S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Upload: alisha-proudfoot

Post on 15-Dec-2015

213 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

S&I Framework InitiativeProvider Directories Project Plan and Timeline

Certificate Discovery for Directed Exchange

June 20, 2011

Page 2: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

High Level Project Plan and Timeline

1. Certificate discovery for directed exchange with a known end-point address (e.g., Direct address)

2. Electronic Address discovery

Priority Must-have Must-haveUrgency Very High:

Real-world usefulness Mandated: recommendation to HITSC

by mid-July for IFR Use Case & Analysis doable within ~6

weeks Prototypes/Reference Implementation

to be completed by fall, in time for MU2 Final Rule

Very High: Real-world usefulness: Need to have

standard as soon as possible, but may not be feasible by July 15th

Not certain about inclusion into regulation at this point (MU2) or later (other rule-making, MU3, etc.)

Important not to rush a short-term solution that impedes a good long-term solution.

High-level Project Plan & Timeline

a) Use Case and Standards Analysis - by July 15th

b) Prototypes/RI: by mid-September

a) Use Case + Standards Analysis – by end of August or earlier (tentative)

b) Prototypes/RI: by mid-SeptemberTimeline for Use Case and Standards Analysis

June 3rd to July 15th (6 weeks) June 3rd to August 26th (12 weeks)

Page 3: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Provider Directories: Milestones and TimelineCertificate Discovery for Directed Exchange

Apr 2011

• 6/3 – 6/10:Use case development –user stories, scenarios, context diagrams; • 6/13 – 6/17: Use case development – scenarios, data flows, sequence and activity diagrams, data elements, functional requirements

May2011

June2011

July2011

Aug2011

Sept2011

• 6/20 – 6/24: Use case development – policy and regulatory issues, and other introductory sections

• 6/27 – 7/1: Use case development – final consensus

6/27 – 7/1: Standards Analysis

• 7/4 – 7/8: Standards Analysis

• 7/11 – 7/15:Standards Analysis

• 7/20: HIT Standards Committee Review

• 8/03: HIT Policy Committee Review

Use Case

Standards

Revised

Page 4: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Certificate Discovery: Consensus Process and Timeline• Following June 24th PD Sprint Team meeting, Use Case package to

be submitted for formal consensus with one week period• Each Committed member will review the full Use Case package and

then vote “Yes” or “No” on the Wiki – Any “No” votes should be accompanied with actionable feedback which will be

addressed– PD - Query for Destination Digital Certificate Use Case Consensus Page:

http://wiki.siframework.org/PD+-+Query+for+Destination+Digital+Certificate+Use+Case+Consensus+Page

• Address all comments received and present disposition• If time permits, gather verbal consensus on 6/20 SWG meeting and

6/24 Sprint Team and turn those votes into formal votes• Consensus to be completed by 7/1 and handoff to Harmonization on

7/1 meeting

Page 5: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Certificate Discovery for Directed Exchange Work Stream Milestones

5

Mon 6/20 Tues 6/21 Wed 6/22 Thurs 6/23

• Address parking lot items & unresolved comments on Use Case

• Present and discuss consensus process

• Present next steps on Harmonization work

• Each Committed Member will review Use Case and then provide comment (if any) to be addressed on 6/24 meeting OR vote “Yes” or “No” towards consensus

(NOTE: Only

comments received on Wiki by 6/23 COB will be addressed during 6/24 meeting)

• Each Committed Member will review Use Case and then provide comment (if any) to be addressed on 6/24 meeting OR vote “Yes” or “No” towards consensus

(NOTE: Only

comment received on Wiki by 6/23 COB will be addressed during 6/24 meeting)

• Each Committed Member will review Use Case and then provide comment (if any) by COB to be addressed on 6/24 meeting OR vote “Yes” or “No” towards consensus

• Analyze comments and assemble unresolved comments to discuss during Friday PD Sprint Team meeting

Fri 6/24

• Post disposition of comments on Wiki for review

• Address any unresolved comments

• Gather verbal votes (if time permits)

• Post full Use Case to Wiki for formal consensus (1 week period)

• The schedule below shows milestones for week 6/20 – 6/24

Page 6: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Certificate Discovery for Directed Exchange Work Stream Milestones

6

Mon 6/27 Tues 6/28 Wed 6/29 Thurs 6/30

• Each Committed Member will review Use Case and vote “Yes” or “No” towards consensus

• Continue Harmonization work during SWG meeting

• Each Committed Member will review Use Case and vote “Yes” or “No” towards consensus

• Each Committed Member will review Use Case and vote “Yes” or “No” towards consensus

• Each Committed Member will review Use Case and vote “Yes” or “No” towards consensus by COB Consensus

Fri 7/1

• Handoff final Use Case package to Harmonization Team

• The schedule below shows milestones planned for week 6/27 – 7/1

Page 7: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Sample Consensus Page

Page 8: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Sample Consensus Page (With Actionable Feedback)

Page 9: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

PD Query for Destination Digital Certificate Use Case Consensus

• List of Committed Members and space for consensus voting is available via: http://wiki.siframework.org/PD+-+Query+for+Destination+Digital+Certificate+Use+Case+Consensus+Page

• A link to the consensus page is available from the Sprint Team Wiki Page: http://wiki.siframework.org/PD+-+Sprint+Team

Page 10: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

ORIGINAL WORK STREAM TIMELINES

APPENDIX

Page 11: S&I Framework Initiative Provider Directories Project Plan and Timeline Certificate Discovery for Directed Exchange June 20, 2011

Provider Directories: Milestones and TimelineCertificate Discovery for Directed Exchange

Apr 2011

• 6/3 – 6/10:Use case development –user stories, scenarios, context diagrams; • 6/13 – 6/17: Use case development – scenarios, data flows, sequence diagrams, and activity diagrams

May2011

June2011

July2011

Aug2011

Sept2011

• 6/20 – 6/24: Use case development -- data elements and functional requirements

• 6/27 – 7/1: Standards Analysis

• 7/4 – 7/8: Standards Analysis

• 7/11 – 7/15:Standards Analysis

• 7/20: HIT Standards Committee Review

• 8/03: HIT Policy Committee Review

Use Case