site acceptance test - harrington plastics r2 - site... · site acceptance test client name bayer...

23
R-0 For approval Rev No. Issue Date Description Remarks SITE ACCEPTANCE TEST Client Name Bayer Vendor’s Name Exergy LLC / Hydropure Systems Project Name Bayer Shawnee R&D PO No 140524-P-100 Document Name Site Acceptance Test Document No HPS-PR 247-SAT Rev 0 Reference Drawing No 02922 Rev B 02923 Rev B Issue Date October 31, 2014

Upload: vanngoc

Post on 02-Apr-2018

238 views

Category:

Documents


6 download

TRANSCRIPT

Page 1: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

R-0 For approval

Rev No. Issue Date Description Remarks

SITE ACCEPTANCE TEST

Client Name Bayer

Vendor’s Name Exergy LLC / Hydropure Systems

Project Name Bayer Shawnee R&D

PO No 140524-P-100

Document Name

Site Acceptance Test

Document No HPS-PR 247-SAT Rev 0

Reference Drawing No

02922 Rev B

02923 Rev B

Issue Date October 31, 2014

Page 2: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 2 of 23

TABLE OF CONTENT

1.0 APPROVAL .......................................................................................................... 4

2.0 SAT PLAN ............................................................................................................ 5

2.1 INTRODUCTION .................................................................................................. 5

2.2 ABBREVIATIONS ................................................................................................. 5

2.3 REFERENCE DOCUMENTS .................................................................................. 5

2.4 PURPOSE OF THE TESTS ..................................................................................... 5

2.5 OBJECT DESCRIPTION ........................................................................................ 6

2.6 SAT PERFORMANCE ........................................................................................... 6

2.6.1 RESPONSIBILITIES ............................................................................................... 6

2.6.2 GOOD TESTING PRACTICE .................................................................................. 6

2.6.3 HOW TO FILL IN THE TESTS / INSPECTIONS ....................................................... 7

2.6.4 DEVIATION HANDLING....................................................................................... 8

2.7 ACCEPTANCE CRITERIA ...................................................................................... 8

2.8 SAT RESULT ........................................................................................................ 8

3.0 TESTS .................................................................................................................. 9

3.1 MECHANICAL & DOCUMENTATION INSPECTIONS .......................................... 10

3.1.1 FAT CLOSURE .................................................................................................. 10

3.1.2 VERIFICATION OF COMPONENTS AS PER P & ID ............................................. 11

3.1.3 VERIFICATION OF ELECTRICALS ....................................................................... 12

3.1.4 VERIFICATION OF COMPONENT SPECIFICATIONS ........................................... 13

3.1.5 REVIEW OF TEST CERTIFICATES & TEST REPORTS ........................................... 14

3.1.6 CHECK FOR AVAILABILITY OF MANUAL & DATA .............................................. 15

3.2 SYSTEM ACCEPTANCE TEST ............................................................................. 16

3.2.1 TO CHECK FUNCTIONAL LOGIC & ALARM ....................................................... 16

3.2.2 TO CHECK THE I/O ........................................................................................... 17

3.3 OPERATION TEST ............................................................................................. 18

3.3.1 LEAK TEST ......................................................................................................... 18

3.3.2 CHECK FOR SYSTEM OPERATING PARAMETERS………………………………….……….19

4.0 SAT REPORT ..................................................................................................... 20

4.1 PURPOSE OF THE REPORT ............................................................................... 20

4.2 DEVIATIONS ..................................................................................................... 20

Page 3: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 3 of 23

4.3 RETESTS ............................................................................................................ 22

4.4 FINAL APPROVAL ............................................................................................. 23

Page 4: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 4 of 23

1.0 APPROVAL

Signatures on this page indicate that this document has been reviewed, checked and

approved by the concerned persons. It shall be signed and dated as shown below.

