social monitoring report€¦ · email: [email protected] report on results of external...
TRANSCRIPT
Social Monitoring Report Final Independent Monitoring Report January 2017
VIE: Mong Duong 1 Thermal Power Project
Prepared by the Development and Research & Consultancy Centre for Vietnam Electricity
Thermal Power Project Management Unit 1 and the Asian Development Bank.
This social monitoring report is a document of the borrower. The views expressed herein do not
necessarily represent those of ADB's Board of Directors, Management, or staff, and may be
preliminary in nature.
In preparing any country program or strategy, financing any project, or by making any
designation of or reference to a particular territory or geographic area in this document, the
Asian Development Bank does not intend to make any judgments as to the legal or other status
of any territory or area.
DEVELOPMENT RESEARCH & CONSULTANCY CENTER
No. 1 Lieu Giai Str. Ba Dinh Dist. Ha Noi City, Vietnam
Phone No: (04)62730414 Fax: (04) 62730448
Email: [email protected]
------------------------------------------
FINAL REPORTON RESULTS OF EXTERNAL MONITORING AND EVALUATION OF
RESETTLEMENT ACTION PLAN AND LIVELIHOOD RESTORATION
PORGRAMIMPLEMENTATION
PROJECT
MONG DUONG 1 THERMAL POWER PLAN
MONG DUONG POWER CENTRE – QUANG NINH PROVINCE
HA NOI, 2016
2
Ha Noi,20 March 2016
Subject:Final report submitted by DRCC
For Independent monitoring and evaluation of RAP implementation and LRP
Mong Duong 1 Thermal Power Plant Project, QuangNinh Province.
TO: ASIAN DEVELOPMENT BANK (ADB) IN HA NOI
THE THERMAL POWER PROJECTS MANAGEMENT BOARD1.
The Development Research and Consultancy Centre (DRCC) would like to submit the
final report on Independent monitoring and evaluation of RAP and LRP implementation for
theMong Duong 1 Thermal Power Plant Project, QuangNinh Province.
Your consideration and opinions would be highly appreciated.
Yours truly,
DIRECTOR
Nguyen Hong Quang
3
TABLES OF CONTENTS
TABLES OF CONTENTS ................................................ Error! Bookmark not defined.
ABBREVIATIONS ............................................................................................................. 4
SUMMARY......................................................................................................................... 5
PART I................................................................................................................................. 6
INTRODUCTION, OBJECTIVES, INDEPENDENT MONITORING METHODS ........ 6
PART II ............................................................................................................................... 9
EVALUATION OF COMPENSATION, ASSISTANCE AND RESETTELMENT
AFTER SITE CLEARANCE .............................................................................................. 9
PART III ............................................................................................................................ 16
ASSESSMENT OF LIVELIHOOD RESTORATION PROGRAM ................................ 16
PART IV............................................................................................................................ 39
CONCLUSIONS, RECOMMENDATIONS VÀ LESSONS LEARNED........................ 39
APPENDIX ....................................................................................................................... 41
4
ABBREVIATIONS
ADB
AH
AP
Asian Development Bank
Affected household
Affected person
PMU Project Management Unit
DRCC Development Research and Consultancy
Centre
DCARB District Compensation Assistance Resettlement
Board
TOR Terms of Reference
RP
LRP
Resettlement Plan
Livelihood Restoration Program
PC People’s Committee
CLFD
CSR
DMS
GoV
FWSS
CWDC
EVN
TPP
SPS
Centre of Land Fund Development
Compensation, Assistance and Resettlement
Detailed Measurement Survey
Government of Vietnam
Freshwater supply system
Cooling water discharge channel
Electricity of Vietnam
Thermal power plant
Safeguard Policy Statement
5
SUMMARY
This final report is preparedfor independent monitoring results of the implementation of
compensation and land acquisition and livelihood restoration program of affected households by
Mong Duong 1 Thermal Power Plant, located in Mong Duong Ward, Cam Hai and Cong Hoa
Communes, Cam Pha City, QuangNinh Province. The final report (12th monitoring) aims to
describethe overall progress of the project; results of compensation and site clearance
implementation in main plant area; auxiliary components and freshwater supply system;
evaluation oflivelihood restoration program after site clearance; review ofthe resolution for
pending issues as described in the 11thmonitoring and evaluation report (if any) and new ones
arising during this monitoring and evaluation; and recommendations and lessons learned.
