Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project. SMACC Twentieth report [20 min ] 14/03/2014. Activities since last LSC (28/02/2014) Arc splices installation By Activities By sectors SIT DFBA Dashboards Specials Update on overheated splices End of project issue - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SMACC Twentieth report [20 min ] 14/03/2014
Page 2: SMACC Twentieth report [20 min ] 14/03/2014

SMACC Twentieth report[20 min]

14/03/2014

Jean-Philippe Tock (TE-MSC)

On behalf of the SMACC project

Page 3: SMACC Twentieth report [20 min ] 14/03/2014

Activities since last LSC (28/02/2014) Arc splices installation

• By Activities• By sectors

SIT DFBA

Dashboards Specials

Update on overheated splices End of project issue

Activities for the next 2 weeks

Conclusions

Page 4: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock4/29

Sector 56 : Final leak test and reconnection of DFBAK

Sector 67 : Complete interventions on NC, reclose insulation vacuum

Sector 78 Work on NC, Reconnection of DFBAO-SHM

Sector 81 (Priority) Progress on insulation vacuum leak test

Sector 12 Complete last IC (#1) Progress on closure of ICs

Sector 23 Progress on the installation of electrical insulation Complete Q diodes consolidation Complete M line rewelding (but NCs)

Sector 34 Complete installation of electrical insulation Work on overheated splices Start consolidation of Q diodes

Sector 45 Complete resoldering of splices Progress on installation of shunts

SMACC Main activities for the last 2 weeks

>98 % done

All shunts are installed

> 95% rewelded

Resoldering completed

DFBAK SHM reconnection on-going [Splices are resoldered],

> 98% reclosed, 12/14 vac subsectors leak tested

Leaks on K hoses repaired, > ½ is finally LT

> 40% done

From last LSC (28.02.2014)DFBAK SHM reconnection on-going [Splices are resoldered], Only the last subesector remains to be leak tested

Completed

> 90% injected and controlled

> 75% reclosed

>95 % of the shunts are installed

Interventions completed, ICs to be reclosed then final LT

1 out of 4 repaired, on-going

Page 5: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock5/29

SEQUENCE AND STATUS

OK to open Open ICs

Install DN200

Open M sleeves

ElQC (old splices)

Undo / Redo splices ElQC (new splices)

Machine Cu

> 7.9 sectors

ElQC after Cu mach.

> 7.9 sectors

Install shunts

≈ 7.9 sectors

ElQCafter shunt

≈ 7.9 sectors

Insulate splices

≈ 7 sectors

Weld M

≈ 6 sectors

Leak test M

≈ 5.5 sectors

Close IC

> 4.5 sectors

Final LT

≈ 3.5 sectors

Consolidate Q diodes

≈ 6.5 sectors

Cancelled

Completed

Completed

Completed

Completed

Completed

Non-conformities (Before P Test)

Non-conformities (After P Test)

1 completed≈ 3.5 sec-eq

Almost completed in 1st sector (67)

Completed

Page 6: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock6/29

SMACC Progress report by activity

Courtesy H Prin

Resoldering: Completed for the whole LHC

Some desoldering/resoldering will be necessary because of NCDegradation after Cu machining, non-conformities,…

Competence and minimum capacity will be kept up to the end of the project

Page 7: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock7/29

SMACC Progress report by activity

Cu machining completed in > 7.9 sectors-eq

• Completed in 3 sectors• Only 11 remaining,

mostly linked to overheated splices and DFBA SHM reconnection

Courtesy MDumas

Page 8: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock8/29

SMACC Progress report by activity

Shunts are installed in ≈ 7.9 sectors-eq

• 2 weeks ahead of schedule• Saturation effect is seen

• Completed in 3 sectors (67, 81, 12)• Only 16 ICs remains in the whole LHC

(≈1%)Shunt weekly installation rate

(4 weeks sliding average)*Estimate for W11

Courtesy H Prin

Page 9: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock9/29

SMACC Progress report by activity

Insulation box: Installed in > 6.5 sectors equivalent

Courtesy H Prin / G Maury

On the baseline > 3 weeks buffer wrt welding Only 8 ICs left in 6 first sectors

(<1 %) but it was 12 ICs 2 weeks ago Issue with some tooling components (mixer), should be solved next week A fall back solution exists

