smacc twentieth report [20 min ] 14/03/2014
DESCRIPTION
Jean-Philippe Tock (TE-MSC) On behalf of the SMACC project. SMACC Twentieth report [20 min ] 14/03/2014. Activities since last LSC (28/02/2014) Arc splices installation By Activities By sectors SIT DFBA Dashboards Specials Update on overheated splices End of project issue - PowerPoint PPT PresentationTRANSCRIPT
SMACC Twentieth report[20 min]
14/03/2014
Jean-Philippe Tock (TE-MSC)
On behalf of the SMACC project
Activities since last LSC (28/02/2014) Arc splices installation
• By Activities• By sectors
SIT DFBA
Dashboards Specials
Update on overheated splices End of project issue
Activities for the next 2 weeks
Conclusions
JPh Tock4/29
Sector 56 : Final leak test and reconnection of DFBAK
Sector 67 : Complete interventions on NC, reclose insulation vacuum
Sector 78 Work on NC, Reconnection of DFBAO-SHM
Sector 81 (Priority) Progress on insulation vacuum leak test
Sector 12 Complete last IC (#1) Progress on closure of ICs
Sector 23 Progress on the installation of electrical insulation Complete Q diodes consolidation Complete M line rewelding (but NCs)
Sector 34 Complete installation of electrical insulation Work on overheated splices Start consolidation of Q diodes
Sector 45 Complete resoldering of splices Progress on installation of shunts
SMACC Main activities for the last 2 weeks
>98 % done
All shunts are installed
> 95% rewelded
Resoldering completed
DFBAK SHM reconnection on-going [Splices are resoldered],
> 98% reclosed, 12/14 vac subsectors leak tested
Leaks on K hoses repaired, > ½ is finally LT
> 40% done
From last LSC (28.02.2014)DFBAK SHM reconnection on-going [Splices are resoldered], Only the last subesector remains to be leak tested
Completed
> 90% injected and controlled
> 75% reclosed
>95 % of the shunts are installed
Interventions completed, ICs to be reclosed then final LT
1 out of 4 repaired, on-going
JPh Tock5/29
SEQUENCE AND STATUS
OK to open Open ICs
Install DN200
Open M sleeves
ElQC (old splices)
Undo / Redo splices ElQC (new splices)
Machine Cu
> 7.9 sectors
ElQC after Cu mach.
> 7.9 sectors
Install shunts
≈ 7.9 sectors
ElQCafter shunt
≈ 7.9 sectors
Insulate splices
≈ 7 sectors
Weld M
≈ 6 sectors
Leak test M
≈ 5.5 sectors
Close IC
> 4.5 sectors
Final LT
≈ 3.5 sectors
Consolidate Q diodes
≈ 6.5 sectors
Cancelled
Completed
Completed
Completed
Completed
Completed
Non-conformities (Before P Test)
Non-conformities (After P Test)
1 completed≈ 3.5 sec-eq
Almost completed in 1st sector (67)
Completed
JPh Tock6/29
SMACC Progress report by activity
Courtesy H Prin
Resoldering: Completed for the whole LHC
Some desoldering/resoldering will be necessary because of NCDegradation after Cu machining, non-conformities,…
Competence and minimum capacity will be kept up to the end of the project
JPh Tock7/29
SMACC Progress report by activity
Cu machining completed in > 7.9 sectors-eq
• Completed in 3 sectors• Only 11 remaining,
mostly linked to overheated splices and DFBA SHM reconnection
Courtesy MDumas
JPh Tock8/29
SMACC Progress report by activity
Shunts are installed in ≈ 7.9 sectors-eq
• 2 weeks ahead of schedule• Saturation effect is seen
