Software Project Management Plan Hilal Engineers
ii
Change History
Major Field Achievement Test
SPMP Version 1.0 Release date: 02/09/11 Baseline Version
-
8/2/2019 Smt Spmp for Aets
3/30
Software Project Management Plan Hilal Engineers
iii
PREFACE
The purpose of this document is to specify the project plan to develop the Automated
Examination Timetable System (AETS). The primary audience is the project advisor, Madam
Marina Hassan, and other members of the faculty overseeing final projects. This document
outlines a brief plan about how the project is to be shaped and also includes the milestones and
deliverables. The SPMP document will serve as a guide for me the student, developing the
product as part of the project. Updates of this document will serve to record the progress of the
project.
-
8/2/2019 Smt Spmp for Aets
4/30
Software Project Management Plan Hilal Engineers
iv
ContentsChange History ............................................................................................................................................... iiList of Figures ................................................................................................................................................ v1.0. Overview ........................................................................................................................................... 2
1.0. Project Summary ........................................................................................................................... 21.1.1. Scope, Purpose and Objectives ................................................................................................. 2
1.1.2. Assumptions and Constraints ................................................................................................... 21.1.3. Project Deliverables .................................................................................................................. 31.1.4. Schedule and Budget Summary ................................................................................................ 3
1.2. Evolution of Plan ................................................................................................................................. 41.3. Project Responsibilities ....................................................................................................................... 4
References ...................................................................................................................................................... 5Definitions, Acronyms and Abbreviations ..................................................................................................... 6Project Organization ....................................................................................................................................... 7
4.0. External Interfaces ........................................................................................................................ 74.1. Internal Interfaces ......................................................................................................................... 74.2. Roles and Responsibilities ............................................................................................................ 7
Managerial Process Plans ............................................................................................................................... 85.1.2 Resource Allocation ................................................................................................................12
5.1.3 Budget Allocation ....................................................................................................................125.2.1 Requirements Control Plan ......................................................................................................125.2.2 Schedule Control Plan .............................................................................................................125.2.3 Budget Control Plan ................................................................................................................135.2.4 Quality Control Plan ................................................................................................................135.2.5 Reporting Plan .........................................................................................................................13
5.3. Risk Management Plan .......................................................................................................................136.0. Technical Process ...............................................................................................................................156.1. Process Model ....................................................................................................................................156.4. Product Acceptance Plan ....................................................................................................................16
7.0. Support Process Plans ......................................................................................................................177.1. Configuration Management Plan .................................................................................................177.2. Validation & Verification Plan ....................................................................................................17
7.3.
Documentation Plan .....................................................................................................................17
7.4. Quality Assurance Plan ................................................................................................................177.5. Problem Resolution Plan ..............................................................................................................187.6. Subcontractor Management Plan .................................................................................................187.7. Process Improvement Plan ...........................................................................................................18
Glossary of Terms .........................................................................................................................................19
-
8/2/2019 Smt Spmp for Aets
5/30
Software Project Management Plan Hilal Engineers
v
List of Figures
1. Figure 1. Schedule 42. Figure 2. Definitions, Acronyms and Abbreviations 53. Figure 3. Work Breakdown Structure (WBS) 84. Figure 4. Gantt Chart 19
-
8/2/2019 Smt Spmp for Aets
6/30
Software Project Management Plan Hilal Engineers
2
1.0. OverviewThis document defines the Software Project Management Plan for the Automated Exam
Timetabling System (AETS) product of Hilal engineers (HG). This plan is based on IEEE STANDARD
1058.1,Standard for Software Project Management Plans (ANSI).
1.0.Project Summary1.1.1. Scope, Purpose and ObjectivesThe Automated Examination timetable system (AETS) is an online system which will be
primarily used generate examination timetables. The AETS is being created for Universiti Selangor,
but is not restricted for application in the University. Meaning, it can be implemented in other
Institutions where the necessary infrastructure is in place. The AETS will be able to generate
timetables for each student from a general timetable, therefore students can search using their
names or student ID for a timetable which comprises of their registered subjects.