The report is dividedinto 4 parts:
o Part I: Overview: Introduction, Objectives, Monitoring and Evaluation Methods
o Part II:General Evaluation of Resettlement Plan regarding land
acquisition,compensation, and resettlement for the entire project after site clearance.
Pending and arising issues related to site clearance and compliance with RP of main
plant components and auxiliary components, and freshwater supply system.
o Part III: Evaluation of livelihood restoration program for entire project including main
plant area, auxiliary components, and freshwater supply system.
o Part IV: Conclusion, recommendations and lessons learned
6
PART I
INTRODUCTION, OBJECTIVES, INDEPENDENT MONITORING METHODS
I.1. INTRODUCTION
Mong Duong 1 Thermal Power Project (hereinafter referred to as the Project), which
was approved by the Government of Vietnam (GoV) and commenced since 2008, islocated in
Mong Duong Ward, Cam PhaCity, QuangNinh Province. The Project used Official Development
Assistance (ODA) financed by the Asian Development Bank (ADB) witha total amount ofUSD
930,710,000 USD, approved on September 21, 2007, including two loans for the construction of
(i) Mong Duong 1 (MD1) thermal power plant using 1000 megawatt (MW) circulating fluidized
bed boilers (CFB); and (ii) Shared infrastructure components for Mong Duong 1 plant and Mong
Duong 2 plant in the same complex invested by an USA private company. Components include
the main plant, freshwater supply system (FWSS), Cooling Water Discharge Channel (CWDC),
ash pond, and a fence between the boundaries of MD1 and MD2.
The loan for Tranche1, which was signed on 9 October 2007 with the amount of USD
27,860,000, ensures satisfactory completion of the following components: (i) Levelling the
layout for constructing the power plant, intake and discharge canals; (ii) Technical consultancy
services for phase 1; (iii) Electricity supply system for construction sites; (iv) PMU and
consultancy offices; and (v) Internal roads ofMongDuong thermal power plant complex
connecting with the National Highway 18.
The USD 902,850,000 loan for Tranche2 was signed on 9 November 2010 for the
following components: (i), Engineering, procurement, and construction contract (EPC) for MD1
thermal power plant; (ii) Technical consultancy services for phase 2; (iii) FWSS; (iv) CWDC); (v)
Ash pond and (vi) Fence surrounding MD1 thermal power plant.
To date, the construction ofMong Duong 1 thermal power plant has beencompleted and
came into operation, and officially synchronized to the national power system by the end of
2015; thereby, contributing a significant amount of power to the national grid. MD1 TPP also
has the largest capacity in Vietnam compared to other thermal power plant systemsof the
country. MD 1 TPP is invested by theElectricity of Vietnam (EVN) and assigned to Power
Generation Corporation 3 (GENCO 3)todirectlymanage and operate the plant.
At the present time, the compensation, assistance, and resettlement for main plant area,
cooling water channel, cooling water discharge channel, ash pond, freshwater supply system
and auxiliary components have been completed incompliance with the policy framework of the
7
Project. Livelihood restoration program for severely affected households has been conducted
and achieved certain results.
I.2. OBJECTIVES OF THE TWELFTH MONITORING
The overall objectives of the 12th monitoring are to:
Review outstandingissues as mentioned in the 11thmonitoring and resolved issues. The
follow-up direction and plan to resolve these pending issues are also provided.
Verify, monitor and evaluate whether the compensation, assistance, and
resettlementimplementation for components that have been and being carried outare
compliedwith the RP policies of the Project.
Verify whether the RP with proposed mitigation measures ensures the fairness and
providesassistances for APs in order to improve, or at least restore,their living standardsto the
pre-project level.
Evaluate the effectiveness, impacts, and sustainability of the resettlement and LRP for
entire Project. Provide recommendations forthe resettlement implementation of thenext
components of the Project (if any) and lessons learned.
