sl seminar 11 july 20021 machine protection and interlock systems for the lhc sl-seminar rüdiger...
TRANSCRIPT
SL Seminar 11 July 2002 1
Machine Protection and Machine Protection and Interlock Systems for the LHCInterlock Systems for the LHC
SL-Seminar
Rüdiger Schmidt
on behalf of the MPWG
The LHC challenges
Powering Operation and Protection
Beam Operation and Protection
SL Seminar 11 July 2002
OutlineOutline
LHC parameters and layout LHC stored energy and associated risks LHC protection systems
Protection and interlocks for powering
Protection and interlocks for beam operation Beam Dump Beam Cleaning Beam Loss Monitors Beam Interlock System
Conclusions
LHC parameters and layout LHC stored energy and associated risks LHC protection systems
Protection and interlocks for powering
Protection and interlocks for beam operation Beam Dump Beam Cleaning Beam Loss Monitors Beam Interlock System
Conclusions
4
Momentum at collision 7 TeV/cMomentum at injection 450 GeV/cDipole field at 7 TeV 8.33 TeslaCircumference 26658 mNumber of electrical circuits ~1700
Luminosity 1034 cm-2s-1 Number of bunches 2808 Particles per bunch 1.1 1011 DC beam current 0.56 AStored energy per beam 350 MJ
Normalised emittance 3.75 µmBeam size at IP / 7 TeV 15.9 µmBeam size in arcs (rms) 300 µm
High beam energy in LHC tunnelSuperconducting NbTi magnets at 1.9 KStored energy in magnets very large
High luminosity at 7 TeV very high energy stored in the beam
beam power concentrated in small area
LHC Parameters and Challenges for LHC Parameters and Challenges for ProtectionProtection
5
Energy in the magnet system: 11 GJ
In case of failure, extract energy with a time constant of up to about 100 s
Energy in two LHC Beams: 700 MJ
Dump the beams in case of failure within 89 s after dump kicker fires
Drop 35 tons from 28 km
Energy in Magnets and Beams Energy in Magnets and Beams
Drop it from 2 km
One beam, nominal intensitycorresponds to an energy that melts 500 kg of copper
6
Challenges: Challenges: Energy stored in the magnetsEnergy stored in the magnets
Energy stored in the LHC magnets, powered in ~1700 electrical circuits - all need protection
HERA: all dipole magnets store about 700 MJ
LHC: to limit energy - powering in eight sectors
Energy in dipole magnets (one sector): 1.3 GJ eight systems in the LHC - 8 dipole circuits
Energy in main quadrupole magnets (one sector): 40 MJ sixteen systems in the LHC for main quadrupoles
Energy in special quadrupole magnets (6 kA): about 100 circuits
Energy in 600 A circuits (i.e. chromaticity correction): 10 - some 100 kJ several 100 systems
7
Challenges:Challenges: Energy stored in the beam Energy stored in the beam
courtesy R.Assmann Momentum [GeV/c]
Ene
rgy
stor
ed in
the
bea
m [
MJ]
Energy density: even larger factor between LHC and other machines
x 200
x 10000
The risksThe risks
Damaging equipment in case of uncontrolled release of energy stored in the magnets Dipole magnet replacement would take about 30 days
Damaging equipment in case of uncontrolled beam losses No realistic estimation of possible damage
Magnets could quench due to beam losses, or due to other failures Quench recovery at 7 TeV could take several hours
Beam losses due to a large variety of failures (sc magnets, resistive magnets, …) Recovery from 7 TeV could take hours
9
Failures of machine equipment must be Failures of machine equipment must be anticipatedanticipated
Risk comes from large stored energy plus possible failures
7000 magnets (most of them superconducting), powered in ~1700 electrical circuits …. ~1700 power converters
Superconducting magnets operate at 1.9 K with a small margin in temperature, at the edge of their performance
The protection of the sc elements (magnets, busbars and current leads) requires several 1000 detectors
The protection from beam losses includes more than 1000 channels (beam loss monitors and other equipment)
Realistic failure scenarios => Protection systems
A quench in a superconducting magnet could lead to beam losses A failure of a power converter could lead to beam losses Failures in many other systems could lead to beam losses
10
LHC Machine Protection is to…..LHC Machine Protection is to…..
