slusd measure m elementary school … · such as ball walls and volleyball courts ... project...
TRANSCRIPT
• Repair/replace play structures
• Install fitness par courses
• Install resilient surfacing
• Repair, resurface and restripe asphalt
• Install and/or repair game court equipment
such as ball walls and volleyball courts
• Install outdoor classroom structures
• Install measured running paths
BOND APPROVED SCOPE OF WORK
2
• Conceptual Design - Held three group
programming meetings and met with each
school to introduce program and scope of
project (between 10-11 to 11-11)
• Schematic Design - Met with each school two
or three times and presented results to the
School Board (between 1-12 to 5-12)
• Design Development – Met with each school
two or three times (between 8-12 and 10-12)
• Construction Documentation – Met with each
school once and received sign off from site
(between 11-12 and 12-12)
DESIGN AND OUTREACH PROCESS
3
• Held three group programming meetings
with School Principals, Physical Education
Teachers, Custodians, City Personnel and
Community Members, District Staff
• October 25, 2011
• November 9, 2011
• November 29, 2011
CONCEPTUAL DESIGN
4 Madison Elementary
SCHEMATIC DESIGN
• Conducted site analysis, developed program
and scope and preliminary palette of
products
• First round of meetings with schools
• Prepared preliminary schematic designs
• Second round of meetings with schools to
come to consensus on program
5
Madison Elementary
DESIGN DEVELOPMENT
• Conducted safety inspections of play structures
• Conducted pavement inspection at each site,
confirmed site features and took measurements
• Prepared design development drawings based on
site meetings, inspections and presented to the
School Board
• Third round of meetings with schools to gain
consensus on site program, layout, and priorities
6
CONSTRUCTION DOCUMENTATION
• District conducted additional safety inspection
of play structures at each site due to damage
over the summer
• Combined safety inspections and solicited
parts lists and pricing information for
structure repairs from each play structure
manufacturer
• Prepared draft construction documents based
upon site approved design development
drawings
• Fourth round of meetings with school to
obtain approval from the site on the design
7
• BASE BID - repair structures that are able to
be repaired and replace those that aren’t
(Wilson, Washington, Roosevelt)
• ALTERNATE BID – replace all structures with
new equipment that is a standardized
manufacturer
9
SCOPE OF WORK –
REPAIR PLAY STRUCTURES
10
SCOPE OF WORK –
REPAIR/REPLACE PLAY STRUCTURES
Typical Primary Structure with Par Course Elements
SCOPE OF WORK –
INSTALL PAR COURSES
14
• BASE BID – install stand alone par course
fitness equipment with resilient safety
surfacing at seven of the eight school sites
with the exception of Roosevelt
• ALTERNATE BID – install fitness components
within new primary play structure at seven of
the eight school sites with the exception of
Roosevelt
SCOPE OF WORK –
INSTALL SAFETY SURFACING
16
• BASE BID – remove bark and install base
rock, weep holes and safety surfacing within
the existing play boxes
• Cost may be offset by $150,000.00
CalRecycle’s Tire-Derived Product (TDP) Grant
program application
SCOPE OF WORK – REPAIR,
RESURFACE & RESTRIPE ASPHALT
18
• BASE BID – repair cracks and slurry seal
existing asphalt and restripe with colored
paint. Some sites will have new areas of
asphalt (Madison, Wilson and Roosevelt)
SCOPE OF WORK –
INSTALL GAME AND COURT EQUIPMENT
20
• BASE BID – repair, replace or install new
court equipment including ball walls, drop
shots, basketball back boards, volleyball
posts and nets
SCOPE OF WORK – INSTALL OUTDOOR
CLASSROOM STRUCTURES
22
• BASE BID – install metal roofed outdoor
classroom structures at seven of the eight
school sites with the exception of Roosevelt
SCOPE OF WORK – INSTALL
MEASURED RUNNING PATHS
24
• BASE BID – install stabilized decomposed
granite running paths at five schools,
combination stabilized decomposed granite
and stabilized infield loam running paths at
two schools or renovated asphalt path at one
school
• ALTERNATE BID – install asphalt running
paths or combination stabilized infield loam
and asphalt running paths at each school
PROJECT BUDGET & COST ESTIMATES
39
• Approved Budget in A-A -
$5,398,000.00
• Current Base Bid Construction Estimate -
$5,371,430.53 (-$26,569.47)
• Current Alternate Construction Estimate -
$5,448,932.97 (+50,932.97)
NEXT STEPS
• Submit construction documents to Division
of the State Architect (DSA) in late January
2013
• Anticipated DSA approval March 2013
• Bid Spring of 2013
• Construction Summer of 2013
40