small and micro generation · microsoft powerpoint - smg presentation 2016 [read-only] author:...
TRANSCRIPT
Small and Micro Generation
Valmon Muller
Senior Advisor IPP’s
Date: 2016-04-14
Other
1 %
Renewables
21 %
4 %
Peaking - OCGT8 %
Mid-merit Gas
3 %
Baseload - Import
5 %
Baseload - Nuclear
13 %
Baseload - Coal
46 %
The (policy-adjusted) IRP leads to a new 2030 capacity mix (national and energy planning process)
40,996 MW
11,400 MW
4,109 MW
2,370 MW
7,330 MW
3,512 MW
18,925 MW
890 MW
1 %5%
6%0%
3%
4%
81%
• The forecasted peak demand will
grow from 38.9 to 62 GW by
2030. Total 81.3 GW of
Generation capacity is required
by 2030 (revised IRP, 2013),
growth mostly from renewables
• DoE is driving the growth of
Renewable Energy and other
generation (e.g. Procurement
Programmes)
• DoE is also encouraging power
generation by other IPP means
(Wheeling, Self-Generation etc.)
Peaking – Pumped Storage, Hydro
2030
2010
Source: IRP2010 published in 2010 < www.doe-irp.co.za >
3
GAU facilitation role of the SMG framework
Pricing (costing) and Contracts
Process excellence: Application through to Operations
Billing and Cost recovery (Payments)
Technical (Eskom Group Techn and Dx)
Operations
IDM & Renewable Integration
• Use GAU to manage service
relationship, stakeholder
management and interfaces related
to SMG’s in the interim until the
framework is finalised.
• Define and implement technical rules
for evaluation, connection and
operation.
• Develop an optimised SMG IPP
connection process
• Define operations process for SMG
• Resolve pricing policy and cost
recovery issues
• Build IPP intelligence framework and
capability (inside and out)
• Establish resource capability to
integrate SMG’s across the business
Establish clear accountability
Improve Eskom’s image and reputation in dealing with SMG’s
Achieve non-discriminatory grid access for SMG’s
Effective organization with process excellence in SMG connection and operations
Communication
Area To Be Addressed AmbitionMeasures
4
5
6
7
Eskom process, related to the Eskom Grid Access Unit role
Quotation, Contracting
and Connection of
IPPs
Consultation with, and advising IPPs
Operation of IPPs and
generators
Manage service relationships with IPPs and generators
Facilitate Grid Access for generators
The role of Eskom Grid
Access Unit for Generators
• Enabling and facilitating generators (including IPPs) grid access, giving effect to commercial options
requires a service relationship, interface management and communication.
• Managing and integrating the development of appropriate standards, processes, frameworks.
• Facilitating various connection, grid access and commercial options.
• Pricing frameworks for generators (e.g. costing of connection and “wheeling”).
• Developing technical capability for integration of the IPPs and renewable generators.
• Enabling process and system capability, and facilitation thereof, to ensure grid access.
• Collecting sufficient data and information, to effectively facilitate, enable, plan and support.
• Ensuring long-term viability of the Eskom approach.
Application
• All applicants must complete Part 1 of the
Eskom application form in order to register
a project and obtain a invoice for the Cost
Estimate Letter - (High-level basic
information required).
• This is applicable to both Distributions and
Transmission applications
• Application will be submitted firstly to
Distribution and registered in ACNAC
(which is a Distribution project scheduling
tool for processing)
10
Customer category solutions
SMG Category – less than 1MW
Small power users Large power users
Prepaid Dedicated
Eskom
Transformers
Distributed
LV feeders
LPU 1: Eskom
supply at LV –
SMG at LV &
less than
100kW
LPU 3: Connected at MV – SMG at LV or MV
• No solution in
this phase
• Risk factor
low
• No solution in
this phase
• PILOT
PROJECT
• YES
• Use MACRO connection
process
• Provide options for:
1.Operating in island
mode
2.Convert supply to
MV for dedicated
transformer supplies
and use LPU 3
process
LPU 2: Eskom
supply at LV –
SMG at LV &
greater than
100kW
• Issue letter for
disconnection
and meter
changed out to
electronic
meter (if not
already done)
• NO
• Use INTERIM connection
process
3. Grid Connection Process for Generators including IPPs
SubmitPart 1 of
App. Form
Eskom
Generators
Provide Cost
Estimate Letter
Produce prelim design
and cost project
ProvideEIA
approval
Issue Budget Quote
Perform /ApproveDetailedDesign
ProcessPart 1 of App. Form
Accept Budget Quote
Perform Detailed Design (Self Build
Option)
Request EIA for project
Accept Cost
Estimate Letter & Submit
Part 2 of App. Form
1
2 3
4
5 6
7
8A
8B
Part 1 of
Application
Form contains
basic generator
contact details
and connection
requirements.
