smupa - pbi ik- ji · 2018. 11. 9. · the vibracion along the longitudinal axis were changed from...

17
is. 00 U«xc*l Regcarch Reference: 6065 Ao^ust 26, 19CU Pic«tinny Arsenal Dor«r, I. Y, Atta: Procurewnt and Product ion Directorate SMUPA - PBI HARD COPY MICROFICHE Subject: Contract lo. DA-0A-20O-AMC-A77 (A) Developnent and Bhraluatioo of a Lightvelght Alu»inum Honeycomb Caae Ik- Ji Monthly Progress Baport #7 QmtltWMt Enclosed is the report describing the work done on the subject contract daring the aonth of July 196k. The report v«s prepared by the Advanced Struc- tures Group, Research Division, Hexoel Products, Inc., Berkeley 10, California« Included as attachaen are (1) Statement of Man Hours Expended - July 1961*, (2) Schedule shoving Current Progress - July 196k t and (3) Schedule shoving Prograa of Ensuing Activities - August and September I96H. Yours very truly. ECVtJee Attachaents (3) l, C, Vicars Research Director DDC JAN i ö IdbD ÜlbU U bill DDCIRA B

Upload: others

Post on 13-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • is. 00

    U«xc*l Regcarch Reference: 6065 Ao^ust 26, 19CU

    Pic«tinny Arsenal Dor«r, I. Y,

    Atta: Procurewnt and Product ion Directorate SMUPA - PBI

    HARD COPY

    MICROFICHE

    Subject: Contract lo. DA-0A-20O-AMC-A77 (A) Developnent and Bhraluatioo of a Lightvelght Alu»inum Honeycomb Caae

    Ik- Ji Monthly Progress Baport #7

    QmtltWMt

    Enclosed is the report describing the work done on the subject contract

    daring the aonth of July 196k. The report v«s prepared by the Advanced Struc-

    tures Group, Research Division, Hexoel Products, Inc., Berkeley 10, California«

    Included as attachaen .« are (1) Statement of Man Hours Expended - July

    1961*, (2) Schedule shoving Current Progress - July 196kt and (3) Schedule

    shoving Prograa of Ensuing Activities - August and September I96H.

    Yours very truly.

    ECVtJee Attachaents (3)

    l, C, Vicars Research Director

    DDC

    JAN i ö IdbD

    ÜlbU U bill DDCIRA B

  • -1-

    Hexcel Research CONTRACT NO. DA-OH-^QO-AMC-l*77(A) Reference: 6065

    REPORT OF PROORESS JULY 196i*

    1. TRGTINC OF CA3B HXJi-5477

    1.1 Vibration Taste

    The aet-up for the testa vaa the siuae aft that used during

    the Tlbration testing on Case HXL-U-i*77 vtth the follovlng ex-

    ceptions. Aceeleroaeters #2 and 0h were mored fron the internal

    pay load veb (subject to oil canning) to the edge of the more

    rigid plate which is attached to the front end of the adapter

    ring. The tie rods on the fixture used to support the Case for

    the vibracion along the longitudinal axis were changed from

    606I-T6 aluBlmuD to cold rolled steel.

    The Case was placed with the longitudinal axis in a horizontal

    position and tested by vibrating it along the vertical axis. The

    Case was then placed with the longitudinal axis in a vertical

    position and vibrated along the longitudinal axis. Peak accelera-

    tion values are sunarised in Table 1. No daaage occurred to the

    Case during either test.

    1.2 Svaluatioo of Vibration Test Results

    A coaparison of the peak accelerations occurring during the

    testing on Cases \lJL~h-hj'J and HXL-5-^77 is shown in Table 1.

    All of the significant peaks on both Cases were recorded either

    on Acceleroaeter 12 or fit. Therefore, values recorded fro« the

    other aceeleroaeters wejat not listed in Table 1. The differences

  • -2-

    Haxc«! Research COITRACT JIO. DA-oW00-AMC-J»7T(A) Rafarence: 6065

    in tha aeealaratlon Bagnltudes for paaks which occurred at siallar

    frequanclet on tha two Casas «ara apparently tha result of Boring

    AccalaroMtera #2 and #** fro« tha internal payload vab to the

    plate attached to the front end of the adapter ring, Vor all hut

    tvo peaks, the acceleration aagnitudes were lover for Case HXL-5-^77

    than for Case HXL-J»-^TT. This indicates that then vas less magni-

    fication on the adapter ring plate than on the internal vab.

