Last Updated: 8-28-13 Team: Bend But Don’t Break Bill Busutil (Team Leader) Harold Concepcion (Co-Team Leader) Teri Aking-Dindial Christa Erml-Martinez Cristian Guerrero Donna Romito Matthew Davis Craig Grossenbacher Lee Hefty Green Belt Project Objective: To Reduce Cycle Time For Issuing Tree Permits Six Sigma DMAIC Improvement Story Jack Osterholt (Sponsor)

Upload: others

Post on 04-Oct-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Last Updated: 8-28-13

Team: Bend But Don’t Break

Bill Busutil (Team Leader) Harold Concepcion (Co-Team Leader)

Teri Aking-Dindial Christa Erml-Martinez Cristian Guerrero Donna Romito

Matthew Davis Craig Grossenbacher Lee Hefty

Green Belt Project Objective:

To Reduce Cycle Time For Issuing Tree Permits

Six Sigma DMAIC Improvement Story

Jack Osterholt (Sponsor)

Page 2: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Six Sigma Problem Solving Process

2 Define Measure Analyze Improve Control

Process StepDescription of Team Activities

Number Name

1 DEFINE

· Select Problem

· Identify Project Charter

· Develop Project Timeline

· Establish Method to Monitor Team Progress

· Construct Process Flowchart

· Develop Data Collection Plan

· Display Indicator Performance “Gap”

2 MEASURE· Stratify Problem (i.e.“Gap”)

· Identify Problem Statement

3 ANALYZE· Identify Potential Root Cause(s)

· Verify Root Cause(s)

CONTROL

· Standardize Improvements within Operations

· Implement Process Control System (PCS)

· Document Lessons Learned

· Identify Future Plans

5

DMAIC Performance Improvement Process

4 IMPROVE

· Identify and Select Improvement(s)

· Identify Barriers and Aids

· Develop and Implement Improvement Plan

· Confirm Improvement Results

The team utilized the 5-Step DMAIC problem solving process.

Page 3: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Review Process Flow Chart

Define Measure Analyze Improve Control 3

The team constructed a flowchart for the Tree Permit Process.

The team developed Outcome Indicators from SIPOC and Customer Rqmts analysis (see Appendices A and B)

Page 4: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Review Selected Indicator The team collected indicator data and reviewed performance trends:

4 Define Measure Analyze Improve Control

GAP

Target = 90%

GOOD

Months of the Year

Page 5: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

0

10

20

30

40

50

60

70

-14.5 0.5 15.5 30.5 45.5 60.5 75.5 90.5 105.5 120.5 135.5 150.5 165.5 180.5 195.5 210.5 225.5 240.5 255.5 270.5

Nu

mb

er o

f Tr

ee P

erm

its

Number of Days to Issue Permits

Total Tree Permits Issued: May 2012 - February 2013

23

51

61

44

34

25

9

6

3

11

3 3 1 2 1

_

n = 277

mean = 57.2 Days

median = 44 Days

std. dev. = 41.4 Days

Standard: 30 Days

203 Permits were issued beyond

the 30 day standard

Stratify the Problem The team stratified the 277 permits many ways and found…

Define Measure Analyze Improve Control 5

Page 6: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Stratify the Problem The team stratified 202 permits issued beyond the 30 day standard many ways and found…

Define Measure Analyze Improve Control 6

186

16

%

%

0

10

20

30

40

50

60

70

80

90

100

0

50

100

150

200

S N .

% o

f To

tal

Nu

mb

er o

f P

erm

its

Issu

ed

Specimen vs Non-Specimen

Total Number of Permits Issued Beyond 30 days

n = 202 (1 permit data point was not available)

92

Page 7: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

131

23 20 12

%

%

%

0

10

20

30

40

50

60

70

80

90

100

0

20

40

60

80

100

120

140

160

180

TP RELO AF AFMI

% o

f To

tal

Nu

mb

er o

f P

erm

its

Issu

ed

Type of Permit

Total Number of Specimen Permits Issued Beyond the 30 day Standard

n = 186

70

83

94

Stratify the Problem The team stratified the 186 specimen permits many ways and found…

Define Measure Analyze Improve Control

TP = Removal

RELO = Relocation

AF = After the Fact

AFMI = After the Fact w/ Mitigation

7

Problem Statement: “Of the 277 tree permits issued from May 2012 to February 2013, 131 tree removal permits

involving specimen trees were issued beyond the standard of 30 days from receipt of permit application.”

Page 8: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Identify Potential Root Causes The team completed Cause and Effect Analysis and found…

Define Measure Analyze Improve Control 8

Problem Statement:

“Of the 277 tree

permits issued from

May 2012 to February

2013, 131 tree removal

permits involving

specimen trees were

issued beyond the

standard of 30 days

from receipt of permit

application.”