(4 weeks sliding average)*Estimate for W8

Page 10: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock10/29

SMACC Progress report by activity

Consolidation of Q Diodes: in ≈ 6.5 sectors equivalent

Detailed schedule worked out Should not interfere with welding activities NC of un~/badly coated BB Already decided to “use as is” if on magnet side Decision extended to diode side [Diodes WG

26.02.2014] was confirmed at TETM 11.03.2014

Courtesy L Grand-Clement,

Page 11: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock11/29

SMACC Progress report by activity

M Welding : Done in ≈ 6 sec-eq:

Routinely 60 ICs/week Work concentrated in 1 sector, starting in

34 (7th/8) No major disturbance Exactly on the baseline presented on

4.10.2013 Detailed presentation at next LSC

As presented LSC 4.10.2013

11 weeks @ 34

18 weeks @ 51

Slightly ahead of revised schedule

Courtesy S Atieh

Page 12: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock12/29

SMACC Progress report by activity

M sleeves leak testing : Completed in ≈ 5.5 sec-eq

Following the M lines rewelding, less regular by nature (sectorization) ≈ 3 weeks behind schedule Under recovery as for the M welding

Courtesy P Cruikshank / L Mourier

Page 13: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock13/29

SMACC Progress report by activity

Reclosure of interconnections : > 4.5 sec equivalent are reclosed

Work mainly in S12 and starting in S23 On the baseline The 1000th IC will be closed this afternoon

Courtesy A Chrul / A Musso

Page 14: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock14/29

SMACC Progress report by activity

Final leak test: > 750 ICs validated, > 3.5 sec equivalent

3 weeks to have results after repumping S56: only DFBAK subsector remains S67: fully validated but subsectors to be revalidated after interventions on NC S78: 12 subsectors validated S81: 11 subsectors validated, 3 under test, several interventions S12: 6 subsectors under test About 1 week behind schedule, was 3 weeks at last LSC

Page 15: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock15/29

SMACC Sector 67

2 leaks fixed, one not localised, accepted as isOn-going:

Reclosure and final leak test of insulationvacuum

SMACC Sector 81

Remaining : Less than half of W leak test and DN200 (Back on baseline )

Page 16: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock16/29

SMACC Progress report by sector

Main activities are : Leak test of M lines Closure of interconnections 6/14 subsectors are under final LT

Main activities are : Welding of M lines Leak test of M lines Start reclosure of Ics (Today)

Page 17: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock17/29

SMACC Progress report by sector

Main activities are : Work on overheated splices

(More info in next slides) Q diodes consolidation Rewelding of M lines

Main activities are : Installation of shunts Installation of electrical insulation

Page 18: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock18/29

SMACC Dashboards

Shunting is slowing down (Difficult cases: overheated splices, DFBAs,… ) The installation of insulation boxes is ahead of the baseline Welding and M leak test rates are recovering the baseline schedule in parallel Reclosure: On baseline, nominal rate achieved Insulation vacuum leak test : RECOVERING Disturbances of leak tests (M lines and insulation vacuum) have to be minimised

Page 19: SMACC Twentieth report [20 min ] 14/03/2014

SMACC summary status Updated 13-Mar-14

19-Apr-13 212 13-May-13 17-Jun-13 211 19-Jul-13 05-Jul-13 211 08-Aug-13 19-Jul-13 211 15-Aug-13 30-Aug-13 211 27-Sep-13 17-Sep-13 198 25-Oct-13-11 212 -6 -54 212 -41474 -58 212 -41494 4 212 -41501 -10 212 8 212

08-Apr-13 100% 07-May-13 24-Apr-13 99.5% 08-May-13 99.5% 23-Jul-13 99.5% 20-Aug-13 99.5% 25-Sep-13 93%

16-May-13 211 06-Jun-13 22-Jul-13 211 23-Aug-13 13-Aug-13 211 17-Sep-13 27-Aug-13 211 24-Sep-13 30-Sep-13 211 27-Oct-13 15-Oct-13 211 22-Nov-13-20 211 10 -31 211 60 8 211 48 5 211 51 -27 211 22 7 211 11

