MCG MISSIONMCG MISSION Improve health and reduce the burden of illness in societyImprove health and reduce the burden of illness in society
• educating the health professionals of the futureeducating the health professionals of the future
• advancing scienceadvancing science
• leveraging the state's investment in MCGleveraging the state's investment in MCG
• improving the health and well-being of Georgiansimproving the health and well-being of Georgians
The master facility plan supports the mission of the The master facility plan supports the mission of the Medical College of Georgia by guiding the Medical College of Georgia by guiding the enhancement of our physical resources to support:enhancement of our physical resources to support:
Shepley Bulfinch / PlanningMay 20, 2008
P
PP
P
P
P
P
P
P
P
P
P
15th Street
RA Dent Blvd
Campus Circulation: Vehicular, Campus Entrances
Future entrance on St. Sebastian Way
Surface Lots
Parking Decks
Campus Entrances
P
P
Shepley Bulfinch / PlanningMay 20, 2008
Connecting across 15th Street
Integrating campus along Laney Walker Boulevard
Pedestrian connectivity beyond campus
Way-finding on campus
Connecting across 15th Street
Integrating campus along Laney Walker Boulevard
Pedestrian connectivity beyond campus
Way-finding on campus
Campus Circulation: Pedestrian Vehicular Conflict
Shepley Bulfinch / PlanningMay 20, 2008
Phase 1: 2008 - 2009
Aug. 2008 Complete acquisition of Gilbert Manor property
Oct. 2008Demolish structures and
construct surface parking
Aug. 2008Complete acquisition of
Fat Man’s property
Sept. 2008MCGH commences construction
of new Clinical Cancer Center & parking deck
Shepley Bulfinch / PlanningMay 20, 2008
Phase 2: 2009 - 2011
June 2009Begin construction
of new School of Dentistry
Jan. 2009Begin construction of replacement student housing
June 2010Implement Laney Walker
improvements
Jan. 2010Relocate partial surface parking & convert site to landscaped campus green
Jan. 2011Begin construction ofSchool of Medicine & Education Commons
Jan. 2010Completion of Clinical
Cancer Center
Shepley Bulfinch / PlanningMay 20, 2008
Phase 3: 2011 - 2012
Jan. 2011St. Sebastian Way extension
June 2011Occupy replacement student housing
Aug. 2011Occupy new
School of Dentistry
Aug. 2012 - Aug. 2013Occupy School of Medicine
& Educational Commons
June 2011Demolish residences IV & V
To create space for future development
Oct. 2011Begin renovation of old School of Dentistry