smcswtse-jcg-sbr-tm-pln-002258-f barangaroo stage 4 · 2018-10-31 · construction traffic...
TRANSCRIPT
Construction Traffic Management Plan Barangaroo Stage 4
Project: Sydney Metro City & Southwest – TSE Works
Document No: SMCSWTSE-JCG-SBR-TM-PLN-002258
DOCUMENT APPROVAL REVISION DATE PREPARED BY REVIEWED BY APPROVED
BY REMARKS
A 2 May 18 S Lewis Internal review
B 11 May 18 S Lewis T Ferrero S Burns For external review
C 20 June 18 S Lewis T Ferrero S Burns For approval
D 27 June 18 S Lewis T Ferrero S Burns Resubmitted for approval
E 3 July 2018 S Lewis T Ferrero S Burns Resubmitted for approval based on comments received from CoS (28 June) and SCO (27 June)
REVISION DATE PREPARED BY REVIEWED BY APPROVED BY
REMARKS
F 17 Oct 2018
S Lewis D McGarry S Burns For approval to change gates
Signature:
General CorrespondenceReference No: SMCSWTSE-RMS-GEN-000276Project Title: Sydney Metro City & Southwest - TSEDLM: Orig Ref No: SMCSWTSE-JCG-C_GEN-001990
Date: 22 October 2018, 10:28 AM Response required by:
From: Quac Minh LA (Roads and Maritime Services)
To: Christian Timney (John Holland CPB Ghella JV) ; Declan Mcgarry (John Holland CPB Ghella JV)
Cc:Sue Lewis (John Holland CPB Ghella JV) ; Berin Gordon (Sydney Metro) ; Giovanny Ramirez (Sydney Coordination Office) ; Anthony McMahon (Roads and Maritime Services) ; Carl Mella (Roads and Maritime Services) ; Phil Brogan (Sydney Metro)
Subject: RE: Barangaroo Stage 4 Amendment 1 - gate access changes
Contract No: -
Classification:
Christian / Declan,
SCO and RMS have reviewed the ‘Barangaroo Stage 4 CTMP – Rev F’. SCO has advised of their endorsement of the changes proposed in the Rev F submission.
Accordingly, RMS is satisfied to adopt the changes proposed in ‘SMCSWTSE-JCG-SBR-TM-PLN-002258-F Barangaroo Stage 4’ as approved, with the original ‘Conditions of Approval’ still being applicable.
Regards,Minh
Discipline: Logistics Management Area: Location: Barangaroo Station
----- Original Message -----
Contractor General Correspondence
Reference No: SMCSWTSE-JCG-C_GEN-001990Project Title: Sydney Metro City & Southwest - TSEDLM: Orig Ref No:
Date: 17 October 2018, 01:09 PM Response required by:
From: Sue Lewis (John Holland CPB Ghella JV)
To:
Quac Minh LA (Roads and Maritime Services) ; Shannon Souksavong (Roads and Maritime Services) ; Carl Mella (Roads and Maritime Services) ; Anthony McMahon (Roads and Maritime Services) ; Berin Gordon (Sydney Metro) ; Giovanny Ramirez (Sydney Coordination Office) ; Jake Coles (Sydney Coordination Office) ; Mark O'Shea (Barangaroo Delivery Authority) ; Justin Knight (Barangaroo Delivery Authority)
Cc:Declan Mcgarry (John Holland CPB Ghella JV) ; Christian Timney (John Holland CPB Ghella JV) ; Steve Burns (John Holland CPB Ghella JV) ; Steven Kotevich (John Holland CPB Ghella JV)
Subject: Barangaroo Stage 4 Amendment 1 - gate access changes
Contract No: -
Classification:
All
as discussed at the last TCG please find attached the above document for your approval
Sue
Discipline: Logistics Management Area: Location: Barangaroo Station
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 3 of 31
Table of Contents 1. Introduction ................................................................................................................. 5
1.1. Project Overview ......................................................................................................... 5
1.2. Purpose of this Plan .................................................................................................... 5
2. Locality and existing conditions ............................................................................... 6
2.1. Hickson Road .............................................................................................................. 7
3. Site operations ............................................................................................................ 7
3.1. Construction and traffic phases ................................................................................... 8
3.2. Works required .......................................................................................................... 11
3.3. Operating Conditions ................................................................................................. 11
4. Fleet Management ..................................................................................................... 15
5. Other Considerations ............................................................................................... 16
5.2. Police and Emergency Services ................................................................................ 16
5.3. Communications and the community ........................................................................ 16
5.4. Inspections and monitoring ....................................................................................... 20
5.5. Environmental Management ..................................................................................... 20
5.6. Site Contacts ............................................................................................................. 20
5.7. References ................................................................................................................ 20
Appendix 1 Implementation phases .................................................................................. 22
Appendix 2 Road design drawings ................................................................................... 23
Appendix 3 Temporary traffic drawings ........................................................................... 24
Appendix 4 Approved Traffic Control Signal Plan ........................................................... 25
Appendix 5 Traffic control plans ....................................................................................... 26
Appendix 6 Barging Access arrangement and Impact Assessment .............................. 28
Appendix 7 Haulage Routes ............................................................................................... 29
Appendix 8 Road Safety Audit ........................................................................................... 30
Appendix 9 Consultation and review comments ............................................................. 31
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 4 of 31
Figures Figure 1: Sydney Metro Project ................................................................................................ 5
Figure 2: Hickson Road construction site ................................................................................. 7
Figure 3: EIS routes ............................................................................................................... 15
Tables Table 1 Construction and traffic changes ................................................................................. 8
Table 2: Average vehicle movements per hour Phases 2-7 ................................................... 11
Table 3: Average vehicle movements post signals ................................................................ 12
Table 4 Proposed Communications ....................................................................................... 16
Table 5: Stakeholder Consultation ......................................................................................... 19
Table 6: Site contacts ............................................................................................................. 20
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 5 of 31
1. Introduction
1.1. Project Overview
The Sydney Metro is Australia’s biggest public transport project. The metro project currently consists of:
Stage one is the Sydney Metro Northwest, formerly the North West Rail Link, connecting the north western suburbs of Sydney, through to Chatswood.
