Page 1: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

Small Generation Interconnection Standards - IOU

Dennis ReedWestar Energy

Topeka, KSSeptember 26, 2007

Page 2: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

2

Summary

Generation Interconnections Large Generators Small Generators

Westar’s Standards Parallel Generation Rider (Small Gen) Facility Connection Standard SPP Interconnection Standards

Page 3: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

3

Generation Interconnections

Come in two types: Large Generators (20 MW or more)

Handled with the Southwest Power Pool interconnection standards (Attachment V)

Small Generators (<20 MW) Under state jurisdiction if a QF facility Under FERC jurisdiction if selling into the

wholesale market Any time you interconnect on the

Transmission System you must apply at the SPP or if the unit size or change in rating is 20 MW or more.

Page 4: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

4

Small Generators Defined as less than 20 MW If selling into the Wholesale markets

Under FERC rules Must comply with:

Host Utility interconnection standards Southwest Power Pool SGIA/SGIP rules

If Operating as a QF (most likely scenario) Under State rules Must Comply with:

Host Utility interconnection standards Follow State approved tariffs for payment for energy

Page 5: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

5

Westar’s procedures Facility Interconnection Standards

Applies to all generators connecting to the Westar North or South systems

Applies to all voltages Special rules apply for generators of 3000 kVA or

greater. Special rules also apply if generator has a

measurable impact on the local facilities Rules are to ensure the SAFE operation of the

Westar system Safety to Westar Employees Safey to the Public

Page 6: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

6

Costs

Customers are responsible for all costs associated with the interconnection Metering Protective relays Any equipment needed to meet ANSI,

NERC or related standards Engineering Studies Permits, licenses, etc.

Page 7: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

7

Special Equipment A second meter Possibly a different or second

transformer Automatic disconnects Fault current relays Other equipment may be required based

upon the Engineering study Transmission voltages (60 kV or higher)

require additional special equipment

Page 8: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

8

General Items Westar has the authority to disconnect the

generator from its system Customer must apply to Westar at least 120

days prior to interconnecting with the grid Westar can dictate power factor issues Standards also cover other special

circumstances related to the type of generator (ie Synchroous, Induction, Converter, etc.)

Your consultant should help you through these issues

Page 9: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

9

Facility Connection Standard

Standards can be found at:www.westarenergy.com1. Click on “About Us”2. Click on “Our Energy”3. Click on “view the Facility

Connection Standard” link about ½ way down the page

Page 10: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

10

Payments to Customer Payments to small QF’s is regulated by

the KCC Westar is in the Parallel Generation

Rider Follows state law Residential up to 25 kW Non-residential up to 100 kW Payment is based on 150% of the average

fuel cost of Westar North or Westar South Average Fuel cost: Nuclear, fossil, and Purchase

Power

Page 11: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

11

Southwest Power Pool Two similar sets of rules, Large Generator and

Small Generator Are required to request to SPP to interconnect

either a new unit or an upgrade greater than 20 MW

Small Generator rules apply only if the Generator is selling into the Wholesale Market QFs do not use the SGIA/SGIP rules unless

connecting to the transmission system SGIA/SGIP rules can apply to interconnections

made at the distribution level.

Page 12: Small Generation Interconnection Standards - IOU Dennis Reed Westar Energy Topeka, KS September 26, 2007

12