    2. DBSIGW OF CASS HIL-6-^77

    Mo drop tests were performed on Case HXL-^^TT so there vas no basis

    for aodifying the core design on Case HXL-6-U77, The primary change vas

    in the use of Mylar for the skin of the energy absorption cylinder and

    Butyrate Cellulose Acetate for the skin of the front and rear energy ab-

    sorption end caps. A diagram of the Case la shovn in Fl(Pfure 1. The

    dimensions of the core cutouts are the same as those on Case HXL-5-U77

    vhich are shovn lr Figure k of Progress Report #6.

    3. TT-^THQ OF CASE HXL-6-477

    3.1 Hydrostatic Preasure Test - 3 psl

    A diagram of Case HXL-6-J477 is shown in Figure 1. The bond

    between the plaatic faces and the energy absorption core of the

    and caps vas very poor in that large areas remained unbonded

    after fabrication.

    A prototype locking device was used in the front end cap in

    place of the aluminum seal plate which vas used in previous

  • -3-

    H«c«l ÜOMarch OOHTRACT MO. DA-(A-200-AMC-^T7(A) R9fer»ne« t 6065

    prtvsor« tests. Th« locking derlcs VM f%st«D«d to the head of

    ths toamj psjrload by a msehiiM scrsv. Details are shown ID

    Figure 2.

    Strips of blotter paper were placed Inside of the hydrostatic

    eyllnder to senre as a eethod of detecting water leakage. One

    piece was placed on the inside of the reeorable front end cap around

    the opening for the locking derice. A second piece was placed on -

    the inside of the rear end cap« Two additional pieces were placed

    around tbm circtvference of the inside of the cylindert one Ineedl-

    ately above the adapter ring and one lanediately below It.

    The gage pressure was cycled fro« lero to 5 pel twice. The

    pressure was held at 5 psl for 5 minutes at the end of each cycle.

    Ho noticeable pressure drop occurred at any tine during the test.

    During the test, the front and rear end caps becaae partially m

    filled with water. The energy absorption core filled with water

    to a lewel of frost 7 to U inches free the rear end of the energy

    absorption cylinder (excluding the rear end cap).

    After the speeiaen was reaored fron the pressure tank, the

    front end cap was reaored. There was approximately one inch of

    water at the botton of the hydrostatic cylinder. All blotter paper

    used in the cylinder wan dsap.

    The edges of the front end cap buckled inward lA" to 3/6" all

    around the eircunference. The core was crushed Inward (and pulled

    away fro« the skin) approxinetely one Inch at two points on the

  • -4-

    H«xc«l Research CORTHACT HO. DA-OH-200-AMC-l»77( A) B»ference: 6065

    circuaference. There ma very little peraanent deforvation in the

    skin of the rear end c*p or the cylinder other than a alight vaviaesa.

    3.2 BTaluatlon of Hydroetatlc Pressure JIU& Raaolta

    Part of the water In the hydrostatic cylinder probably entered

    the cylinder vhile the front end cap was being removed. There was

    no vay to tell what proportion of the water cane fro« this source.

    Tbc reayainier of the water could have leaked in (1) through the

    Joint between the hydrostatic cylinder and rear hydrostatic end cap,

    (2) throogh the Joint where the threaded I-sectlon is bonded into

    the hydrostatic cylinder, (3) past the O-ring at the front end cap,

    (1») past the seal ring between the locking device and the front hydro-

    static end plate, (3) past the bolt and washer which attach the locking

    device to the dtusqr pay load f or (6) through the longitudinal seaa in

    the wall of the hydrostatic cylinder.

    It was concluded that the priaary source of the leakage into the

    hydrostatic cylinder occurred by way of the locking device seal ring.

    k. DgaiCB Of CAaJt aiL-7^77

    This Case is basically the saas as Case HIlr-^-^YY. Aluainu« skin was

    used throughout. The circusiferentlal cutouts in the energy absorption core

    extend coepletely through the core as with Case HXL-^??, and the core

    cutout diesnsions are the saas as those on Case HXL-5-1»77. A diagran of

    the Case is shown in Figure 3.

  • -5-

    Hexc«! Research CONTRACT SO. DA-0'4-2OO-AMC-^7Y( A) Reference: 6065

    The priB&ry design differences between rases HXL-5-^77 *nfi

    UXL-T-1*?? are susaarired below.

    H,1 The skin gage was changed from .012 to .00^3 In the following

    places: inner and outer faces and edgeR of front energy ab-

    sorption cap; outer face of rear energy absorption cap,

    inner edge of rear energy absorption cap.

    k,2 The ,012 Alclad 202U-T3 skin on the inner face of the rear

    energy absorption cap was omitted.