8
I.3. MONITORING METHODOLOGY
The External Monitoring Agency (EMA) used the following methods: review of secondary
documentation (desk study), sociological survey method, and field visit (interviews, observation,
and consultation with local officials and affected household…)
The EMA has conducted desk study, observed, met, and interviewed the stakeholders
and AHs to review the compensation payment activities, LRP for severelyAHs, queries and
complaints of AHs, and monitor the RP implementation of households affected by main plant,
auxiliary components, and freshwater supply system (including water pipeline and freshwater
reservoir…).
Key informants include:
TPMB1at the Main Office located at the Management House of Mong Duong Power
Centre.
Mong Duong Ward People’s Committee (Ward PC), Cam Hai Commune People’s
Committee (CPC), Cong Hoa Commune People’s Committee;
Cam Pha CityCompensation, Assistance, and Resettlement Board (CCARB) atCam Pha
City PC’s office;
Sociologicalsurveyand interview withseverely AHs and someslightly affected
households, with focus on those with outstanding issues and complaints.
9
PART II
EVALUATION OF COMPENSATION, ASSISTANCE AND RESETTELMENT
ACTIVITIES
II.1. SUMMARY OF THE NUMBER OF AFFECTED HOUSEHOLDS AND LAND
ACQUISITION IMPACTS
Land acquisition ofMong Duong TPP is divided into 2 phases: (i) Phase 1: Site
clearance for main plant area and auxiliary components,(ii)Phase 2: Site clearancefor
freshwater component (FWC) including water pipeline and reservoir area. Summary ofthe
number of AHs by components is presented in Table 1 below.
Table1: Summary of affected and relocated households by components
No. ComponentTotalAHs
TotalAPs
Totalrelocatedhousehol
ds
Totalseverely
AHs
Total AHsreceived
compensation,assistance
Note
I Main plant area 53 261 15 24 53
1.1 Main plant 21 111 5 13 211.2 River diversion 2 9 0 0 21.3 Cooling water channel 1 4 0 0 11.4 Discharge channel 16 53 6 8 161.5 Ash pond 13 93 4 6 13II Auxiliary components 101 101
2.1 Management house and staffhousearea
19 67 3 9 19
2.2 35kV Electricity Line 24 72 0 0 242.3 110kVTransmission Line 4 15 0 0 42.4 Spoil disposal site 15 36 0 0 152.5 Discharge channel (end part) 19 52 1 3 192.6 Additional discharge channel
(acquire more land)11 42 0 0 11
2.7 Additional discharge channel (flood) 4 14 0 0 42.8 Containment dyke for ash pond 4 16 0 0 42.9 Connection to the National Highway
181 1 0 0 1
VIII Freshwater Component (FWC) 195 731 37 117 195Total 349 1297 56 153 349
Phase 1: Acquisition of land of 154 AHs was carried out for construction of the main plant
area and auxiliary components. Out of which, 53 households are affected at the main plant area
including 15 relocated households; and 101 households affected by the auxiliary components,
including four (04) relocated households. Site clearance for phase 1 started in 2008 and completed
by the end of 2013.
10
Phase 2: Land acquisition of 195 households for the implementation of the FWC. Out of
which, a total of 65 AHs are affected by the pipeline component and 130 are affected by the
freshwater reservoir in the Residential Quarter 10 of Mong Duong Ward, including 37 relocated
households.Regarding land acquisitionof phase 2, DMS wascarried out in 2010 and finished by
the end of 2014.
The land acquisition process for both phases has complied with the procedures and
legal framework of the Project. During project preparation, the Social and Environment
Safeguards documents (RP and EIA) have been fully and properly prepared. During land
acquisition process, activities including DMS, compensation plan preparation,submission of
compensation plansfor appraisal and approval, and compensation/assistance payment,have
been seriously and properly carried out under the policy framework of GoV, QuangNinhPPC,
and ADB.
