SMU CSE 7315 Planning and Managing a Software Project. Module 21 Software Scheduling, Part 1. Objectives of This Module. To discuss how to estimate the length of a schedule To begin the discussion of how to develop a detailed schedule Basics of PERT charts. Source Information - PowerPoint PPT PresentationTRANSCRIPT
Copyright 1995-2008, Dennis J. Frailey CSE7315 – Software Project ManagementCSE7315 M21 - Version 8.01
SMU CSE 7315Planning and Managing a Software Project
Module 21
Software Scheduling, Part 1
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 2
Objectives of This Module
To discuss how to estimate the length of a schedule
To begin the discussion of how to develop a detailed schedule
– Basics of PERT charts
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 3
Detailed Planning Process
EstimateSize
EstimateEffort and
Cost
EstimateSchedule
Evaluate
Source InformationStatement of Work
RequirementsConstraintsStandardsProcesses
Historyetc.
WBS Size
Effort &
Cost
Schedule
OKCompleteDetailedPlanning
Revise &Negotiate
Not OK
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 4
Levels of Schedule Detail
Top Level Project Schedule and Software Schedule
– Generally produced during initial planning
– Represented in the initial IMS for the project
– Based on project constraints, deadlines, etc.
– Focuses on
The major phases of software development
How software tasks relate to the rest of the project Prototype
Final DesignBuild
Design
PrototypeFinal Design
Build
Design
PrototypeFinal Design
Build
Design
PrototypeFinal Design
Build
Design
PrototypeFinal Design
Build
Design
PrototypeFinal Design
Build
Design
PrototypeFinal Design
Build
Design
CodeDesign Test
Build
DeliveryContract
PrototypeFinal Design
Build
Design
PrototypeFinal Design
Build
Design
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 5
Note about Generic Schedule(in estimating spreadsheet)
This is initially based on the top level software schedule, but can be refined based on later levels of schedule detail.
Phase Percentage Eff ortM1 M2 M3 M4 M5 M6 .
Rqmts 25% 25% 25% 15% 10%
P Des 15% 25% 30% 20% 10%
D Des etc etc
C&UT etc
I nteg.
REVIEWS SRR PDR
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 6
Levels of Schedule Detail (continued)
Intermediate Software Schedule
– Generally produced during effort estimation, based on information gained from the estimating process
– The focus is still on the major (high level) software phases and when they occur in time
– But additional detail and refinement are generally included, such as working out iterative development plans or parallel development of major software components
Note that the IMS is typically updated as a result of this
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 7
Levels of Schedule Detail (continued)
More Detailed Schedules
– Generally produced when you are about to execute the project or a phase of the project
– The focus is on how and when you will do the detailed work tasks
– Often results in detailed earned value planning (see later module)
IMS must be updated if major phases are shifted in time
– But the additional details may or may not be added to the IMS
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 8
Schedules are Developed in a Hierarchy
Rqmts DeliverTest
CodeDesign
Set up Test Development
Model RefineSimulate
Elaborate
Evaluate
TestCodeDesign
Top Level SW Schedule
Schedule for Design
Phase
Schedule for Simulate
Task
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 9
Here We Will Cover Two Topics
How to verify that the top levels of the schedule are realistic
– Normally this is done as part of the effort estimating process
How to develop a detailed schedule
– This tends to be done when you are just about to begin a particular phase of development
– But it can be done at a higher level for other purposes
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 10
Verifying that theSchedule is Reasonable
Two issues are of concern:
Total time to do the job
Percent of time and effort in each phase of the job
How do you know whether the top level schedule is realistic?
How do you determine schedule details?
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 11
Total Time Needed
Total time needed to do the project is a direct factor of
– Size and nature of software developed
– Organizational capability
– Process and methods
– Time constraints
– Financial constraints
This can vary significantly from one organization to the next
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 12
Estimating the Time Needed
Estimation models like Cocomo can be used to predict the length of the schedule
These models usually predict an ideal or optimal schedule
Each model bases its estimate on a particular set of assumptions, reflecting the experience of those who developed the model
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 13
Warning about Schedule Length Estimates
Most models and formulas for schedule length are based on someone else’s data and experience
All such data and experience are obsolete!
– We have better tools, faster computers
– We may have improved our process cycle time (see later module)
So we usually can do better than the schedules estimated by such models and formulas
Moreover, schedule length is flexible
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 14
Schedules Tend to beSomewhat Flexible
You can vary the actual schedule to fit your conditions
– You have flexibility in matching the schedule to other project constraints
– Cycle time improvement techniques can also improve your schedule
But you can drive up cost and risk as you deviate too far from the optimal
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 15
The Optimal Schedule...