Stage two is the City & South West project linking Chatswood through to Sydenham. Stage three includes the upgrade of the existing rail line between Sydenham and
Bankstown.
Figure 1 shows the proposed Sydney Metro project and stages.
Figure 1: Sydney Metro Project
1.2. Purpose of this Plan
The purpose of this Construction Traffic Management Plan (CTMP): BARANGAROO STAGE 4 is to detail the site operations for the phased introduction of the long-term work site at Barangaroo for the Sydney Metro City & South West project. This plan will set out the traffic management initiatives that will be deployed to minimise disruption to and ensure the safety of the wide range of stakeholders potentially affected by the works, including but not limited to: motorists, pedestrians; cyclists; public transport users, local residents and property owners; business owners; and workers/staff engaged on the Project.
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 6 of 31
The Barangaroo staging for the works will consist of the following:
Stage 1: Diversion of pedestrians to the western side of Hickson Road and barriers placed on the eastern existing edge line adjacent to southbound traffic. A pedestrian refuge island is to be constructed at the northern end of the site – refer to SMCSWTSE-JCG-SBR-CN-PLN-002257. Implemented November 2017 to January 2018.
Stage 2: Pedestrians retained on Stage 1 alignment. Barriers remain in place on the southbound carriageway with new barriers installed on the western side of the northbound carriageway – refer to SMCSWTSE-JCG-SBR-CN-PLN-002257. Implemented November 2017 to January 2018.
Stage 3: Pedestrians diverted through Block 7 to facilitate the piling works. Traffic laterally shifted to the west to allow commencement of station excavation and bridge works – refer to SMCSWTSE-JCG-SBR-CN-PLN-002259 Implemented January 2018 to June 2018.
Stage 3A – Northern Shaft works including installation of acoustic shed and associated works. Works proposed between April 2018 to May 2018 refer to SMCSWTSE-JCG-SBR-TM-PLN-002343
Stage 3 Addendum 1 – Diversion of southbound traffic at the northern end of site to facilitate construction of the western footing of the northern acoustic shed – refer to SMCSWTSE-JCG-SBR-CN-PLN-002259. Implemented March to April 2018. Please note that Stage 3 traffic layout was reimplemented following completion of the western footing
Barangaroo Bridge Works – details the requirements for traffic control during night time installation of bridge infrastructure elements for the eastern bridge – refer SMCSWTSE-JCG-SBR-TM-PLN-002353. Planned for implementation in June 2018
Stage 4: New bridge with traffic signals in operation under ultimate arrangement for the works. Traffic maintained along Hickson Road with pedestrians on the eastern side of the bridge with signalised pedestrian crossings across Hickson Road and site access points. THIS PLAN. CTMP to be implemented in phases between July 2018 and December 2018 and then remaining in place until February 2021.
Stage 4 Addendum 1: This CTMP may be developed depending on the impact to TSE's access/ egress once the developer has gained access to Block 7.
Stage 5: Demobilisation of the bridge and traffic signals. Implemented February 2021 to April 2021.
2. Locality and existing conditions
The Barangaroo station excavation site is within the road reserve of Hickson Road, south of Towns Place and north of the High Street stairs to the south, at Barangaroo. The main construction site is shown on Figure 2 below.
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 7 of 31
Figure 2: Hickson Road construction site
2.1. Hickson Road
Hickson Road is classified as a local road which is under the control of Barangaroo Delivery Authority between Napoleon Street and Windmill Street bridge. Outside of this location the City of Sydney is the responsible road authority. The road commences at Sussex Street to the south and continues to meet George Street at The Rocks. The speed limit on Hickson Road is currently signposted as 40km/hr.
Bus stops exists on the southern carriageway at the northern end of the site, south of Towns Place. The bus stop serves routes 311, 324 and 325.
Parking removal on both sides of Hickson Road was undertaken during Stages 1 and 2 of the works between the southern site boundary and the Munn Street over bridge. Further parking removal was completed in Stage 3 between the Munn Street and Windmill Street over bridges. Parking is available between the Windmill Street over bridge on the western side of Hickson Road and on the eastern side.
There is an existing footpath on the eastern side of Hickson Road between Windmill Street over bridge and Towns Place which is approximately 4m wide, this footpath provides access to the bus stop and premises. On the western side of Hickson Road pedestrians are diverted through Block 7 at the southern end of the site and have access back to Hickson Road through a dedicated pathway within the construction site and immediately adjacent to the Universal Studios carpark. Cycling facilities on this section of Hickson Road north of the construction site were removed as part of the Stage 3 works implementation.
3. Site operations
Duration of implementation: 6 months
Timing of implementation July 2018 to December 2018
Timing of operations December 2018 to February 2021
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 8 of 31
3.1. Construction and traffic phases
The site operations will be installed progressively between June and December 2018. The phases for the construction works and the corresponding traffic and access/ egress changes are detailed below in Table 1 and the corresponding drawings are included in changes Appendix 1.