• Completed in 3 sectors (67, 81, 12)• Only 16 ICs remains in the whole LHC
(≈1%)Shunt weekly installation rate
(4 weeks sliding average)*Estimate for W11
Courtesy H Prin
JPh Tock9/29
SMACC Progress report by activity
Insulation box: Installed in > 6.5 sectors equivalent
Courtesy H Prin / G Maury
On the baseline > 3 weeks buffer wrt welding Only 8 ICs left in 6 first sectors
(<1 %) but it was 12 ICs 2 weeks ago Issue with some tooling components (mixer), should be solved next week A fall back solution exists
(4 weeks sliding average)*Estimate for W8
JPh Tock10/29
SMACC Progress report by activity
Consolidation of Q Diodes: in ≈ 6.5 sectors equivalent
Detailed schedule worked out Should not interfere with welding activities NC of un~/badly coated BB Already decided to “use as is” if on magnet side Decision extended to diode side [Diodes WG
26.02.2014] was confirmed at TETM 11.03.2014
Courtesy L Grand-Clement,
JPh Tock11/29
SMACC Progress report by activity
M Welding : Done in ≈ 6 sec-eq:
Routinely 60 ICs/week Work concentrated in 1 sector, starting in
34 (7th/8) No major disturbance Exactly on the baseline presented on
4.10.2013 Detailed presentation at next LSC
As presented LSC 4.10.2013
11 weeks @ 34
18 weeks @ 51
Slightly ahead of revised schedule
Courtesy S Atieh
JPh Tock12/29
SMACC Progress report by activity
M sleeves leak testing : Completed in ≈ 5.5 sec-eq
Following the M lines rewelding, less regular by nature (sectorization) ≈ 3 weeks behind schedule Under recovery as for the M welding
Courtesy P Cruikshank / L Mourier
JPh Tock13/29
SMACC Progress report by activity
Reclosure of interconnections : > 4.5 sec equivalent are reclosed
Work mainly in S12 and starting in S23 On the baseline The 1000th IC will be closed this afternoon
Courtesy A Chrul / A Musso
JPh Tock14/29
SMACC Progress report by activity
Final leak test: > 750 ICs validated, > 3.5 sec equivalent
3 weeks to have results after repumping S56: only DFBAK subsector remains S67: fully validated but subsectors to be revalidated after interventions on NC S78: 12 subsectors validated S81: 11 subsectors validated, 3 under test, several interventions S12: 6 subsectors under test About 1 week behind schedule, was 3 weeks at last LSC
JPh Tock15/29
SMACC Sector 67
2 leaks fixed, one not localised, accepted as isOn-going:
Reclosure and final leak test of insulationvacuum
SMACC Sector 81
Remaining : Less than half of W leak test and DN200 (Back on baseline )
JPh Tock16/29
SMACC Progress report by sector
Main activities are : Leak test of M lines Closure of interconnections 6/14 subsectors are under final LT
Main activities are : Welding of M lines Leak test of M lines Start reclosure of Ics (Today)
JPh Tock17/29
SMACC Progress report by sector
Main activities are : Work on overheated splices
(More info in next slides) Q diodes consolidation Rewelding of M lines
Main activities are : Installation of shunts Installation of electrical insulation
JPh Tock18/29
SMACC Dashboards
Shunting is slowing down (Difficult cases: overheated splices, DFBAs,… ) The installation of insulation boxes is ahead of the baseline Welding and M leak test rates are recovering the baseline schedule in parallel Reclosure: On baseline, nominal rate achieved Insulation vacuum leak test : RECOVERING Disturbances of leak tests (M lines and insulation vacuum) have to be minimised
