slc.gov - 1700 south reconstruction...upon completion of this task, they’ll repave the street with...

1
PROJECT UPDATE | JANUARY 2019 Due to inclement weather, crews are now expected to finish upgrading the storm drain system by the end of the month. Upon compleon of this task, theyll repave the street with temporary asphalt to resume travel on 1700 South. In order for this repaving acvity to not be delayed, and to avoid damage to vehicles, on-street parking well be prohibited from 1700 East to 1900 East. Crews are expected to work Monday through Friday, and possibly Saturdays from 7 a.m. to 5 p.m. More updates will be provided as crews move to different areas and achieve project milestones. WHAT TO EXPECT Residents should expect heavy construcon equipment, noise, vibraons, dust, and temporary modified access to residences with brief ulity interrupons during the work day. Due to the narrow street width, only eastbound travel will be allowed along 1700 South while we complete these tasks, however temporary road closures should be ancipated as well. Both travel direcons will open during the first week in February. SAFETY Safety is our highest priority. Please be cauous of trucks and equipment around the construcon site. Work zone will be barricaded to protect the public, while acvies arent in progress. Please keep children from playing on or around parked equipment and materials stored on-site. If anyone in your household has a disability and needs special accommodaons while our crews are present, ask them for help and theyll be happy to assist. For any emergencies please call 911. PROJECT CONTACT INFORMATION Email: [email protected] | Website: www.slcgov.com/mystreet Social Media: @SLCgov | Hashtag: #1700SouthSLC PROJECT TEAM MEMBERS Jordan Valley Superintendent: Kelly Smith, 801-842-7190 Email: [email protected] Project Manager: Josh Thompson, 801-535-6177 Civic Engagement Specialist: Adan Carrillo, 801-535-6251 1700 SOUTH RECONSTRUCTION From 1700 East to 1900 East

Upload: others

Post on 04-Oct-2020

0 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: SLC.gov - 1700 SOUTH RECONSTRUCTION...Upon completion of this task, they’ll repave the street with temporary asphalt to resume travel on 1700 South. In order for this repaving activity

PROJECT UPDATE | JANUARY 2019

Due to inclement weather, crews are now expected to finish upgrading the storm drain system by the end of the

month. Upon completion of this task, they’ll repave the street with temporary asphalt to resume travel on 1700 South.

In order for this repaving activity to not be delayed, and to avoid damage to vehicles, on-street parking we’ll be

prohibited from 1700 East to 1900 East.

Crews are expected to work Monday through Friday, and possibly Saturdays from 7 a.m. to 5 p.m. More updates will

be provided as crews move to different areas and achieve project milestones.

WHAT TO EXPECT

Residents should expect heavy construction equipment, noise, vibrations, dust, and temporary modified access to

residences with brief utility interruptions during the work day. Due to the narrow street width, only eastbound travel

will be allowed along 1700 South while we complete these tasks, however temporary road closures should be

anticipated as well. Both travel directions will open during the first week in February.

SAFETY

Safety is our highest priority. Please be cautious of trucks and equipment around the construction site. Work zone will

be barricaded to protect the public, while activities aren’t in progress. Please keep children from playing on or around

parked equipment and materials stored on-site.

If anyone in your household has a disability and needs special accommodations while our crews are present, ask them

for help and they’ll be happy to assist. For any emergencies please call 911.

PROJECT CONTACT INFORMATION

Email: [email protected] | Website: www.slcgov.com/mystreet

Social Media: @SLCgov | Hashtag: #1700SouthSLC

PROJECT TEAM MEMBERS

• Jordan Valley Superintendent: Kelly Smith, 801-842-7190

Email: [email protected]

• Project Manager: Josh Thompson, 801-535-6177

• Civic Engagement Specialist: Adan Carrillo, 801-535-6251

1700 SOUTH RECONSTRUCTION From 1700 East to 1900 East