No uncontrolled release of stored energy
Priority I: prevent damage of equipment
Priority II: prevent unnecessary down-time - for example: DUMP the beam in case of beam losses that could lead to a magnet quench
The Machine Protection Systems include
A) Systems to protect the LHC superconducting elements in case of a quench, or others failures in the powering system
B) Systems to protect the LHC equipment in case beam losses become unacceptable
…together with tools for consistent error and fault diagnostics ……. POST MORTEM
11
Beam InterlockSystem
Powering InterlockSystem
Beam lossMonitorSystem
Beam CleaningSystem
Beam Dump
SystemQuench
ProtectionSystem
Warm Magnet
Protection
LHC protection systems and main LHC protection systems and main interfacesinterfaces
Accessystem
CryogenicsSystem
Power converterSystem
Emergency Stop (AUG)
MagnetSystem
warm+coldVacuumSystem
InjectionSystem
Experiments
RFSystem
BIAll systems interface to All systems interface to control systemcontrol system
12
LHC Machine Protection = Integration of systemsLHC Machine Protection = Integration of systems
This presentation focuses with the integration of systems into the LHC MACHINE PROTECTION SYSTEM,… with the interlocks as glue linking systems
Input from
Superconducting Magnet tests, String 2 Accelerator Physics - Collimation - input for BEAM LOSS
SCENARIOS
And experience from other accelerators
SPS, LEP, HERA, RHIC and FERMILAB
13
Some Systems for Machine Protection were already in the baseline: Quench Protection (LHC-ICP), Beam Dump (SL-BT), Beam Losses (SL-BI), Beam Cleaning (J.B.Jeanneret, SL-BI) …
Machine Protection WG started in March 2001, R.Schmidt and J.Wenninger (chairman, scientific secretary) - reports to LCC
Interlock System: Architecture of Interlock Systems, LHC Project Report 521, (F.Bordry et al.), System done in SL-CO, B.Puccio
Autumn 2001 Beam Cleaning Study Group (BCSG, chairman R.Assmann): “Study beam dynamics and operational issues for the LHC collimation system. Identify open questions, assign priorities, and show the overall feasibility of the LHC cleaning system.“ Reports to LCC and works in close collaboration with MPWG
This presentation is on behalf of the MPWG - and many other colleagues that contributed to the work (in particular in the Beam Cleaning Study Group)
How did it start….How did it start….
14
…….. where should it go - .. where should it go - be ready in timebe ready in time
Fabrication of equipment
Installation of completed components
Very thorough commissioning of the hardware systems starting in 2005, sector by sector, as key for successful fast start up with beam, throughout 2005 and 2006
From
now
to
2006
In 2006 - one beam injected and transported across two sectors (hopefully - requires operation of SPS )
Start-up with two beams in spring 2007
15
Layout of the LHC ring: 8 arcs, and 8 long Layout of the LHC ring: 8 arcs, and 8 long straight sections straight sections
Betatron Cleaning
WARM
Momentum Cleaning
WARM
Beam dump system
RF + Beam instrumentation
One sector
= 1/8
LHC parameters and layout LHC stored energy and associated risks
Protection and interlocks for powering
Protection and interlocks for beam operation Beam Dump Beam Cleaning Beam Loss Monitors Beam Interlock System
Conclusions
17
Sector
Continuous Cryostat / Cryoline Superconducting bus-bars runthrough cryostat connecting magnets.
Current feeds at extreme ends.
Other central insertion elementseg. Low Betas, separator dipoles, matching
COLD (<2K) 2.9km
WARM500m
1
5
DC Power feed
3
Oct
ant
DC Power
Main Arc FODO cells
main dipoles, quadrupoles, chromaticity sextupoles, octupoles tuning and orbit correctors, skew quadrupoles, spool pieces
End of Continuous Cryostatdispersion suppressors,
Some of the matching section, and the electrical feedbox.