SMACC summary status Updated 13-Mar-14
19-Apr-13 212 13-May-13 17-Jun-13 211 19-Jul-13 05-Jul-13 211 08-Aug-13 19-Jul-13 211 15-Aug-13 30-Aug-13 211 27-Sep-13 17-Sep-13 198 25-Oct-13-11 212 -6 -54 212 -41474 -58 212 -41494 4 212 -41501 -10 212 8 212
08-Apr-13 100% 07-May-13 24-Apr-13 99.5% 08-May-13 99.5% 23-Jul-13 99.5% 20-Aug-13 99.5% 25-Sep-13 93%
16-May-13 211 06-Jun-13 22-Jul-13 211 23-Aug-13 13-Aug-13 211 17-Sep-13 27-Aug-13 211 24-Sep-13 30-Sep-13 211 27-Oct-13 15-Oct-13 211 22-Nov-13-20 211 10 -31 211 60 8 211 48 5 211 51 -27 211 22 7 211 11
26-Apr-13 100% 16-Jun-13 21-Jun-13 100% 22-Oct-13 21-Aug-13 100% 04-Nov-13 01-Sep-13 100% 14-Nov-13 03-Sep-13 100% 18-Nov-13 22-Oct-13 100% 03-Dec-13
07-Jun-13 212 27-Jun-13 26-Aug-13 211 30-Sep-13 18-Sep-13 211 22-Oct-13 02-Oct-13 209 29-Oct-13 28-Oct-13 209 22-Nov-13 12-Nov-13 180 20-Dec-13-24 212 12 -3 212 -41547 33 212 -41569 44 212 -41576 29 212 -41600 83 212 -41628
14-May-13 100% 09-Jul-13 23-Aug-13 99.5% 21-Oct-13 99.5% 15-Nov-13 99% 26-Nov-13 99% 03-Feb-14 85%
28-Jun-13 212 18-Jul-13 01-Oct-13 212 04-Nov-13 23-Oct-13 212 26-Nov-13 06-Nov-13 212 03-Dec-13 27-Jan-14 212 21-Feb-14 11-Feb-14 174 21-Mar-14-38 212 8 -11 212 81 34 212 73 29 212 83 -7 212 6 8 212 -41719
21-May-13 100% 26-Jul-13 20-Sep-13 100% 24-Jan-14 26-Nov-13 100% 07-Feb-14 05-Dec-13 100% 24-Feb-14 20-Jan-14 100% 27-Feb-14 19-Feb-14 82%
19-Jul-13 212 08-Aug-13 05-Nov-13 212 09-Dec-13 27-Nov-13 211 14-Jan-14 11-Dec-13 198 21-Jan-14 24-Feb-14 156 21-Mar-14 11-Mar-14 0 22-Apr-14-53 212 21 -11 212 80 55 212 -41653 48 212 -41660 -5 212 -41719 -41709 212 -41751
27-May-13 100% 29-Aug-13 25-Oct-13 100% 27-Feb-14 21-Jan-14 99.5% 28-Jan-14 93% 19-Feb-14 74% 0%
09-Aug-13 212 29-Aug-13 10-Dec-13 212 27-Jan-14 20-Jan-14 204 21-Feb-14 31-Jan-14 85 27-Feb-14 24-Mar-14 0 22-Apr-14 08-Apr-14 0 21-May-14-67 212 19 -25 212 35 24 212 -41691 26 212 -41697 -41722 212 -41751 -41737 212 -41780
03-Jun-13 100% 17-Sep-13 15-Nov-13 100% 03-Mar-14 13-Feb-14 96% 26-Feb-14 40% 0% 0%30-Jul-0025-Nov-13 212 13-Dec-13 29-Jan-14 205 04-Mar-14 24-Feb-14 20 28-Mar-14 07-Mar-14 0 03-Apr-14 24-Apr-14 0 22-May-14 07-May-14 0 20-Jun-14
-188 212 -49 -48 212 -41702 15 212 -41726 -41705 212 -41732 -41753 212 -41781 -41766 212 -4181021-May-13 100% 25-Oct-13 12-Dec-13 97% 11-Mar-14 9% 0% 0% 0%
06-Jan-14 212 24-Jan-14 05-Mar-14 204 08-Apr-14 31-Mar-14 0 07-May-14 11-Apr-14 0 13-May-14 22-May-14 0 20-Jun-14 06-Jun-14 0 18-Jul-14-255 212 -53 -27 212 -41737 -41729 212 -41766 -41740 212 -41772 -41781 212 -41810 -41796 212 -41838
26-Apr-13 100% 02-Dec-13 06-Feb-14 96% 0% 0% 0% 0%
19-Apr-13 1695 24-Jan-14 17-Jun-13 1678 08-Apr-14 05-Jul-13 1280 07-May-14 19-Jul-13 1126 13-May-14 30-Aug-13 999 20-Jun-14 17-Sep-13 763 18-Jul-14-11 1695 -53 -54 1695 -41737 -58 1695 -41766 4 1695 -41772 -10 1695 -41810 8 1695 -41838
08-Apr-13 100% 02-Dec-13 24-Apr-13 99.0% 08-May-13 76% 23-Jul-13 66% 20-Aug-13 59% 25-Sep-13 45%
Sleeves Welding M lines Leak Test ICs closure Ins Vac Leak testShunts InstallationICs Opening