Department Name Designation Signature Date

Exergy, LLC

Project Engineer

Project Manager

Bayer

Engineering

Validation

QA

Page 5: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 5 of 23

2.0 SAT Plan

2.1 Introduction

Point of Use cooler is specially designed for cooling of PW/WFI water in loop at required temperature. It contains Sanitary Type Double Tube Sheet Heat Exchangers, which reduces PW Water temperature from 65 Deg. C to 30 Deg. C at maximum flow rate of 5 GPM. Chilled Water at the inlet of Heat Exchanger is required at Temperature of 5.5 Deg. C at a flow rate of 8.6 GPM. The SAT shall show that the Point of Use Cooler is manufactured and operates in accordance with the design specifications, functional logics and operating Instructions. The SAT is divided into three test sections:

Mechanical & Documentation Inspections

Hardware Acceptance Test

Operation Test

2.2 Abbreviations

SAT Site Acceptance Test MOC Material of Construction TC Tri Clover Ra Average Roughness NLT Not Less Than

2.3 Reference Documents

1. P & ID 2. Design Qualification 3. Test Certificates 4. Manuals & data sheet check 5. GA Drawings 6. Control Wiring Diagram

7. FAT Report

2.4 Purpose of the Tests

The purpose of the SAT is to test, inspect and show that the Point of Use Cooler is installed correctly according to mechanical and electrical specifications, that components are marked and located according to the valid P & ID and that the system works according to the Functional Logics.

Page 6: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 6 of 23

2.5 Object description

Product : Point of Use Cooler Function : for cooling product water in loop Manufacturer : Exergy LLC / Hydropure Systems Project number : Year of manufacture :

2.6 SAT Performance

The tester shall first read this SAT Plan section, then perform the tests and finally fill in the Report in the end of this document. The performance of the specific Factory Acceptance Tests is described for each test in the test sheets.

2.6.1 Responsibilities

The person who performs the tests (Tester) is responsible for the execution of the tests. The tester confirms with his/her initials that the test is performed correctly. A second person, (Witness) checks if the test was correctly performed and that the result was in accordance with the acceptance criteria and if not, that a deviation report is filled in.

2.6.2 Good Testing Practice

A (archive resistance) blue pen shall be used for the SAT tests, for approvals and for the corrections in the attached design documents (such as Tank Drawing). Correction fluid and other correction techniques that obscure the original entry shall not be used. Spelling mistakes and other changes shall be corrected as follows:

Ex: Installation 20/01/04 Initials

Deviations are recorded and traceable. Fields in a test, which is not filled out, shall be clearly marked as N/A (not applicable) Attachments such as Drawing and MOC check lists shall be marked with the name of the SAT test and date and initials of the tester. This shall be written on all attached page

Ex) Attachment to test FAT 2.1.1 Components 20/01/04 Initials

When the SAT is performed and completed, all documents associated with the SAT shall be reviewed for correctness and completeness before the SAT Report section is filled in.

dhodge
Cross-Out
dhodge
Inserted Text
The Exergy Site Representative will review with the Exergy Project Manager all relevant Site Acceptance Testing (SAT)documentations prior to start-up and have a complete understanding of the procedures for start-up. SAT will reflect, as closely as possible, parameters and testing in the Factory Acceptance Tests (FAT).
dhodge
Cross-Out
dhodge
Inserted Text
The Exergy Site Representative will be responsible for observing the results and recording of the step-by-step SAT with the customer representatives. All results, deviations and notes will be recorded in the Operation Test.
Page 7: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 7 of 23

2.6.3 How to fill in the tests / inspections

Name of Test

Test procedure

Required document(s) / equipment

Acceptance criteria

1)

Pass /Fail + Deviation no

2)

Comment

3)

Tester, Date / Initials

4)

Witness, Date /initials

5)

For a description of the different sections of each test script please see below: 1) The acceptance criteria are specified in this square and if values are to be recorded there

will also be an “Actual value” result table provided. The tester shall Fill in the actual value observed and then indicate a “Pass” or “Fail”. in the square provided.

Description Required value Actual value Result (Pass /Fail)

Ex) Temperature at TT270.6.3

> 80°C

2) If the acceptance criteria are fulfilled, “Pass” is written in the square. If not, “Fail” and

deviation number(s) are written, and a deviation report is filled in. (See deviation Report) 3) Comment: This field is used to provide additional information on how the test was

executed, any anomalies identified, additional explanatory information and additional details if required to explain what occurred in a particular deviation, the tester should include the Date of the execution of the test / inspection and initials of the tester.

4) The witness should include the date of the execution of the test /inspection and initials of

witness.

Page 8: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 8 of 23

2.6.4 Deviation handling

A Deviation report regarding SAT is filled in, if the result of a test is not according to the acceptance criteria. It could be necessary, to write more than one deviation report per test. In this case all deviation numbers have to be filled in the test sheet.

2.7 Acceptance criteria

The acceptance criteria for each Site Acceptance Test are specified in the test sheets.