2
4 6
8
7LHC27 km Circumference
LHC Powering in 8 Sectors
Slide from P.Proudlock
Powering Sector
18
Separation of Protection systemsSeparation of Protection systems
With respect to operation with BEAM:
Energy stored in beams
Two systems - one BEAM DUMP SYSTEM for each beam
With respect to operation of the POWERING system:
Energy stored in magnets of one cryostat
Electrical circuits in one continuous cryostat independent from circuits in other cryostats
POWERING ABORT POWERING ABORT BEAM ABORT BEAM ABORT
Dump Trigger
Back to EDF
POWERING Detect quenches or other failures Energy stored in magnets to be
safely deposited with POWER DUMP SYSTEM (Energy extraction)
ExtractionResistors 2min
MagnetsCryogenics 500ms
MagnetEnergy
EDF
Beam Dump 89s
Collimation system 0.1-10h
Magnets / Cryogenics 10h
LHC Experiments 10hSPS + RF
BeamEnergy
BEAM OPERATION Detect dangerous failures or
beam losses Energy stored in beams to be
safely deposited with BEAM DUMP SYSTEM
20
Example: Protection main dipolesExample: Protection main dipoles
When conditions are OK - green light for powering
In case of a failure (quench), uncontrolled release of energy is prevented:
Fire quench heaters (quenched magnets)
Current by-passes magnet via power diode
Extract energy by switching a resistor into circuit - eight tons of steel heated to 300 °C
Switch off dipole power converter, and possibly others
Release helium by safety relief valve
13 kA switches from Protvino Russia
K.Dahlerup-Petersen (LHC-ICP)
21
Example for architecture in one LHC sector - Example for architecture in one LHC sector - powering subsectorspowering subsectors
Scheme of POWERING SUBSECTORSexample for sector between IP8 and IP1
arccontinuous cryostat 1L
continuous ARC cryostatInner Triplet
IP 1ATLAS
Matching sectionQ5+Q4D2
Inner Triplet
IP 8LHCb
arccontinuous cryostat 8R
Matchingsection cryostats 8R
Innertriplet cryostat
PIC
Matchingsection cryostat 1L
PC and QuenchProtection
Innertriplet cryostat
Matching sectionQ6Q5Q4D2
PC and QuenchProtection
PC and QuenchProtection
PC and QuenchProtection
PC and QuenchProtection
PC and QuenchProtection
PIC PIC PIC PIC PIC
22
Results from the StringResults from the String
String 2: commissioning of Powering, Magnet Protection and Powering Interlocks successfully in 2001 and 2002
String 2 gave us confidence as we observed a smooth commissioning of the powering protection systems
Complexity of powering systems for String 2 are similar to one of the LHC Powering Subsectors
=> scaling to the LHC is reasonable
R.Saban and the String TeamR.Saban and the String Team
LHC parameters and layout LHC stored energy and associated risks
Protection and interlocks for powering
Protection and interlocks for beam operation Beam Dump Beam Cleaning Beam Loss Monitors Beam Interlock System
Conclusions
Machine protection when operating with beamMachine protection when operating with beam
Early commissioning: First injection of beam into the LHC
Regular injection into the LHC
At 450 GeV During the energy ramp
At 7 TeV - before squeezing At 7 TeV - after squeezing
Operation with beam is discussed in the LHC Commissioning Committee (LCC) - chaired by S.Myers, scientific secretary O.Brüning
Beam intensitiesBeam intensities
Energy of LEP beam
Number of bunches
Bunch Intensity
Number of protons Comment
1 5.00E+09 5.00E+09 pilot bunch
1 1.10E+11 1.10E+11 nominal bunch
216 1.10E+11 2.38E+13nominal batch from
SPS
2808 1.10E+11 3.09E+14 nominal LHC beam
Intensity range~ 1:60000 !!