Table 2: Summary of compensation, assistance, and resettlement costs
No Component TotalAHs
Planedarea
Affected landarea by
Decision ofland
acquisition(ha)
Total costsofcompensation,assistance for
HHs/organizations(VND)
Note
I Main plant area 53 277.01 269.40 91,349,972,800
IIAuxiliarycomponents
101 70.25 70.25 17,783,007,900
VIII FWC 195 187.19 187.19 105,483,244,300
Total 349 534.45 526.84 263,496,220,342.00
Total land area planned for the construction of Mong Duong TPP was 534.45 ha. The
total land area of HHs/organizations acquiredin accordance withland acquisition decisions of
QuangNinhPPC for both phases was 526.84ha. In which: Land area acquired for main plant
area, auxiliary components, and freshwater reservoir system were 269.40 ha, 70.25 ha, and
187.19 ha, respectively.
Total amount for compensation/assistance payment was VND 263,496,220,342.Out of
which, the compensation and assistance cost for the main plant area wasVND 91,349,972,800;
forauxiliary components were VND 17,783,007,900 VND; and for FWC wasVND
105,483,244,300.
11
The compensation and assistance have been fully paid for 349 affected households of
both phases. To date, there is no additional query and complaint; the AHs have settled down
and their incomes have been improved compared to the pre-project level.
II.2. LAND ACQUISITION AND COMPLIANCE WITH RESETTLEMENT PLAN
II.2.1. INFORMATION DISCLOSURE, PUBLIC CONSULTATION, DMS AND
COMPENSATION PLAN PREPARATION
o Information disclosure:
Information disclosure for Mong Duong 1 TPP was conducted in accordance with
procedures. During RP updating process, TPMB1 hascoordinated with Cam PhaCCARB – now
called Centre of Land Fund Development (CLFD) of Cam Pha City and local authorities in order
to disseminate project information to people in the project area. Key information of the Project as
well as resettlement plan have been disseminated to all affected households through the
distribution of the Project Information Booklets (PIBs) and public posting at the commune/ward
offices and public places.
CLFD of Cam Pha City have copied and stamped the compensation dossiers and then
distributed to the AHs for reference and keeping. The CLFD has also organized public meetings,
posted notices, and compensation rates and policies at the project wards/communes as well as at
the residential groups; together with Poyry to disseminate information and hold public
consultations regarding compensation, resettlement, and livelihood restoration activities.
Basically, information disclosure to local people was conducted in compliance with procedures
and RP; most of interviewed AHs were aware of theproject information and their entitlements.
o Public consultation:
Key topics at the public meetings and consultations included project planning, legal
documents as rationale for land acquisition implementation, funding, compensation and
assistance policies, project implementationschedule, entitlements and responsibilities of
theAHs, and grievances redress mechanism. PCs of Mong Duong Ward, Cong Hoa Commune,
Cam Hai Commune, and Cam Pha CCARB as well as the Project Owner and consulting
agencies have directly disseminated, attended meetings, and received people’s opinions and
feedback.
o Participation of AHs:
AHs have participated in information disclosure meetingsand public consultations. 100%
of AHs sent their representatives to participate in DMS process and sign DMS records, and
compensation/assistance payment vouchers.
o Detailed measurement survey (DMS):
12
DMS process: DMS was conducted by a working group comprisingrepresentative of
CARB of Cam PhaCity, representatives of some departments, agencies, and organizations,
chairmen of Ward/Commune PCs, leaders of residential groups, representative of the Project
Owner, and affected households. The DMS working group was responsible for determining the
exactamount of each type of lost assets, preparingDMS records signed by participants and
affected households,and preparing compensation plans.
o Accuracy of DMS:
The DMS process was conducted equitably and publicly. The records were signed
sufficiently by the participants and posted publicly. In case of queries regarding the affected
assets, the DMS working group would directly meet the households to verify, determine, and
confirm the amount of losses.
Types of impacts were various, including residential land, garden land, agricultural land,
forestry land, and land for aquaculture, trees and crops, houses and structures, and particularly,
56 householdshave to relocate (including the main plant area, auxiliary components, and FWC).
o Price establishment and compensation payment
Approval for compensation and assistance plans for the Project has been implemented
based on legal documents of GoV, social safeguard policies of ADB, and decisions issued by
QuangNinhPPCannually and applied at the time of DMS, price application, and compensation
paymentfor affected organizations/households to ensure full replacement cost so that they are
not disadvantaged and worse off.
