site safety documentation[1]
TRANSCRIPT
-
8/2/2019 Site Safety Documentation[1]
1/20
Wor k p e r m i t Working document 1Page 1/2Apply form
(To be filled in by applier)
Location Department ................................................................................................
Equipment n ...............................................................................................
Work description .......................................................................................................................................................................................................................................................................................................
Procedure mounting/demounting chopping / boring
opening of installations grinding
entering closed space high pressure spraying
burning/gouging/welding sand blasting
X-rays/radiation work digging hoisting / lifting placement of scaffold
.
Tools ....................................................................................................................................................................................................
Vehicles ..............................................................
Marks .............................................................
Number of persons ..............................................................
Persons < 18 years Yes
No
Start date .............................. End date ..............................
Work time from .............................. Work time - till ..............................
Special permits Dig permission Scaffold permission Entering closed space Hot work permission
Works on piping .MEASURES BEFORE STARTING THE WORKS(To be complete by the distributing department)
General measures Required Ok
Check environment combustible material
Free connect apparatus electrical
Block apparatus mechanical
Condition closed space with/without gas free certificate
Foresee signalisation
Mark out work space (white/red or yellow/black)
Seal wells, sewers, ... in a radius of . m
Health- and safety planSite XXX Page 1 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
2/20
Wor k p e r m i t Working document 1Page 2/2
Specific measures : fire hazard Required Ok
Deploy fire brigade
Set ready fire hose Extra foresee in .. mobile fire extinguishers class
.
Specific measures : fall hazard Required Ok
Place up railing (between 100 cm and 120 cm)Place intermediate railing (between 40 cm and 50 cm)
Place baseboard (min. 15 cm from work surface)
.
Supplementary personal protection means to foresee by contractor
spatial view glasses / acid glasses face screen ear protection fall protection
personal gas alarm breathing protection
LEL dust mask
O2 filter mask
CO fresh air cap
H2S compressed air mask
..........................
Extra tests Required Ok
Hoisting machines
Ladders
Electrical connections
Scaffolds
.
RATIFICATION(To be complete by the distributing department)
Sort of the risks extreme high low
relative high relative low
high extreme low
Judged by (name and first name) .................................................................
.................................................................Signatures
Distributor ..............................................................
Requestor .............................................................
Valid from ............................... Valid till ...............................PROLONGATION(To be complete by the distributing department)
From Till Name and first name Signature
.............................. .............................. .............................. ..............................
Health- and safety planSite XXX Page 2 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
3/20
Reg i s t r a t ion VGM i n s t r u c ti on s Working document 2Undersigned, ...................................................., clarifies herewith that he took upthe safety prescriptions of Waterleau and the ruling safety prescriptions of RED
STRIPE BREWERY into the general safety plan and that he transferred theprescriptions from the site regulations to his employees and subcontractors.
Explanation held on: .........................................................................
By: .........................................................................
Following persons were present and have understood the explanation of the safetyprescriptions.
Name Function Signature................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
Health- and safety planSite XXX Page 3 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
4/20
Reg i s t r a t ion Too l box mee t i n g Work document 3Undersigned, ......................................................., clarifies herewith that he dealedwith the beneath standing safety subjects and that he has explained those to a
sufficient extent so that his audience has understood.
Treated safety subjects:
1. .................................................................................................................2. .................................................................................................................3. .................................................................................................................4. .................................................................................................................
Explanation held on: .........................................................................
By: .........................................................................
Following persons were present and have understood the explanation of the safetyprescriptions.
Name Function Signature................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
Health- and safety planSite XXX Page 4 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
5/20
I n c i den t r e po r t Work document 4Page 1/4
Incident number:
1. General information
Date: ................................. Location: .................................
Hour: .................................
Person involved: Name: .........................................................Address: .........................................................
.........................................................Telephone: .........................................................
Employer: Name: ...................................................................Address: ...................................................................
...................................................................Telephone: ...................................................................Contact: ........................................................
Type of incident:
Accident with work delay Incident with damage to property
Accident without work delay Environmental incident
Almost-accident Serious risk
Nursing .....................................................
External aid:
Ambulance (called by: ........................................... ) ............................................................................................................
