six lan rocad construction

35
Component of national highways road 1. O.G.L. (original ground level) 2. Embankment 3. Subgrade 4. G.S.B. (Grannular sub base) 5. W.M.M. (water mix macadam) 6. Prime coat 7. Tech coat 8. D.B.M. (dense bitumen macadam) 9. B.C. (bitumen coating)

Upload: devendra-sharma

Post on 21-Apr-2015

95 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Six Lan Rocad Construction

Component of national highways road1. O.G.L. (original ground level)2. Embankment3. Subgrade4. G.S.B. (Grannular sub base)5. W.M.M. (water mix macadam) 6. Prime coat7. Tech coat8. D.B.M. (dense bitumen macadam)9. B.C. (bitumen coating)

Page 2: Six Lan Rocad Construction

1. OGL – It stands for original ground level. There are some tests perform for this layer-

Lab. test Sieve analysis - (gradation test ) Proctor test - MDD OMC Liquid limit & plastic limit Free swelling test

Site test- FDD test (Field dry test) Degree of compaction = core density /marshall density

= 95%

Page 3: Six Lan Rocad Construction

2. Embankment- an artificial slope made of earth and/or stones: thickness of every layer 200 mm.

Lab. test Sieve analysis - (gradation test ) Proctor test - MDD OMC Liquid limit & plastic limit Free swelling test

Site test- FDD test (Field dry test) Degree of compaction = core density /marshall

density = 97%

Page 4: Six Lan Rocad Construction

3. Subgrade- Combination of sand , crushed stone and bricks

Lab. test Sieve analysis - (gradation test ) Proctor test - MDD OMC Liquid limit & plastic limit Free swelling test C.B.R.

Page 5: Six Lan Rocad Construction

Site test- FDD test (Field dry test) Degree of compaction = core density /marshall

density = 98% 

Page 6: Six Lan Rocad Construction

Serial no. Name of test Method Min. requirement Frequency

1. Sand content (GSA) IS-2720 part-4

Max. size<75mm 2 test/3000m3

2. Atterberg limits IS-2720 part-5

LL<70%PI<45%

2 test/3000m3

3. Modified proctor density

IS-2720 part-8

MPD>1.5gm/cc(for embankment)MPD>1.75gm/cc(for subgrade)

2 test/3000m3

4. Free swelling index IS- 2720 part-28

50% max. 2 test/3000m3

5. Field density IS- 2720 part-28

Degree of compaction>95% (for embankmemt)

Degree of compaction >97% (for subgrade)

1 test/1000m21 test/500m2

6. CBR (for subgrade) IS- 2720 part-16

CBR>10% 1 test/3000m2

Page 7: Six Lan Rocad Construction

CBR apparatus

Page 8: Six Lan Rocad Construction

G.S.B.- GSB composed in two layers -1.lower layer

2.uper layer Thickness of 1st layer – 100mm for MCW Thickness of 2nd layer- 175 mm for MCW Thickness of GSB for service road – 200 mm GSB consist natural sand, crushed stone,

crushed gravel, combination of these

Page 9: Six Lan Rocad Construction

Lab. test Sieve analysis - (gradation test ) Proctor test - MDD OMC Atterberg limit (Liquid limit & plastic limit) Free swelling test C.B.R. Moisture limit 10% fine value

Page 10: Six Lan Rocad Construction

Site test- Field dry density test Degree of compaction = core density /

marshall density = 98%

Page 11: Six Lan Rocad Construction

Serial no. Name of test Method Min. Requirement

Frequency

1. Gradation IS-2386 part-1 IS-2720 part-1

As per MORT&H

1 test/200m3

2. Atterberg limit IS-2720 part-5 LL<25%PI<6%

1 test/200m3

3. Moisture content IS-2720 part-2 -2&+1 of OMC

1 test/250m3

4. Field density IS-2720 part-28 98% of OMD 1 test/500m3

5. Surface level tolerance

  +10mm &-20mm

Regular chacking

6. CBR (4 days socking)

IS-2720 part-16 30% min.(Table-400-1)

As required

Page 12: Six Lan Rocad Construction

7. Modified proctor density

IS-2720 part-8

  One test per source

8. 10% fine value

BS-812 part-3

50kn (min.)(Table-401.2.2)

One test per source/as required

9. Water absorption

IS-2386 part-3

<2% One test per source/as required

Page 13: Six Lan Rocad Construction

ATTERBERG LIMITS APPARATUS

Page 14: Six Lan Rocad Construction

W.M.M. WMM composed in two layers -1.lower layer

2.uper layer Thickness of 1st layer – 125mm for MCW Thickness of 2nd layer- 125 mm for MCW Dust (30%) + aggregate (10mm + 20mm +

40mm)(70%) ---------- mix------add water (5.7%)------ mix.------------- truck----------- site.