Examination timetabling is one of the most important administrative activities that take place in all
academic institutions. Hence, developing a system which will automate this activity using a well
formulated algorithm achieved through thorough referencing and research, will certainly ease the
task of examination timetabling. Currently, the examination timetabling is done using an almost
manual and rudimentary method, this allows for human errors which may stem from poor logic or
failure in having a good oversight of the variables involved in creating an efficient timetable.
Examination timetabling might seem like a trivial activity to many, however, there are quite some
significant researches which deal with the potential complexity of creating efficient timetables.
The researches which will be used to accomplish the development of the Automated Examination
System are cited under the references section.
1.1.2. Assumptions and ConstraintsThe author of this document is expected to complete the project within three semesters. This
project will use resources in the form of time and effort that will be spent developing the project
deliverables. The project will be completed under the guidance of a supervisor which is yet to be
appointed.
-
8/2/2019 Smt Spmp for Aets
7/30
Software Project Management Plan Hilal Engineers
3
There are constraints in the form of delay in receiving a dump of the current database been used by
the university, however, this is not a major constraint as itll be resolved in due time.
1.1.3. Project DeliverablesThe list of project deliverables is:
Software Project Management Plan (SPMP) Software Requirements Specification (SRS) Software Design Description (SDD) Software Quality Assurance Plan (including the Software Verification and Validation Plan and
the Test Design Document)
Working System1.1.4. Schedule and Budget Summary
Budget Summary: No budget required.
A tentative schedule is as shown below in table 1.
Figure 1: Schedule
Item Due date
Software Project Management Plan (this
document)
September 27, 2011
Software Requirements Specifications October 15, 2011
Software Design Document March, 2012
Software Quality Assurance and Verification &
Validation Plan
Fourth Quarter, 2012
Updated SPMP Fourth Quarter, 2012
Database May, 2012
Software Testing Description Fourth Quarter, 2012
System Integration First Quarter, 2013
-
8/2/2019 Smt Spmp for Aets
8/30
Software Project Management Plan Hilal Engineers
4
1.2. Evolution of Plan
The preliminary drafts of the SPMP will be submitted to my software modeling technique lecturer,
after which the plan will be updated, for each semester an update will be submitted to the lecturer
under which the project documentation is continued. The final SPMP will be submitted along with all
other documentations after completion of the implementation.
1.3. Project Responsibilities
There is one mentor, who is yet assigned from the faculty to the group. The mentor will also function
as the advisor and provide valuable guidance throughout the project. A technical advisor, an expert
from outside the university, will also available to the group.
The client in the project is the Examination unit, Universiti Selangor, represented by the Assistant
Registrar, Norhuda bt Rahmattullah.
Group: Hilal engineers
Project Leader: Shuaib Yunus
Project Manager: Shuaib Yunus
Programmer: Shuaib Yunus
Team Lead: Shuaib Yunus
-
8/2/2019 Smt Spmp for Aets
9/30
-
8/2/2019 Smt Spmp for Aets
10/30
Software Project Management Plan Hilal Engineers
6
Definitions, Acronyms and Abbreviations
The following list of acronyms is used throughout the document. Section 8 contains a glossary of
terminology used in the software industry.
Figure 2.0
Term Description
AETS Automated Exam Timetabling System
HE Hilal Engineers
UNISEL Universiti Selangor
CMMI Capability Maturity Model Integration
RDBMS Relational Database Management System.
SCMP Software Configuration Management Plan
SDD Software Design Document
SQAP Software Quality Assurance Plan
SRS Software Requirement Specification.
WBS Work Breakdown Structure
Stakeholder A person, group or organization with a stake in the outcome of an
application that is being developed.
TDB / tbd To be decided
-
8/2/2019 Smt Spmp for Aets
11/30
Software Project Management Plan Hilal Engineers
7
Project Organization
4.0.External InterfacesThe external interfaces for the project would be the assistant registrar of the Exam Unit of Universiti
Selangor, Norhuda bt Rahmattullah, who is the stakeholder for this project.
4.1. Internal InterfacesNone.
4.2.Roles and ResponsibilitiesThe software developer is responsible for all documentation to be developed and for all work to be
done.