26
Machine protection: Machine protection: Beam energyBeam energy
For 7 TeV: fast beam losses between 106 and 107 protons could quench a
dipole magnet fast beam losses with less intensity than one “nominal bunch”
could already damage superconducting coils slow regular losses could quench the magnets
Quench limits: J.B.Jeanneret, D.Leroy, L.Oberli and T.Trenkler, LHC Project Quench limits: J.B.Jeanneret, D.Leroy, L.Oberli and T.Trenkler, LHC Project Report 44, 1996Report 44, 1996
Requirements and Design Criteria for the LHC Collimation System, Requirements and Design Criteria for the LHC Collimation System, R.W.Assmann et al., EPAC 2002 and Project Note 277R.W.Assmann et al., EPAC 2002 and Project Note 277
27
Machine Protection Systems must be operationalMachine Protection Systems must be operational
Beam Dump System The beam dump block is the only element that can stand the full 7 TeV beam without
damage
Beam cleaning system (collimators) Capture particles with collimators in the warm insertions, with an efficiency of > 99.9%, to minimise
losses in superconducting magnets For equipment failure, collimators are the first to capture beam losses Collimator position adjustment is critical
Beam Loss Monitor System Measures beam losses and, possibly triggers a beam dump
Beam Interlock System “Green Light” for beam operation, if changes to red => BEAM DUMP
Post Mortem recording must be operational Working Group on Post Mortem, chaired by J.Wenninger
Beam “lifetime” for optimum operationBeam “lifetime” for optimum operation
During “healthy” operation with nominal luminosity the lifetime is determined by the collision of two protons (beam lifetime in the order of 20 hours)
A large fraction of the protons is “lost” in the high luminosity collision points - and into ATLAS and CMS (corresponds to 10 kW per experiment)
At the end of the fill or in case of failure - the residual beam will be dumped, and its energy will end in the beam dump blocks
29
Lifetime of the beam with nominal Lifetime of the beam with nominal intensity at 7 TeVintensity at 7 TeV
Beam lifetime
Beam power into equipment (1 beam)
Comments
100 h 1 kW Healthy operation
10 h 10 kW Operation acceptable, collimation must absorb large fraction of beam energy
(approx. = cryogenic cooling power at
1.9 K)
1 h 100 kW Operation only possibly for short time, collimators must be very efficient
1 min 6 MW Equipment or operation failure - operation not possible - beam must be dumped
Acceptable lifetimes worked out by Beam Cleaning Study Group - see reports
30
Lifetime of the beam at 7 TeVLifetime of the beam at 7 TeV
Beam lifetime
Comments
1 s Failure of equipment - beam must be dumped fast
15 turns Failure of D1 normal conducting dipole magnet - monitor beam losses, beam to be dumped as fast as possible
1 turn Failure at injection, failure of beam dump kicker, or injection kicker misfiring with stored beam, potential damage of equipment, protection relies on collimators
Comments:The parameters at injection energy of 450 GeV are much more relaxed
Specification for the BLMs, J.B.Jeanneret+H.Burkhardt in the BI-Specification Committee
Very fast losses due to failures of the dump systems, LHC Project Note 293, R.Assmann, B.Goddard, E.Vossenberg, E.Weisse - not discussed here
31
Though the LHC cycle: Though the LHC cycle:
First injection into the LHCFirst injection into the LHC Early commissioning: first injection into the LHC with low intensity beam
would neither quench magnets nor damage equipment (pilot bunch with about 5 · 109 protons)
Establish circulating beam Commission beam monitoring and other systems Commissioning of beam dump system Possibly first energy ramp with pilot bunch
Protection against beam losses is not required
…but it needs to be certain that beam intensity is low, at top energy collimators should be in “coarse” position
32
Regular injection - consider the first turnRegular injection - consider the first turn
There are about 7000 magnets powered in ~1700 electrical circuits, >100 collimator jaws, more than 100 vacuum valves, roman pots….