2. Short description of the incident
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
Indicate if applicable
Health- and safety planSite XXX Page 5 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
6/20
I n c i den t r e po r t Work document 4Page 2/4
3 Cause of incident
Use of tools Managing of vehicles Moving objects Working on height
Operating of machines Welding / burning
Handling with products Cleaning
Mounting / demounting Digging
Set-up of scaffold Sampling
Climbing / descending Tapping / spooling
Slipping / falling / stumbling Loosen connections
..................................................
4. Circumstances of incident
Leakage Falling object
Fire / explosion Electrical
Environmental pollution Vandalism
Transportation Unsafe handling
Slipping / falling / stumbling Hoisting works
..................................................
5. Injury
First aid: ..........................................................................................Medical treatment: ..............................................................................
Kind of injury: ..............................................................................Date of recovery (estimated): ..................................................................Date of recovery (effective): ..................................................................Remarks: ..................................................................
6. Results of incident examination and analysis
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
Indicate if applicable
Health- and safety planSite XXX Page 6 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
7/20
I n c i den t r e po r t Work document 4Page 3/4
7. Cause
Direct cause: Lack of communication
Insufficient follow-up of rules and procedures
Insufficient safety signalizations
Ignoring or not-use of safety signalizations
Incorrect handling
Insufficient personal protection means
Not-use of personal protection means
Influence of alcohol or drugs
Unsuitable or failing tools or machines
Incorrect use of tools or machines
Work environment Order en neatness
Access
External factors, thirds, weather conditions
............................................................................................................
Underlying cause:
Physical of mental inaptitude
Insufficient knowledge
Overburding
Insufficient motivation
Insufficient supervision Insufficient policy
Insufficient planning or organisation
Insufficient procedures or prescriptions
Incorrect design or technique
Insufficient maintenance or inspection
............................................................................................................
8. Conclusions and recommendations
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
Indicate if applicable
Health- and safety planSite XXX Page 7 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
8/20
I n c i den t r e po r t Work document 4Page 4/4
9 Witness
Name: ........................................................................................Address: ........................................................................................
........................................................................................Phone:........................................................................................Employer: ........................................................................................
Name: ........................................................................................Address: ........................................................................................
........................................................................................Phone:........................................................................................Employer: ........................................................................................
10. Correction measures
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
................................................................................................................
11. Signature
Person involved .................................... Date: .................
Prevention advisor .................................... Date: .................
Employer .................................... Date: .................
Coordinator ................................... Date: .................
Site supervisor .................................... Date: .................
Indicate if applicable
Health- and safety planSite XXX Page 8 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
9/20
I n spe c t i on c he c k l i s t s i te Work document 5aInspection date : Inspection by : Contractor :
ORDE R EN NEATNESS SITE
Are corridors, stairs passable and clean?
Is material storage safe?
Garbage containers, is garbageseparated?
Lighting on the spot alright?
Sufficient ventilation?
Fire extinguishers accessible?
...
SUPPORT TOOLS
Gas storage in conformity with ARAB
313/318 Fire extinguisher on bottle rack?
Cylinders placed upright and fixed?
Control hand tools, machines, ...- Condition- Isolation
...
PERSO NAL PROTECTION MEANS
Safety helmet (Art. 54-60)
Eye protection
Safety shoes
Protecting cloths, gloves Falling protection, line (Art. 158)
Ear protection
Breathing protection
Prevention of falling (Art. 42 - Art. 269)
...
SCAFFOLDS, LADDERS, STAIRS
Is the scaffold checked?
Is the scaffold foreseen of a test sticker?
Is the scaffold free of materials?
Falling protection in good state? Correct and safe implant
- Fixed- Frame, ladder, securization present- Ladder of sufficient length
...
FIRST AID
Is First Aid box complete?
Is the content clean?
Stretcher present?
First Aid phone numbers are marked?
Blankets present?
...
LIGFTING TOOLS, HOIST INSTRUMENTS
Crane book present and alright?
Certificates hoisting material alright?
Indications readable present on: hoist,straps,...
Visual alright?
Driver possesses a certificate?
...ELECTRICIT Y
Electrical installation in good state?