Table 1 Construction and traffic changes
PHASE AND TIMING CONSTRUCTION PHASE TRAFFIC PHASE ACCESS/ EGRESS/ TRAFFIC CONTROL DRAWINGS
Phase 1 – switch to new bridge
1-2 night shifts
Remove barriers at northern and southern tie ins
Line marking removal and installation
Install temporary barriers on the western side of the bridge across the temporary southern ramp area and ramp area to 25 Hickson Road
Minor asphalt works at both tie in areas
Traffic lanes = 3.2m on bridge
Traffic shifted to the new bridge
Pedestrians maintained on Block 7 diversion
Loss of site access to the western side and access to 25 Hickson Road
Stop/ slow required during works
Pedestrian management required during tie in works at southern end
Appendices 1 and 5
Phase 2
Weekend 1 – day shifts
Construct the southern temporary ramp
Construct ramp from bridge to 25 Hickson Road
Remove temporary barriers on the western side across the temporary southern ramp and ramp access to 25 Hickson Road areas once completed
No change to pedestrian/ traffic layout from previous phase
As per previous phase Appendix 5
Phase 3
Post Weekend 1
Approximately 2 months depending on archaeological finds recorded
Commence archaeological investigations at the northern and central part of the bridge
Once investigations are completed, commence construction of the permanent ramps at the northern and central locations
No change to pedestrian/ traffic layout from previous phase
Vehicle access/ egress via southern temporary ramp – left in/ left out/ right out/ right in from southbound Hickson Road.
Stop/ slow required at northern end of Hickson Road for northern shaft works – facilitates a G turn manoeuvre (mimics the ultimate signal arrangement)
Access into 25 Hickson Road via left turn in/ out and right turn in from southbound carriageway required for commercial
Appendices 1 and 3
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 9 of 31
PHASE AND TIMING CONSTRUCTION PHASE TRAFFIC PHASE ACCESS/ EGRESS/ TRAFFIC CONTROL DRAWINGS
garbage truck between midnight and 4AM and limited tenant numbers during the weekday
Pedestrian management at Block 7 pathway and truck access to barging facility
Phase 4
1 night shift to complete tie in and in operation for 2 months
Complete the central ramp No change to pedestrian/ traffic layout from previous phase except for split of access/ egress
Access and egress via Central ramp – will require stop/ slow at a revised location, no egress via southern temporary ramp
There will be only one vehicle movement at any time. These movements will be controlled by the installation of barriers within the site to control movements out with two way notice to security of approaching heavy vehicles.
Semitrailer movements are limited at this stage of construction and estimated at 1 per hour maximum
All other movements as per previous phase
Appendices 1, 3 and 5
Phase 5
1 day shift to complete tie in and in operation for 1 week
Complete the northern ramp No change to pedestrian/ traffic layout from previous phase except for split of access/ egress
Access via North ramp this mimics the ultimate signal arrangement using Stop/ slow operations
Access/ egress for 25 Hickson Road remains unchanged from previous phase
Appendices 1, 3 and 5
Phase 6
1 week
Complete permanent barriers across the southern temporary ramp – reinstate temporary barriers as per Phase 2 for duration and then remove at completion
No change to pedestrian/ traffic layout from previous phase
Stop/ slow required during works Appendices 1, 3 and 5
Phase 7
1 week
Complete the construction of the footpath on the eastern side of the bridge
Remove line marking and install ultimate arrangement
No change to pedestrian/ traffic layout from previous phase
Stop/ slow required during works Appendices 1, 3 and 5
Phase 8
2 weeks
Install remaining signal posts and islands
Commission signals Access/ egress as per ultimate arrangement Appendices 1, 2 and 4
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 10 of 31
PHASE AND TIMING CONSTRUCTION PHASE TRAFFIC PHASE ACCESS/ EGRESS/ TRAFFIC CONTROL DRAWINGS
Phase 9
Overnight 1st Quarter 2019 for approximately 4 nights
Removal of bridge bearings required to facilitate demolition of central piles during station excavation
Road closure overnight No vehicle or pedestrian access during these works Appendix 5
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 11 of 31
3.2. Works required
Works to be undertaken during the operation of this CTMP include:
Completion of piling and pile caps Archaeology Construction of northern and central crossovers Ground anchors Continuation of installation of TBM support facilities Excavation of the cross over cavern including shotcreting works Station box excavation
3.3. Operating Conditions
Traffic will be switched onto the new bridge overnight. The bridge will generally have 3.2m traffic lanes with localised lane widening at the southern temporary ramp location. The footpath on the bridge will not be available until the traffic signals are commissioned (December 2018), pedestrian access is maintained along the Block 7 diversion. The majority of the footpath will be constructed but the section opposite the southern temporary ramp and south of this location will be constructed at a later phase immediately prior to the commissioning of the signals. At the southern and northern ends, temporary barriers will be in place during the construction of the temporary southern ramp and access ramp to 25 Hickson Road, refer to Appendix 3. These works will occur over a weekend. Once these works are completed, the barriers will be removed. Traffic will generally be on a straight other than at the southern access ramp where traffic will be shifted to the east over the future footpath area. Traffic arrangements for the majority of the phases remains constant other than the changes of the access/ egress requirements as noted in Table 1. For phase 8, the traffic signals at the intersection of Hickson Road and the site access/ egress for the northern site will be commissioned, refer to Appendix 4 for the approved signal plan and Appendix 2 for the Local Area Works drawings showing the ultimate traffic and pedestrian arrangements for Barangaroo Stage 4. .
Phase 9 requires the removal of bridge bearings from on top of the temporary piles supporting the Hickson Road bridge. This work requires the synchronised lifting of groups of girders with hydraulic jacks under the bridge to free up the bearings for removal. This work cannot be completed under traffic as the jacks are unable to cope with the dynamic loads from traffic. This work will require road closures on four separate nights. Pedestrians will be diverted during these works.
3.3.1. Impact on Traffic Flows
Trucks will use the temporary asphalt ramp at the southern end of the site for both access and egress until the works are completed at the northern and central ramps. Vehicles will be able to turn left in/ left out/ right out, (swept paths are provided in Appendix 3) and turn right into site from Hickson Road southbound carriageway. This access is shown in Appendix 6.
Table 2 provides a comparison of the EIS and TSE traffic movements at the site during Phases 2-7. These numbers are similar to the traffic generation during Stage 3 operations.
