six+sgma+3
TRANSCRIPT
-
7/29/2019 six+sgma+3
1/6
An Integrated Approach to TPM and Six Sigma Development in
the Castings Industry.
A.J. Thomasa, G.R. Jones
b, P. Vidales
c
aManufacturing Engineering Centre, Cardiff University, CF24 3AA, UK
bWall Colmonoy, Pontardawe, Swansea, SA1 3DEcEcole d'ingeniear CESI, France
Abstract
Both Total Productive Maintenance (TPM) and Six Sigma are key business process strategies which are
employed by companies to enhance their manufacturing performance. However, whilst there is significant research
information available on implementing these systems in a sequential manner, there is little information available
relating to the integration of these approaches to provide a single and highly effective strategy for change in
companies.
This paper proposes an integrated approach to TPM and Six Sigma which was developed as a result of workundertaken in the castings industry. The effectiveness of the approach is subsequently evaluated highlighting the
benefits the host organization received through this new approach by measuring the effects of implementation against
the seven Quality, Cost and Delivery (QCD) measures.
Keywords: TPM, DMAIC, QCD Measures
1. Introduction to TPM and the Six Sigma
Approach
Total Productive Maintenance (TPM) is a
maintenance program which employs a strategy for
maintaining plant and equipment to its optimum level
of operational effectiveness. Primarily the TPMapproach links into the Lean concept and aims at
reducing waste due to poorly maintained machinery
and provides for value added inputs by way ofensuring machinery remains in productive operation
for longer periods of time [1]. Maintenance procedures
and systems are designed so that they are easier to
accomplish and this is achieved through machine
redesign and modifications in order to facilitate this
process.
Six Sigmacan be considered both a business strategy
and a science that has the aim of reducing
manufacturing and service costs, and creating
significant improvements in customer satisfaction and
bottom-line savings through combining statistical and
Business Process methodologies into an integratedmodel of process, product and service improvement
[2].
Although both strategies have similar aims, those of
improving productive effectiveness, the way in which
these strategies are implemented into companies varies
greatly. Traditionally Six Sigma employs a structured
five-phased DMAIC methodology. Six Sigma teams
are created to tackle specific problems to reach Six
-
7/29/2019 six+sgma+3
2/6
Sigma levels of performance [2]. TPM implementationon the other hand is seen to be implemented in a range
of different ways, although attempts have been made to
formalise the TPM strategy [3], [4], [5], there is still no
formally defined approach that can be considered as an
industry standard approach to TPM implementation.
However, when considering TPM, it is worth notingthat the basic principles of the TPM strategy have very
close links to the Six Sigma approach. In TPM the
ultimate aim is to achieve significantly reduced
breakdown levels through developing autonomous
maintenance teams.
Employing therefore a standard operational framework
for implementing both approaches is seen as an
obvious and necessary step for companies to achieve
simultaneous benefits from the TPM and Six Sigma
strategies. To this end the DMAIC process is used as
the main operational approach for the implementation
of TPM. The following section highlights the
application of the DMAIC process in theimplementation of TPM in a castings company.
2. Introduction to Wall Colmonoy
Wall Colmonoy is a manufacturer of specialist
castings. The company is based in South Wales and
manufactures its products to a world wide market.
Over the years the company has experienced
increasing competition from the far-east where product
unit costs have been dramatically reduced. This has
brought about major changes to the company
operations and has raised the need for the company to
become leaner and more responsive to customers if
they are to remain as serious competitors in their
market.
Over the past two years the company has embarked on
a Lean manufacturing program. As part of the Lean
approach, TPM and Six Sigma are seen as essential
strategies for success. However, the company is
concerned that the separate implementation of such
approaches means the requirement of large scale
human, financial and technical resources as well as the
associated problems of running competing projects in
the company. The company requires a simple yet
effective operational framework that can be used as a
standard approach to adopting both strategies in thecompany. The company expects that worker buy in
will be easier if one common operational approach is
adopted
3. DMAIC at Wall Colmonoy
The Six Sigma strategy concentrates on a simple
five phase methodology called DMAIC. DMAIC is an
acronym of the major steps within the methodology
namely Define, Measure, Analyse, Improve, Control. It
was decided that the DMAIC process would form thebasic foundation for the TPM strategy and hence the
standard approach for adopting the major stages of the
TPM project. Each stage is explained in detail in the
following section of the paper.