26-Apr-13 100% 16-Jun-13 21-Jun-13 100% 22-Oct-13 21-Aug-13 100% 04-Nov-13 01-Sep-13 100% 14-Nov-13 03-Sep-13 100% 18-Nov-13 22-Oct-13 100% 03-Dec-13

07-Jun-13 212 27-Jun-13 26-Aug-13 211 30-Sep-13 18-Sep-13 211 22-Oct-13 02-Oct-13 209 29-Oct-13 28-Oct-13 209 22-Nov-13 12-Nov-13 180 20-Dec-13-24 212 12 -3 212 -41547 33 212 -41569 44 212 -41576 29 212 -41600 83 212 -41628

14-May-13 100% 09-Jul-13 23-Aug-13 99.5% 21-Oct-13 99.5% 15-Nov-13 99% 26-Nov-13 99% 03-Feb-14 85%

28-Jun-13 212 18-Jul-13 01-Oct-13 212 04-Nov-13 23-Oct-13 212 26-Nov-13 06-Nov-13 212 03-Dec-13 27-Jan-14 212 21-Feb-14 11-Feb-14 174 21-Mar-14-38 212 8 -11 212 81 34 212 73 29 212 83 -7 212 6 8 212 -41719

21-May-13 100% 26-Jul-13 20-Sep-13 100% 24-Jan-14 26-Nov-13 100% 07-Feb-14 05-Dec-13 100% 24-Feb-14 20-Jan-14 100% 27-Feb-14 19-Feb-14 82%

19-Jul-13 212 08-Aug-13 05-Nov-13 212 09-Dec-13 27-Nov-13 211 14-Jan-14 11-Dec-13 198 21-Jan-14 24-Feb-14 156 21-Mar-14 11-Mar-14 0 22-Apr-14-53 212 21 -11 212 80 55 212 -41653 48 212 -41660 -5 212 -41719 -41709 212 -41751

27-May-13 100% 29-Aug-13 25-Oct-13 100% 27-Feb-14 21-Jan-14 99.5% 28-Jan-14 93% 19-Feb-14 74% 0%

09-Aug-13 212 29-Aug-13 10-Dec-13 212 27-Jan-14 20-Jan-14 204 21-Feb-14 31-Jan-14 85 27-Feb-14 24-Mar-14 0 22-Apr-14 08-Apr-14 0 21-May-14-67 212 19 -25 212 35 24 212 -41691 26 212 -41697 -41722 212 -41751 -41737 212 -41780

03-Jun-13 100% 17-Sep-13 15-Nov-13 100% 03-Mar-14 13-Feb-14 96% 26-Feb-14 40% 0% 0%30-Jul-0025-Nov-13 212 13-Dec-13 29-Jan-14 205 04-Mar-14 24-Feb-14 20 28-Mar-14 07-Mar-14 0 03-Apr-14 24-Apr-14 0 22-May-14 07-May-14 0 20-Jun-14

-188 212 -49 -48 212 -41702 15 212 -41726 -41705 212 -41732 -41753 212 -41781 -41766 212 -4181021-May-13 100% 25-Oct-13 12-Dec-13 97% 11-Mar-14 9% 0% 0% 0%

06-Jan-14 212 24-Jan-14 05-Mar-14 204 08-Apr-14 31-Mar-14 0 07-May-14 11-Apr-14 0 13-May-14 22-May-14 0 20-Jun-14 06-Jun-14 0 18-Jul-14-255 212 -53 -27 212 -41737 -41729 212 -41766 -41740 212 -41772 -41781 212 -41810 -41796 212 -41838

26-Apr-13 100% 02-Dec-13 06-Feb-14 96% 0% 0% 0% 0%

19-Apr-13 1695 24-Jan-14 17-Jun-13 1678 08-Apr-14 05-Jul-13 1280 07-May-14 19-Jul-13 1126 13-May-14 30-Aug-13 999 20-Jun-14 17-Sep-13 763 18-Jul-14-11 1695 -53 -54 1695 -41737 -58 1695 -41766 4 1695 -41772 -10 1695 -41810 8 1695 -41838