Cabinet alright?
Extension leads, plugs, ... alright?
Earthing placed?
Electrical hand tools alright?
Glow equipment alright?
Generators alright?
Welding transformer alright?
...
CHEMICALS
Legend per product present?
Hazard labels correct?
Facilities at spills present?
Protection means present?
Storage in conformity with legislation?
Storage chemical trash present?
...
ROADS , GROUNDS, TRAFIC
Boarding present?
Signalisation placed (day)?
Signalisation placed (night)?
Street lighting sufficient?
Road blockade reported?
Digging work barrier placed?
Band or turn wall necessary?
...
OTHER SAFETY POINTS
Propane-Butane storage in conformity?
Emergency road marked?
Work permit, instruction, alright?
Barrier on heights?
...
= Correct = Not acceptable = Not applicable
Health- and safety planSite XXX Page 9 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
10/20
I n spe c t i on c he c k l is t - a c c ommo da t i on Work document 5bInspection date : Inspection by : Contractor :
OFFICE, CANTEEN, DRESSING-, WASH-, OR SANITARY ROOMS
Is the building far enough of the road?
Is the interspace large enough?
Order and neatness around the accommodation correct?
Entrances safely accessible, lighting present?
Emergency doors foreseen of panic lock?
Pictogram emergency exit placed?
Fire extinguishers present (6 kg per 30 m)?
First aid box present?
Electrical heating with thermostatic regulation installed?
Electrical heating not covered?
Main current switch accessible?
Electrical installation in conformity?
...
HYGIENE
Office (floor, ashtray, litter bin, windows)
Canteen (tables, fridge, machines, ventilation, rubbish)
Wash- and dressing rooms (ventilation, wash and shower installation, sewageconnection)
Sanitary rooms (general neatness, sewage connection)
Warehouse (storage, paths, unload- and hoisting means)
...CONTAINER FOR STORAGE MATERIAL
Safely accessible?
Electrical installation in conformity? Are storage racks secured against falling over?
Contains container inflammable or explosive products?
Fire extinguisher present (6 kg per 30 m)?
...WAREHOUSE
Has the warehouse a flat floor?
Safe access for persons and material?
Electrical installation in conformity?
Earthing present?
If warehouse is also work floor, is emergency exit present?
Fire extinguisher present (6 kg per 30 m)? ...CONTAINER IN USE AS WORK SPACE
In conformity with local legislations?
Mechanical ventilation sufficient internal height - 180 cm?
Lighting present?
Fire extinguishers present (6 kg per 30 m)?
Space free from inflammable liquid and gas?
Clean floor?
Entrance good accessible?
...
= Correct = Not acceptable = Not applicable
Health- and safety planSite XXX Page 10 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
11/20
I n spe c t i on c he c k l i s t a c t i v i t ie s ge ne r a l Work document 5cInspection date : Inspection by : Contractor :
DIGGING WORKS
Subterranean pipes localized and
marked? Subterranean pipes out of use?
Passages held free?
Safe storage of material?
...
DESTRUCTION WORKS
Persons protected against noise?
Persons and environment protectedagainst falling objects?
Inspection of hoisting machines andaccessories?
Loads rated by certified riggers?
Free or protected passages?
Openings enclosed with fix fence?
Orderly stock and carry away ofrubbish?
...WORKS ON DIFFERENT LEVELS
Adapted passages above wells? Adapted passages around wells?
Protection against ground collapse?- calculation of stability- protection against crumbling off
...
GROUND WATER TABLE PUMPS
Wells dimmed? Give pipes stumbling danger?
...
CONCRETE WORKS
Facilities for safe access of enclosedplaces?
Use of stable (preferable metal)formworkselements
...
HOISTING
Are all risks examinated?- disconnect installation- emptying installation- free passages- capacities and mobility
Are entrances enclosed? Remain passages safe?
Is certified rigger present?
...PROBING
Use of efficient and certified material?
Data available on map?
Piping marked?
...
MACHINES / MATERIAL
Examination obliged installation tested?
All machines in good state?
Electrical installation in order?
...MANIPULATIONS
Installation emptied?
Valves closed and danger marked?
