slipstream pilot plant demonstration of an amine- based ... library/events/2012/co2 capture... · 2...

27
1 Slipstream pilot plant demonstration of an amine- based post-combustion capture technology for CO 2 capture from coal-fired power plant flue gas DOE funding award DE-FE0007453 2012 NETL CO 2 Capture Technology Meeting Krish R. Krishnamurthy, Linde LLC July 9-12, 2012 Pittsburgh, PA

Upload: ngonguyet

Post on 05-Feb-2018

215 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

1

Slipstream pilot plant demonstration of an amine-based post-combustion capture technology for CO2capture from coal-fired power plant flue gas

DOE funding award DE-FE0007453

2012 NETL CO2 Capture Technology MeetingKrish R. Krishnamurthy, Linde LLCJuly 9-12, 2012Pittsburgh, PA

Page 2: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

2

The Linde Group Overview and Carbon Capture Expertise

1

Linde Engineering

Technology-focused Air Separation

Global #1

Air Separation

Global #1

Hydrogen/Syn Gas

Global #2

Hydrogen/Syn Gas

Global #2

Olefins

Global #2

Olefins

Global #2

Natural Gas

Global #3

Natural Gas

Global #3

HyCO Tonnage Plants

>70 plants

HyCO Tonnage Plants

>70 plants

HyCO Tonnage Plants

>70 plants

ASU Tonnage Plants

>300 plants

ASU Tonnage Plants

>300 plants

ECOVAR Std Plants

>1,000 plants

ECOVAR Std Plants

>1,000 plants

Linde Gas - Tonnage

World-class operations

CO2 Plants

>100 plants

Leveraging Synergies

1879

$18 billion

50,000

>100

Founded

Sales (2011)

Employees

Countries

US Linde Gas HQ Murray Hill, NJ

Linde pursues technology development

and solution offer in all three CC pathways

US Linde EngineeringFacilities

Blue Bell, PA; Tulsa, OK & Holly Springs, GA

Page 3: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

3

Project Participants

-NCCC Host site (Wilsonville, AL)-Infrastructure and utilities for pilot plant build and operations

Frank MortonMichael England

Southern Co./NCCC

-Basic engineering-Support for commissioning-Operations and testing

Torsten StoffregenHarald Kober

Linde Engineering, Dresden

-Detailed engineering-Procurement and installation

Lazar KoganSFPC(Linde Eng)

-Techno-economics review-Independent validation of test analysis and results

Richard RhudyEPRI

-OASE® blue technology owner -Basic design-Solvent supply and analysis

Iven Clausen (BASF SE)Sean Rigby (BASF Corp)

BASF

-Prime contract-Overall program management-Operations and testing

Krish Krishnamurthy, PIStevan Jovanovic, Technical Lead

Linde LLC

-Funding & SponsorshipAndrew P. Jones, Project Manager

DOE-NETL

Key Role(s)Lead contact(s)Partner/

Organization

Page 4: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

4

Overall Objective

— Demonstrate Linde-BASF post combustion capture technology by incorporating BASF’s amine-based solvent process in a 1 MWel slipstream pilot plant and achieving at least 90% capture from a coal-derived flue gas while demonstrating significant progress toward achievement of DOE target of less than 35% increase in levelized cost of electricity (LCOE)

Specific Objectives

— Complete a techno-economic assessment of a 550 MWel power plant incorporating the Linde-BASF post-combustion CO2 capture technology to illustrate the benefits

— Design, build and operate the 1MWel pilot plant at a coal-fired power plant host site providing the flue gas as a slipstream

— Implement parametric tests to demonstrate the achievement of target performance using data analysis

— Implement long duration tests to demonstrate solvent stability and obtain critical data for scale-up and commercial application

Project Objectives

Page 5: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

5

Project schedule and milestones: Budget Period 1

Budget Period 2: March 2013 to February 2014 (Pilot plant procurement, fabrication and installation)

Budget Period 3: March 2014 to November 2015 (Pilot plant operations, parametric and long-duration testing)

Page 6: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

6

Project Budget: DOE funding and cost share

$3,698,091$688,641$2,455,612$553,838Cost Share

$18,490,456$3,443,205$12,278,061$2,769,190Total Project

$14,792,365$2,754,564$9,822,449$2,215,352DOE Funding

TotalBudget Period 3

Mar 2014 – Nov 2015

Budget Period 2

Mar 2013 – Feb 2014

Budget Period 1

Dec 2011 – Feb 2013Source

Cost share commitments:

Linde: $3,107,352

BASF: $ 493,360

EPRI: $ 97,379

Page 7: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

7

Key Project Milestones (Budget Period 1)

