siet_lakshyacase_group2

Upload: priynci

Post on 02-Jun-2018

212 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    1/11

    SEIT Assignment

    1

    Lakshwiz Factory Module

    Radharaman Jha 65

    Rishabbh Sahu 69

    Salil Parashar 74

    Yash Deep Pandey 103

    Mohit Mahant 104

    Group 2

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    2/11

    Case Summary

    2

    GapsAnalyzed

    Inventory shortage problem and excess inventory in some items

    Material shortage -> Delayed production and delivery of thefinished product -> Huge loss to the company

    High transportation cost and also the cost of holding the inventory

    Most of the suppliers more than 200 kms away from the plant

    Company

    Autoflex industries, established in 1961, Leader in Auto Electricalsin India with expertise in design and manufacturing.

    4 out of 5 vehicles rolled out daily in India are fitted with Autoflexproducts.

    All the products are manufactured at Autoflex, Coimbatore plant( 3separate plants for different products).

    Overall, Autoflex Industries, Coimbatore has about 900components to be procured, which get assembled into differentproducts depending on the specification.

    Major customers are: Almost all auto manufacturing companies in

    India and few companies abroad.

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    3/11

    3

    The rental cost of the warehouses include the setting up of the warehouse, no

    separate capital investment is required in any of the 4 locations.

    We have assumed that the company uses a standard software based MRP system

    which shows real time inventory level data. If not, it can be bought but we have not

    included the cost for buying and switching to this system. Though we have kept a

    safety stock to compensate for demand fluctuations, the calculations have been made

    assuming constant rate of utilization of components

    Though the case clearly mentions the fluctuations in demand, but no break-up or

    forecast on monthly basis has been provided

    The demand mentioned in the question is the actual demand and not a forecast

    The transportation cost is 50% of the ordering cost

    Since the ordering cost in Pondicherry is Rs1500, it is likely that a major

    component of the ordering cost in other cities would be transportation cost.

    Thus the ordering cost for the new model has been considered 70% of the currentordering cost (30% reduction in ordering cost due to reduction in transportation

    cost which is almost 50% of ordering cost).

    The size of the components has not been considered

    Assumptions

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    4/11

    4

    Each warehouse has enough space to keep all the inventory at the same time Since we do not have sufficient information regarding the above two points in the

    case

    The prices and the ordering costs remain the same throughout the year

    The demand given would be applicable from the day this strategy would be used

    The benefits calculated are from 115 components mentioned in Appendix VII of the

    case provided

    Since the details of the rest of the components has not been provided.

    The MRP system used is software based and is capable of showing inventory data

    almost in real-time

    Autoflex is a leader in Auto electrical in India, and as mentioned in the case most of

    the MRP systems these days are software based.

    The item: V Milling Rear has been excluded from the calculations, since the demand

    given in exhibit VII for this item is 0

    Although the company procures around 900 items, only the ones in exhibit VII have

    been used to calculate the cost benefit using this model.

    Assumptions Continued..

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    5/11

    5

    Old Model (As-

    is) Centralized warehouse:

    One warehouse at

    Comibatore

    2-Bin System

    Ordering System: Lot for

    Lot

    Product Managerpurchasing components

    Proposed New Model

    New Model(To-be) Decentralized warehouse

    : Four warehouses, one

    in each Bangalore,

    Chennai, Pondicherry

    and Coimbatore

    Safety Stock

    Ordering System :

    Economic Order Quantity

    Sourcing manager who

    keeps a record of the Bill

    of materials (BOMs)

    made by a product

    managers

    Advantages ofNew Model Since most of the

    suppliers are located

    nearby these 4 cities, we

    can significantly cut on

    transportation costs (usingfull truck loads) and

    inventory costs

    Safety stock would help in

    optimal space utilization

    and reduction in costs

    compared to 2 Bin

    system. Ordering using EOQ

    reduces the inventory and

    transportation costs

    significantly

    The BOMs can be

    combined for full truckload or FTL

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    6/11

    The Material Requirement Planning (MRP) System

    We should also use the Continuous review policy, this would help us reduce theordering cost and also save on extra inventory holding costs. Using this system well

    order only those components which are on the limit and need to be re-ordered as per

    the re-order point formula.

    Instead of product managers ordering for themselves we will have a sourcing

    manager who can order on behalf of them, each product manager should raise a bill

    of material (BOM) that he/she needs. This BOM should reach the sourcing manager,who would give a collective order to the warehouses.

    The sourcing manager at the warehouses should keep a check on the inventory

    levels, should order as the inventory reaches the re-order point.

    MRP System and EOQ Model

    The EOQ ModelOrdering costs vary inversely with carrying costs. It means that the more orders a

    business places with its suppliers, the higher will be the ordering costs. However, more

    orders mean smaller average inventory levels and hence lower carrying costs.

    It is important for a business to minimize the sum of these costs which it does by

    applying the economic order quantity model.

    6

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    7/11

    7

    Annual Demand (d)Ordering Cost (c)

    Price of component(h)

    No. Of Orders(Lotfor lot) (n)

    Quantity to beordered as per new

    model(EOQ) (q)

    Cost of procuringas per new model

    (y)Handling cost (new

    model) (x)

    Variables

    Set of Variables and Formula used

    Formulas used:

    Quantity ordered (Lot for lot) (Q) = d/n

    Annual Cost for double bin (Lot for lot)(For a component) = (c + h/5*Q/d*2)*d/Q

    Quantity ordered (new model) (EOQ) (q)=(2*0.70*c*d/((h/5) + x))^0.5

    Total cost of component (new model) =(0.70*c + h/5*q/2*q/d + q/2*x*q/d)*d/q

    Safety Stock = Z * STD * L^0.5

    Where: Z is a factor, referred to as Safety

    Factor(associated with service level), STD :

    Standard deviation in demand per unit time,L :

    Lead time for getting the component

    Variables

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    8/11

    Reordering pointThe inventory level at which an order should be placed; it considers two

    factors:

    Safety Stock

    The safety stock is the amount of inventory that needs to be kept at

    the warehouse in Coimbatore to protect against deviations fromaverage demand.

    Average inventory during lead time= L * AVG

    L : Lead time for getting the component

    AVG: Average demand per unit time

    Thus,

    Reorder point = Average inventory during lead time + Safety

    Stock

    = Z * STD * L^0.5 + L * AVG

    Reorder Level

    8

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    9/11

    The following table and graph shows the cost analysis done for the component:

    Condenser (All Products)

    Example

    Microsoft Office

    Excel Worksheet9

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    10/11

    Cost Benefits

    The annual cost benefits by using this model as per the sheet = Rs 2,44,52,381.2

    The annual rental costs of ware-houses = (5,000+10,000+15,000+20,000)*12 = Rs

    6,00,000

    Cost Benefit Warehouse rents= Rs 2,38,52,381.2

    Safety stock

    The cost incurred in safety stock has not been subtracted from the net benefit

    since the lead times and the demand fluctuations would vary for each component.

    If we consider the safety stock to be around 30% of average inventory of a

    component, the total sum for storing safety stock of all components in exhibit VII =

    Rs 41,05,355

    Thus Approx Net Cost benefit = Rs 2,38,52,381.2 - Rs 41,05,355

    = Rs 1,97,45,025

    The net cost benefit is only from the components mentioned in exhibit VII, the cost

    benefits would increase further if the model is used for all the 900 components

    procured by Autoflex Industries.

    Cost Savings

    10

  • 8/10/2019 SIET_LAKSHYACASE_GROUP2

    11/11

    11

    Thank You