II.2.2.LAND ACQUISITION AND COMPLIANCE WITH RP OF MAINT PLANT AND
AUXILIARY COMPONENTS
Compensation of the first phase for acquisition of 269.4 ha of land for the construction of
main plant area and 70.25 ha for auxiliary components (staff area, cooling water supply channel,
cooling water discharge channel, ash pond, the ending part of discharge channel, spoil disposal
site, 110kV transmission line, etc.) has been completed since 2013; to date, there is no pending
issue.
Compensation and assistance have been implemented based on legal documents of
GoV, ADB policies and approval decisions issued by QuangNinhPPC and Cam PhaCity PC and
in compliance with the approved RP. To date, compensation payment has been completed. A
total of154 AHs/organizations (including 53 AHs in the main plant area and 101
AHs/organizations of auxiliary components) received compensation and assistance. Relocated
households have built new houses and settled down, severely AHs as well as relocated AHs have
13
restored their livelihoods. Most of the households have better incomes and living standards than
the pre-project level.
II.2.3. LAND ACQUISITION AND COMPLIANCE WITH RP OF FRESHWATER COMPONENT
FWC construction has been signed by the TPMB1 with Song Da No. 11 Joint Stock
Company (JSC) on 11 October 2012 with construction duration of 18 months. To date, the system
has been completed andsupplied water for Mong Duong Power Centre since 27 April 2014. Land
acquisition and RP implementation for FWC construction (including the pipeline system and
freshwater reservoir located in Mong Duong Ward and Cong Hoa Commune) has been completed
since 2014. Allof 195HHs/organizations (one organization is Cam PhaForestry Ltd Company)
affected by construction of FWC have received compensation, 37 relocated households affected by
reservoir have built new houses and settled down. Livelihood restoration activities have been
commenced and achieved good outcomes.
The majority of the AHs have expressed their satisfaction and support towards the Project. As
of now, there is no complaint or grievance except for some expectations of the APs which have
been being considered by the Project Owner.
II.2.4. ASSISTANCES
Different assistancesas per ADB’s policy framework, including relocation assistance for
relocated households, life stability supports, job changing supports, and allowances
forvulnerablehouseholds, etc. have been adequately provided by Cam Pha CCARB in
coordination with TPMB1as per RP for households/organizations affected by components of
both phases.
II.2.5. LIVELIHOOD RESTORATION
Livelihood Restoration Program (LRP) prepared by Poyry and approved by ADB for
severelyAHs and relocated HHs of both phases have been adequately implemented.
Livelihood restoration activities, including agriculture and forestry extension programs,
vocational training, and veterinary specialist training, etc., have been carried out for the
households affected in the main plant area and auxiliary components. Theorganizers of these
programs have worked with local authorities of Mong Duong Ward, Cam Hai Commune and Cong
Hoa Commune regarding veterinary training and additional members for livelihood restoration
board.The implementation of these programs have achieved certain results. Although veterinary
training has been provided for land lost HHs, they did not want to participate. According to
provisions of PPC, job changing supports in cash equivalent to two (02) times of the rates of
affected agricultural land have been provided in an adequate manner. However, loan access
program had difficulties due to a lack of funding sources(there is no agency providing loans in
14
relation to mortgaged properties). As reported by TPMB1, LRP was not effective and suitable for
the local area, which is an Industry Park, where local people mainly rely onbusinesses and mining
enterprises.
Training courses, including guidance on cultivation, livestock husbandry, cooking,
motorcycle and car repairing, etc. for HHs affected by FWC, have been organized by theProject
Owner in coordination d with Mong Duong CPC. The affected households have been invitedto
participate in the LRP training courses and register for vocational training. The implementation of
these programs have achieved certain results. (Details will be presented in the Evaluation of LRP
for both phases).