Table 2: Average vehicle movements per hour Phases 2-7
TIME EIS LIGHT VEHICLES
TSE LIGHT VEHICLES
EIS HEAVY VEHICLES
TSE HEAVY VEHICLES
0700-1000 2 2 6 5
1000-1200 10 8 26 22
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 12 of 31
TIME EIS LIGHT VEHICLES
TSE LIGHT VEHICLES
EIS HEAVY VEHICLES
TSE HEAVY VEHICLES
1200-1400 10 8 26 22
1400-1600 5-10 8 6-26 22
1600-1800 2 2 6 5
1800-0700 2 6 5
For vehicles accessing the northern shaft site, traffic will turn left out of site and continue to the northern end to use the slip lane (constructed as part of the signal arrangement) to allow the G-turn movement required to access the northern shaft site. Once within the site, trucks willreverse into the loading area. When loaded, trucks will turn left onto Hickson Road southbound.There are anticipated to be approximately 6 number of trucks undertaking this movement perhour.
Appendix 6 also contains the Construction Traffic Impact Assessment (CTIA) for the signal operations. This assessment has been previously provided to RMS during the WAD design review process for the Hickson Road signals. As noted the signal phase timings allows for 12 second stoppages of Hickson Road for the egress from site. The proposed stop/ slow operations would mimic this timing. As noted in the CTIA, the 95%ile queues would not extend to adjacent intersections, Towns Place and Watermans Quay and the delays to traffic are expected to be within 5 seconds to both north and southbound traffic. Coordination of the various stop/ slow operations along Hickson Road will be undertaken via radio communications between the on-site traffic controllers. This would mean that traffic would only be stopped once whilst travelling along Hickson Road, either at the northern end or at the ramp access point(s).
Table 3 provides a comparison of EIS and TSE traffic numbers post the commissioning of the signals.
Table 3: Average vehicle movements post signals
TIME EIS LIGHT VEHICLES
TSE LIGHT VEHICLES
EIS HEAVY VEHICLES1
TSE HEAVY VEHICLES
0700-1000 2-10 3 12-50 12-47
1000-1200 10 3-10 50 47
1200-1400 10 10 50 20-47
1400-1600 10 10 12-50 12-20
1600-1800 2-10 12 12
1800-0700 0-2 2 12 12
The closure of Hickson Road will have a moderate impact on traffic flow. Traffic will be redirected via Napoleon Street and onto Kent Street and back onto Argyle Street and then onto Towns Place to regain access to Hickson Road. The southbound route is the northbound route but in reverse. It is proposed that these road closures be undertaken at night when traffic volumes are lower. The schedule of the road closure will consider the schedule of cruise ship dockings at the Overseas Passenger Terminal, refer to https://www.portauthoritynsw.com.au/cruise/cruise-schedule/
1 Vehicle numbers are based on EIS station and tunnel excavation occurring simultaneously
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 13 of 31
3.3.2. Impact on Public Transport
At night the works are proposed to commence from 2000 through to 0500. The 311 bus service operates every 30minutes and ceases at midnight recommencing at 0615. The 324 and 325 are more frequent services operating between 0530 and 0200 – later during the night the services go from every 15 minutes out to an hour. The service frequency increases on a Friday night. Works are also proposed over a weekend using stop/ slow operations – this has been undertaken on a number of occasions with no adverse feedback from bus operators received.
For the full closure of Hickson Road, bus services 311, 324 and 325 will be rerouted via the general traffic detours noted in Section 3.3.1. From discussions with Sydney Buses, this detour has been successfully used previously during Hickson Road closures implemented by others.
For the inbound routes of 324, 325 the newly installed bus stop on Towns Place will be used. A new southbound bus stop will be placed on Kent Street as previously required by Sydney Buses and SCO. For the outbound routes of 324 and 325 there is no change to the current bus stop arrangements.
For the inbound route of 311, Kent Street will be used in lieu of Hickson Road. Buses will turn left from Argyle Street into Kent Street and access Hickson Road via Napoleon Street. The bus stop currently on Dalgety Road, immediately west of Kent Street will be closed, another bus stop exists on Argyle Street approximately 70m to the east. For the outbound route, buses will turn right from Kent Street onto Argyle Street. The bus stop unable to be serviced via the 311 is the bus stop on Towns Place which will be serviced by routes 324 and 325.
Outside of the short-term impacts, there are no other impacts to public transport operations. Appendix 9 contains Sydney Buses agreement to 3.2m lanes on the bridge and 3.3m through the curve at the southern end for Phases 1-7.
3.3.3. Impact on Pedestrians and Cyclists
Pedestrians will be retained on the current Block 7 alternate pathway opened for use for Barangaroo Stage 3. This pathway will be retained until the traffic signal commissioning. Cyclists who continue to use the general traffic lanes on Hickson Road will be impacted as per Section 3.3.1.
Pedestrian management will be required during the tie in works of the bridge to Hickson Road and during the jacking operations. This will require the temporary diversion of pedestrians to the south of the current marked foot crossing via the H4 gate into Lendlease under traffic control. These works will be conducted at night when the gate is not in use.
3.3.4. Impacts on commercial and residential access
There will be no impact on existing commercial and residential access. Please note that other contractors along Hickson Road do not typically work at night.
Current occupants of 25 Hickson Road are businesses that operate weekdays only and the TSE contractor. Therefore, works over a weekend will not impact on any access/ egress requirements. Consultation with these businesses will be ongoing.
3.3.5. Cumulative impacts
The current BDA work sites will continue to operate with access/egress located south of the Sydney Metro site. Initially, access to and egress from works on the western side of Hickson Road are a minimum distance of 80 m north of the existing access of the most northern BDA contractor access point and will therefore not interfere with their access. With the
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 14 of 31
construction of the northern and central access ramps, the distance between work sites will be greater. The access/ egress requirements for the Block 7 developer are currently unknown.