Low beam intensity (pilot bunch, 109 - several 1010) - no problem Beam intensity is above about 1010 - quenches of sc magnets Beam intensity is much higher, up to 2·1013 - equipment could be damaged
see J.B.Jeanneret et al.
Experience from SPS - injected beam hits UA2, could happen for LHC (studies by W.Herr): NOT TOLERABLE FOR LHC
Example: magnet has wrong setting (Power Converter fault, or Power Converter has wrong input)
• The beam is deflected during the first turn • The beam touches / traverses the vacuum chamber • The beam hits equipment (magnet, collimator, experiment, ...)
33
If beam is already circulating, injected beam will survive
LHC ring with several 1000 objectsthat could prevent the beam from circulating (magnets, mechanical objects, …)
In principle, one proton for checking would be sufficient - in practice 1010 -
1011 are more practical
Any relevant failure would prevent the beam from circulating
34
How to avoid damage at injectionHow to avoid damage at injection
No beam is circulating In case of equipment failure condition - no injection Injection of intense beam NOT ALLOWED (interlock)
Step 1: Injection of weak beam <1011 protons - ALLOWED
Step 2A: If beam circulates - request injection of intense beam
Step 2B: JUST BEFORE INJECTION check if circulating beam is OK
Step 3: Injection of beam with higher intensity, ONLY, if beam is still present
If there is no circulating beam => no injection => go back to step 1
If there is circulating beam - inject beam => go to step 2
If there is a bunch present at the longitudinal position of the fresh beam to come
in, it will be deflected into the TDI - go to step 2
35
MKI - injection kicker
TDI - injection dump
Beam from SPS
Circulating beam
Pilot beamkicked out
Replacing pilot beam by batch from SPSReplacing pilot beam by batch from SPS
Injection failures have been worked out by the Injection WG and the BT-Group - led to proposal for TDI
36
Beam Dump SystemBeam Dump System
The beam dump system has many active components - kicker magnets, septum magnets, dilutor - all need to ramp with beam energy
The beam dump is an active system - it requires a trigger to dump the beam Quality and reliability of the beam dump system can not be better than the
quality and reliability of the trigger
The beam is dumped, either due to an operator request, or by the
beam interlock system after a failure has been detected
From SL-BT, E.Carlier
37
Beam dump must be synchronised with particle free gap
Strength of kicker and septum
magnets must match energy of the beam
« Particle free gap » must be free of
particles
Requirement for clean beam dumpRequirement for clean beam dump
particle free abort gapof 3 s
Kicker magnets constant angle
Beam dump block
Time
Kicker strength
Illustration of kicker risetime
38
Beam dump must be synchronised with particle free gap
Strength of kicker and septum
magnets must match energy of the beam
« Particle free gap » must be free of
particles
Requirement for clean beam dumpRequirement for clean beam dump
The entire beam would be deflected with an angle that does not correspond to the nominal angle
Beam Energy Tracking using special hardwareBEAM ENERGY METER
I) Cleaning of particle free gap (active and passive)II) Monitoring of beam intensity - if too large- dump beams
About 100 bunches would be deflected with an angle between 0 and the nominal kick
I) Rigorous synchronsationII) Additional collimators 1)
Depending on the beam intensity in the gap, particles would be sprayed
1) TCDQ - suggested by SL-BT, and LHC Project Note 297
39
Energy tracking required locally in insertion 6 for the beam dump system: Extraction kicker Septum magnets Dilution kickers
The field of the septa magnets needs to track the beam energy within about +-0.5 %
The dump kickers need to track the beam energy It is required to apply trims to the extraction trajectory
M.Gyr, J.B.Jeanneret
Distribution of energy information to Beam Loss Monitors around the ring (how…?)
