7/23/2019 Snag List for Staff Office_08 Nov 15
1/1
STAFF OFFICE
03.11.15
Item
no. Date
snaged Raised AREAS Particular Item
description Type Resp Accounted Dateplannedto
complete STATUS
1 03-Nov-15 IKEA Com-in & Office AC Ducting AC diffuser with ties. Defect Progress Mick 6-Nov-15 Done
2 03-Nov-15 IKEA Com-in & Office Speakers Speaker not level Defect KEMJ Mick 6-Nov-15 Done
3 03-Nov-15 MCD Learning centre Floor Patch on floor holes with protuding
rebar.Defect Zachlim Bayne 6-Nov-15 Done
4 02-Nov-15 MCD Corridor Floor Remove residue and polish floor Defect MCD Bayne 8-Nov-15 Done
5 02-Nov-15 MCD IT Training room Floor Floor at bottom door (closing
position) to even and smooth.Defect Zachlim Bayne 6-Nov-15 Done
6 02-Nov-15 MCD IT Training room Ceiling
Ceiling tiles surrounding AC to be
replaced due to wet marks. Defect Hatori Bayne 8-Nov-15 Done
7 03-Nov-15 MCD IT Training room Alum windowAluminum edge to wall make nice
with acrylic or other medium.Defect MCD Bayne 7-Nov-15 Done
8 03-Nov-15 MCD IT Training room Alum door Door stopper to install Defect Masterskill Bayne 7-Nov-15 Done
9 02-Nov-15 MCD Sales HQ Vinyl skirting Straighten wavy vinyl skirting Defect MCD Bayne 7-Nov-15 Done
10 03-Nov-15 MCD Sales HQ Alum windowAluminum edge to wall make nice
with acrylic or other medium.Defect MCD Bayne 7-Nov-15 Done
11 03-Nov-15 MCD Sales HQ Alum door Door stopper to install Defect Masterskill Bayne 7-Nov-15 Done
12 03-Nov-15 MCD Cash office Ceiling Defects ceiling tiles to be replaced. Defect Hatori Bayne 8-Nov-15 Open
13 03-Nov-15 IKEA Cash office Smoke detector Cover missing Incomplete KEMJ Mick 8-Nov-15 Done
14 03-Nov-15 MCD Cash officeMetal door
frameEdging to make to nice. Defect DuoDex Bayne 9-Nov-15 Open
15 03-Nov-15 MCD Cash office Wall socket Wall socket cover loose Defect KEMJ Mick 7-Nov-15 Done
16 03-Nov-15 MCD Office storageMetal door
frameEdging to make to nice. Defect DuoDex Bayne 6-Nov-15 Done
17 03-Nov-15 IKEA Office storage Ceiling Close all gaps on ceiling tile system Defect Hatori Bayne 8-Nov-15 Open
18 03-Nov-15 IKEA Storage Ceiling Close all gaps on ceiling tile system Defect Hatori Bayne 7-Nov-15 Done
19 03-Nov-15 MCD Storage Alum window
Aluminum edge to wall make nice
with acrylic or other medium. Defect MCD Bayne 7-Nov-15 Done20 03-Nov-15 MCD Storage Alum door Door stopper to install Defect Masterskill Bayne 7-Nov-15 Done
21 03-Nov-15 MCD P-Tag CeilingDamaged ceiling tiles to be
replaced.Defect Hatori Bayne 7-Nov-15 Done
22 03-Nov-15 MCD P-Tag Alum windowAluminum edge to wall make nice
with acrylic or other medium.Defect MCD Bayne 7-Nov-15 Done
23 03-Nov-15 MCD P-Tag Alum door Door stopper to install Defect Masterskill Bayne 7-Nov-15 Done
24 03-Nov-15 MCD Medical room Wash basin Sensor wirings Defect Edlamb Amirul 6-Nov-15 Done
25 03-Nov-15 MCD Medical roomMetal door
frameEdging to make to nice. Defect DuoDex Bayne 6-Nov-15 Done
26 03-Nov-15 MCD Medical room Floor drain floor drain grille cover Incomplete Edlamb Amirul 6-Nov-15 Done
27 03-Nov-15 MCD Storage & ArchiveMetal door
frameEdging to make to nice. Defect DuoDex Bayne 9-Nov-15 Open
28 03-Nov-15 IKEA Storage & Archive Wall Painting Incomplete MCD Bayne 9-Nov-15 Open
29 03-Nov-15 IKEA Staff Prayer room Tiling floor tilings Variation MCD Amirul 9-Nov-15 Open
30 03-Nov-15 MCD Staff Prayer room Ceiling Close all gaps on ceiling tile system Defect Hatori Bayne 8-Nov-15 Open
31 03-Nov-15 MCD Training room Door Door gaps with vinyl floor. Grind off
bottom door.Defect DuoDex Bayne 9-Nov-15 Open
32 03-Nov-15 MCD Training room Ceiling Replace damaged ceiling tiles Defect Hatori Bayne 9-Nov-15 Open
33 03-Nov-15 MCD Training room Ceiling Close all gaps on ceiling tile system Defect Hatori Bayne 6-Nov-15 Open
34 03-Nov-15 MCD Training room Floor Concrete residue to remove atcolumn corner. - Drywall
constructed to mask this
Defect MCD Bayne 9-Nov-15 Done
35 03-Nov-15 IKEA Training room Cable tray
Cable tray exposed to server room,
mask on walls. - Drywall constructed
to mask this
Defect MCD Stuart 7-Nov-15 Done
36 03-Nov-15 MCD Training room Wall paper Wall paper still wet. Check curing Defect MCD Bayne 6-Nov-15 Done
37 03-Nov-15 IKEA Training room DoorKnob closer to be switch inside
room rather than outsideDefect DuoDex Bayne 10-Nov-15 Open
38 03-Nov-15 IKEA Training room Wall Wall uneven surface bottom to floor Defect MCD Bayne 9-Nov-15 Open
39 03-Nov-15 IKEA Training room WallDrywall and Concrete wall not
flushedDefect Hatori Bayne 9-Nov-15 Open
40 03-Nov-15 IKEA Steel staircase Wall Wall touch-up painting Defect MCD Bayne 9-Nov-15 Open
41 03-Nov-15 IKEA Corridor WallProtuding PVC pipe to cut flush with
wallDefect MCD Bayne 7-Nov-15 Done
42 03-Nov-15 IKEA Office open area Faay wall Electrical provision to be installed Incomplete KEMJ Bayne 9-Nov-15 Open
43 03-Nov-15 IKEA Corridor Wall protection Bolt heads are bulky Design KEMJ Bayne 9-Nov-15 Open
44 03-Nov-15 MCD Steel staircase Stair Cover gaps on concrete floor to first
thread stepDefect MCD Bayne 9-Nov-15 Open
45 03-Nov-15 MCD Steel staircase Stair Walls going to AS-IS require re-
painting on cosmetic damage;Defect MCD Bayne 9-Nov-15 Open
46 03-Nov-15 MCD Corridor WallWall bottom corner damaged. Needto rectify;
Defect MCD Bayne 7-Nov-15 Done
IKEA Cheras Main Bui lding Works MCD notes following inspect ion