3.1 Define
A benchmarking exercise was undertaken into the
major product lines operated by the company. The
product lines were benchmarked against on-time
delivery and right first time quality levels. A gauge
R+R study was undertaken in order to ensure that themeasuring equipment was suitable for measuring the
outgoing quality from the processes. From the analysis
of the key casting processes within the company, the
investment casting process was highlighted as the area
requiring greatest attention with scrap rates in excess
of 4% and on-time delivery at only 65%. The
definition stage triggered the development of a TPM
team within the company. This involved the training ofteam members in the principles of TPM as well as the
implementation of a 5S program* aimed at piloting
autonomous cleaning and teamworking prior to
specific and targeted TPM projects being undertaken
within the investment casting area.
3.2 Measure
Overall Equipment Effectiveness (OEE) was
calculated on each of the machines within the
investment casting area. Also, the company measured
parts throughput (parts per hour) through the cell in
order to identify whether the inefficiencies were due to
the machinery or to the operations surrounding the
machinery or both. As an example, OEE calculated for
one machine was calculated at 75% however partsthroughput in the cell where the machine operated in
was 43% less than the theoretical throughput for that
cell. Further analysis of the cell indicated that the
process surrounding the machine was at fault rather
than the machine itself.
One casting cell was measured as having a throughput
at 36% of its theoretical value and an OEE value of
30% for the wax making machine. A process mapping
exercise confirmed that the wax making machine was
the major cause of the low cell throughput and so thismachine became the focus of the remainder of the
project.
3.3 Analyse
The OEE value was split down to its constituent
parts namely; Availability, Performance and Quality.
* 5S A systematic process of workplace cleaning and
maintenance. Sort, Sanitize, Stabilize, Systematize, Sustain
-
7/29/2019 six+sgma+3
3/6
The results of this analysis showed that machineavailability was lowest at 34% compared to
performance at 94% and quality at 96%. This clearly
indicated that machine breakdowns and major stoppage
problems were the causal point for the poor OEEvalue. A Fault Tree Analysis (FTA) was therefore
carried out by a team of engineers from within thecompany in order to ascertain the root cause(s) of high
machinery failure. The FTA is shown in Fig 1 and lists
the failure routes identified from the brainstorming
session. Following the FTA, the engineering team
progressed to creating Failure Modes and Effects and
Criticality Analysis (FMECA) on each of the areasidentified from the failure routes on the FTA. The
FMECA allowed the company to identify the potential
causes of failure, assess its effect on the machine and
process and also, and most importantly, allow for
corrective actions to be identified. The engineering
team did not follow normal FMECA convention at this
stage and decided to employ individual FMECA sheets
for each potential failure mode. The benefit this gavethe team was that each sheet could be given to the
maintenance teams in turn in order to apply the
corrective action specified in the documents. In order
to prioritise the issuing of the FMECA sheets to the
maintenance teams, a Pareto analysis was constructed
of the Risk Priority Number (RPN) from each
FMECA study with the higher ranked RPNs being
tackled first.
3.4 Improve
Three levels of TPM were adopted in the
company in order to improve the machines reliability.
Level 1 was the introduction of shop floor autonomous
maintenance teams. These teams applied basic
maintenance practices including regular daily cleaningregimes as well as undertaking sensory maintenance
tasks (smell, sound, sight, feel etc). However, prior to
this level being undertaken, it was essential that major
machinery and equipment was completely overhauled
in order to revert the machinery to its original level of
reliability. This was considered to be Level 2 in the
TPM system and the work undertaken by the
maintenance department. Level 3 involved the
engineering department becoming more pro-active in
the development of preventive maintenance practices
including machine modification and enhancementstrategies that allow for easier maintenance etc. Level
3 work also included the monitoring of maintenance
FMECA An advanced planning technique aimed at
systematically assessing all the potential failures of a machine and
the potential impact (criticality) of the failure on a human and/or the
system.