II.2.6. GRIEVANCE RESOLUTION
During the implementation process of site clearance, many meetings and consultations
have been conducted for households affected by components of both phases (main plant,
auxiliary components, and FWC). These meetings and consultations have been held by Cam
Pha CCARB, project implementation consultant, TPMB1, and Commune/Ward PCs. The
meetings focused on explainingAPs’ questions regarding compensation rates,
compensation/assistance policies, and project information dissemination. During the monitoring,
some AHs who had queries as above have been considered and solved by Cam Pha CCARB in
cooperation with TPMB1 and Mong Duong Ward PC. Until the 10th monitoring (November
2013), most of the queries and complaints have been solved. At the monitoring time (January
2016), there is no complaint and query; all of the interviewed households have expressed their
total supports to the Project.
II.2.7. INTERAL MONITORING
Through desk study, the EMArecognized that:
(i) With regard to TPMB1, at their office of the main plant in Cua Ong Ward, Cam
PhaCity, the document was stored sufficiently; Cam Pha CCARB supplied
information frequently and adequately for the PMB.
(ii) Reporting regime from the stakeholders to TPMB1 was in a frequent and timely
manner.
(iii) Legal documents issued by City and Province PCs and grievances of
households in the project area are stored adequately.
II.2.8. RESETTLEMENT
All of relocated HHs in main plant area and freshwater reservoir area located in Quarter
10, Mong Duong Ward haveresettled by themselves according to their wishes through meetings
with CCARB and there is registration application of these households (which were sent to
15
households by Project Owner and Mong Duong Ward PC). Therefore, a resettlement site is not
needed as all of the relocated households have opted to self-relocation.
Self-relocatedhouseholds have been assisted as follows: each relocated household, on
top of their compensation for land, house, and assets attached to land, is provided with cash
assistance of VND90 million (following the Decree No.69/2009/ND-CP issued by GoV and
Decision No.499/2010/QD-UBND issued by PPC) for self-relocation. However, there are
differences in each area, and location of the land plot based on land price issued by PPC (for
example, Mong Duong Ward: VND 90 million, Communes: VND 75 million).
All of the resettlement assistance were paid in cash for AHs. To date, relocated HHs
have built their new houses, settled down and had better income. Most of the relocated HHs are
satisfied and support the Project.
16
PART III
ASSESSMENT OF LIVELIHOOD RESTORATION PROGRAM
III.1. ASSESSMENT OF LIVELIHOOD RESTORATION PROGRAM IN MAIN PLANT
AREA (Phase 1)
III.1.1. SURVEY METHODOLOGY
III.1.1.1. Identification of affected household
The total 53 affected households and organizations of this component included 40
affected households and 13 public and private organizations. Out of which, 15 households have
to relocate, most of whom are residents of Mong Duong Ward. However, a resettlement site is
not required as all of these households opted to self-relocation.
During the site visit, the EMAhas worked with TPMB1, cadastral officials, Mong Duong
Ward authority, in cooperation with village and residential group leaders in the affected area to
make a check list of AHs in main plant area. This check list has been served as the basis for the
survey of HHs living the affected area and vicinity.At the survey time, there were only 33 HHs
living in Mong Duong Ward while the others have moved to other places.
III.1.1.2.Survey Methodology
The survey were conducted using sociological survey method with sample size of33/40
AHs (accounting for 82.5%), equivalent to 33 HHs living in this area.
III.1.2. DEMOGRAPHIC AND OCCUPATIONAL STRUCTURE OF THE AFFECTED
PERSONS
o The number of persons and household size:
The survey of livelihood and income restoration of phase1 was conducted at Mong
Duong Ward with 33 households whoselands, houses, and structures were affected by land
acquisition for the construction of TPP 1.
There were total of 135 persons with average household size of 4.09 persons. In
particular, HHs with 3 persons accounted for39.4% while HHs with 4 and 5 persons were 30.3%
and 18.2%, respectively. The percentages of HHs with 6 persons and HHs with 7 persons each
were equivalent to 6.1%
Table 3: Persons and household size
The number of persons The number of household Proportion % Average
3 13 39.44.09
4 10 30.3
17
The number of persons The number of household Proportion % Average
5 6 18.2
6 2 6.1
7 2 6.1
Total 33 100.0
o The population structure by age, ethnic minority and gender
The age structure of the APs from the survey is presented in Table 4. The household
members in working age that are classified by age that have the ability to converse
occupations.