Budget Period 1 (Dec. 1, 2011 – Feb. 28, 2013)

— Submit project management plan (03/09/2012) √— Conduct kick-off meeting with DOE-NETL (11/15/2011) √— Complete initial techno-economic analysis on a 550 MWel power plant (05/04/2012) √— Complete basic design and engineering of a 1 MWe pilot plant to be tested at NCCC

(06/20/2012) √— Execute host site agreement (10/31/2012)

— Complete initial EH&S assessment (10/31/2012)

— Complete detailed pilot plant engineering and cost analyis for the 1 MWe pilot plant to be tested at NCCC (01/31/2013)

Page 8: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

8

Key Project Milestones (Budget Periods 2 and 3)

Budget Period 2 (Mar. 1, 2013 – Feb. 28, 2014)

— Complete purchase orders and fabrication contracts for the 1 MWe pilot plant (03/29/2013)

— Complete shop fabrication of equipment and modules and associated engineering checks (07/31/2013)

— Complete site preparation and foundation installations at NCCC to receive pilot plant (08/15/2013)

— Complete installation of the 1 MWe pilot plant at NCCC (11/30/2013)

— Mechanical completion of 1 MWe pilot plant at NCCC (02/28/2014)

Budget Period 3 (Mar. 1, 2014 – Nov. 30, 2015)

— Complete pilot plant start up and demonstrate plant operation at steady state (05/31/2014)

— Develop pilot-scale parametric test plan (06/30/2014)

— Complete 1 MWe pilot-scale parametric tests (11/30/2014)

— Develop pilot-scale long duration test plan (12/31/2014)

— Complete 1 MWe pilot-scale long duration tests (08/31/2015)

— Complete updated techno-economic analysis (10/31/2015)

— Complete updated EH&S assessment (11/30/2015)

Page 9: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

99

Linde-BASF experience in large scale carbon captureCO2 capture in natural gas processing: Re-injection Project - Hammerfest

700,000 tpa CO2 capture and re-injection (part of world scale LNG project, Snøhvit, Norway)

World’s first industrial project to deliver CO2 separated onshore from the well-stream back offshore for re-injection into a reservoir

— Partnership with StatoilHydro Petroleum

— Melkoya island near the town of Hammerfest, Norway

—CO2 sequestration and re-injection integral part of the Hammerfest LNG project. Linde performed design, EPC and commissioning

—One dedicated well for CO2 storage in a sandstone formation sealed by shale cap.

— Re-injection started in April 2008

— BASF’s OASE® purple process used in CO2capture

Page 10: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

10

CO2 removal rate (90 %)low amine emissions

50 ppm – 2 % CO2

S < 4 – 10 ppm

Treated gas specification

of highest priorityη 7-10% points

not a key issueEnergy efficiency

N2, O2, H2O, CO2, (SOx) NOxCH4, C2H6, …, CO2, H2S, COS, CxHy,S, H2OGas composition

up to 120 mio scf/hrup to 60 mio scf/hrFlowrate

30 – 150 mbars1 – 40 barsCO2 partial pressure

1 bara50 – 100 barsPressure

Flue gasNG/LNG

large volume flows @ low pressuresolvent stability

overall power plant efficiency lossesemissions of solvent

BASF Gas Treatment GroupPost combustion CO2 capture: Challengescompared to CO2 removal in NG/LNG plants

Page 11: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

11

BASF OASE® blue Technology DevelopmentDesigned for PCC Applications

0102030405060708090

1 2 3 4 5 6 7 8 9 10 11 1 2 1 3 14 15 1 6 1 7 1 8 1 9 20 2 1 2 2 2 3 24 25 2 6 2 7 2 8 2 9 30 3 1 3 2 3 3 34 35 3 6 3 7 3 8 3 9 40 4 1 4 2 4 3 44 45 4 6 4 7 4 8 4 9 50 5 1 5 2 5 3 54 55 5 6 5 7 5 8 59 60 6 1 6 2 6 3 6 4 65 6 6 6 7 6 8 69 70 7 1 7 2 7 3 7 4 75 7 6 7 7 7 8 79 80 8 1 8 2 8 3 8 4 85 8 6 8 7 8 8 89 90 9 1 9 2 9 3 9 4 95 9 6 9 7 9 8 99 1 0 0 10 1 10 2 1 03 1 0 4 1 0 5 10 6 1 07 1 08 1 0 9 1 1 0 11 1 11 2 1 13 1 1 4 1 1 5 11 6 11 7 1 18 1 19 1 2 0 12 1 12 2 1 23 1 2 4 1 2 5 12 6 12 7 1 28 1 29 1 3 0 13 1 13 2 1 33 1 3 4 1 3 5 13 6 13 7 1 38 1 39 1 4 0 14 1 1 42 1 43 1 4 4 1 4 5 14 6 14 7 1 48 1 4 9 1 5 0 15 1 1 52 1 53 1 5 4 1 5 5 15 6 15 7 1 58 1 5 9 1 6 0 16 1 1 62 1 63 1 6 4 1 6 5 16 6