... depends on people, process, nature of task, environment, etc. …
Until we have a better theoretical foundation, experience remains the best way of predicting your optimal schedule
Remember too that concerted efforts to reduce cycle time can improve your optimal schedule
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 16
Total Time to Do the JobCocomo Formula ...
e = .38 for organic
.35 for semi-detached
.32 for embedded
Effort is measured in staff-months, as computed by the Cocomo formula (basic, intermediate, or detailed)
Schedule is measured in calendar-months
Schedule = 2.5 * Efforte
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 17
Why is the Exponent Smaller for Embedded?
Note that the variable is EFFORT.
An embedded project of comparable size will have considerably more effort than a non-embedded project, thus the actual schedule will be longer, despite the formula.
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 18
Notes on Cocomo Formula
This formula assumes schedule compression adjustment factor = 1 (nominal)
In other words, the schedule computed by the above Cocomo formula is an ideal schedule.
– Yours is probably different.
Schedule = 2.5 * Efforte
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 19
The Cocomo Model ofTime vs Effort
staff-days
required to do
the work
Calendar Time Allocated for the Work
Optimal Schedul
e
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 20
Beware of Circular Relationship
(ideal) schedule length is a function of effort in most models, including Cocomo
If your actual schedule is different from the ideal, then you must:
– Change the “schedule compression” cost adjustment factor
– Re-compute the effort (it should go up)
– Do NOT re-compute schedule length as a function of effort, because the formula is no longer valid
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 21
Other Models Give Different Formulas for Time
SLIM formula for TOTAL effort (lifetime):
SLIM equation for development effort vs development time is slightly different:
Size = Ck*Effort1/3*t4/3
So t4/3 = Size / Ck*Effort1/3)So t = (Size / Ck*Effort1/3))3/4
DE = Constant / Time4
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 22
0
2
4
6
8
10
12
14
16
18
0.5 0.6 0.7 0.8 0.9 1 1.1 1.2
RELATIVE TIME
RELATIVE
EFFORT
• EFFORT = CONSTANT / TIME4
Putnam’s “SLIM”Time vs. Size Equation
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 23
Why Do Models Vary on Schedule?
One reason is that schedules are flexible and you have some control over them.
Grady and Caswell compare 5 different sources (p34, 35) (see references)
Differences they identified stem from:
– Type of software being developed
– Schedule compression
– Organizational differences
– Process and methods
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 24
What to Do About Variation
Hewlett-Packard recommendations:
– Measure actual data & keep for the future
– Count everything (overtime, etc.)
Once you know YOUR organizational behavior, you can better calibrate the models to fit your experience
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 25
For Small Projects ...
General formulas tend to fit large projects better than small ones
And you may not have a good data base of historical schedule information
...
So it may be better to estimate the time in a more detailed manner, as will be shown later
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 26
Time May Require Adjustment
Your actual project may require a different amount of time than the “ideal” computed by the models or suggested by prior experience
Project constraints may also affect the schedule
You usually have a lot more flexibility with schedule than you do with size or cost
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 27
When Will Each Specific Task be Performed?
Many models will estimate this
Your past experience and your method of doing business are good guidelines
But initial estimates will seldom be precisely accurate for detailed tasks
Better accuracy requires developing a more detailed schedule
– Which can also be used to give a more accurate estimate of the total time
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 28
Schedules are Developed in a Hierarchy
Rqmts DeliverTest
CodeDesign
Set up Test Development
Model RefineSimulate
Elaborate
Evaluate
TestCodeDesign
Top Level SW Schedule
Schedule for Design
Phase
Schedule for Simulate
Task
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 29
Scheduling Order Generally you start with the top level
software schedule from initial planning (the software part of the integrated master schedule)
Develop the intermediate schedule during the effort estimate, with a more detailed schedule for each of the major phases or tasks
– The WBS serves as a guide
Very finely detailed schedules are best done just prior to performing the actual work
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 30
Developing theDetailed Schedule
I needA detailed schedule!Tell me how long it Will take and when each task will be
complete.
What do Ido now?
Yes, sir!Right away,
sir.
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 31
Information Needed to Develop an Effective Schedule
Desired start and completion dates
Other critical dates (reviews, interim milestones)
Process or lifecycle (major phases, milestones)
Tasks (organized by phase)
Control or review points
Task dependencies (which ones are sequential, which can be done in parallel)
Resources required for each task (personnel, skill levels, special equipment, etc.)