S56
S34
S45
LHC
S67
S78
S81
S12
S23
Completed
Completed
New
New
JPh Tock20/29
SMACC Progress report SIT
SIT Team is reduced but can be remobilised very quickly Activities linked to NC, leaks and overheated splices
Courtesy N Bourcey, S Le Naour
JPh Tock21/29
SMACC DFBA
Courtesy A Perin, E Vergara
95% of splices are consolidatedOK for just in time
(New schedule)
Many operations are well advanced but not completed
8 DFBAs are completed
JPh Tock22/29
SMACC Dashboards
Baseline: 82.7 % (77.4 %)Completed: 84.2 % (78.9 %)Delay -3 (-3) days
Baseline: 76.9 % (72.8 %)Completed: 74.9 % (69.0 %)Delay 10 (20) days
Ahead of schedule
Decreasing delay
Arc splices: Stable but difficult cases ahead
SITDelay decreases, waiting validation
DFBA: Many activities on-goingIn the shadow of the arcs
Baseline: 85.7 % (81.1 %)Completed: 67.1 % (57.4 %)Delay 3 (4) months
Recovering
JPh Tock23/29
SMACC Dashboards
Progress:Baseline: 82.5% (77.5 %)Completed: 82.1% (76.6 %)
Delay 2 (6) days
Decreasing ; Δbaseline <≈ Δcompleted
JPh Tock24/29
SMACC Overheated splices
From LSC of 07.02.2014
9
Courtesy C Scheuerlein, F Savary
5
16Confirmed as is
Within the present schedule, possible to repair 4 to 5 splices with new cables[Forecast is max 6]
JPh Tock25/29
End of project issue
Courtesy R Ostojic, M Struik
In order to alleviate effect of the end of work atmosphere, presence in the tunnel is increased:
* One extra staff (Thx TE-VSC) to second worksite supervisors* Auditors are reinforced and are intensifying audits
JPh Tock26/29
SMACC Summary on progress
Main 13 kA Splices: On schedule Q Diodes consolidation :
Almost all components are at CERN and tested Overheated splices : to be followed up closely Leak test rate is according to forecast, slightly more needed
Special Interventions: Delay is decreasinng Almost all planned interventions are completed
Focus on NC DFBA: Activities are back in the shadow of arc splices (except 56-78)
SMACC: About 2 days of delay, reducing
wrt schedule defined one year ago !!
Very slightly more than nominal rate achieved these last 24 weeks !
JPh Tock27/29
Sector 56 : Final leak test and reconnection of DFBAK
Sector 67 : Reclose insulation vacuum and start final leak tests
Sector 78 Work on NC Reconnection of DFBAO-SHM
Sector 81 (Priority) Complete insulation vacuum leak test
Sector 12 (Priority) Reclose last ICs Progress on insulation vacuum leak test
Sector 23 Complete the installation of electrical insulation Complete M line rewelding (but NCs) Progress on M-lines leak testing Start reclosure of ICs
Sector 34 Work on overheated splices Complete consolidation of Q diodes
Sector 45 Progress on installation of shunts Progress on electrical insulation
SMACC Main activities for the next 2 weeks
JPh Tock28/29
ConclusionsProject is almost back on schedule (-2 days)
Mind the last X % effectLeak testing is reaching the planned rates
DFBA consolidation is progressing very well
Overheated splices : On the critical path
S67 is almost ready for next step (ElQA before cooldown foreseen end of April)
S81 should be ready on time for pressure test (8.04.2014)
JPh Tock29/29
Advancement is > 80 % ….
But
JPh Tock31/29