08-Apr-13 100% 02-Dec-13 24-Apr-13 99.0% 08-May-13 76% 23-Jul-13 66% 20-Aug-13 59% 25-Sep-13 45%

Sleeves Welding M lines Leak Test ICs closure Ins Vac Leak testShunts InstallationICs Opening

S56

S34

S45

LHC

S67

S78

S81

S12

S23

Completed

Completed

New

New

Page 20: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock20/29

SMACC Progress report SIT

SIT Team is reduced but can be remobilised very quickly Activities linked to NC, leaks and overheated splices

Courtesy N Bourcey, S Le Naour

Page 21: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock21/29

SMACC DFBA

Courtesy A Perin, E Vergara

95% of splices are consolidatedOK for just in time

(New schedule)

Many operations are well advanced but not completed

8 DFBAs are completed

Page 22: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock22/29

SMACC Dashboards

Baseline: 82.7 % (77.4 %)Completed: 84.2 % (78.9 %)Delay -3 (-3) days

Baseline: 76.9 % (72.8 %)Completed: 74.9 % (69.0 %)Delay 10 (20) days

Ahead of schedule

Decreasing delay

Arc splices: Stable but difficult cases ahead

SITDelay decreases, waiting validation

DFBA: Many activities on-goingIn the shadow of the arcs

Baseline: 85.7 % (81.1 %)Completed: 67.1 % (57.4 %)Delay 3 (4) months

Recovering

Page 23: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock23/29

SMACC Dashboards

Progress:Baseline: 82.5% (77.5 %)Completed: 82.1% (76.6 %)

Delay 2 (6) days

Decreasing ; Δbaseline <≈ Δcompleted

Page 24: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock24/29

SMACC Overheated splices

From LSC of 07.02.2014

9

Courtesy C Scheuerlein, F Savary

5

16Confirmed as is

Within the present schedule, possible to repair 4 to 5 splices with new cables[Forecast is max 6]

Page 25: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock25/29

End of project issue

Courtesy R Ostojic, M Struik

In order to alleviate effect of the end of work atmosphere, presence in the tunnel is increased:

* One extra staff (Thx TE-VSC) to second worksite supervisors* Auditors are reinforced and are intensifying audits

Page 26: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock26/29

SMACC Summary on progress

Main 13 kA Splices: On schedule Q Diodes consolidation :

Almost all components are at CERN and tested Overheated splices : to be followed up closely Leak test rate is according to forecast, slightly more needed

Special Interventions: Delay is decreasinng Almost all planned interventions are completed

Focus on NC DFBA: Activities are back in the shadow of arc splices (except 56-78)

SMACC: About 2 days of delay, reducing

wrt schedule defined one year ago !!

Very slightly more than nominal rate achieved these last 24 weeks !

Page 27: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock27/29

Sector 56 : Final leak test and reconnection of DFBAK

Sector 67 : Reclose insulation vacuum and start final leak tests

Sector 78 Work on NC Reconnection of DFBAO-SHM

Sector 81 (Priority) Complete insulation vacuum leak test

Sector 12 (Priority) Reclose last ICs Progress on insulation vacuum leak test

Sector 23 Complete the installation of electrical insulation Complete M line rewelding (but NCs) Progress on M-lines leak testing Start reclosure of ICs

Sector 34 Work on overheated splices Complete consolidation of Q diodes

Sector 45 Progress on installation of shunts Progress on electrical insulation

SMACC Main activities for the next 2 weeks

Page 28: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock28/29

ConclusionsProject is almost back on schedule (-2 days)

Mind the last X % effectLeak testing is reaching the planned rates

DFBA consolidation is progressing very well

Overheated splices : On the critical path

S67 is almost ready for next step (ElQA before cooldown foreseen end of April)

S81 should be ready on time for pressure test (8.04.2014)

Page 29: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock29/29

Advancement is > 80 % ….

But

Page 30: SMACC Twentieth report [20 min ] 14/03/2014
Page 31: SMACC Twentieth report [20 min ] 14/03/2014

JPh Tock31/29