SHORELINE SCHOOL DISTRICT
Site & Facilities Assessment
September 22, 2008
SHORECREST HIGH SCHOOL
![Page 2: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/2.jpg)
Aerial View
![Page 3: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/3.jpg)
Site Opportunities & Constraints
SITE ASSESSMENTSite OrganizationVehicle Access & ParkingSite SecurityPaving & LandscapingCivil/Geotech Report
CODE COMPLIANCELand Use Compliance ReportEnvironmental Compliance ReportTraffic ReportEmergency Vehicle Access
![Page 4: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/4.jpg)
Site Assessment
Site OrganizationVehicle Access & ParkingSite SecurityPaving & LandscapingCivil/Geotech Report
![Page 5: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/5.jpg)
Site Organization
• Site organized into a series of 4 parallel terraces on east facing slope
• Original buildings organized around exterior courtyards with exterior circulation
• Mixed pedestrian and vehicle circulation
![Page 6: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/6.jpg)
Vehicle Access and Parking
• 3 principal parking areas
• Need to determine the optimal number and location of driveways at NE 25th St
![Page 7: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/7.jpg)
Security
• Minimize site entry points
• Organize site circulation to aid in monitoring of visitors
![Page 8: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/8.jpg)
Paving and Landscaping
• Coordinate landscape design and maintenance plan
• Ensure safety and accessibility of site paving
![Page 9: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/9.jpg)
Code Compliance
• Land Use Compliance – Conditional Use Permit– Height Variance
• Traffic – No additional volumes anticipated
• Emergency Vehicle
![Page 10: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/10.jpg)
Facility Opportunities & Constraints
EXISTING BUILDING ASSESSMENTSStructuralArchitecturalMechanicalElectricalLightingLow Voltage AssessmentWet Utilities AssessmentDry Utilities Assessment
CODE COMPLIANCEBuilding CodeADASeismic DesignWashington State Energy CodeIndoor Air QualityWSSP
![Page 11: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/11.jpg)
Site Plan
![Page 12: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/12.jpg)
Existing Building Assessments
Conditions
Key to Diagrams
Good- Component is functionally and aesthetically sound; remaining lifespan is 20 or more years.
Fair- Component exhibits minor functional or aesthetic deficiency; remaining lifespan is 10 years.
Poor- Component exhibits significant functional or aesthetic deficiency; remaining lifespan is 5 years.
Unsatisfactory- Complete functional deficiency and/or aesthetic deficiency; remaining lifespan is 0 years.
![Page 13: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/13.jpg)
Structural - Gravity
Existing buildings generally in good condition with respect to gravity loads
![Page 14: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/14.jpg)
Structural - Lateral
Compliance with current codes required when:- threat to life safety- building undergoes significant remodel- new construction
![Page 15: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/15.jpg)
Buildings A-F
• Casework is uneven- ranges from good to poor condition
• All restrooms are non-accessible
• Flat roofs are in fair condition; metal roofs are unsatisfactory
![Page 16: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/16.jpg)
Buildings A-F
• Substandard ventilation and natural light in classrooms
• Canopies are in poor condition
• No sprinkler system
• Many windows have failed seals.
![Page 17: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/17.jpg)
Main Gym
• Locker rooms in poor condition
• Substandard ventilation and natural light throughout classrooms, aerobics room, weight rooms, locker rooms, and offices
• No sprinkler system
![Page 18: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/18.jpg)
Auxillary Gym
• Significant problem with roof leaks and consequent ceiling damage.
• No sprinkler system.
![Page 19: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/19.jpg)
Building H
• Repair work needed on original exterior wood siding, trim, and canopies
• Inadequate natural light and ventilation in classrooms
• Classroom doorways are not ADA accessible
• No sprinkler system
![Page 20: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/20.jpg)
Building J
• Building constructed in 1996
• Only building on campus that has a complete sprinkler system
• Some relatively minor, repairable damage to exterior EIFS (stucco like siding)
![Page 21: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/21.jpg)
Building S
• Wood and metal shops are generally in good
condition • Inadequate natural light
and ventilation in drafting and electronics labs.
• Curriculum doesn’t fit well in original spatial layout for a drafting and electronics labs.
• Lots of unused space
![Page 22: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/22.jpg)
Building T
• Theatre constructed in 1986
• Overall in good condition
• Sprinkler system for lobby & stage
• Condensation build-up at lobby windows
• No interior circulation for backstage functions.
![Page 23: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/23.jpg)
Flooring
![Page 24: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/24.jpg)
Ceilings
![Page 25: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/25.jpg)
Exterior Walls
• Primary deficiencies are mostly cosmetic. Clean and spot repair water stains and moss growth on Buildings G and S
![Page 26: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/26.jpg)
Exterior Windows & Doors
![Page 27: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/27.jpg)
Roofing
• Metal roof panel seam failure
![Page 28: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/28.jpg)
Heating
• Upgrade to natural gas system to serve the entire facility and to reduce maintenance costs • Replace outdated equipment
![Page 29: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/29.jpg)
Ventilation
• Provide long term use of the facility and create comfortable conditions that meet current codes and optimize energy efficiency
![Page 30: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/30.jpg)
Fire Protection Systems
• Provide new sprinkler system for the entire facility
![Page 31: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/31.jpg)
Plumbing
• Pipes replaced with copper in 1996• Replace existing plumbing fixtures and showers with more water efficient fixtures and heads in Building G• Install emergency shower and eyewash stations in Building S
![Page 32: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/32.jpg)
Electrical
• Provide a new utility service with double-ended substation and generator backup • Establish new code and safety compliant electrical rooms• Update electrical distribution system to support new mechanical equipment• Not enough outlets• Electrical panels are out of capacity
![Page 33: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/33.jpg)
Lighting
• Replace existing light fixtures with new fixtures• Provide occupancy sensors and low voltage lighting controls to meet the current requirements of the WA Energy Code
![Page 34: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/34.jpg)
Communication Systems
• Provide dedicated, secured and environmentally controlled spaces for communications equipment• Install a cable tray system with conduit drops to each jack
![Page 35: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/35.jpg)
Aerial View
![Page 36: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/36.jpg)
Looking ahead
![Page 37: SHORELINE SCHOOL DISTRICT Site & Facilities Assessment September 22, 2008 SHORECREST HIGH SCHOOL](https://reader035.vdocument.in/reader035/viewer/2022062619/5516987f550346f0208b4972/html5/thumbnails/37.jpg)
SHORELINE SCHOOL DISTRICT
Site & Facilities Assessment
September 22, 2008
SHORECREST HIGH SCHOOL