slide set 4 kostt
DESCRIPTION
Kosovo- International investors’ conference New Kosovo Power Plant Fadil Ismajli Prishtina 20 January 2010 Chief Executive Officer - K O S O V A N T R A N S M I S S I O N S Y S T E M & M A R K E T O P E R A T O R - O P E R A T O R I I S I S T E M I T, T R A N S M I S I O N I T & T R E G U T T Ë K O S O V Ë S - developments strategies and Nomination Economic regulation of the market energy sector system and electricity Licensing Operation of the electricity Designing sectors’ policies 2 2TRANSCRIPT
- K O S O V A N T R A N S M I S S I O N S Y S T E M & M A R K E T O P E R A T O R - O P E R A T O R I I S I S T E M I T, T R A N S M I S I O N I T & T R E G U T T Ë K O S O V Ë S -
KOSTT JSCFunctioning
Developments Perspective
Prishtina20 January 2010
Fadil IsmajliChief Executive Officer
Kosovo- International investors’ conference New Kosovo Power Plant
2
Legal & Regulatory Framework in Kosova
2
July 06Establishment ofITSMO
July 04Establishment ofEnergy Regulatory Office
Dec 04Establishment ofMinistry of Energy & Mining
Primary Legislation in Energy Sector in Kosovo (June 04)- Law on Energy -- Law on Electricity -- Law on Energy Regulator -
Nomination
Licensing
Economic regulation of the
energy sector
Designing sectors’
developments strategies and
policies
Operation of the electricity
system and electricity
market
3
KOSTT and its functions
3
• KOSTT JSC is responsible for:
– Bulk transmission of electricity on HV network and other ancillary services (…secondary regulation, etc.)
– Maintenance & development of TS
– Operation of Kosovo electricity system
– Balancing (demand = supply)
– Operation of electricity market
– Congestion management (allocation of interconnections)
4
License obligation-development of rules, codes, etc.-
• Market Rules – OP for implementation of rules
• Grid Code & Metering Code
• Electrical Standards Code & Technical Equipment Code
• Distribution Code (in cooperation with DSO)
• Technical performance indicators
• Commercial Agreements
• Long-term Power Balance (& PB on annual basis)
• Business Plan of KOSTT (2007-2012)
• Connection Charging Methodology • Transmission Network Development Plan• Other documents under preparation/under approval
4
5
Access to the Transmission Network
• KOSTT will offer its transmission capacities for all usersEC Directive → Law on Electricity → TSO License– Cost reflective and regulated tariffs & charges
• Transmission Use of System Charges (EROs Tariff Methodology)Generation component in the Tariff methodology for Transmission Use of Charge
(ToUS) equal to zero (G=0)• Physical connection to the transmission network (KOSTTs Charging
Methodology): Deep connection approach• Cross border related mechanisms (CB principles & rules)
– Parties’ access is granted following the fulfillment of technical & financial criteria
– Transparency in Third Party Access (TPA) ensured by the Grid Code and other technical codes
5
6
Transmission network development
6
• Investment plan – approved by ERO (regulator)• Significant projects, which will accommodate system users’ needs
Results
→ Increase of transmission capacity (53%)
→ Improve the security of the network
→ Increase interconnection capacities for regional market
→ Enabling higher level of cross-border flows over KOSTT’s system
→ To meet future generation capacities and supply in Kosovo
→ Improve the quality of supply & system operations capabilities
7
Perspective for investments
• Well developed legal framework (all in compliance with EU legal framework)
• Strong and autonomous agencies (Regulators, Antitrust, etc.)
• Very well developed electricity transmission infrastructure - regulated and easy access to the network
No requirements for generation developer to invest in interconnections
Establishment of the appropriate SCADA system
Establishment of the tools for monitoring and settling all power transactions in the market (software platform reflecting the market)
• Well operational Transmission, System and Market obligations with motivated and skilled staff
7
8
Historic Electricity Consumption & Peak Load
8
0
500
1000
1500
2000
2500
3000
3500
4000
4500
5000
1980 1981 1982 1983 1984 1985 1986 1987 1988 1989 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
504
537 621
693690
624 603
500
525
550
604
692733
656617
653
755780
808
892 914970
0
100
200
300
400
500
600
700
800
900
1000
GWh
MW
Year
Year
Constantl
y
IndustryHousehold War
High Increase
(7% average)
Similar reflections on the peak load (MW)
In 10 years
=double
9
Energy sector developments
• Continuous need for power import of neighboring countries like Macedonia, Albania, Montenegro, etc.
• Privatization of distribution and supply of electricity
• Emerging regional market – wider market, more possibilities
– Development of regional bodies for facilitation of electricity market and trades
– Development of electricity trading mechanism
Regional and European integration
9
10
www.kostt.com
Thank You
Kosovo- International investors’ conference Kosova e Re Power Plant
20 - 21 January 2010
KOSTT - Transmission, System and Market Operator j.s.c.Iljaz Kodra nn
10000 Prishtina, Kosova