screened solvents

cycl

ic c

apac

ity /

Nm

3 /t

MEA

EquilibriaEquilibriaKineticsKinetics

0

2

4

6

8

10

12

14

16

18

20

0 10 20 30 40 50 60

Loading

Abs

orpt

ion

rate

MEAtested solvent

StabilityStability

60

70

80

90

100

0 100 200 300 400 500 600time [h]

cont

ent o

f am

ine

tested solvents

MEA

Fundamental Lab Scale R&D: Advanced Solvents Screening, Development, Optimization

0.45 MWe PCC Pilot, Niederaussem, Germany:

Preliminary ProcessOptimization

BASF Miniplant, Ludwigshafen, Germany:

Solvent Performance Verification

Page 12: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

12

Niederaussem* pilot plant key results

>90% carbon capture rate achieved

>20% improvement in specific energy compared to MEA

New BASF solvent is very stable compared to MEAAcknowledgement: * Pilot project partner RWE

duration of operation

tota

l con

tent

of c

arbo

nic

acid

sMEA

New BASF Development

duration of operation

tota

l con

tent

of c

arbo

xilic

acid

s

~ 5,000 hrs

MEAOASE® blue

OASE® blue

Page 13: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

13

Solutions for Large Scale PCC Plant (1100 Mwel Power)Design challenges

Lower number of trains results in bigger size of components, e.g.

– Absorption column: diameter ca.18 m, height ca. 75 m on site fabrication required

– Pipes ducts and valves: diameters up to 7 meters

– Plot : ca. 100 m x 260 m

Compressor sectiontwo lines per train

flexible turn down operation

Optimizing CAPEX by reduced number of trains to handle 18,000 tpd CO2

- 2 process trains selected

- reduced plot space

Page 14: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

14Fußzeile 14

Concepts for a Large Scale PCC Plant Key elements of plant costs

Main challenges

— Large equipment size requires new concepts

— Required plot area is very significant

— Alternative materials need to be assessed

— New equipment arrangements needed

— FIeld fabrication

— Large pipe and duct

Linde studies to address challenges

— Scaling to a very large single train

— Optimize equipment arrangement (flue gas blower, pre-cooler, absorption columns sump etc)

— Develop new column construction materials

— Optimize machinery options

Total plant cost distribution

Engineering and supervision

Equipment incl. columns(w/o blowers & compressors)

Blowers & compressors

Bulk Material

Civil

Construction

Page 15: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

15

Linde-BASF advanced PCC plant design*

Advanced emission

control system

Gravity Flow

Interstage Cooler

Advanced Column

Material & Design

Optimized Blower

Concept

Optimized Energy

Consumption

High capacity

structured packing Higher

Desorption Pressure

Optional

Interstage Heater

Condensate

LP_Steam

•Patent Applications 2010-2012

Source: Project DE-FE0007453 Techno-economic analysis of 550 MWe PC power plant with CO2 capture, May 2012.

Page 16: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

16

Project progress and accomplishments

- Preliminary NEPA document completed.

- Hazop review completed and design updates incorporated.

Complete preliminary environment, health and safety assessment for the pilot plant

Pilot plant cost and safety analysis

5

-Preliminary 3-D model developed

- Detailed engineering in progress (30% model)

Complete detailed design and engineering of the pilot plant (ready to build).

Pilot plant system design and engineering

4

-Design basis document completed and pilot plant features selected.

- Basic design and engineering completed.

Define pilot plant design basis and the key features incorporated. Complete basic design and engineering.

Pilot plant optimization and basic design

3

- Techno-economic assessment completed and presented to DOE-NETL

Complete techno-economic analysis on a 550 MWe coal-fired power plant incorporating Linde-BASF PCC technology.

Techno-economic evaluation

2

- Project kick-off meeting held

- Updated project management plan completed

Complete project management plan and implement to agreed cost and schedule.