-
8/2/2019 Smt Spmp for Aets
12/30
Software Project Management Plan Hilal Engineers
8
Managerial Process Plans
5.0. Work Plan
Work Breakdown Structure (WBS) (Figure 3.0)
WBS Task Name SPMP Creation Task ID 1
Description Create SPMP for the team project
Sub Tasks
1. Study SPMPs of other projects2. Identify a template3. Outline SPMP format and review it4. Identify all relevant information related to the project5. Gather data, other plans needed for SPMP6. Write SPMP7. Formal review of SPMP8. Receive review from lecturer9. Update with review comments
Entry Criteria
(Dependencies)
Task assignment;
Risk Plan, Estimation plan, Process Plan are all ready
Exit Criteria
(Output)Submit the final SPMP to the lecturer and Exam unit
Milestones SPMP Outline, SPMP draft, review SPMP, final SPMP for the semester
WBS Task NameSRS Creation
Task ID2
Description Create SRS for the team project
Sub Tasks
1. Start gathering requirements from the client (interviews, meetings)2. Get current exam timetabling creation data3. Study current method and identify unfulfilled requirements4. Identify the format for SRS, select a template5. Start populating SRS6. Call formal review7. Send it to client8. Incorporate lecturers comment9.
Submit the final SPMP to the lecturer and Exam unitEntry Criteria
(Dependencies)
Task assignment;
Contact with the client, Contact with the lecturer.
WBS Task Name Technical training and studying Task ID 3
DescriptionTechnical study of existing exam timetable creation method and research
works related to automated timetabling
Sub Tasks
1. Learning of JSP and related concepts of the java web-basedplatform.
2. Learning of JSP API
-
8/2/2019 Smt Spmp for Aets
13/30
Software Project Management Plan Hilal Engineers
9
3. Studying of current database architecture4. Gaining familiarity with the NetBeans for enterprise applications5. Study of mix format data parsing and comparison
Entry Criteria
(Dependencies)
Task assignment;
Environment set up
Exit Criteria
(Output)
Report about the API
NetBeans works
Milestones API study, report
WBS Task Name Software Design Task ID 4
Description Create Software Design of the project
Sub Tasks
1. Identify functionalities2. Create high level design3. Create low level designs4. Create interfaces5. Define algorithms and data structures6. Review design
Entry Criteria
(Dependencies)
Task assignment;
SRS ready, Architecture ready
Exit Criteria
(Output)Forward the design for implementation and testing
Milestones Design Outline, Design draft, review design, final design for the term
WBS Task Name System Test Plan Task ID 5
Description Create System Test Plan
Sub Tasks
1. Study other project plans and outline2. Write test cases for requirements3. Populate the plan4. Formal review the plan
Entry Criteria
(Dependencies)
Task assignment;
SRS ready; Architecture ready, Design Ready
Exit Criteria
(Output)Post the final plan on team web page
Milestones Plan Outline, Plan draft, review plan, final plan for the term
-
8/2/2019 Smt Spmp for Aets
14/30
Software Project Management Plan Hilal Engineers
10
WBS Task Name Software Test Report Task ID 6
Description Create a test report of System testing results
Sub Tasks
1. Define data collection metric2. Begin testing3. Report defects accurately4. Populate metric with pass/fail data5. Produce system test report by functional areas6. Review report7. Incorporate comments8. Post it on the web
Entry Criteria
(Dependencies)
Task assignment;
Test Plan; Software ready for testing
Exit Criteria
(Output)Submit the final report to the advisor
Milestones Test report on a weekly basis covering individual features/functions
WBS Task Name Software Installation Guide Task ID 7
Description Installation guide for the user
Sub Tasks
1. Study other installation guides2. Analyze user interface3. Write instructions for installation4. Formal review the guide5. Incorporate review comments6. Test installing the product from the CD following the manual7. Post it on the web, make it available to the client
Entry Criteria
(Dependencies)
Task assignment;
Software
Exit Criteria
(Output)Present the installation guide to the examination unit
Milestones Guide draft, guide final, test guide, final guide ready
WBS Task Name User Manual Task ID 8
Description Create user manual for the client
Sub Tasks
1. Study other user manuals2. Capture GUI information for the Manual3. Divide the writing tasks and assign to developers who implemented
the functions
4. Incorporate all writings5.
Incorporate limitations, known issues6. Formal review of the manual
-
8/2/2019 Smt Spmp for Aets
15/30
Software Project Management Plan Hilal Engineers
11
7. Incorporate review comments8. Burn it on the CD along with the software9. Present to the examination unit
Entry Criteria
(Dependencies)
Task assignment;
Software
Exit Criteria
(Output)Submit the final user manual to the exam unit and any related units.