Regular meetings are held with all parties with work sites on Hickson Road. BDA is the permit issuer for works on Hickson Road for all parties. TSE will continue to coordinate works through the BDA permit process.
3.3.6. Special Events
During the life of this CTMP, there are a number of known scheduled special events. TSE will continue to coordinate with BDA, SCO and TMC.
3.3.7. Traffic Control Plan (TCP) / Road Occupancy License (ROL) Identified Works
Works that have been identified as requiring a Traffic Control Plan are detailed below. Appendix 5 provides timing for implementation; the works being undertaken and the expected traffic impacts.
1. Stop/ slow operations on Hickson Road at various locations
2. Pedestrian management prior to the traffic switch to the new bridge
3. Pedestrian management at the barge truck crossing point
4. Road closure
5. Oversize and over mass deliveries to site
3.3.8. Sydney City Council required approvals
Works that have been identified as requiring Council approval include:
1. Oversize and over mass deliveries to site
2. Temporary road closure application
3. Overnight change to parking restrictions on Kent Street to facilitate bus stop relocations
All application forms and guidelines are available on the City of Sydney website
City of Sydney Forms and Publications
3.3.9. Barangaroo Delivery Authority required permits
Works that have been identified as requiring BDA approval include:
1. Stop/ slow operations on Hickson Road
2. Pedestrian management prior to the traffic switch to the new bridge
3. Pedestrian management at the barge truck crossing point
4. Temporary road closure application
5. Oversize and over-mass deliveries
3.3.10. RMS Works Authorisation Deed requirements
Works that have been identified as requiring RMS approval include:
1. Hickson Road traffic control signals
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 15 of 31
4. Fleet Management
Trucks to be used on the project will be compliant with NSW legislation and standards including the Heavy Vehicle National Legislation. A combination of truck types will be used during the works including semi-trailers, truck and trailers, flatbed trucks etc. Bogie tippers will be used for the barging operation.
4.1. Haulage Routes
Generally, the haulage routes will be via arterial roads/ freeway or Tollway. Where possible the routes have taken into account the requirements of the Environmental Impact Statement (EIS). Where the routes differ from that in the EIS, the routes chosen are based on the availability of the arterial road system and these are detailed in this CTMP.
The EIS routes are shown in Figure 3 below:
Figure 3: EIS routes
Spoil will be loaded onto the barge at Barangaroo and taken to Clyde, refer to SMCSWTSE-JCG-TPW-TM-PLN-002360 Clyde Transfer Facility CTMP. Refer to Appendix 7 for details on the proposed routes to the nearest arterial road/ motorway.
4.2. Permits/ Over Dimensional Vehicles
Permit issue for vehicles greater than 45.5 tonnes is through the National Heavy Vehicle Regulator (NHVR). This applies to particular special purpose vehicles (SPV) such as mobile cranes and other oversize/over mass vehicles (OSOM). At present, RMS is currently undertaking this permit issue for State Roads and Motorways whist local councils provide the permits for local and regional road travel.
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 16 of 31
For over dimensional vehicles, generally vehicles that are greater than 25m length or 3.5m width require a pilot(s). Extremely long or wide vehicles will require an escort (fee payable). Permits will be applied for by the transport operator to RMS and City of Sydney Council. These deliveries will occur at night.
There is a requirement for over mass deliveries:
Delivery of girders for completion of the northern and central crossovers (≈25#)
5. Other Considerations
5.1. Road Safety Audits
Road safety audit has been undertaken during the development of the CTMP and where long-term work sites are required. Refer to Appendix 8.
5.2. Police and Emergency Services
The Police and relevant Emergency Services will be informed in a timely manner of relevant activities proposed within this CTMP. The initial communication to these stakeholders will be via the Traffic and Transport Liaison Group (TTLG). Regular updates will be provided to emergency services, including changes to road network configurations, changes to road conditions and worksite access locations, through emails and face to face discussions.
5.3. Communications and the community
The TSE will be responsible for the dissemination of information to the community including affected residents, relevant Councils, businesses and the public. Refer to Sydney Metro Community Consultation Strategy – Early Works.
Any enquiries, complaints and/ or compliments are to be directed to the TfNSW’s Sydney Metro Project Information line - 1800 171 386 or via email to: [email protected] or Sydney Metro City & Southwest, PO Box K659, Haymarket, NSW 1240 or Sydney Metro City & Southwest Website.
Table 4 provides the proposed communications to be implemented for this CTMP
Table 4 Proposed Communications
NOTIFICATION APPLICABLE
Community notice YES
Precinct update/ e-update YES
Email YES
Internet YES
On site briefings YES
Variable message signs YES
Advanced warning signs YES
5.3.1. Travelling public
Where our works will impact on the travelling public we will undertake the following, where detailed in this CTMP:
Public transport interruptions will be communicated via on site signage
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 17 of 31
Motoring public will be forewarned of any changes, including road closures, road changesand lane closures well in advance using appropriate signage, including variable messagesigns (VMS)
Pedestrians and cyclists will be provided with advance warning signs
5.3.2. VMS Traffic switch
VMS will be installed 5 days prior to the works at both the northern and southern ends of Hickson Road, as shown in Appendix 5. This VMS will display the following pre-works message:
FRAME 1 FRAME 2
HICKSON
RD
CHANGES
DD/ MM
2018
VMS messages will be changed on the morning of the changes and will display the following messages:
FRAME 1 FRAME 2
CHANGED
TRAFFIC
CONDTONS
REDUCE
SPEED
5.3.3. VMS Hickson Road closure
Hickson Road
Two VMS will be installed 5 days prior to the closure of Hickson Road. One at the northern end of Hickson Road around Townes Place and another at the southern end north of the pedestrian crossing for the pre-works message – refer to Appendix 5 for location details.
