sLHC Engineering Upgrade
FCAL Remove-Install step by step procedure.
Mircea Cadabeschi-University of Toronto March 01, 2010
1
Step by step procedure
2
Step by step procedure
3
Step by step procedure
4
Estimate tooling cost
5
Install the first minivan to the front of the EC
- Lower the minivan on the rails by crane. - Time for installing 4 hours by 2 people..- No shield necessary.
6
The extension tube is attached to the extension support, rotated 90 degree
Rotary table
Move back the first minivan
- Two people move back the minivan 3m.- Time of moving 4 hours by 2 people.- No shield necessary. 7
Insert the second minivan
- Install the minivan by crane.- The minivan has a shield attached. - Time for insertion 4 hours by 2 people. - No shield necessary. 8
Two THK rails are attached to the second minivan.
Set up the extension tube on minivans.
- Move the second minivan close to the first.- Rotate the extension tube and install it in the right position.- Connect the second minivan with the first.- Time to set up, 16 hours.- No shield necessary.
9
Shield attached to the minivan
Attach the extension tube to the con forward
- Move the EC close to the assembly and set the position.- Adjust the height of the extension tube to match the FCAL.- Insert the extension tube inside the con forward.- Time: 16 hours, by 4 people. 10
Install the structure to the back of the EC
- Lower the structure (already assembled outside of the cavern) on the rails, by crane. - Time for installing 4 hours by 2 people.- No shield necessary.
11
Set-up the structure- Move the structure and set
it up in position. Set-up the position of the mandrel.
- Attached the mandrel flange to the bulkhead. Connect the mandrel with the extension tube.
- Remove the 48 bulkhead bolts.
- Lift the FCAL (by turnbuckles) to clear the EC.
- Time for installing 24 hours by 4 people.
- No shield necessary. The mandrel square flange work as a shield.
12
Remove the FCAL- Move the FCAL on THK rails
500mm.- Time: 8 hours by 4 people.- Cut the 112 connectors wires. - Special tool is necessary to cut
the wires. - Protective gear are necessary
for the people who cut the wires.
- Time: 4 hour by 2 people.
13
Wires to be cut
14
To remove the old FCAL will use a new cradle made from two halves, which will have a double purpose, as a cradle and a shield.
I called it sarcophagus, because the FCAL will stay inside the cradle all the time.
15
Remove the FCAL
16
- Move the FCAL 1500mm to clear the scissor table.- Time: 4 hours by 4 people. - No shielding is necessary.
Remove the FCAL
- Lift the sarcophagus to touch the FCAL.- Release the turnbuckles to change the FCAL load on sarcophagus.- Time: 8 hours by 2 people.- No shielding is necessary. 17
Remove the FCAL
- By crane, lower the top half of sarcophagus which will engage the bottom half.- Time 4 hours by 2 people.- No shielding is necessary.
18
Remove the FCAL
- Move the extension tube, to clear the con forward.
- By crane, lift the FCAL just to clear the table and move it backward for the con forward to clear the EC.
- Time: 4 hours by 2 people.
- No shielding necessary.
19
Remove the FCAL
- Lift slowly the FCAL and clear the area.- Time: 4 hours by 2 people.- No shielding necessary. 20
The summing boards
- 112 connectors for the FCAL to be disconnect.
28 boards, 4 connectors per
board
21
The summing boards connectors.
The diameter for the bulkhead.
22
Removing the old connectors
- The shield lowered by crane.- Rotating the flange, position the window in front of each summing board, allowing to
disconnect the old connectors.- Time 24 hours by 1 person.
shield
Rotating flange
window
23
FCAL on Cradle
- The existing cradle can be used with the crane to insert the new FCAL.
FCAL Cradle
24
- The Installation of the new FCAL will be made in reverse order.
- The new FCAL will install with the existing cradle.
- To connect the new connectors some tooling is necessary!!!???
- A lifting table possible to be design (using mechanical jacking screws), in stead of buying a scissor table.
- The time to remove the old FCAL and install the new one, about 6 weeks on each side.
25