Application forms are
verified, captured on an
Eskom Generator system
and allocated to an IPP
Executive., upon receipt of
the CEL Fee Proof of
payment this application is
forwarded to the Network
Planning Department
A Grid or Network
Planner will assess the
network requirement of
the application. The IPP
Executive will then
compile and deliver a
Cost Estimate letter to
the IPP. The Cost
Estimate letter will
contain an estimate of
costs and timelines,
scope and quotation
fees.
On acceptance of the On acceptance of the
Cost Estimate letter
and payment, Part 2 of
the Application Form
(Detailed generator
technical information)
needs to be completed
and submitted to
Eskom.
request On receipt of request
to proceed to BQ and
payment, Eskom will
initiate preliminary
design and costing of
the project. Bidder
must have consulted
and agreed on
approach to secure
Eskom EIAs and
Servitudes.
A Budget Quote is compiled
based on the project cost, which
is delivered to the IPP. The BQ
will contain the Scope, Cost,
Timeframe and T&Cs. Eskom
BQ & and relevant agreements .
IPP accepts terms
and conditions of the
Budget Quote and
arranges payment.
Eskom will not
proceed with the
connection works
until payment is
received.
When Eskom
performs the
detailed design:,
Eskom completes
and approves the
detailed project
design.
When Generator performs
the detailed design, Eskom
approves the detailed
project design.
Grid Connection Process for Generators including IPPs (cont.)
Project Close Out (incl. Cost
Reconciliation)
Test & Commission connection
asset
Perform Detailed Design
Construct Connection Work (Self
Build Option)
Project Close out
Synchronise Network
AssetEskom
IPP
DEA
Construct Connection
Works
TestGenerator
8 9 10 11 12
The connection
work is completed. The constructed grid
connection will be tested
and commissioned by
Eskom.
The generator is synchronised to
the Eskom Grid. The constructed
IPP facility test certificates are
made available to Eskom who in
turn issues an operational
notification in writing to use the
system.
The project is
closed out, costs
reconciled and Bill
produced on the
billing system.
13
SMG: some pegs in the ground
• SMGs areprivate, grid tied generation < 1MW.
• There are three distinct categories viz.
• Category 1: Medium voltage (greater than 1,000V, but less than 33,000V),
• Category 2: Low voltage (less than 1,000V) with dedicated MV/LV Eskom transformers, and
• Category 3: LV on shared LV networks.
• In June 2014, a SMG Steering Committee (SMG SC) was established by GCS Manco, and supported by EXCO Ops.
14
SMG: some pegs in the ground (cont . )
• Eskom’s current stance:
• Technical options that are currently available for connection of Category 1are expensive and not always practical.
• As there are no SABS standards for connection of Category 2 and 3 types, connections would compromise safety in Dx Operations.
• Eskom has not given formal permission for connection of any of category 2 or 3, unless part of the pilot testing phase (which are category 2) (38). Many customers are not aware of these issues and this market is being aggressively driven by suppliers/installers of these types of generation.
• A bill insert (customer pamphlet) for all metered customers was issued in October 2014. The strategy of which was to empower customers with required understanding of the environment and curtail “illegal” connections being done.
Eskom Connection Agreements
• Budget Quote:
• is the basis for the costs and scope of the connection works.
• Connection and Use of System Agreement (ie. Distribution or Transmission):
• Technical : Dispatch, ancillary services
• Financial : responsibilities, price, invoicing
• Operations : ownership, events
• Legal : Liability, confidentiality, dispute resolution, force majeure, termination.
• Electricity Supply Agreement (ESA):
• Technical : auxiliary usage, temporary construction supply.
• Financial : responsibilities, price, invoicing
• Operations : ownership, events
• Legal : Liability, confidentiality, dispute resolution, force majeure, termination.
• Reconciliation Agreement / amendment to Electricity Supply Agreement if the IPP is
embedded (e.g. in a municipal network).
• For municipal connections the bidders need to contact and sign the required agreements with the relevant municipality.
• Direct Agreement
• Self Build Agreement
• Operating agreement
16
17
Further Inputs and Questions
Thank You