Program Management

1

AccomplishmentsKey ObjectivesTask DescriptionTask#

Page 17: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

17

Basis for techno-economic assessment for 550 MWe power plant with 90% CO2 capture

Computational Platform

UniSim Design Suite R390, integrated with

— Brian Research & Engineering ProMax®

software for PCC parametric optimization

— BASF’s proprietary package for rigorous solvent performance predictions

Specifications and Design Basis

identical to DOE/NETL Report 2007/1281

as per DE-FOA-0000403 requirements

— Bituminous Illinois #6 Coal Characteristics

— Site Characteristics and Ambient Conditions

— Pulverized Coal Boiler Design

— Subcritical Steam Turbine Design

— Steam Cycle Conditions

— Environmental Controls and Performance

— Balance of Plant

— Economic Assumptions and Methodology

Absorber

Treated flue gas

CO2

Reboiler

Desorber

Condenser

Make-up water

Solvent Tank

InterstageCooler

Steam

Page 18: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

18

PCC – Power Plant Typical Process Integration Option (LB-1)

SECONDARY AIR FANS

COAL FEED

PULV

ERIZ

ED C

OAL

BOIL

ER

PRIMARY AIR FANS

INFILTRATION AIR

SCR

BOILER

FEEDWATER

HP ST

FEEDWATER HEATER SYSTEM

MAIN STEAM

COLD REHEAT

HOT REHEAT

IP ST LP ST

CONDENSER

CO2 CAPTURE & COMPRESSION PLANT

BAGHOUSE FGD

ID FANS

LIMESTONE SLURRY

CO2 COMPR.

TO STACK

MAKEUP WATER

OXIDATION AIR

GYPSUM

BOTTOM ASH

FLY ASH

CO2 PRODUCT

EL. POWER GENERATOR

10

8

7

5

21

43

6

9

1413

1512

1611

23

25

24

26

19

1817

21

20

22

Absorber

Treated flue gasto stack

CO2to Compression

Reboiler

Desorber

Condenser

Make-up water

SolventStorage

Tank

Interstage Cooler

Flue gas

DCC

NaOH Tank

Rich/LeanSolvent

Hex

Flue gas blower

Solvent Cooler

Interstage Heater

LP_Steam

Condensatereturn

LP/IP_Steam

Condensate return

Solvent Filter

Water Wash

Water Wash

WaterCooler

Cooler

Separator

Page 19: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

19

PCC – Power Plant Advanced Process Integration Option (LB-2)

SECONDARY AIR FANS

COAL FEED

PULV

ERIZ

ED C

OAL

BOIL

ER

PRIMARY AIR FANS

INFILTRATION AIR

SCR

BOILER

FEEDWATER

HP ST

FEEDWATER HEATER SYSTEM

MAIN STEAM

COLD REHEAT

HOT REHEAT

IP ST LP ST

CONDENSER

CO2 CAPTURE & COMPRESSION PLANT

BAGHOUSE FGD

ID FANS

LIMESTONE SLURRY

CO2 COMPR.

TO STACK

MAKEUP WATER

OXIDATION AIR

GYPSUM

BOTTOM ASH

FLY ASH

CO2 PRODUCT

EL. POWER GENERATOR

10

8

7

5

21

43

6

9

1413

1512

1611 11aHRU

23

25

24

26

19

18b

18

17a

17

17b

21

20

BPST

Absorber

Treated flue gasto stack

CO2to Compression

Reboiler

Desorber

Condenser

Make-up water

SolventStorage

Tank

Interstage Cooler

Flue gas

DCC

NaOH Tank

Rich/LeanSolvent

Hex

Flue gas blower

Solvent Cooler

Interstage Heater

LP_Steam

Condensatereturn

LP/IP_Steam

Condensate return

Solvent Filter

Water Wash

Water Wash

WaterCooler

Cooler

Separator

22

Partial Recovery of Sensible Heat from

Flue Gas

LP Steam for Desorber’s

Interstage Heater

Power Cogeneration Utilizing BPST

Significantly Increased

Power Plant Efficiency

Page 20: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

20

Linde-BASF PCC Plant Design for 550 MWePC Power Plant

Single train PCC design for ~ 13,000 TPD CO2 capture

40-50% reduced plot area to 180m x 120 m

Page 21: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

21

Energy demand for different PCC plants

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

Reboiler Duty Cooling Duty Electrical Power

Spec

ific

ener

gy d

eman

d el

emen

ts

NETL-MEA Linde-BASF PCC (LB-1) Linde-BASF PCC (LB-2)

`

Effect of PCC technology improvementson incremental energy requirement for

power plant w ith CO2 capture and compression

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

100%

NETL-MEA Linde-BASF PCC(LB-1)

Linde-BASF PCC (LB-2)