Milestones User manual Outline, review manual, final manual for the term
WBS Task Name Software Developers Guide Task ID 9
Description Create developers guide for future work
Sub Tasks
1. Study other guides and outline one for the team2. Identify APIs3. Test APIs4. Document APIs5. Document major functionalities and describe6. Justify design choices7. Provide a code tree structure8. Identify all tools used9. Write the guide10.Formal review11. Incorporate review comments12.Post it on the web page
Entry Criteria
(Dependencies)
Task assignment;
All artifacts including software
Exit Criteria
(Output)Post the final guide on team web page
Milestones Guide Outline, review guide, final guide for the term
WBS Task Name AETS Software Task ID 10
Description Software product ready
Sub Tasks
1. Setup environment2. Resources and tools ready3. Assign coding tasks4. Code5. Code reviews6. Unit test7. Integrate8. System Test9. Fix defects
-
8/2/2019 Smt Spmp for Aets
16/30
Software Project Management Plan Hilal Engineers
12
10.Regression testing11.Acceptance test12.Burn it on a CD13.Test CD installation14.Product ready for the client
Entry Criteria
(Dependencies)
SRS finalized; Design ready; architecture identified; System test plan in place
Configuration Management plan ready, tools and environment ready
Exit Criteria
(Output)Acceptance criteria satisfied
Milestones Intermediate weekly builds
5.1.2 ResourceAllocationThis project will use resources in the form of time and effort that I shall spend developing the project
deliverables as mentioned in section 1.1.4.
5.1.3 Budget AllocationNone.
5.2. Control Plan
5.2.1 Requirements Control PlanWhen changes are to be made in the requirements after the SRS has been released, the changes
shall be brought to the attention of the developer and discussed. Any changes that are to be made
will be with the prior approval of the developer and only if feasible in terms of resources, knowledge
and skill of the developer required. Once the changes have been made to the SRS document, an
updated version of the SRS shall be released and circulated to the committee. However, no changes
shall be made to the requirements once the SDD is completed.
5.2.2 Schedule Control PlanIf the work scheduled as described in the work breakdown structure gets behind, the developer is
ready to spend extra time on the project in between and after the schedules and also during
semester breaks to make up for the lost time and deliver the final project on time.
-
8/2/2019 Smt Spmp for Aets
17/30
Software Project Management Plan Hilal Engineers
13
5.2.3 Budget Control PlanNone.
5.2.4 Quality Control PlanPlease refer to Software Quality Assurance Plan regarding Quality Control.
5.2.5 Reporting PlanThe updated SPMP will be circulated as mentioned in schedule. Each of preliminary versions of all
the documents and updates and status reports will be sent and discussed with the advisor and upon
approval the approved document will be circulated to the other client at the exam unit and any
other parties involved. The report on the status of the project will be sent to the advisor and the
exam unit will be notified if need be.
5.3. Risk Management Plan
Risk # 1Deficiency in the knowledge and understanding of the problem and its solution indicates
that the developer does not have the complete understanding of the problem. This will affect the
quality of the project in terms of requirements of the product and their fulfillment, which is not
desirable. Building a prototype for the project model and doing an extensive literature search can
overcome this. This will help the developer in delivering an efficient and quality product.
Risk # 2Lack of Skills and knowledge of tools needed for data analysis and algorithm design, which
means that the developer does not have knowledge about the tools and knowledge of working on
data analysis and effective algorithm design. In this case, the developer is expected to update his
knowledge of tools available for this purpose and decide the one that will be used in the project and
-
8/2/2019 Smt Spmp for Aets
18/30
Software Project Management Plan Hilal Engineers
14
master it. The developer may consult the faculty and other lecturers of the faculty especially, the
advisor for this purpose.
5.4. Closeout Plan
All the system and supporting documents will be delivered to the exam unit, accompanied by a final
project presentation.
-
8/2/2019 Smt Spmp for Aets
19/30
Software Project Management Plan Hilal Engineers
15
6.0. Technical Process
6.1. Process Model
The Automated Examination Timetabling System will be implemented and executed using extreme
programming and prototyping.