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
DD MM YY
HH TO
HH
During the closure, VMS will be located prior to the closure points and will display:
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
USE
DETOUR
AHEAD
VMS Dalgety Road
A VMS will be installed 5 days prior to the closure of Hickson Road on Dalgety Road for traffic into the city or south of the CBD. The VMS will be installed between Windmill Street and Towns Place. refer to Appendix 5 for location details. The following message will be displayed.
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 18 of 31
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
DD MM YY
HH TO
HH
During the closure, VMS will be located as per the pre-message location. Motorists not wanting to continue to The Rocks will be able to perform a U-turn at the roundabout at the intersection of Dalgety Road and Towns Place. The VMS will display the following message:
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
NO RIGHT
TURN
HICKSON
VMS Kent Street
A VMS will be installed 5 days prior to the closure of Hickson Road on Kent Street, south of Napoleon Street. Refer to Appendix 5 for location details. The following message will be displayed:
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
DD MM YY
HH TO
HH
During the closure, VMS will be located as per the pre-message location. The VMS will display the following message:
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
NO RIGHT
TURN
HICKSON
VMS Margaret Street
A VMS will be installed 5 days prior to the closure of Hickson Road on Margaret Street, east of Kent Street. Refer to Appendix 5 for location details. The following message will be displayed:
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
DD MM YY
HH TO
HH
During the closure, VMS will be located as per the pre-message location. The VMS will display the following message:
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 19 of 31
FRAME 1 FRAME 2
HICKSON
ROAD
CLOSED
NO RIGHT
TURN
HICKSON
5.3.4. Stakeholders consulted
Table 5 identifies the stakeholders consulted during the development of this CTMP:
Table 5: Stakeholder Consultation
STAKEHOLDER DATE CONSULTATION MAIN CONTACT PEOPLE
Lendlease 12 Apr 18 Presentation of CTMP phases
Murray Graham/ Martin Parkinson
TCG 23 Mar 18 Presentation of CTMP phases
SCO/ TfNSW/ Councils/ RMS/ BDA
RMS 11 May 2018 Submission of CTMP Carl Mella
City of Sydney Council
11 May 2018 Submission of CTMP Tony Ly/ Van Le
SCO 11 May 2018 Submission of CTMP Giovanny Ramirez/ Aaron Gale/ Justine Bryant
TfNSW 11 May 2018 Submission of CTMP Berin Gordon
Barangaroo Delivery Authority
11 May 2018 Submission of CTMP Justin Knight/ Mark O’Shea
RMS 20 June 2018 Resubmission of CTMP Carl Mella
City of Sydney Council
20 June 2018 Resubmission of CTMP Tony Ly/ Van Le/ Asad Rajbhoy
SCO 20 June 2018 Resubmission of CTMP Giovanny Ramirez/ Aaron Gale/ Justine Bryant
TfNSW 20 June 2018 Resubmission of CTMP Berin Gordon
Barangaroo Delivery Authority
20 June 2018 Resubmission of CTMP Justin Knight/ Mark O’Shea
RMS 27 June 2018 Resubmission of CTMP Carl Mella
City of Sydney Council
27 June 2018 Resubmission of CTMP Tony Ly/ Van Le/ Asad Rajbhoy
SCO 27 June 2018 Resubmission of CTMP Giovanny Ramirez/ Aaron Gale/ Justine Bryant
TfNSW 27 June 2018 Resubmission of CTMP Berin Gordon
Barangaroo Delivery Authority
27 June 2018 Resubmission of CTMP Justin Knight/ Mark O’Shea
RMS 3 July 2018 Resubmission of CTMP Carl Mella
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 20 of 31
STAKEHOLDER DATE CONSULTATION MAIN CONTACT PEOPLE
City of Sydney Council
3 July 2018 Resubmission of CTMP Tony Ly/ Van Le/ Asad Rajbhoy
SCO 3 July 2018 Resubmission of CTMP Giovanny Ramirez/ Aaron Gale/ Justine Bryant
TfNSW 3 July 2018 Resubmission of CTMP Berin Gordon/ Edward Borgos
Barangaroo Delivery Authority
3 July 2018 Resubmission of CTMP Justin Knight/ Mark O’Shea
RMS 17TH Oct 2018 Resubmission of CTMP Carl Mella
City of Sydney Council
17TH Oct 2018 Resubmission of CTMP Tony Ly/ Van Le/ Asad Rajbhoy
SCO 17TH Oct 2018 Resubmission of CTMP Giovanny Ramirez/ Aaron Gale/ Justine Bryant
TfNSW 17TH Oct 2018 Resubmission of CTMP Berin Gordon/ Edward Borgos
Barangaroo Delivery Authority
17TH Oct 2018 Resubmission of CTMP Justin Knight/ Mark O’Shea
5.4. Inspections and monitoring
The site will be monitored by the site supervisor. Any changes as noted in this CTMP, to signs/ lines that impact on the public will be monitored daily during site operating hours.
Traffic control used for pedestrian management, lane closures etc. will need to provide records of the traffic control implemented. Any changes required to the traffic control set up will be authorised by a holder of an RMS “Prepare a Work Zone Traffic Management Plan” or equivalent.
5.5. Environmental Management
All works will be undertaken in accordance with the TSE Construction Environmental Management Plan (SMCTSE-JCG-TPW-EM-PLN-002010) and associated sub plans including the Construction Noise and Vibration Management Plan (SMCSTSE-JCG-TPW-EM-PLN-002012). The TSE Works are also regulated by the NSW Environment Protection Authority and works to be undertaken outside of standard construction hours will need to comply with the requirements of the Environment Protection License.