Hazardous products safe?- efficient packed- risk and hazard identification present- prevention measures marked
Efficient inspection before use?
ELECTRICITY
Installation tested for start-up?
Installation under tension marked?
Installation ready to start marked?
Interventions with personal padlock?
Signalisation PROHIBITED TO SWITCH?
...
= Correct = Not acceptable = Not applicable
Health- and safety planSite XXX Page 11 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
12/20
Reque s t f o r a c c e s s on s i t e a f te r wo r k i ngh ou r s
Work document 6
Considering the identification of the persons who are on site, we ask you to fillin this form for each worker to become access on site after the normal workinghours.
Employer: Name: Address:
Phone: . Fax: ..
Present superior:
Date: From: Till:
Number of persons:
Name Function Signature................................... .................................. .................................................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
Health- and safety planSite XXX Page 12 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
13/20
A n n ou n c e m e n t o f n e w e m p l o y e e s Work document 7Considering the identification of persons who are on site, we ask you to fill in this formfor each worker to become access on site.
Employee Name: .....................................................................Address: .....................................................................
.....................................................................Phone: .....................................................................
Employer: Name: .....................................................................Address: .....................................................................
.....................................................................Phone: ....................... Fax: .......................
Direct superior: .....................................................................
Personnel number: .....................................................................
Date van employment: ..............................................................Date of birth ..............................................................
Nationality ..............................................................
If EU EG citizen: E101 form in annex
Identity card number: ..............................................................Social security number: ..............................................................
All data available by means of this form are kept under strict secrecy to protectthe private life. The data can be put at someones disposal after request ofofficial authority.
Health- and safety planSite XXX Page 13 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
14/20
Fo rmu l a t i on o f r ema r k s Work document 8Undersigned, .............................................................. of thecompany, .............................................................., wants to declare a remark to the
site management. The site management obliges hisselfs to formulate an answer oneach remark that has been formulated via this organized way.
Remark
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
Date: ..............................................................................................
Name and signature of the contractor:
For: ..............................................................................................
Results
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
.....................................................................................................................
Date: ..............................................................................................
Name and signature of site supervisor:
For: ..............................................................................................
Health- and safety planSite XXX Page 14 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
15/20
I den t i f i c a t i on shee t f o r c on t r a c t o r s Working document 9Page 1/3
Within the framework of the activities Construction of an effluent treatment plant onthe site of RED STRIPE BREWERY on location 214 Spanish Town Road, Kingston
Jamaica
the undersigned clarifies the principalWaterleau Global Watertechnology NV.Radioweg 18B-3020 HerentBelgiumthat he has received the safety plan en that he will comply with it.
For the execution of the works the following identification data apply:
Firm: Name: ...........................................................................Address: ...........................................................................
...........................................................................Telephone: ............................... Fax: ............................VA.T..: ...........................................................................
Date of order: ................................................................Sort of works: ................................................................
................................................................Presumable start date: .........................................
end date: .........................................
Number of foreseen workers on site: ..................Number of foreseen vehicles on site: ..................
Notified body:Name: .......................................................................................Address: .......................................................................................
.......................................................................................Phone : ............................... Fax: ............................
Health- and safety planSite XXX Page 15 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
16/20
I den t i f i c a t ion shee t f o r c on t r a c t o r s Working document 9Page 2/3
Managing Director:
Name: .......................................................................................Phone: ............................... Fax: ............................
Prevention advisor:Name: .......................................................................................Phone: ............................... Fax: ............................
Project engineer:Name: .......................................................................................Phone: ............................... Fax: ............................
Site supervisor:Name: .......................................................................................Phone: ............................... Fax: ............................
Safety expert on site:Name: .......................................................................................Phone: ............................... Fax: ............................
First aid (present on site):Name: .......................................................................................Certificate: .......................................................................................Means: .......................................................................................Phone: ............................... Fax: ............................
Insurer work accident:Name: .......................................................................................Address: .......................................................................................
.......................................................................................
Phone: ............................... Fax: ............................
Health- and safety planSite XXX Page 16 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
17/20
I den t i f i c a t ion shee t f o r c on t r a c t o r s Working document 9Page 3/3
Medical officer:Name: .......................................................................................