6.2. Methods, Tools, and Techniques
The AETS will be developed for online usage with a web interface, and mySQL as its database
management system. The server-side scripting language to be used is the Java Server Pages (JSP)
with SQL for queries; the client-side scripting language will be HTML + CSS + JavaScript. The tool for
the data parsing and analysis is undecided at this point of time and would be mentioned in the
updated version of this document.
The method that the team wishes to follow for the project is borrowed from a couple of
methodologies. The team intends to RUPs use case analysis for requirements analysis during the
semester 1/2011/2012. However, RUPs heavy reliance on supporting tools was a reason for the
team to keep away from using that method fully.
The system will be algorithm intensive, which can be understood as trial intensive (a lot of trial and
error), therefore for development of the timetable generating functionality, the team will use
Extreme Programming practices.
The development activities will be carried out on Pentium based Personal Computers (PC) running
Windows 7, provided by the MSE program. The team has decided to use Eclipse (version 2.1) as the
Integrated Development Environment (IDE) for development, testing, integration as well as building
activities. The team will use Java (JDK 1.7) as the programming language.
The team is considering using JUnit for unit testing tools. However this choice may change
depending on the usability of the tool. Bugzilla will be used for defects tracking system. Teams
Software Quality Assurance Plan will be followed to keep the quality of the product to acceptable
standards as agreed between the team and the client.
6.3. Infrastructure Plan
The hardware resources is one 1.0 GHz Pentium computer running Windows 7 Operating System.
The computer should have at least 512 MB RAM and a minimum of 2 GB of disk space.
-
8/2/2019 Smt Spmp for Aets
20/30
Software Project Management Plan Hilal Engineers
16
6.4. Product Acceptance Plan
The developer will test the final system for the exam unit, the results will be presented to the exam
unit, and therefore the system is subject to the exam units acceptance.
-
8/2/2019 Smt Spmp for Aets
21/30
Software Project Management Plan Hilal Engineers
17
7.0. Support Process Plans
7.1. Configuration Management PlanAll the project deliverables are to be considered as configuration items. The configuration item
as well as its file would be named after the document like SRS, SDD and followed by the version
number. For example, all the preliminary versions that are submitted to the advisor for review would
be named with the abbreviation followed by 0.1, 0.2. After the advisor approves the basic SPMP, this
baseline document will be version 1.0 and is distributed to the advisor and stakeholders (exam unit).
Informal updates with the advisor will be numbered with 1.1, 1.2, etc. and the next full distribution
to the committee would be version 2.0, etc.
7.2. Validation & Verification PlanA Verification and Validation Plan as a part of the Software Quality Assurance and Verification &
Validation Plan will be developed following recommended departmental standards. See section
1.1.4 for its delivery date.
7.3. Documentation PlanThe IEEE standards would be followed for all documentation purposes. All the documents would be
discussed and reviewed with advisor before their baseline versions are issued and distributed to the
members of the committee on the due dates mentioned in section 1.1.4 for delivery dates.
7.4. Quality Assurance PlanThe purpose of the SQAP plan is to describe the procedures and control mechanisms used by the
team to ensure high levels of quality in each of its products. The document describes both the
quality assurance activities undertaken by the team and the methods used for monitoring and
tuning the efficiency of those activities. The QA manager is responsible for all QA related activities
and will assign resources. He will also ensure that the successful execution of activities identified in
the plan.
-
8/2/2019 Smt Spmp for Aets
22/30
Software Project Management Plan Hilal Engineers
18
There are two main activities as far as the Quality assurance activities for the project is concerned.
The first one is related to documents and code reviews and the other is to testing.
Document reviews
For all written documentation formal reviews will be held to establish the quality of the documents.
All documents will follow templates borrowed or adapted from known, accepted standards such as
the IEEE etc.
7.5. Problem Resolution PlanNone, problems would be resolved informally between the developer, the advisor and the assistant
registrar of the exam unit
7.6. Subcontractor Management PlanNone.
7.7. Process Improvement PlanNone, this is a single software development experience and the lessons learned will be included in
the final AETS document.