5.6. Site Contacts
Table 6: Site contacts
NAME POSITION CONTACT #
Steven Kotevich Construction Manager
Shane Stewart Project Engineer
Graeme King Superintendent
Sydney Metro Traffic Team phone
5.7. References
The following documents were used in the development of this CTMP:
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 21 of 31
Construction Traffic Management Framework – TfNSW, v2.5 provided 22nd December2017
Principal’s General Specification G10 Traffic and Transport Management, v2.0 Roads and Maritime Service Traffic Control at Worksites Manual v 4.0 Relevant AustRoads Guides and RMS Supplements Sydney Metro Principal Contractor Health and Safety Standard Clyde Transfer Facility CTMP SMCSWTSE-JCG-TPW-TM-PLN-002360
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 22 of 31
Appendix 1 Implementation phases
DRAWING NUMBER DESCRIPTION
SMCSWTSE-CST-SBR-SLYT-100 Sheets 1-8 Temporary Works Site Layout
CHANGE TO SHEET 4 of 8 – OTHER SHEETS NOT INCLUDED AS PREVIOUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 23 of 31
Appendix 2 Road design drawings
DRAWING NUMBER DESCRIPTION
SMCSWTSE-JAB-SBR-LW-DRG-532010 Local Area Works Overview Plan
SMCSWTSE-JAB-SBR-LW-DRG-532011 Local Area Works General Arrangement Plan Sheet 1
SMCSWTSE-JAB-SBR-LW-DRG-532012 Local Area Works General Arrangement Plan Sheet 2
SMCSWTSE-JAB-SBR-LW-DRG-532013 Local Area Works General Arrangement Plan Sheet 3
SMCSWTSE-JAB-SBR-LW-DRG-532014 Local Area Works General Arrangement Plan Sheet 4
SMCSWTSE-JAB-SBR-LW-DRG-532015 Local Area Works General Arrangement Plan Sheet 5
NOT INCLUDED AS PREVIOUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 24 of 31
Appendix 3 Temporary traffic drawings
DRAWING NUMBER DESCRIPTION
SMCSWTSE-JAB-SBR-TM-DRG-534971 Traffic Management Stage 4 Traffic Staging Plan Sheet 1 of 5
SMCSWTSE-JAB-SBR-TM-DRG-534972 Traffic Management Stage 4 Traffic Staging Plan Sheet 2 of 5
SMCSWTSE-JAB-SBR-TM-DRG-534973 Traffic Management Stage 4 Traffic Staging Plan Sheet 3 of 5
SMCSWTSE-JAB-SBR-TM-DRG-534974 Traffic Management Stage 4 Traffic Staging Plan Sheet 4 of 5
SMCSWTSE-JAB-SBR-TM-DRG-534975 Traffic Management Stage 4 Traffic Staging Plan Sheet 5 of 5
JCG-SBR-TM-DRG-002258-0001 General Notes and Legend for drawing 002258-0027
JCG-SBR-TM-DRG-002258-0027 Barrier arrangement at northern end during ramp construction for 25 Hickson Road and traffic signal island works
NOT INCLUDED AS PREVIOUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 25 of 31
Appendix 4 Approved Traffic Control Signal Plan
DRAWING NUMBER DESCRIPTION
DS2017/002795 Approved Traffic Control Signal Plan
Swept paths previously provided to RMS
NA Overlay of traffic islands
NOT INCLUDED AS PREVIOIUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 26 of 31
Appendix 5 Traffic control plans
TCP # LOCATION FROM TO TIMING TRAFFIC CONTROL
WORKS IMPACTS
TCP-SBR-HIC-AL-1110 Hickson Road
Towns Place Bridge area Nights/ weekends
Phase 1
Stop Slow Traffic switch tie in works
Barrier removal/ installation
Line marking removal and installation
Minimal impact to traffic operations as works are undertaken at night/ weekends when traffic volumes are low
TCP-SBR-HIC-AL-1111 Hickson Road
North of Waterman Quay
Bridge area Nights/ weekends
Phase 1
Stop/ slow
Pedestrian management
Traffic switch tie in works
Barrier removal/ installation
Line marking removal and installation
Minimal impact to traffic operations as works are undertaken at night/ weekends when traffic volumes are low
TCP-SBR-HIC-AL-1112 Hickson Road
North of Waterman Quay
Bridge area Nights/ weekends
Phase 1
Stop/ slow
Pedestrian management
Traffic switch tie in works
Barrier removal/ installation
Line marking removal and installation
Minimal impact to traffic operations as works are undertaken at night/ weekends when traffic volumes are low
TCP-SBR-HIC-AL-1113 Hickson Road
Near pedestrian crossing at southern end
All hours
Phase 2
Pedestrian management
Access/ egress during southern temporary ramp construction
Girder delivery
Minimal impacts as pedestrian access retained
TCP-SBR-HIC-AL-1114 Hickson Road
Northern shaft site
All hours
Phases 3-8
Stop. Slow G-turn movement from western side
Impacts similar to ultimate signal operation
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 27 of 31
TCP # LOCATION FROM TO TIMING TRAFFIC CONTROL
WORKS IMPACTS
TCP-SBR-HIC-AL-0001 Block 7 At truck crossing point
All hours
Phases 3-8
Pedestrian management
Access. Egress from barging area and northern shaft
Minor impact to pedestrian movements.
