

60000

70000

3  Well  Avg  PI                            Water  Injection  Rates

Water  Injection            Potential

Estimated  CO2                    Injection  Potential

Quest  CO2  injection  requirement

Injection  Ra

te,  [reservoir  m

3/d]

Water  PICO2  UncertaintyQuest  Requirement

Linear  adjustmentto  FBHP  of  26  MPa

CO2/waterinjectivityratio  of  1.5  -­‐ 3

Quest  Initial  Rate=  900  -­‐ 1800  %  

Well  Core  Avg        k  (D)  

Core  Max                k  (D)  

Test        Low          Keff  (D)  

Test          Mid    

keff  (D)2  

Test      High    

keff    (D)3  8-­‐19   0.5   3.6   0.5   0.8   1.1  5-­‐35   0.9   2.2   0.8   1.0   1.3  7-­‐11   0.9   2.9   1.2   1.8   2.0  

Well FEP FCP

1AA/11-32 45.4 MPa (20.7 kPa/m)

31.7 MPa (14.5 kPa/m)

100/08-19 42.4 MPa (20.6 kPa/m)

34.6 MPa (16.8 kPa/m)

102/05-35 48.1 MPa (23.5 kPa/m)

33 MPa (16.1 kPa/m)

103/07-11 42.5 MPa (21.0 kPa/m)

24.5 MPa (12.1 kPa/m)

May 2014 QUEST Update - Pittsburgh CCUS Conference

Regulatory Constraint Ø  30 Mpa

PERMEABILITY (TEST vs CORE) WATER INJECTIVITY / TEST RESULTS

CO2 INJECTION CAPABILITY FRACTURE EXT. PRESSURE

Page 26: Shell Quest CCS Project

Heavy Oil Shell Canada

Atmospheric Monitoring

LightSource: CO2 mass flux rate Baseline Injection Closure Baseline Injection Closure

Atmosphere Biosphere

Hydrosphere

Geosphere

BCS Storage Complex