    U,3 "Hie skin around the edge of the rear energy absorption cap was

    overlapped onto the cylinder 1/2".

    5. TESTING OF CAS£ HIL-T-UTT

    5.1 hydrostatic Pressure Test - 12 psi

    A diagraa of Case HXL-T-1*?? Is shown In Figure 3. The proto-

    type locking deTice was used in the front end cap. See Figure 2

    for details.

    Strips of blotter paper were placed inside of the hydrostatic

    • cylinder as was done on Case HTL-6-U77.

    The gage pressure was cycled fron zero to 12 psl* twice. The

    pressure was held at 12 psi for 'j minutes at the end of each cycle.

    •The pressure reached 13 psi during one cycle.

  • «•xcel Research COITRACT «0# nA-OU-200-AMC-V77(A) Reference; 6065

    Ro noticeable pressure drop occurred at any tlae duriog the test.

    The front and rear end caps and the cylinder energy absorption

    core becajae partially filled with water during the test« After the

    speciaen was removed from the pressure tank, the front end cap vas

    renored. Thor« was no water In the bot to» of the hydrostatic cyl-

    inder .id no dsjspoess In any of the pieces of blotter paper.

    There vaa no indication of skin buckling or daaage to the seaas

    or Joints on the inside of the hydrostatic cylinder. A pattern of

    longitudinal vrinkles occurred in the energy absorption cylinder

    stln orer each circumferential core cutout. The vrinkles we.« ap-

    proocimately uaiforaly spaced around the circumference of the cylinder.

    The edges of the front and rear end caps had similar patterns of longi-

    tudinal vrinkles extending around the circumference of the caps. The

    circumferential skin Joints opened intermittently. ,

    5.2 Evaluation of Hydrostatic Pressure Test Reaulta

    No leakage Into the inside of the hydrostatic cylinder occurred v

    during this test. However, leakage past the seal ring occurred during

    the test on Case IlXL-6-^77. The probable cause of the different re-

    sults of the two tests is that the plastic seal ring used during the

    test on Case HJL-6-^77 appeared to be faulty and was replaced prior

    to the test on Case HXIr-7-^77.

  • Hexc«l Reittarch Refitrenc«: 6065

    COiTRACT HO. DA-0»4-200-AMC-i»77(A)

    TABLB I

    QOWARISOH OF VIDPATIOW TEST RESULTS OH CASES

    VERTICAL AXIS YTBRATIJN TB8T a)Par*lltl to vibration

    ^tU-AceclerQMtfcr/te

    TE3T ■■ PEAK MUMREP

    b)Perpendicular to vi- bration axis - Accellb

    CAgj Kjggj^rf

    fREQUENCY (CPS)

    JL

    1 ?

    1214 19^

    122 19U

    ACCSL,

    12 J8

    38

    3lL

    CASE H3

    FPfqiinicY (CPS")

    115

    115

    ACCBL,

    18

    12

    LOIKWUDIHAL AXIS yiBRATIOH ISST a)Parallel to ribration

    axis - Accel.lb 1 2

    k2 60

    121

    30 25 »♦6

    b)Perpendicular to ▼1 bratIon axis -

    125 1? 0»4 .2ä~~i •Peak #1 on each set of data has similar frequencies for the two Cases.

    ••Acceleroasters for Case aXL-5-^77 vere located as shown below. The arrows

    indicate the direction along which each accelemoaoter neasured g values.

    See Progress Report ^6 for acceleroraeter locatioaa for Case UXL-Ji-J*77«

    &» t\ (*\ % V

    ic

    l\>

    csr.

    \ -

    II—

  • H«K«1 Re »«arch OOiTRACT »0. DA-04-200-AMC-Jirr( A) Refsrenc« t 6065

    ATTÄCHWMT #1

    ATTACHM8HT 01

    LTATEMKMT OF MAN HOURS EXPSNDSD - JULY 19Ch

    KngineeriDg:

    Sr. Professional 55.0 Profistlonal 181.5

    Technician:

    drafting, fabrication, & testing lift.5

    Other:

    Clerical U.Q

    TOTAL HOUHS KXPKMDfciD 359.0

  • ^ V ^ V

    u

    M CD

    >

    (a

    n I

    0.

    a

    ar o

    3 n u

    a o

    < n n c 5

    O

    a *■%

    w • v 0

    •-1

    9

    O («

    >

    •»3

    T-

    o c

    I P r.

    n

    u a o

    CO

    ?

    ti

    I

  • MBchlne Schrew (Sealed vith futty)

    Plwtlc Shire Locldn^ Device

    ^ Front

    Frvtr^r Absorption Coro

    Rytiroartatlc Cylinder

    .