Phone: ............................... Fax: ............................In case of external practice:Name: .......................................................................................Address: .......................................................................................
.......................................................................................Phone: ............................... Fax: .............................
Identification subcontractors:Name: .......................................................................................Address: .......................................................................................
.......................................................................................
Managing Director: ...........................................................................Phone: ............................... Fax: ............................
Identification subcontractors:Name: .......................................................................................Address: .......................................................................................
.......................................................................................Managing Director: ...........................................................................Phone: ............................... Fax: ............................
Identification subcontractors:Name: .......................................................................................Address: .......................................................................................
.......................................................................................Managing Director: ...........................................................................Phone: ............................... Fax: ............................
Signature: .......................................................................................
Health- and safety planSite XXX Page 17 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
18/20
I den t i f i c a t i on shee t f o r s i t e m a t e r i a l Work document 10Page 1/3
For the execution of the works, the responsible of following company declares that:
Firm: Name: ...........................................................................Address: ...........................................................................
...........................................................................Phone: ............................... Fax: ..............................
Following site material is applied:
Name Identification Administrator................................... .................................. .................................................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
................................... .................................. .................................
For equipment wherefore an official test is obliged, the test certificates are presenton site and a copy has to be handed over to the site management.
For equipment which make use of chemical products (others then fuel), the productinformation is available on site.
All site material that are apparatus, machines, installations, rooms, , arefound safe and are checked on safety and soundness on a regular base.The users of the site material are sufficiently educated and possibly medicalfollowed up to use the material.
Health- and safety planSite XXX Page 18 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
19/20
I den t i f i c a t ion shee t f o r s i t e ma t e r i a l Work document 10Page 2/3
Are scaffolds used? : Yes : No
Are hoisting machines used? : Yes : No
Which : Tirfort
Electrical hoist
Sky workers
Tele handler
Scissor lifts
Mobile crane
Lift truck
Front lift Hang lift
Others: ........................................
Are these hoisting machines tested by a notified body? : Yes : No
Which equipment / means are used?
Drill hammer & drill machines
Electrical shorten saws
Cut out saws
Grinding tools
Shoot hammers (pattern)
Table saws
Electrical groups
Compressors
Core drills
Others: ...................................
Which products are used?
Inflammable products and max. quantity on site
(White Spirit, degreaser, petrol, ...)Product: ............................................... quantity: ......................................................... quantity: ..........
Chemical products and max. quantity on site(Methyl-ethyl keton, glues, .......)
product : ............................................... quantity: ......................................................... quantity: ..........
Indicate if applicable
Health- and safety planSite XXX Page 19 of 20Version 1.0 d.d. 01-02-2006
-
8/2/2019 Site Safety Documentation[1]
20/20
I den t i f i c a t ion shee t f o r s i t e ma t e r i a l Work document 10Page 3/3
Use of:
- Distiller (propane / butane) : Yes : NoIf yes:
- check valve foreseen? : Yes : No
- fire extinguisher foreseen? : Yes : No
- storage of bottles? : Yes : No
- bottles identified? : Yes : No
- Oxy / acetylene distillers : Yes : NoIf yes:
- check valve foreseen? : Yes : No
- fire extinguisher foreseen? : Yes : No
- storage of bottles?
: Yes
: No- bottles identified? : Yes : No
- pressure gauges tested? : Yes : No
- Boilers (roofer) : Yes : NoIf yes:
- check valve foreseen? : Yes : No
- fire extinguisher foreseen? : Yes : No
- storage of bottles? : Yes : No
- bottles identified? : Yes : No
- retention tank foreseen? : Yes : No
- instructions for personnel? : Yes : No
Electrical equipment
- Use of extension lead : Yes : No
- Type H07RNF, H05RNF of CTMB : Yes : No
- Are they identified : Yes : No(name of firm mentioned on cable or colour code)
- Sockets
Sealed (IP classified as required?) : Yes : No
Is this equipment tested by a notified body? : Yes : No
Date: .......................................................................................
Signature: .......................................................................................
Indicate if applicable
Health- and safety planSite XXX Page 20 of 20Version 1 0 d d 01 02 2006