RPN Risk Priority Number. A numerical method of analysing the
failure mode and its effect on the system. RPN = Severity x
Occurrence x Detection.
activities and concentrating primarily on approachestowards increasing Mean Time Between Failures
(MTBF) so that higher machine availability is
achieved. The aim here is to systematically extend the
mean time between failure so that the machinery can
remain productive for longer thus providing greater
return on machine performance. Table 1 shows thework undertaken at each level in the TPM system.
Table 1 TPM Levels and Work Definition
Levels of TPM Operation and Typical Activities
Level 1 Level 2 Level 3
Basic Cleaning Machine
overhaul
Machine
redesign
Machine care
plans
Major
Maintenance
MTBF analysis
& extension
Sensorymaintenance
Level 1Monitoring
Level 2Monitoring
3.5 Control
The work undertaken by the pilot TPM work wasmeasured for its effectiveness before being rolled out
through the company. Machine maintenance schedules
and plans were formalized and attached to each
machine. All operators were trained to undertake the
maintenance schedules and to report any issues to the
maintenance teams. As a control mechanism, it is the
responsibility of the maintenance department to
monitor the work of the operators and to rectify any
issues raised by the shop floor personnel.
The engineering department in turn monitored theoutputs from the maintenance department in order to
identify recurring failures and issues that could be
redesigned in order to prevent future failures. Theengineering team provided the technical and financial
support to the maintenance department in order to
facilitate the high level maintenance activities
undertaken at the level 2 stage. Fig 2 shows the
autonomous team approach at each of the TPM levels
in the organization and how each level integrate with
each other.
Fig 2 Autonomous Team Structure
TPM Autonomous teams
11
22
33
44
OperatorsOperators
Team LeaderTeam Leader
11
22
33
44
11
22
33
44
MaintenanceMaintenance
Team LeaderTeam Leader
EngineersEngineers
Team LeaderTeam Leader
Complexity of maintenance function- +
-
7/29/2019 six+sgma+3
4/6
4. Evaluation
As part of the companys approach to improving
their Quality, Cost and Delivery targets, i t was decided
to measure the QCD [6] outputs as a direct result of theTPM project. Table 2 shows the improvements made
in each QCD area.
In this case, the benefits gained from undertaking theTPM project may be considered idealistic when
comparing the large benefits gained from a relatively
small initial financial outlay. However, the costs
incurred in continuously controlling the input variables
and factors means that the monitoring costs can be
large and greater than first expected. This in turn can
affect the true savings achieved from the project. The
issue of cost analysis and control is as a key
consideration and its correct analysis and interpretation
is key to providing credibility to the TPM strategywithin the company.
5. Conclusions
A TPM pilot study was undertaken in order toimprove the Quality, Cost and Delivery measures
of the company. In all measures, the TPM project
achieved significant improvements.
This relatively simple application of TPM using astructured DMAIC technique should allow for
increased use of the methodology for tackling
many maintenance issues. Likewise, the results
can also provide the stimulus for the widerapplication of the technique to create process
improvements at relatively lower costs.
The application of the TPM approach to the waxmachine area at Wall Colmonoy achieved savings
in excess of 200,000 for an initial outlay of less
than 4,000 in experimental and project costs.
The development of the TPM approach developeda culture towards continuous improvement and the
systematic implementation of the system
throughout the organisation.
The application of the TPM approach allowed thecompany to develop advanced systems mapping
and analysis techniques and to become generally
more technical in their approach to problem
solving .
Acknowledgements
The authors would like to express their
appreciation to the following organisations for their
support during the development of the project and the
writing of this paper: Wall Colmonoy, I*PROMS,
Cardiff University Innovative Manufacturing Research
Centre.
References
[1] Jostes R S, Helms M M. Total Productive
Maintenance and Its Link to Total Quality
Management. Work Study Journal. (1994), 43,7.[2] Breyfogle, F.W. Implementing Six Sigma,
Smarter Solutions - Using Statistical Methods,
(1999).John Wiley & Sons Inc.
[3] Blanchard,B S.An enhanced approach for
implementing total productive maintenance in the
manufacturing environment, Journal of Quality in
Maintenance Engineering.(1997), 3,2.
