silt excluders

19
Silt Excluders

Upload: raees-shah

Post on 21-Apr-2017

3.054 views

Category:

Engineering


3 download

TRANSCRIPT

Page 1: Silt excluders

Silt Excluders

Page 2: Silt excluders
Page 3: Silt excluders
Page 4: Silt excluders
Page 5: Silt excluders
Page 6: Silt excluders

A little flashlight How Silt Regulation works The entry of silt into a canal, which takes off

from a head works, can be reduced by constructed certain special works, called silt control works.

These works may be classified into the following two types:

(a)    Silt Excluders(b)   Silt Ejectors(a) Silt Excluders

Page 7: Silt excluders

Silt excluders

The idea of the silt excluder was first presented by Elsdon in his

Irrigation Branch Paper No.5 of 1922. The first silt excluder was

designed by Nicolson at Khanki head works in 1934 as shown in Figure.

Page 8: Silt excluders
Page 9: Silt excluders

The basic idea behind the design is that the lower layers of the flowing water carry a higher concentration of silt and therefore if the upper layers of the water only can be skimmed into the canal, all the rolling bed silt and the silt in the lower layers is excluded.

This is achieved by a silt excluder. This is a diaphragm slab supported on a number of tunnels. Tunnels are placed parallel to the head regulator and discharge d/s through the under sluice. The water above the silt excluder slab containing less silt is then diverted into the canal. The following points should be kept in mind while designing a silt excluder:

Page 10: Silt excluders

i) The tunnel discharge through the undersluice is recommended to be 20 per cent of the canal discharge.

ii) The silt excluder should cover only two bays of the undersluice as this was found to be more efficient in the model studies of Kalabagh barrage than a silt excluder covering four bays.

iii) The approach channel need not be lined.iv) The divide wall should be 1.2 to 1.4 times

the head regulator length.

Page 11: Silt excluders

v) The top of the silt excluder slab should be flushed with the head regulator crest, i.e. the clear height of the tunnels would be 1/3 the depth of the water minus the slab thickness.

vi) The roof slab should be designed to carry a full water load in case the tunnels are empty.

vii) The first tunnel should cover completely the head regulator, the other tunnels should be of shorter lengths.

viii)The discharge through the tunnels will depend upon the head measured above the centre line of the tunnel. Tunnels can be treated as box culverts.

Page 12: Silt excluders

Principles of Silt Control

Before we describe the mechanism and functioning of these silt control devices, we shall explain the basic principle on which the silt is removed from the water.

The fundamental principal the behind silt control is : that most of the silt tries to settle down in water, thus, confining itself mostly in the bottom layers of water.

We also know that the silt is kept in suspension by the force of the vertical eddies generated by the friction of the flowing water against the bed.

Page 13: Silt excluders

In other words, if this bed friction is more, the upward force of eddies shall be more, and hence, lesser chances of silt settlement wiII exist.

Hence, if the friction can be reduced by constructing a smooth approach channel, more settlement of silt and its consequent removal, is possible. Further, the silt from the bottom layers can be removed, by separating the top layers and the bottom layers, without causing any disturbance to the flow.

Page 14: Silt excluders

The chances of less disturbance and that of providing a smooth approach channel can be better attained in a canal rather than in the river bed.

Hence, the works which are constructed in the canal (i.e. the silt extractors or silt ejectors) will definitely be superior and more effective than the works which are constructed in the river bed (i.e the silt excluders).

Silt extractor is therefore, better than a silt excluder. However, the silt extractor shall be costlier because

surplus water has to be taken into the canal' from the head, and an escape, channel which will feed the highly silted water back into the river, shall have to be constructed.

Page 15: Silt excluders

Description and Design of a Silt Excluder A silt excluder consists of a number of

rectangular tunnels running parallel to the caxisohhe head regulator and terminating near the under-sluiced weir. The tunnel nearest to the crest of the head regulator has to be at least of the same length as the head regulator. Other tunnels may be shorter in length. The roof slab of the excluder tunnels is kept at the same level as that of the regulator crest, as shown in Figure.

Page 16: Silt excluders
Page 17: Silt excluders

The bottom layer of water which is highly charged with silt and sediment will pass down the tunnels and escape over the floor of the under-sluice way(s), since the gates of the under sluice way(s) shall be kept open upto the top of the tunnels. The clearer water over the top of the roof of the excluder tunnels, will thus enter the canal through the head regulator.

Usually , two or three bays of the 'under-sluices of the weir or the barrage are covered by the excluder.

However, excluder covering only one bay has been designed and is usually adopted for sandy rivers.

Page 18: Silt excluders

Factors effecting the efficiency of silt excluders

i) An increase in escape supply increases the efficiency to a certain point but further increases in escape supply may not increase the efficiency substantially.

ii) The grade of sediment affects the efficiency. For coarser silt the efficiency is more. For smaller grades it is less.

Page 19: Silt excluders