2.8 SAT Result

The result of the SAT will be concluded in the SAT Report section.

Page 9: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 9 of 23

3.0 Tests

Company Name Initials

XXXXXXXXX

XXXXXXXXX

Exergy LLC

Exergy LLC

Attachments to this Site acceptance test (To be filled in on the day for SAT start)

P & ID No. And Revision No.

Components List, Revision No.

Control Panel Wiring Diagram, Revision No.

Page 10: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 10 of 23

3.1 Mechanical & Documentation Inspections

Name of test

3.1.1 FAT Closure

Test procedure

Check if the retests specified in the FAT Report are performed, and signed in the FAT test sheets. If not, perform those tests now and write “Pass” or “Fail” for the corresponding test in the FAT document. All the deviations should be closed before start of SAT.

Required document(s) / equipment

The FAT Report.

Acceptance criteria

All the Factory Acceptance Tests shall have been executed.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
The mechanical (mounting, piping of water and air, leak detection), electrical (incoming power and control wiring, grounding) inspections should be in a single test document - PRE-OPERATION CHECK OUT. This is the first step in the start-up.
Page 11: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 11 of 23

Name of test

3.1.2 Verification of components as per P & ID

Test procedure

Check that the Point of Use Cooler is built according to the P & ID and that all equipment/components are marked with the correct Tag Numbers as shown on the P & ID. Write, “Pass” at the valve /instrument /component on the P & ID if both criteria are fulfilled. If not write “Fail” and the deviation number on the drawing. Corrections shall be written with an archive safe pen on the P & ID. The tester, witness shall Sign & date the P & ID marked up for this test. Attach the marked up P & ID to this document.

Required document(s) / equipment

P & ID

Acceptance criteria

All valves, instruments and components shall be located according to the P & ID and be marked with the correct Tag Number.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
This section is not required and should be covered in the submittal process. Hydropure needs to manufacture to the submittal.
dhodge
Sticky Note
This will be marked on the final drawing. Tags locations could be part of the list of the PRE-OPERATION CHECK OUT.
Page 12: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 12 of 23

Name of test

3.1.3 Verification of Electricals

Test procedure

Check that the Control panel is built according to the circuit diagram and that the items are marked with the correct ferrule / tag numbers. Write “Pass” at the valve/instrument /component on the circuit diagrams if both criteria are fulfilled. If not, write “Fail” and the deviation number in the drawing. Sign & date the circuit diagram. Attach the circuit diagram used to verify the actual system (Electrical connections, Wiring) showing the verification results to his document.

Required document(s) / equipment

Circuit Diagram

Acceptance criteria

All the items shall be located according to the circuit and be marked with the correct Ferrule/Tag numbers.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
Part of submittals. Not part of the start-up
Page 13: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 13 of 23

Name of test

3.1.4 Verification of Component specifications

Test procedure

Check that Valves, Instruments and Components installed are in accordance with their description and specification as mentioned in the List /design qualification. Write, “Pass” at the Valve /Instrument /Component in the list, if the item is in compliance with the specifications. If not write “Fail” and the deviation number in the list. Corrections shall be written with an archive safe pen in the component list. The Tester, Witness shall Sign & date in the bottom of each page of the marked up component list. Attach the marked up Component List to this document.

Required document(s) / equipment

Component List /Design Qualification

Acceptance criteria

All Valves, Instruments and Components shall be in the accordance with their description and specifications in the Component List /Design Qualification.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
Part of the submittal. Not required for startup
Page 14: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 14 of 23

Name of test

3.1.5 Review of Test Certificates & Test Reports

Test procedure

Check that test certificates / Test Reports for components/ piping /fittings, and other Inspection /test Reports are available as per the component list. Write, “Pass” at the Valve /Instrument /Component in the list, if the required certificate is present. If not write “Fail” and the deviation number. Sign & date in the bottom of each page. Attach the used component list to this document.

Needed document(s) / equipment

Certificates and the Component List.

Acceptance criteria

Certificates shall be present according to specifications in the Component list.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
Part of submittal. Not required for startup
Page 15: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 15 of 23

Name of test

3.1.6 Check for availability of Manuals / Data

Test procedure

Check that Instruments/Component manual are present for instruments from the supplier as per the component list. Write, “Pass” at the Instrument /Component in the list, if the required certificate is present. If not write “Fail” and the deviation number. Sign & date in the bottom of each page. Attach the used component list to this document.