    FIDDRE 2

    HYDROSTATIC PRESSURE 5EALIND CASSS HXI^6^77 AND HIL-7^77

    l]S Tl» seal ring consists of a Plastic Ring of rectangular cross-SBCtion and a rubber back-up ring»

    Ifot to Scale «/n/61i F.F.

  • a: o

    c* O

    W o

    OO

    c

    V V e

    3 •

    ro UJ

    p* h-1 * n M h-1 n ID »-' a f\j o ro ro q c- IV; 1 r- -J UJ

    «

    s ■3- 9 3 e*

    cr o C r» o a

    & a 8. 31

    *K M- ^ H-( c»-

    8 3" 3- | K

    K W R

    h o to c+

    o h-» o

    6 • sr w 4

    -J fO ^J £

    sr I

  • BLANK PAGE

  • HiEXC E L- BERKELEY, CALIFORNIA

    REFEREHCB; Rfcp 606$. Ooatract Ifo. DA-Oi*-200-AMC-^7T(A) — ii

    ._i-

    ■ -+ M -- 4-4—f

    I-

    i

    4—H _. -^—4

    B. AntlyiiB

    A. H^droatatlc Prei«ur» (12 p«l)

    TBSTIIIC AT OIIOIJY (HXL-7^771 _

    D, Analyslt

    C, Fl«t ^rcip B. End Drop

    A. .Hydro«t«Uc Presenf (^ pal)

    TSSTIWO AT BERKBIZY (HXL-6-i»77) CASE FABRICAnOi (HXL- 6*7 -^77)

    DBSIGII »»DlflCATIOII (HXL-6 k 7 -i»77)

    DBLIVIW 10 PICATHIX («11^5-^171 _ B, Analysis

    A. Vibration

    TigTIHG AT BElRgLEY (HXL-MTT)

    PROGRAM OF EVENTS

    "t -+—

    ! M ' M : 1 | -4- ♦ - -4 .- +- -t t 4-—I

    -f-i 4-4- - t--^ -4- 4 r

    ♦ r ' -♦ 1 - +—i i ;

    -f- -^ -■' * - 4- — ♦

    4-- ^ i i

    1" »—

    i

    i

    t" 14-

    -I- -*. . + 4- f--

    4 -r-

    f.4- 4. ; T 4-- ♦ * . f- t +

    -f-f ■-f

    • —-r j- i-i-t--!-L.

    1-4--t 1 t 1 ■■ 4 - 1—1-4-4 -4— i

    __f-4-f-.l_ . f-4-|-4- I- -4-

  • ■■■■ ■

    ARCM ATTACHHDTT # 2 CURKKIT PROGRBSvS JULY 190*

  • MEXCE RE S E AF BERKELEY, CALIFORNIA

    REFERgMCE; RfcD 6063. Oootrmct Bo. DA-OU-gOO-AMC-JtTTtA)

    W&ICl WODIFICAnOH (HXI^IO^TT)

    • . Analriia d. Drop Tests

    c. Hydrostatic Pressur« Test (22 psi)

    _b' Y^ftloa T9»t (D-V)

    %f_Wjst Drop Tsst

    TESTIIO AT BKHdlJUf (HXL-^TT)

    CA3B PABRICATIOI (HXL-9-^77)

    EKSIOI HDDIFICATIOII

    f. Analysis

    «. Drop Tests

    d. Hydrostatic Pressure Test (22 psi)

    c. Flat Drop Test _

    b. Vibration Tsst (IVV)

    %• Teaparrtnra - Shock Test (D-V)

    WSTIHG AT BBWSLXY (HZL-d-^TT)

    CASE FABRICATK» (HIL-^^77)

    DtSIOl MDDIFICATIOB {HTL^S-hlD

    a. Flat Drop

    TK3TIia

    . A» Aatlyeii ct Hydrostatic Pressure (22 jeil

    b. Bd^s Drop

    ggflig AT BiaaSLlT (HIL-7^77)

    4« Analysis

    J5x Hydrostatic Pressure (22 psi)

    bj Flat Drop

    », ted Drop

    PROGRAM OF EVENTS MONTHS AUGUST 1961»

    L

  • RC M Attachwnt I 3 PROGRAM OF EÄSUIHG ACTIVITIBS AUGUST k SEPT8MBBR I96U

    — — —. -

    ti4 1-

    , — 1 _H 4—

    ^ £L£l rr g8 31 2 3 M» 8 9 10 11 Ik 15 16 17 18 21 22 —-t 23 2k 25 28 29 30

    SKPTSMSBR 196^