-
8/2/2019 Smt Spmp for Aets
23/30
Software Project Management Plan Hilal Engineers
19
Glossary of Terms
Figure 4.0 Gantt Chart
Acceptance Criteria The list of requirements that must be satisfied prior to the customer accepting
delivery of the product.
Acceptance Test Formal user performed testing performed prior to accepting the system
(sometimes called client acceptance test or user acceptance test).
Activity- A specific project task, or group of tasks, that requires resources and time to complete.
Application Generic term for a program, or system, that handles a specific business function.
Application Software It is a complete, self-contained program that can perform work for a user.
This is in contrast to system software such as an operating system, server processes, and libraries
that exist in support of application software.
Architecture Imposes order and makes interconnections possible. Generally defined as an
intermediate step between initial requirements and business functional specifications during which
the entire complex of hardware, software, and design considerations are viewed as a whole. It refers
to a blueprint for evolving a technical infrastructure.
-
8/2/2019 Smt Spmp for Aets
24/30
Software Project Management Plan Hilal Engineers
20
Architectural Model It is a high level description of components, their interconnections, and other
constraints.
AvailabilityThe portion of time that a system that is scheduled to operate actually can be used as
expected.
Budget A planned sequence of expenditures over time with costs assigned to specific tasks and
activities.
CASEComputer Aided Software Engineering - Systems that attempt to automate some or all of
the tasks involved in managing, designing, developing, and maintaining software systems.
Change Management The formal process of recording, analyzing, estimating, tracking and
reporting of changes to the project baseline business functional requirements.
Client/Server System It is primarily a relationship between processes running on separate
machines. A client initiates the dialog by sending requests to the server asking for information or
action.
Component
An element within a power train system. The component consists of two parts: acomponent characterization and a Simulink model.
Configuration Management Methodical storage and recording of all software components and
deliverables during development.
Constraint- A restriction or limitation imposed on a model or a component.
Contingency Plan - An alternative for action if the project does not proceed according to plan or if
the expected results are not achieved.
Cost / Benefit Analysis A formal study in which the development, execution, and maintenance
costs for a project are matched against the anticipated value of the product.
mon forms of networking systems. CPM uses a one-time estimate for creating a project schedule.
Customer- The individual or organization that specifies and accepts the project deliverables.
-
8/2/2019 Smt Spmp for Aets
25/30
Software Project Management Plan Hilal Engineers
21
Data Describes the numbers, text, graphics, images, and voice stored in a form that can be used by
a computer.
Data type- Format used to represent signal values internally.
Data Warehouse Where you consolidate and store data from many sources.
Deliverable A tangible, physical object that is the output of a software development task.
Design The tasks associated with specifying and sketching the features and functions of a new
application prior to coding.
Development Project It is the sum of all tasks and activities necessary to build a software product.
Documentation The printed and displayed materials that explain an application to a user.
Duration - The period of time over which a task takes place. Duration establishes the schedule for a
project.
Effectiveness - A measure of the quality of attainment in meeting objectives.
Efficiency- A measure of the volume of output received for the input used.
Effort- The amount of work or labor (in hours or workdays) required to complete a task.
Environment The set of tools and physical surroundings in which software is developed.
Estimate A predicted total of expenditures required to complete a task, activity, or project.
Exit Criteria The set of conditions that must be met prior to completing a project phase or
application.
-
8/2/2019 Smt Spmp for Aets
26/30
Software Project Management Plan Hilal Engineers
22
Feasibility Project A project designed to prove, or disprove, the appropriateness of the technology
solution under existing constraints (sometimes called proof-of-concept project).
Function - An activity that spans the entire duration of a software project (e.g., status reporting,
quality assurance, verification and validation).
Gateway Hardware or software that translates between two dissimilar protocols.
Graphical User Interface (GUI) A manner of presentation that makes use of windows, icons,
menus, pointers, and scroll bars.
Hardware Physical equipment used to process, store, or transmit computer program data.
Information The meaningful interpretation of data.
Integration Describes the work, or device, required to connect two different systems that were
not originally designed to work together.
Integration Test Testing in which software components, hardware components, or both arecombined and tested to evaluate the interaction between them.
Interface A connection between two devices or systems.
Issue A problem to be solved or a decision that has not been made.
Maintenance Refers to the ongoing activity that keeps software functioning in a technical and
business environment (production).