TCP-SBR-HIC-AL-1115 Hickson Road
Central Ramp
All hours
Phases 4-8
Stop/ slow Egress from western site
Minimal impacts as vehicle egress
TCP-SBR-HIC-AL-1116 Hickson Road
Southern end of bridge
North of southern temporary access ramp
Nights/ weekends
Phases 6&7
Stop/ Slow Footpath construction
Minimal impact to traffic operations as works are undertaken at night/ weekends when traffic volumes are low
JCG-SBR-TM-DRG-02343-0004 to 0008
Hickson Road
South of Towns Place
Waterman Quay
Nights/ weekend
Phase 9
Road closure
Bridge jacking works
Minor impacts as undertaken at night
JCG-SBR-TM-DRG-002343-0003
Hickson Road
South of Towns Place
Waterman Quay
Nights/ weekend
Phase 9
Traffic Detour Route Overview
Bridge jacking works
Minor impacts as undertaken at night
TCP-SBR-HIC-AL-1119 Hickson Road
South of High Street stairs
Nights Phase 1 Pedestrian diversion
Tie in works Minor impacts to pedestrian movement
TCP-SBR-HIC-AL-0201 Hickson Road
The Cutaway
Watermans Quay
Nights
Phase 9
Pedestrian diversion
Bridge bearings removal
Associated with full road closure of Hickson Road
TCP-SBR-HIC-NB-1107 Hickson Road
Towns Place South of northern shaft
Nights/ weekends
Phase 8
Stop/ Stow Island and traffic signal works
Minimal impact to traffic operations as works are undertaken at night/ weekends when traffic volumes are low
NOT INCLUDED AS PREVIOUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 28 of 31
Appendix 6 Barging Access arrangement and Impact Assessment NOT INCLUDED AS PREVIOUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 29 of 31
Appendix 7 Haulage Routes
DRAWING NUMBER DESCRIPTION
SMCSWTSE-JCG-SBR-TM-DWG-002258-0001 Site to Anzac Bridge
SMCSWTSE-JCG-SBR-TM-DWG-002258-0002 Anzac Bridge to Site
SMCSWTSE-JCG-SBR-TM-DWG-002258-0003 Site to Harbour Bridge
SMCSWTSE-JCG-SBR-TM-DWG-002258-0004 Harbour Bridge to site
NOT INCLUDED AS PREVIOUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 30 of 31
Appendix 8 Road Safety Audit NOT INCLUDED AS PREVIOUSLY APPROVED
Construction Traffic Management Plan Barangaroo Stage 4
SMCSWTSE-JCG-SBR-TM-PLN-002258 Construction Traffic Management Plan Barangaroo Stage 4 Page 31 of 31
Appendix 9 Consultation and review comments NOT INCLUDED AS PREVIOUSLY APPROVED
Suite 2.06, Level 2 29-31 Solent Circuit Baulkham Hills NSW 2153 Tel: 61 (02) 9659 5433 e-mail: [email protected] Web: www.hbi.com.au
Leaders in Environmental Consulting
1
HBI Healthy Buildings International Pty Ltd A.C.N. 003 270 693 A.B.N. 39 003 270 693
Mr Stuart Hodgson 29 October 2018 Director Program Sustainability Environment & Planning Sydney Metro Transport for NSW PO Box K659 HAYMARKET NSW 1240 Ref: TSE CTMP BA Stage 4 Rev F
Dear Stuart
RE: Endorsement of Construction Traffic Management Plan – Barangaroo Stage 4 (Rev F): Sydney Metro City & Southwest – TSE Works Reference is made to the following documents required by the Condition of Approval E82 of the Sydney Metro City & Southwest project (SSI – 15_7400 January 9 2017) and submitted to the Environmental Representative (ER) for review and endorsement:
Construction Traffic Management Plan – Barangaroo Stage 4: Sydney Metro City & Southwest (Document SMCSWTSE-JCG-SBR-TM-PLN-002258 Revision F (dated 17 October 2018).
Email from the Sydney Coordination office (related to Rev E of the same document) dated 21 May 2018 stating “In accordance with Schedule C1 Appendix A.9 Section 2.1 ( c ) and 2.2 ( c ) of the Principal’s General Specifications G10 – Traffic and Transport Management and Minister’s Condition of Approval E82 for the Sydney Metro City & South West the Roads and Maritime Service of NSW and the Sydney Coordination Office approve the Sydney Metro City & South West Construction Traffic Management Plan – Barangaroo Stage 4 - TSE Works Rev E SMCSWTSE-JCG-SBR-TMPLN-002258 to detail the site operations for the phased introduction of the long term work site at Barangaroo for the Sydney Metro City & South East project”.
Email from RMS dated 22 October 2018 stating “SCO and RMS have reviewed the ‘Barangaroo Stage 4 CTMP – Rev F’. SCO has advised of their endorsement of the changes proposed in the Rev F submission. Accordingly, RMS is satisfied to adopt the changes proposed in ‘SMCSWTSE-JCG-SBR-TM-PLN-002258-F Barangaroo Stage 4’ as approved, with the original ‘Conditions of Approval’ still being applicable.”
The Roads and Maritime Service of NSW and the Sydney Coordination Office’s original approval was and remains conditional on the following requirements:
Obtaining Road Occupancy Licences (ROLs) from the Transport Management Centre (TMC) as required;
Leaders in Environmental Consulting
2
HBI Healthy Buildings International Pty Ltd
Complying with haulage routes as approved by SCO/RMS and described in Appendix 7 of the CTMP;
Addressing any safety issues identified in the Road Safety Audit review of this CTMP;
Addressing any issues raised by BDA, Council, State Transit, Taxi Council, residents/businesses, Emergency Services in the CTMP approval process;
Addressing the requirements arising as an outcome of the Local Pedestrian, Cycling and Traffic Calming Committee meeting;
Ensuring that appropriate resources are provided at short notice to manage traffic issues as a result of an emergency associated with the works; and
Promptly addressing any SCO and/or TMC and/or RMS issue that eventuates during the works.
As an approved ER for the Sydney Metro City & Southwest project, I have reviewed the revised document. The review did not comprise a technical review, as the ERs are not traffic experts and have relied on the SCO and RMS Approval for technical aspects of the Plan. It is noted the document provides review comments and responses in Appendix 9. It is considered that the revised plan remains consistent with Condition E82 of the Project Approval subject to the above conditions being complied with and is endorsed in accordance with Condition A24(d) of the Infrastructure Approval. Yours sincerely
Michael Woolley Environmental Representative – Sydney Metro – City and South West