Results of data processing showed that group in working age have highest percentage;
out of which, the members in the 18-30 age group accounted for 28.9% while those in the 31-60
age group made up 42.2%. In particular, the rate of male/female is quite balance. In addition,
Kinh people make up the majority of the population with 129 persons of 31 HHs (95.6%). There
are 2 ethnic minority HHs (including 1 Dao HH and 1 TayHH) composed of6 persons
(accounting for 4.4%).
Table4. Age structure by gender and ethnic minority
Age
Gender Ethnic Minority
Male Female Total
Kinh
people
Tay, Dao
people Total
0-5 years old4 5 9 9 0 9
44.4% 55.6% 100.0% 0.0%
6-10 years old4 4 8 8 0 8
50.0% 50.0% 100.0% 0.0%
11-14 years old8 2 10 10 0 10
80.0% 20.0% 100.0% 0.0%
15-17 years old3 2 5 5 0 5
60.0% 40.0% 100.0% 0.0%
18-30 years old21 18 39 36 3 39
53.8% 46.2% 92.3% 7.7%
31-60 years old30 27 57 56 1 57
52.6% 47.4% 98.2% 1.8%
Over 60 years old3 4 7 5 2 7
42.9% 57.1% 71.4% 28.6%
Total73 62 135 129 6 135
54.1% 45.9% 100.0% 95.6% 4.4% 100.0%
18
o Level of education and occupational structure
For income and livelihood restoration program, occupational structure of AH members is
very important, whichshows the job shifting trend of peoplein the project area. Occupation of
APs have been influenced by their level of education and training, which in turn shall decide
their occupations/working areas.
o Educational attainmentof affected household members
The results show that members finished secondary school and high school make up the
majority with 31% and 33 %, respectively, these people are mostly spouses of the household
heads; followed by members who completed primary school with the percentage of 15% while
there are a few people who have college and university education, accounting for 11%. They
are mainly APs from the younger generation of these households.
o Occupation before and after the Project
Land acquisition directly affected the production activities and occupations of the APs.
Prior to land acquisition, 12.6% of the HHs had been engaged in agriculture, which is reduced
to 7.4%. These AHs are mainly engaged in farming on the land area outside the project area.
The unemployment rate has increased from 0.7% to 3.0% after the Project. Similarly, the
proportion of people who stay at home as housewives has increased by3%. Due to impacts on
agriculture, people shifted to business and serviceswith the significant boost from 3.7% at the
pre-project time to 10.4% after the project. Some household members chose a new path for
their occupations; however, due to lack of professional skills, many people have come to the
free labour market (increased by3% after the project)
Table5. Occupation of household members before and after the Project
Occupation
Household member
Post-project Pre-project
Under the working age 17 12.6% 17 12.6%
Cultivation 2 1.5% 17 12.6%
Cultivation and livestock husbandry 1 0.7% 1 0.7%
Handicraft 7 5.2% 7 5.2%
Business and services 14 10.4% 5 3.7%
Housewife 12 8.9% 8 5.9%
Pupil, student 25 18.6% 32 23.7%
Free labour 18 13.3% 14 10.4%
Worker 11 8.1% 19 14.1%
Civil servant 4 3.0% 4 3.0%
19
Occupation
Household member
Post-project Pre-project
Soldier, police 2 1.5% 0 0%
Repairer 1 0.7% 0 0%
Retired 10 7.4% 2 1.5%
Loss of working capacity 1 0.7% 0 0%
Driver 5 3.7% 5 3.7%
Unemployed 4 3.0% 1 0.7%
Others 1 0.7% 3 2.2%
Total 135 100% 135 100%
o Qualifications and working area
The survey result shows that one half of people are unskilled labors who have not
received vocational training. Their incomes mainly come from household economy and free
labour. The number of members who have intermediate level/technical workersaccounts for one
third of total number (28.1%), these people mainly work at state enterprises (coal enterprises
and forest plantation) located in Cam Pha City. The proportions of people have intermediateand
advanced levels make up 3.7% and 5.9%, respectively, mainly working for state and private
companies.