[4] Jens,O, Riis J, Luxhj T, Thorsteinsson U. A
situational maintenance model
International Journal of Quality & ReliabilityManagement; (1997).14, 4.[5] Raouf A, Ben-Daya M. Total maintenance
management: a systematic approach,Journal of Quality in Maintenance Engineering;
(1995) 1,1.
[6] Achieving Best Practice in Your Business
QCD Measuring Manufacturing Performance.
Department of Trade and Industry Brochure,
www.dti.gov.uk.(2002).
-
7/29/2019 six+sgma+3
5/6
Fig1
AnFT
A
ofthepossiblefactorsinfluencingmachineperformance
Auto
WaxMachine1
OEE=35,5
%
SCRAP
BREAKDOWN
Partsinoil
Dipping
Parts
c
hipping
Parts
sticking
Air
entrapment
Fla
shing
Tool
jamming
Wiperarm
creeping
down
Injection
system
Hydraulic
pipes
bursting
No
regulators
Noset
variables
Wax
Temp
Back
plates
arentcold
Water
coolingnot
working
Leak
cooling
Par
tsfalling
one
achother
F
lushing
systemnot
w
orking
Pumps
notworking
S
ystem
b
locking
Water
contaminated
Tool
Sprue
T
emp
Control
Wipernot
long
enough
Patterns
notcool
Nozzle
design
Suckingin
air
Nozzle
temp
Spread
of
stirring
Seal
worn
Part
springing
Plate
cooling
Hold
time
Air
entrapment
Wear
onthe
tool
Brass
bush
wearing
Surface
Finish
Sprue
stuck
Ejector
pinsnaps
Nowax
Blockage
Waxblocked
infeedfrom
tank
Blockage
atnozzle
Stirrer
notlong
enough
Debris
intank
Temp
control
Poor
hou
sekeeping
Pouring
system
Nozzle
des
ign
Temp
control
at
nozzle
Water
heating
Handling
problem
Tool
condition
Storage
Dust
Sealsin
system
Oilin
water
AND
OR
LEGEND
-
7/29/2019 six+sgma+3
6/6
Table 2 Quality, Cost Delivery The Seven Measures
ie
60-30
30
5%1%
1% - 5%
5%
Improvement =
ie
Increase
Increase
i.e.
Increase
Number of planned deliveries - Number of not on time
deliveries
30,000 per employee
30,000
50,000 - 30,000Improvement =
Number of employees
30%
(Gross) Value Added
per Person
Basic Measure: / person Example of Improvement Measure
Previous StateOutput value - Input value New State 50,000 per employee
96% - 80%
80%
66% effective
66% - 30%
Value of (Raw material + WIP + Finished Goods)
Improvement =
Overall Equipment
Effectiveness
Basic Measure: % Example of Improvement Measure
Previous S tate 30% e ffective
i.e. Availability % x Perfomance % x Quality % New State
Improvement =
90%
Increase in Stock
Turns
Basic Measure: Number of turns Example of Improvement Measure
Previous S tate 4 S tock Turns
Sales turnover of product New State 5 Stock Turns
99% delivered on Time
Improvement = 99% - 90%
50,000 - 30,000=67%
30,000
On Time Delivery
Improvement
Basic Measure: % delivered correctly and on t ime Example of Improvement Measure
Previous State 90% del ivered on Time
New State
Number of not on time deliveries
People Productivity
Improvement
Improved Space
Utilisation
Basic Measure: per m2 Example of improvement measure
Previous S tate 30,000 per m2
Sales turnover of model area New State 50,000 per m2
Number of square metres of area
Scrap / Defect
Reduction
Basic Measure: % Example of Improvement Measure
Previous StateQuantity of defective units New State
Total quantity of units supplied Improvement =
Basic Measure: Units per direct operator hour Example of Improvement Measure
Previous S tate 30 Uni ts per Hour
Number if good units made New State 60 units per Hour
Number of direct operator hoursImprovement = 50%
i.e a 80%
reduction indefects (reported
as a positive
number
=10%
=20%
=120%
=67%