Needed document(s) / equipment

Manual and the Component List.

Acceptance criteria

Certificates shall be present according to specifications in the Component list.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
Manuals should be provided at startup. Number of copies should be determined during submittal process. FAT results should be available for comparison.
Page 16: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 16 of 23

3.2 System Acceptance Test

Name of test

3.2.1 To Check Functional Logic & Alarm

Test procedure

Test Procedure should be as per the Interlock and Alarm list of Design qualification, to challenge each & every alarm provided in the system. All the alarm will be checked during SAT.

Needed document(s) / equipment

Interlock and Alarm list

Acceptance criteria

All alarm shall be performed as per Interlock and Alarm list.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
List of alrams and interlocks should be listed, tested and intialed.
Page 17: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 17 of 23

Name of test

3.2.2 To Check I/O ‘s

Test procedure

Test Procedure should be to check each & every Digital & Analogue Input & Output of PLC, as per the I/O List mentioned in design qualification.

Needed document(s) / equipment

I/O List

Acceptance criteria

All Inputs & Outputs shall be performed as per I/O List.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
Part of submittal process and final documentation. No required in startup.
Page 18: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 18 of 23

3.3 Operation Test

Name of test

3.3.1 Leak Test

Test procedure

Put the Point of Use Cooler into “Operation mode” by drawing product water from any one user

point. During operation, the operating pressure is maintained for product water circuit as well as cooling water circuit.

Let the Point of Use Cooler run for 15 mins.

Check the tri-clover connections and components for leak test by visual inspection.

If leakage is found, mark the leaking connection and/or components position on P&ID & rectify the leak.

Needed document(s) / equipment

N/A

Acceptance criteria

No leaks shall be observed in the Point of Use Cooler.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
Want to run this test in PRE-OPERATION CHECK OUT.
Page 19: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 19 of 23

Name of test

3.3.2 Check for System Operating parameters

Test procedure

Operate the Point of Use Cooler by drawing water from any sampling point.

Fill in the log sheet and note the flow & temperature of product water exiting from sampling point.

Needed document(s) / equipment

Design Qualification

Acceptance criteria

Flow and temperature of product water exiting from sampling point shall meet the required parameters mentioned in design qualification.

Pass / Fail + Deviation no’s

Comment

Tester, Date / Initials

Witness, Date / Initials

dhodge
Sticky Note
This description should include a sequence of events to show what normal operation will be. 1. start water flow - check HMI shows XX 2. etc.
Page 20: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 20 of 23

4.0 SAT Report

4.1 Purpose of the Report

To conclude the performed Site Acceptance Test of Point of use Cooler.

4.2 Deviations

The deviations shall be measured until the time for SAT.

Deviation summary

Total amount of attached deviations:

Page 21: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 21 of 23

Deviation list:

Deviation No. Description

Noted by: (Date / Sign)

Completed by ( Date / Sign)

dhodge
Sticky Note
This form should be included in the final SAT with each point of testing.
Page 22: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 22 of 23

4.3 Retests

All tests that for some reason were not executed shall be performed after completion.

Test No. Test Name Test

completed

(Yes / No)

Mechanical & Documentation Inspections

3.1.1 FAT Closure

3.1.2 Verification of components as per P&ID

3.1.3 Verification of Electricals

3.1.4 Verification of Component specifications

3.1.5 Review of Test Certificates and Test Reports

3.1.6 Check for availability of Manuals & data

System Acceptance tests

3.2.1 TO check functional logic and alarm

3.2.2 TO check I / O list

Operation Tests

3.3.1 Leak Tests

3.3.2 Check for System Operating parameters.

Page 23: SITE ACCEPTANCE TEST - Harrington Plastics R2 - Site... · SITE ACCEPTANCE TEST Client Name Bayer ... The performance of the specific Factory Acceptance Tests is described for each

Client Name Bayer Project POINT OF USE COOLER

Document Name Site Acceptance Test ( SAT )

Document No. HPS-PR 247-SAT Rev No - 0

Issue Date October 31, 2014 Page 23 of 23

4.4 Final approval

To be signed by the SAT participants. If the customer has chosen not to attend the SAT, HYDROPURE SYSTEMS will decide about the project handover.

POINT OF USE COOLER is validated and handed over to client

Name & Designation

Company

Sign & Date

EXERGY LLC

EXERGY LLC

CUSTOMER

CUSTOMER