Beam Energy MeterBeam Energy Meter and beam dump system and beam dump system
40
Current for the magnet with standard power converter / standard control electronics with a current versus time function loaded into the controller
During the energy ramp the deflection angle is constant. The non-linearity between current of the power converter and magnetic field is taken into account in the definition of the ramp function (as for all other magnets)
This is not sufficient for such critical system, therefore… Reliable monitoring for safe operation is required
Safe tracking that allows trimming of the Safe tracking that allows trimming of the functions in the beam dump system in a functions in the beam dump system in a limited rangelimited range
41
Beam Energy Meter
DCCT
Beam Energy Meter
DCCT
DCCT DCCT
Dump beam
Other
users
Make energy
Beam Energy Meter
Beam Energy Meter
Septum magnet
beam 1
Septum magnet
beam 2
Dipole magnets
Sector 5-6
Energy not consistent
Energy consistent
Prototyping components for Energy Meter has been made by J.Pett et al.
Dipole magnets
Sector 6-7
42
Beam Cleaning SystemBeam Cleaning System
Collimators close to the beam are required during all phases of operation
• Sophisticated beam cleaning system with many collimators has been designed (J.B.Jeanneret, and EPAC 2002 presentation by BCSG - R.Assmann) - limit aperture to about 6-10
• Together with the Beam Loss Monitors produce a fast and reliable signal to dump the beam if beam losses become unacceptable
43
+- 3 1.3 mm
Beam +/- 3 sigma
56.0 mm
Beam in vacuum chamber at 7 TeVBeam in vacuum chamber at 7 TeV
Example for failure Example for failure
at 450 GeVat 450 GeV
Assume that the current inone orbit correctormagnet is off by 10% of maximum current (Imax = 60 A)
12.0 mm
16.0 mm
Beam +/- 3 sigma
Beam +/- 3 sigmaand orbit corrector10 % / 100 % of Imax
56.0 mm
Ralphs EURO
Beam +/- 3 sigma
56.0 mm
1 mm
+/- 8 sigma = 4.0 mm
Example: Setting of collimators at 7 TeV - with luminosity opticsExample: Setting of collimators at 7 TeV - with luminosity optics Beam must always touch collimators first !Beam must always touch collimators first !Collimators might remain at injection position during the energy rampCollimators might remain at injection position during the energy ramp
Ralphs EURO
Collimators at Collimators at 7 TeV, squeezed7 TeV, squeezed
46
Particles that touch collimator after failure of normal conducting D1 magnets
After about 13 turns 3·109 protons touch collimator, about 6 turns later 1011 protons touch collimator
V.Kain
“Dump beam” level
1011 protons at collimator
47
Beam Loss MonitorsBeam Loss Monitors
Primary strategy for protection: Beam loss monitors at collimators continuously measure beam losses
Beam loss monitors indicate increased losses => MUST BE FAST
After a failure: Beam loss monitors break Beam Permit Loop Beam dump sees “No Beam Permit” => dump beams
In case of equipment failure, enough time is available to dump the beam before damage of equipment - including all magnets and power converters - but issues such a General Power Cut etc. are still being addressed
Failure scenarios with circulating beam studied by O.Brüning, and V.Kain
Beam Loss Monitor System: Specifications by BI-Spec-Committee (JBJ+HB), and realisation of the system by B.Dehning et al. in SL-BI
48
Redundant strategy for protection in case of Redundant strategy for protection in case of equipment failure equipment failure
Beam loss monitors around the LHC machine (a subset of all BLMs is critical for protection - to be defined)
Detection of fault states from equipment (e.g. power converter)
Example: Power converter failure of D1 separation dipole induces orbit distortion
Signal from Powering Interlock System to Beam Interlock System to DUMP BEAM
OR
Signal from Beam Loss Monitors to Beam Interlock System to DUMP BEAM
What to include to generate Beam Abort - to be worked out later (some flexibility required, the system must be tuned to optimise operational efficiency)
