snack foods manufacturer fleet ev charging station program
TRANSCRIPT
Fleet EV Charging Station Program Overview 2
Program Goals
EV Charging Station Overview
1. Research and identify charging station technology that is compatible with the
Snack foods Manufacturer /Smith Electric Vehicle “The Newton” Specifications.
2. Visit all assigned sites and assess existing electrical capacity
3. Develop each site plan to “right-size” future electrical infrastructure for charging
station deployment
4. Design single line electrical drawings and scope of work
5. Develop installation budget for all Phase I EV sites
6. Develop and submit a proposal to implement Ft. Worth Pilot Project
7. Develop and submit a bid package Specifications for Pilot Site
8. Support Snack Foods Manufacture In Developing AZ site EV deployment with
consideration of its “Net Zero” plant and PV system
9. Support Fritolay in developing 2011 deployment plan for all Phase I Locations
10. Install selected sites ON BUDGET, ON TIME!
Fleet EV Charging Station Program Overview 3
How did we get this done in 45 days with limited internal
resources?
EV Charging Station Overview
1. “Where there’s a will, there’s is a way”! - "Where there's a will, there's a way" is an
old English proverb meaning a person with determination will find a way of doing
something. A proverb is a short saying that has widespread and frequent use that expresses a basic
truth, familiar experience or concept.
2. We found a outside electrical engineering firm, located in SE to help support the Design
Phase
3. We teamed them up with Several construction groups to help with design and national
installation Phase
4. Signed a PDA, (Project Development Agreement) with Snack foods Manufacturer for
Engineering and Deign
5. Conducted 30 days of research on charging station technology.
6. Forged a relationship with Smith Electric Vehicles out of Kansas City, Mo. And Clipper
Creek who were the selected vehicle and charging stations suppliers.
7. Audited 13 locations in 21 days
8. Designed and built proposal for each site
9. Presented our finding at Headquarters Friday August 6th 2010
10. Received our first contract for the pilot Site in early September 2010
Fleet EV Charging Station Program Overview 4
Discusses existing conditions at each facility
Provides an overview of the electrical distribution system modifications required to
support approximately 10 EV charging pedestal locations per site
Indicates approximate locations of existing electrical distribution equipment and
proposed vehicle charging locations
Scope of Work Details
Preliminary electrical distribution system single-line diagram for each facility
Charger Pedestals – by Clipper Creek
Concrete bollard at each charger pedestal location for protection from vehicles
Concrete housekeeping pad – 36” wide, continuous length at charger pedestal locations
Extra conduit stub-outs for extension to additional chargers
Extra conduits between charger pedestals, charger panelboard and building interior to facilitate
future charger monitoring system
Install LED lighting fixtures, typically two per each group of 5 chargers, on 12- to 15-foot poles
Facility Write Up & Scope of Work Road Map
EV Charging Station Overview
Fleet EV Charging Station Program Overview 5
EV Charging Station Overview - Individual Site Write Ups
HW Lay/DFW NorthCasa
Portland
Mega
La MiradaSylmar
Fort Worth
Austin
Texan SC
Sam Houston SC
Atlanta
West
South
Atlanta SC
South Potomac/Lorton
Beltsville/
Capital Heights
Fleet EV Charging Station Program Overview 6
Charging Station Technology - ClipperCreek
EV Charging Station Overview
• Multiple levels of safety for the customer, the EV
and the charging equipment
• External Control input. Allows external control
from a smart meter (AMI), billing or load
management device
• CCID with automatic re-closure (after nuisance
trip, unit will self check and resume charging)
• Outdoor Rated (NEMA 4) enclosure
• Charging Indicator Lamp
Model
Circuit Breaker
Rating, Amps
Continuous
Current, Amps
CS-100 100 80
Fleet EV Charging Station Program Overview 7
Charging Station Technology - ClipperCreek
EV Charging Station Overview
Charge Circuit
Interruption Device
(CCID):
Ground Fault protection with fully
automatic re-test and re-closure.
Service Ground
Monitor:
Constantly checking for presence
of proper safety ground.
Reclosure: Will automatically resume charging
after a minor fault. No user
intervention required!
Cold Load Pickup: Time delayed and randomized to
allow re-energizing of unit following
power outages.
CCID Self Test: The CCID has a self-check feature
eliminating the need for monthly
testing by the user.
Fleet EV Charging Station Program Overview 8
Charging Station Monitoring
Supply Power
Charger S/S
Power
Metering
Supply Power
Charger S/S
Supply Power
Charger S/S
Supply Power
Charger S/S
DC Amps
Supply Power
Charger S/S
DC Amps DC Amps DC Amps DC Amps
I/P Address
(Through Owner Provided
Ethernet)
Thin Client
Computer
Charging Station Monitors
Fleet EV Charging Station Program Overview 9
EVSE Moving Frito-Lay Controls
InternetVPN Tunnel
Server for:
- EMS Web application
- Database (storage for history)
- Data backup
Servers specifications- Windows XP or Server 2003
- 1 GB ram minimum (recommend 2GB)
- Microsoft SQL Workgroup Edition
- SMTP Mail Account
VPN Access
Servidyne
Support
Hosted servers for:
- Energy Use Report server
Pro’s Con’s
Need to establish and maintain
VPN tunnel between Servidyne
energy reporting server and server
at client’s datacenter.
Server located at client's data
center
Manufacturer’s recommended
configuration
Real time controls
Real time alarms
Client owns / controls server
Servidyne can remotely support
configuration / upgrades
Energy Management Systems (EMS)
Network Design Onsite / VPN Option
Static IP VPN Public IP Onsite Server
● ● ●
Energy Reporting
Server
Individual Facilities
EMS at facility
EMS at facility
EMS at facility
EMS at facility
EMS at facility
TC
P / IP
Ports 80, 1911, 3011
Static
IP (t
ypical)
Customer
Access
Fleet EV Charging Station Program Overview 10
Summary of Controls System Features and Benefits
• Charger can be scheduled in areas with Off-peak / On-peak
utility rates
• Charger diagnostics and alarming
• Can provide information for sustainability reporting (Carbon
footprint)
• Global monitoring via internet
• Can participate in Automatic Demand Response programs
(ADR)
• Smart Grid Integration with Silver Spring NetworksTM
• Integration into facility EMS Systems via Niagara AX open
system driver framework
• Integration with current GPS Truck Tracking systems and Truck
Telemetry Systems.
Fleet EV Charging Station Program Overview 11
Summary of EVSE Program Challenges
• Compress Time Schedule
• Crash Coarse in EVSE Technology
• Local Site Manager Logistics
• Trenching – Utility Support?
• Weather
• UL Listing Issues – Field Inspectors
• IT Security Issues – Web Controls Access
• Training
Fleet EV Charging Station Program Overview 12
Q&A - Servidyne Contact
Learn more about optimizing
your buildings’ performance
Jim Dore
Vice President, Sales
Tel (770) 916-7107
Cell (404) 428-2343
Fax (770) 916-7108
www.servidyne.com
part of the solution