Page 15: Six Lan Rocad Construction

Plant operation

Page 16: Six Lan Rocad Construction
Page 17: Six Lan Rocad Construction
Page 18: Six Lan Rocad Construction
Page 19: Six Lan Rocad Construction

Lab. test Sieve analysis - (gradation test ) Proctor test - MDD OMC Atterberg limit (Liquid limit & plastic limit) Free swelling test C.B.R. Moisture limit A.V.I. test EI & FI

Page 20: Six Lan Rocad Construction

Site test- Field dry density test Degree of compaction = core density /

marshall density = 98%

Page 21: Six Lan Rocad Construction

Serial no.

Name of test Method Min. Requirement

Frequency

1. Gradation IS-2386 part-1

MORT&H table-400-2

1 test/100m3

2. Atterberg limit

IS-2720 part-5

PI<6% 1 test/100m3

3. AIV IS-2386 part-4

30% (max.) 1 test/200m3

4. LAV IS-2386 part-4

40% (max.) As required

5. EI & FI IS-2386 part-1

30% (max.) 1 test/200m3

6. Field density IS-2720 part-28

98% (min.)of MDD

1 test/500m3

7. Modified proctor density

IS-2720 part-8

  One test per source

8. Water absorption

IS-2386 part-3

2% (max.) One test per source/req.

Page 22: Six Lan Rocad Construction

AIV apparatus

Page 23: Six Lan Rocad Construction

FI & EI APPARATUS

Page 24: Six Lan Rocad Construction

Prime coat & Tech coat

it is a spray on wmm layer to avoid voids.

Page 25: Six Lan Rocad Construction

D.B.M.— DBM composed in two layers -1.lower layer

2.uper layer Thickness of 1st layer – 75mm for MCW Thickness of 2nd layer- 50 mm for MCW Aggregate (20mm(35%) +10mm(20%)) +

Dust (43%) +Lime (2%)----- mix.--------Heat----------- Bitumen (4.5%)-----mix.----------- Truck -------- Site

Page 26: Six Lan Rocad Construction

Site test- Field dry density test Degree of compaction = core density /

marshall density = 98%

Page 27: Six Lan Rocad Construction

B.C. – BC composed In single layer of thickness 50

mm. Aggregate [19mm passing (13mm

retaining )]+ dust + lime-------- mix------heat-------------- Bitumen ------- mix--------------- truck-------- site

Page 28: Six Lan Rocad Construction

Serial no.

Name of test Method Min. requirement

DBM BC

1. Quality of binder

  60/70 CRMB-60

2. AIV IS-2386 part-4 27% (max.) 24% (max.)

3. EI & FI IS-2386 part-1 30% (max.) 30% (max.)

4. Water absorption

IS-2386 part-3 2% (max.) 2% (max.)

5. Coating & stripping of bitumen aggregate mixture

AASHTO-182 & IS-6241

Min. retained coating 95%

Min. retained coating 95%

 6.

LOS Angles Abrasion value 

IS-2386 part-435% (max.)

35% (max.) 

30% (max.)

Page 29: Six Lan Rocad Construction

7. Soundness

IS-2386 part-5

12% (max.) 12% (max.) At source approval

8. Marshal stability test

MORT&H table-500-1&ASTM-D-1559

%AV.=3-6%VMA.=12%(min.)VFB=65-75%STABILITY=9knFLOW=2-4mm

%AV.=3-5%VMA.=12%(min.)VFB=65-75%STABILITY=12knFLOW=2-4mm

 

9. Field compaction

ASTM-D-1559 98% of bulk density

98% of bulk density

 

10.

Water sensitivity

IS-clause 507.3.1

<75% <75%  

11.

Roughness

TS clause:903.4.4

2000MM/kn 2000MM/kn  

12.

Plasticity index

IS-2720 part-5 4% (max.) 4% (max.)  

Page 30: Six Lan Rocad Construction

BITUMEN Extractor

Page 31: Six Lan Rocad Construction

MARSHALL STABILITY TEST APPARATUS

Page 32: Six Lan Rocad Construction

DUCTILITY APPARATUS

Page 33: Six Lan Rocad Construction

BITUMEN PENETROMETER

Page 34: Six Lan Rocad Construction

CORE CUTTING

Page 35: Six Lan Rocad Construction

SLUMP CONE