Architecture of the BEAM INTERLOCK SYSTEM Architecture of the BEAM INTERLOCK SYSTEM
Pt.1
Pt.2
Pt.3
Pt.4
Pt.5
Pt.6
Pt.7
Pt.8ATLAS
CMS
LHC-BALICE
Momentumcleaning
RF Beam Dump
Betatroncleaning
BEAM 1clockwise
BEAM 2counter-clockwise
InjectionBEAM II from SPS
InjectionBEAM I from SPS
BEAM DUMPCONTROLLERS
BPC
BIC
BPCBPC
BPCBPCBPC
BIC
BIC
BIC
BIC BIC
BIC
BIC
BIC
BIC
BIC
BIC
BICBIC
BIC
BIC
Beam Interlock Loopssignal transmitted viaoptical fibre at 10 MHz
p. 50
Time Stamping
power in from UPS
BEAM INTERLOCKCONTROLLER
BEAM PERMIT from PICESSENTIAL CIRCUITS OK
Link to Control system
BEAM PERMIT LOOPS
Signals fromPOWERING INTERLOCK CONTROLLERS
Signals fromsubsystems to give BEAM PERMIT,and ABORT ifPERMIT is absent
Machine / Beam Status
Other systemsBeam LossAccessExperimentsVacuumRFBEAM DUMPInjectionWarm magnetsCollimators
BEAM PERMITfrom equipment
BEAM PERMITto equipment
BEAM PERMIT from PICAUXILIARY CIRCUITS OK
POWERING INTERLOCKSYSTEM (several PICs)
BEAM INTERLOCK BEAM INTERLOCK CONTROLLERCONTROLLER
51
General Layout of the 2 Machine General Layout of the 2 Machine Interlock SystemsInterlock Systems
Control Room
B.Puccio
52
Quantifying reliability for the LHCQuantifying reliability for the LHC
Reliability can be quantified - with accepted mathematical tools. Such tools are challenging since mathematics involved can be rather advanced
Reliability of different systems can be compared To estimate the reliability of the entire accelerator, the reliability of all
subsystems need to be estimated Strictly required for systems related to safety of personnel (INB, legal
obligation)
Should be extended to equipment protection systems
… and for other systems in order to optimise the efficiency of LHC operation
Examples of past studies: quench protection system, interconnects between magnets, SPS access system, …
LHC parameters and layout LHC stored energy and associated risks
Protection and interlocks for powering
Protection and interlocks for beam operation Beam Dump Beam Cleaning Beam Loss Monitors Beam Interlock System
Conclusions
ConclusionsConclusions
The LHC is a global project with the world-wide high-energy physics community devoted to its progress and results
As a project, it is much more complex and diversified than the SPS or LEP or any other large accelerator project constructed to date
I consider the complexity of the LHC with its magnets systems at 1.9 K and the machine protection issues to be the main challenges for the LHC
From the summary of the LHC Machine Advisory Committee in March 2002, chaired by Prof. M. Tigner
55
ConclusionsConclusions If the protection systems will not be fully operational for Hardware
commissioning in 2005 and Beam commissioning in 2007 - there is no way to startup the machine
Very good progress for the protection against uncontrolled release of magnet energy, due to the excellent collaboration of people and the experiments at the String - a sound baseline has been established
For the protection against beam losses still substantial work ahead of us - in particular for fast losses - to avoid any damage of collimators or other machine equipment (work ongoing in BCSG and MPWG, LCC is the coordinating body)
For several important sub-systems principles and the architecture has been established - but the technical work is hampered by lack of personal and responsibilities need to be defined
Renovation of SPS interlocks - possibly with the same brainware and hardware (J.Wenninger & R.Giachino + B.Puccio & myself)
56
AcknowledgementAcknowledgement
This presentation is based of the work of many people
Particular thanks to my colleagues in the MPWG, and its scientific secretary J.Wenninger
Particular thanks also to my colleagues in the Beam Cleaning Studies team, to its chairman R.Assmann, and to the “father of LHC collimation” J.B.Jeanneret
References under:
http://www.cern.ch/lhc-collimation/
http://www.cern.ch/lhc-mpwg/
Future related presentation could be on Beam Cleaning, Beam Loss Monitoring, Beam Dump System, Quench Protection System and Post Mortem System