Problem

Statement

Fishbone

Cause and

Effect Diagram

= Potential Root

Cause

Workload exceeds staffing capability

A- Backlog of Applications (100%)

C

B – Applications assigned

to Biologists by the

Supervisor (100%)

In-take personnel are not trained to

conduct thorough pre-screening

Some applications do not belong in the current process

A

Many applicants lack knowledge,

ability and willingness to comply with

process

In-take personnel lack knowledge to

conduct thorough pre-screening

C – Incomplete, Inaccurate

Applications (75%)

Intake personnel lack technical expertise to

conduct thorough pre-screeningThe Process and

requirements are too

cumbersome and complex

BThe County Code is

confusing

No formal policy exists that enables the applicant to obtain a tree

permit through an expedited process

Page 9: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Identify and Select Countermeasures

The team selected all countermeasures for implementation.

The team brainstormed many countermeasures and narrowed them down to these for evaluation:

9 Measure Analyze Improve Control

13.,14.

Countermeasures Matrix

Problem Statement Verified Root Causes Countermeasures

Legend: 3=Moderately

5=Extremely 2=Somewhat

4=Very 1=Little or None

Ratings

Eff

ecti

ve

ness

Feasib

ilit y

Ov

era

ll

Take

Acti

on

?

Yes/N

o

“Of the 277 tree permits

issued from May 2012

to February 2013, 131

tree removal permits

were issued beyond the

standard of 30 days

from receipt of permit

application.”

A - No formal policy exists that

enables the applicant to obtain a

tree permit through an expedited

process.

A1- For non specimen trees, give

applicants the option up front to

obtain permits through an

expedited process

5 4 20 Y

A2- For selected specimen trees

and selected projects, give

applicants the option up front to

obtain permits through an

expedited process

5 3 15 Y

A3- Establish and track cycle time

standards for the revised process

(See Appendix C )

5 4 20 Y

B - Intake personnel lack technical

expertise to conduct thorough pre-

screening.

B1- Have technical staff at DERM

and at the PIC provide thorough

pre-screening and plan review at

point of intake

4 4 16 Y

C - The process and requirements

are too cumbersome and complex.

C1- Implement system upgrades to

enable on-line processing and

staff/applicant interaction

4 3 12 Y

C2- Remove the signature

requirement, thus eliminating the

draft permit and facilitating the

possibility of issuing permits at job

sites

5 4 20 Y

C3- Simplify application forms and

the permit document 5 4 20 Y

Define

Page 10: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Revised Process Flow Chart

Define Measure Analyze Improve Control 10

The team

constructed a

revised

flowchart for

the tree

permit

process.

Define

P2 - % of

sites

inspected

timely

80% of the

sampled

permit

applications

could be

expedited!

P1 - % of applications pre-

screened timely

Q1 - % of permits issued timely

Applicant

Permitting, Environment and Regulatory Affairs – Pollution Regulation and

Enforcement Division

Intake Personnel BiologistSTEP

WHO

Need Tree Permit Required

Submit Complete Tree Permit

Application

Receive /

Review

Review Application for

completeness

Application

Complete?

Reject /

Redirect

Finalize /

Issue

Receive /

Assign

Conduct Site Inspection

Finalize and Issue PermitFinalize and issue permit

Yes

Issued Permit

Inform applicant of requirements

No

Thoroughly prescreen and

evaluate application

Can application

be expedited

w/o inspection?

Yes

(80%)

Assign application to BiologistNo

(20%)

Page 11: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

To estimate the potential impact of the revised tree permitting

process indicated by the countermeasures, the team analyzed

a sample of recent tree permit applications and found …. Tree Permits Issued: May 2012 – February 2013

80% of the tree permit applications in this sample could be expedited

with the revised process! 11

Not Expedited Expedited

24 applications would be expedited (80%)

6 applications would not be expedited (20%)

N=30

Page 12: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Potential Benefits of Countermeasures

Significant reductions in cycle time for processing tree permit

applications will be achieved by eliminating the need for

inspections when applicants provide sufficient information, and by

eliminating the draft permit

Of the 6.35 ERM FTE’s currently deployed to the tree permitting

process, approximately 2 to 4 FTE’s could be reassigned to

conduct follow-up activities or assume other responsibilities

Reassigning tree permitting resources to conduct follow-up

activities could more effectively foster the restoration and

enhancement of the canopy

12

Page 13: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Develop and Implement Action Plan Legend:

= Actual

= Proposed

The team developed an Action Plan for the Countermeasures.

13 Define Measure Analyze Improve Control

16.

Page 14: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

0

10

20

30

40

50

60

70

80

90

100

Oct-13

Nov-13

Dec-13

Jan-14

Feb-14

Mar-14

Apr-14

May-14

Jun-14

Jul-14

Month

%

Target

Tree Permits

Review Results

The team was encouraged by the results and will continue to monitor the countermeasures.

The team collected indicator data and reviewed results of its countermeasures

14 Define Measure Analyze Improve Control

17.,18.,19.,20.