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 32
Techniques for Developing & Documenting a Detailed Schedule
PERT Chart (PDM)
– Shows dependencies and flow
– Can expand to show timing and resources
Critical Path (CPM)
– Shows the longest path in the schedule
GANTT Chart
– Shows timing and parallelism
Network Chart
– Combines the benefits of PERT and GANTT
– But you need a tool to manage
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 33
PERT Charts & Critical Path Analysis
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 34
PERT
“PERT” stands for
“Program Evaluation and Review Technique”
See Modell in reference list.
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 35
PERT Origins
PERT was developed in the 1940’s as a management tool for complex projects
In its fullest form, PERT involves complex statistical analysis of project schedules and plans
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 36
PERT Charts
The basic tool of the PERT technique is the PERT Chart, which represents the schedule and resource needs of a project
The PERT chart uses the Precedence Diagramming Method (PDM), which is similar to a flow chart, to represent the dependencies among activities
Task 1 Task 3 Task 6 Task 7
Task 8Task 2 Task 5
Task 4
Task 9
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 37
A Minimal PERT Chart ...
Lists activities to be performed (from WBS)
Indicates dependencies
– Activity X must precede activity Y, etc.
– This information comes in part from initial planning (life cycle analysis, organizational planning, process definition, etc.)
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 38
Sample PERT Chart from Organizational Planning(in early planning steps)
Prototype Final Design BuildDesignKeyboard
CodeDesignKeyboardSoftware
Test
BuildKeyboardEmulation
DeliverySubcontracted SW for Numeric Key Pad
Contract
This can be produced by hand or with a project management or scheduling tool.
This can be produced by hand or with a project management or scheduling tool.
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 39
Steps of PERT Scheduling
1) Basic PERT -- task dependency and flow
– shows dependencies, but not timing
2) More Complete PERT -- task duration
– shows minimum schedule length
3) Critical path
– shows what tasks contribute to minimum schedule length (what tasks need to be shortened to shorten the overall schedule)
4) Full PERT - resource requirements
– shows manpower loading, resource needs, etc.
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 40
List each task on a “post-it note” or index card
Lay out the tasks on a board
Indicate task dependencies with lines (arcs)
Developing a PERT ChartStep 1 - Task Dependencies
Task 1 Task 3 Task 6 Task 7
Task 8Task 2 Task 5
Task 4
Task 9
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 41
Design Test Code
Design Spec
Integrate
Develop Hardware
Code VerifyTest
Evaluating Dependencies
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 42
“Test” Task
depends on “Code” and “Test
Code”Design Test Code
Design Spec
Integrate
Develop Hardware
Code VerifyTest
Identifying Dependencies
What depends on what?
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 43
Identifying Dependencies
What dependencies are unknown?
Design Test Code
Design Spec
Integrate
Develop Hardware
Code VerifyTest
Who needs this? (no
successor)
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 44
Identifying Dependencies
What depends on what?
Design Test Code
Design Spec
Integrate
Develop Hardware
Code VerifyTest
External task that we depend on
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 45
Finish to Start First task must finish before the second starts
Start to Start Second task must start x months after first starts
Finish to Finish Second task must finish y months after first finishes
Types of PERT Dependencies
x
y
Task 5Task 23
7
6
Task 1 Task 3 Task 6 Task 7
Task 8
Task 4
Task 9
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 46
Do not over-constrain -- use only the the essential dependencies
The following PERT chart represents a much more flexible plan
With most PERTtools, you can
specify a priority amongparallel tasks
Task 1 Task 3 Task 5Task 2 Task 4
Task 5Task 1 Task 3
Task 2
Task 4
Verifying Dependencies
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 47
What to Learn from a Task Dependency PERT Chart
Identify dependencies you did not know existed
Identify missing dependencies where you do not know the successor or the predecessor
Identify critical dependencies, such as a hardware activity that will hold you up if it is late
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 48
NOTE
PERT Charts are a good tool for developing a detailed process description as well as
developing a project schedule
PERT Charts are a good tool for developing a detailed process description as well as
developing a project schedule
Prototype Final Design BuildDesignKeyboard
CodeDesignKeyboardSoftware
Test
BuildKeyboardEmulation DeliverySubcontracted SW for Numeric Key Pad
Contract
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 49
Module Summary
Optimal schedule depends on many factors unique to the project
Models can estimate this, but they are generally inaccurate and you have much flexibility
“Detailed” scheduling uses tools such as PERT, GANTT, and Network charts.
Basic PERT chart shows dependency & flow and can find many problems
Copyright 1995-2008, Dennis J. Frailey CSE7315- Software Project ManagementCSE7315 M21 - Version 8.01 50
References
A Professional's Guide to Systems Analysis, Martin E. Modell, 2nd. Ed. McGraw Hill, 1996