Incr

emen

tal f

uel r

equi

rem

ent f

or C

O2

capt

ure

and

com

pres

sion

Comparative PCC Performance ResultsLinde-BASF vs Reference DOE/NETL Case*

* Reference Case # 10 of DOE-NETL 2007/1281 Report

Page 22: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

22

Total PCC Plant Cost

Total Cost of PCC Plant for 550 MW PC Power Plant

0

50

100

150

200

250

300

350

400

450

500

Case 10 - NETL_2007 LINDE-BASF - Option LB-1 LINDE-BASF - Option LB-2*

PCC Technology Options

Tota

l Cos

t of P

CC

(MM

200

7_$)

CO2 Removal CO2 Compression & Drying

Significantly reduced total PCC

plant Cost relative to DOE/NETL

2007 Reference Case #10 due to

1. Reduced coal combustion (CO2 production) for 11.1% (LB-1) or 15.2% (LB-2)

2. Single train PCC design

3. Optimized PCC plant design

Page 23: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

23

Power plant efficiency improvements and LCOE reductions with Linde-BASF PCC technology

Incremental improvements in power plant efficiencyfrom MEA based PCC to LINDE-BASF LB-2 Option

1.76%

1.35%

24.9%

29.4%

1.39%

20%

21%

22%

23%

24%

25%

26%

27%

28%

29%

30%

NETL - MEA AdvancedSolvent

PCCOptimization

(LB-1)

Heat andPower

Integration(LB-2)

LINDE-BASF(LB-2)

Net

HH

V Ef

ficie

ncy

Incremental Reductions in Levelized Cost Of Electricityfrom MEA based PCC to LINDE-BASF LB-2 Option

5.5

5.5

2.3

101.2101.2103.5109.0114.1119.6

5.1

$65

$70

$75

$80

$85

$90

$95

$100

$105

$110

$115

$120

$125

NETL - M

EAAdv

ance

d Solv

ent

Proce

ss E

nhan

cemen

ts

PCC Opti

mizatio

n (LB

-1)

Heat a

nd P

ower

Integ

ration

(LB-2

)LIN

DE-BASF

LCO

E (2

007$

/MW

hr)

Source: Project DE-FE0007453 Techno-economic analysis of 550 MWe PC power plant with CO2 capture, May 2012.

Page 24: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

24

Detailed Engineering Model of Pilot Plant

24

● Free-standing absorber and stripper

● Equipment modules containing pumps, blower, HX etc

Pilot plant located in NCCC site with the exisiting 0.5 MWe pilot and piperack in the background

Page 25: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

25

Summary and Next Steps

● Linde and project partners are designing and building a 1 MWe post-combustion capture pilot plant to be installed and tested at the National Carbon Capture Center in Wilsonville, AL.

● The plant will incorporate BASF’s OASE® blue solvent technology and Linde-BASF process enhancements and demonstrate that target performance can be achieved.

● Techno-economic assessment on a 550 MWe coal-fired power plant has confirmed the significant energy and capex savings compared to a reference MEA PCC plant, thereby, driving down the levelized cost of electricity.

● Critical next steps for the project:

— Complete detailed engineering of the pilot plant and firm cost estimates and reach “Go”decision to proceed pilot plant procurement and build (Budget Period 1)

— Procure, fabricate and install pilot plant at the NCCC and achieve mechanical completion (Budget Period 2)

— Perform parametric and long duration tests and confirm achievement of target performance. (Budget Period 3)

Page 26: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

26

Acknowledgement and Disclaimer

Acknowledgement: This presentation is based on work supported by the Department of Energy under Award Number DE-FE0007453.

Disclaimer: “This presentation was prepared as an account of work sponsored by an agency of the United States Government. Neither the United States Government nor any agency thereof, nor any of their employees, makes any warranty, express or implied, or assumes any legal liability or responsibility for the accuracy, completeness, or usefulness of any information, apparatus, product, or process disclosed, or represents that its use would not infringe privately owned rights. Reference herein to any specific commercial product, process, or service by trade name, trademark, manufacturer, or otherwise does not necessarily constitute or imply its endorsement, recommendation, or favoring by the United States Government or any agency thereof. The views and opinions of authors expressed herein do not necessarily state or reflect those of the United States Government or any agency thereof.”

Page 27: Slipstream pilot plant demonstration of an amine- based ... Library/Events/2012/CO2 Capture... · 2 The Linde Group Overview and Carbon Capture Expertise 1 Linde Engineering Technology-focused

27

Thank you for your attention!

Project DE-FE00074532012 NETL CO2 Capture Technology MeetingKrish R. Krishnamurthy, Linde LLCJuly 9-12, 2012Pittsburgh, PA