Methodology A set of formal protocols followed when performing a task.
Milestone A major checkpoint in the activities involved in a project. A clearly defined point in a
project that summarized the completion of a related set of tasks.
-
8/2/2019 Smt Spmp for Aets
27/30
Software Project Management Plan Hilal Engineers
23
Model- A way of looking at reality, usually for the purpose of abstracting and simplifying it to make
it understandable in a particular context. A schematic description of a system.
Operating System System software that controls data storage, input and output to and from the
keyboard, and the execution of applications written for it. It performs base services: prioritizing
work, scheduling, memory management, etc.
Phases The divisions of a software development life cycle into discrete stages (e.g., requirements,
design, code, test, etc.).
Planning Project A project intended to gather, or predict, the sequence of activities and resources
needed to complete a work effort.
Platform The hardware and support software with which a program is intended to operate.
Process The step-by-step sequence of activities (systematic approach) that must be carried out to
complete a project.
Programming The art of writing, in a computer understandable language, a set of instructions thatproduces software.
Project The combined resources (people, machines, materials), processes, and activities that are
dedicated to building and delivering a product to a customer.
Project Duration - The time it takes to complete the entire project.
Project Management- The combination of systems, techniques, and people required to successfully
complete a project on time and within budget.
Project Manager The senior person responsible for the entire project.
Project Plan A formal document that describes the technical and management approach to be
followed for a project.
-
8/2/2019 Smt Spmp for Aets
28/30
Software Project Management Plan Hilal Engineers
24
Quality (Product) - Conformance to business functional requirements with defect-free products.
Quality reflects both the completeness of software or system features and functions, and error-free
operation.
Quality (Process) Verification and validation to established policies, standards, procedures and
guidelines for software development.
Relational Database A collection of data that is organized into tables so that relationships
between and among data can be established.
Repository- A place where Ford stores and organizes its components
Requirements The statement of needs by a user that triggers the development of a program,
system, or project. May be called business functional requirements or requirement specifications.
Research and Development Project A definition of a project type essentially exploring options for
developing new systems or work products.
Risk The probability that a project will experience undesirable events, which may create, costoverruns, schedule delays, or project cancellation. The identification, mitigation, tracking, and
management of those elements creating the risk situation.
Risk Analysis - An evaluation of the feasibility or probability that the outcome of a project will be the
desired outcome.
Scope - The magnitude of the effort required to complete a project.
Server A computer on a network that makes applications, print services, data, and communications
available.
Software Computer programs, systems, and the associated documentation that describes them.
SDLC - Software Development Life Cycle The period of time that begins with the decision to
develop a software product and ends when the software is delivered.
-
8/2/2019 Smt Spmp for Aets
29/30
Software Project Management Plan Hilal Engineers
25
Software Development Process The process by which user needs are translated into a software
product.
Software Project Management Plan - The controlling document for managing a software project.
The SPMP defines the technical and managerial project functions, activities, and tasks necessary to
satisfy the requirements of a software project.
Specifications General term for the wide variety of paper-based descriptions of a program or
system.
Stakeholders - People who have a personal or agency interest in the end results of a project.
Statement of Work (SOW) - An integrated set of task descriptions, goal descriptions, risks, and
assumptions that accompany the evolving master project plan during development.
System A linked collection of programs, or components, which performs a generic business or
technical function.
System Test The final stage of testing on a completed project (prior to client acceptance test) whenall hardware and software components are put together and tested as a whole.
Task- A cohesive unit of work on a project (usually 40 to 80 hours of effort).
Task Description - A description that defines all the work required to complete a project task or
activity including input, output, expected results, and quality specifications.
Test Plan A document that describes the scope, approach, resources, and schedule of intended
test activities.
Testing The set of defect removal tasks that include execution of all, or part, of an application on a
computer.
Unit Test - The testing carried out personally by individual programmers on their own code.
-
8/2/2019 Smt Spmp for Aets
30/30
Software Project Management Plan Hilal Engineers
Work Breakdown Structure (WBS) A formal analysis of the activities, tasks, and sub-tasks that
must be accomplished to build a software project. A product or activity oriented hierarchy tree
depicting the elements of work that need to be accomplished in order to deliver a product.