3. Countermeasures to be implemented April 2014

Q1 - % of Non Expedited Tree Permits Issued Within 30 Days

GOOD

Target = 90%

Page 15: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Standardize Countermeasures Process Control System

Process Name: Process Tree Permit Applications

Process Owner: Lee Hefty

Process Customer: RER/Tree Permit Applicants/Public at Large

Critical Customer Requirements: Timely Review and Approval of Tree Permit Applications

Process Purpose: Review & Approve Tree Permit Applications

Current Sigma Level: TBD

Outcome Indicators: P1, P2, Q1 (Revised Process) Process and Quality Indicators Checking / Indicator Monitoring

Contingency Plans / Misc. Actions Required

for Exceptions Procedure

References

Process Indicators

Control Limits Data to Collect

Timeframe (Frequency) Responsibility

Quality Indicators Specs/ Targets

What is Checking Item or Indicator Calculation

When to Collect Data?

Who will Check?

P1 % of applications pre-screened within 2 days of receipt of application

90% Pre-screened tree permit applications

Monthly Tree Permit Supervisor (Lazaro Q.)

Tree Permit Database

P2 % of sites requiring inspection that are inspected within 10 days of receipt of application

90% Tree permit applications requiring site inspections

Monthly Tree Permit Supervisor (Lazaro Q.)

Tree Permit Database

Q1 % of tree permits issued timely (10 days for expedited permits, and 30 days for non- expedited permits)

90% Issued tree permits Monthly Tree Permit Supervisor (Lazaro Q.)

Tree Permit Database

Q2 Ratio of Canopy to be Planted (SQ.FT.) to Canopy Removed through Permitting and Enforcement

TBD Issued tree permits Monthly Tree Permit Supervisor (Lazaro Q.)

Tree Permit Database

Approved: Date: Rev #: Rev Date:

And

Define Measure Analyze Improve Control

The Team looked ahead to the future

15

Page 16: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Lessons Learned

Including a combination of knowledge workers, high level decision

makers and customers on the project team produced aggressive,

creative countermeasures

A significant effort at the beginning of the project to develop a reliable

data set provided a sound launching point for subsequent analysis

Assuring that all team members were thoroughly briefed prior to each

work session fostered consensus and maximized team effectiveness

Next Steps

Obtain a reliable carrying cost estimate

Present project results to the project sponsor

Assist with implementation planning as needed

16

Page 17: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Appendices

Appendix A…S.I.P.O.C. Analysis

Appendix B…Customer Requirements Matrix

Appendix C…Time Standards For Revised Tree Permitting Process

17

Page 18: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Appendix A Date Approved:

Suppliers Inputs Process Outputs* Customers1. Plan Review Docs

Applicant 2. Application

Application with

Tracking Number Supervisor

3. Tree Survey

4. Site Plan

Supervisor

1. Assignment of

Applications Assigned Application Biologist

2. Application with

Tracking number

Biologist 1. Assigned Application Permitting Decision 1. Supervisor

2. Initial Review Document Request 2. Applicant

3. Aerial Review Mitigation Calculation

Completed

Application

Biologist Completed Application Draft Permit Supervisor

1. Supervisor

2. Biologist Draft Permit Executed Permit Applicant

S.I.P.O.C. AnalysisProcess: Tree Removal Permitting Process

Process Owner: Lee Hefty

1. Receive Application

2. Assign Application to Biologist

5. Issue Permit

* Outputs used to Identify Outcomes

4. Prepare Draft Permit

3. Conduct Inspection

18

Page 19: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Appendix B

Process:

Quality

Element Example Question

Accuracy

How accurate does

the application need

to be?

P1 - % of accurate, complete

applications

Timeliness

How quickly does the

app. need to be sent

to Sup.?

P2 - % of applications received timely

from Clerk

Timeliness

How quickly does the

app. need to be sent

to Biologist.?

Assigned

Application

P3 - % of applications received timely

from Supervisor

Timeliness

How quickly must the

inspection be

completed?

Completed

ApplicationP4 - % of inspections completed timely

Timeliness

How quickly must the

draft permit be

completed?

Draft PermitP4 - % of draft permits completed

timely

Timeliness

How quickly must the

executed permit be

issued?

Executed

Permit

Q1 - % of executed permits issued

timely

Timely completion of

inspection and application

Timely completion of draft

permit

Timely issuance of

executed permit

Timely receipt of application

from Supervisor

Outcome IndicatorCustomer Valid

Requirement

Survey Voice of Customer

Timely receipt of application

from Clerk

Process

Output(s)

Customer Requirements Matrix

Accurate, complete

application

Tree Removal Permitting Process

Application w/

tracking

number

19

Page 20: Six Sigma DMAIC Improvement Story - Miami-Dade County · Revised Process Flow Chart Define Measure Analyze Improve Control 10 The team constructed a revised flowchart for the tree

Appendix C

Time Standards for Revised Tree Permitting Process:

• Receipt of Application to Pre-screening and Evaluation: 2 Days

• Receipt of Application to Site Inspection: 10 Days

• Receipt of Application to Permit Issuance (expedited): 10 Days

• Receipt of Application to Permit Issuance (non-expedited): 30 Days

20