Table6.Qualification and working area of APs
Current working
areaNumber Percentage Qualification Number Percentage
Under working age 17 12.6% Under working age 17 12.6%
State enterprise 7 5.2% Not received vocational training 67 49.6%
State agency 8 5.9% Elementary level 5 3.7%
Private enterprise 11 8.1% Intermediate/Technical worker 38 28.1%
Cooperative 2 1.5% Advanced level 8 5.9%
Household 83 61.5%
Others 7 5.2%
Total 135 100.0% Total 135 100.0%
o Woman-headed household and poor household
At the assessment time, the survey result showed that there are 8 woman-headed
households, in which 2 of them are single women raising children belonging to Kinh
group. Ofthe total of 33 HHs, there are no poor households.
o Handing over land/houses/assets time
20
When being asked about the time of handing over site for the Project, more than 50% of
the respondents did not remember the exact time, 36.4% said that they handed over in
2009 and 12.1% said that the handing over time was 2008.
Table7.Pre-project and current houses
Type
Pre-project Current
Percent
age(%)
Area
(m2)
Constructi
on year
Perce
ntage
Area
(m2)
Construction
year
Thatched and bamboo cottage
Temporary house
Wooden house
Grade-IV house with steel roof
Grade-IV house with tiled roof
One-storey house with flat roof
Two-storey house and above
3.0
9.1
0
27.3
51.5
6.1
3.0
57.8 1996-200521.2
24.2
24.2
30.3
94.7 2008-2012
Compared to the pre-project time, the current houses of AHs are regarded as better.
Prior to land acquisition, 51.5% of HHs had Grade-IV houses with tiled roof while the HHs who
had 1-2 storey houses with flat roof accounted for more than 10%, which is also equivalent to
the number of HHs owned thatched cottages and temporary houses. Currently, as the project
has been completed, several HHs used their compensation money to build new houses, more
than 50% of HHs have 1-2 storey houses with flat roof while thatched and temporary houses
had no longer existed. At pre-project time, HHs built their houses in 1996-2005 with the average
area of57.8 m2 whilst houses were built in 2008-2012 with average area of 94.7m2 after the
project implementation.
III.1.3.COMPENSATION AND RESETTLEMENT
o Information disclosure
Prior to project implementation, the project information has been disseminated to 100%
of the AHs through the following forms:
Table8: Forms of information disclosure
Forms Percentage
Distributingleaflets about the Project information 3.0%
Distributing PIBs regarding project information, policies, and entitlements 0.0%
Broadcasting information through loudspeakers in commune, village/hamlet 18.2%
21
Forms PercentageDoor-to-door disseminating about project information and policies by the projectofficials/local authorities 33.3%
Local authorities/Project holding meetings with people in order to disclose information 100%
Local authorities/Project conducting consultations to receive opinions of AHs 60.6%
TPMB1coordinated with CLFD of Cam Pha City and Mong Duong Ward PC held
meetings with local people for information and policies disclosure. AHs have received
information through various forms of disclosure.75.8% of the respondents assessed that the
information disclosure was quite adequate, 21.2% said that the dissemination was very
adequate, while only 3% said that such activity was not sufficient. The project information
dissemination activities have helped the AHs easily understand the project impacts and their
entitlements.
o Detailed measurementsurvey(DMS) andcompensation plan preparation
When being asked about DMS, 100% of the respondents confirmed that they
haveparticipated in DMS activities with CCARB and signed the DMS records. These AHs also
confirmed that they have referred to the compensation plan before receiving the compensation
money and the plan has correctly showed the amount of affected assets and compensation
rates.The compensation planshave been posted publicly at Mong Duong Ward PC Office.
Regarding grievance procedures related to compensation, assistance, and resettlement, 54.5%
of respondentswere aware of this procedure while the rest, 45.5%, did not know. Out of which,
four (04) AHs had queries and complaints related to the followings: two (02) HHs lodged
complaints to Mong Duong Ward PC regarding low compensation rates, 1 HH was concerned
about the flood control plan for discharge channel area which required additional land
acquisition, and anotherhad query related to deduction of agricultural land use tax when
receiving compensation. After CCARB received the complaints, they have advocated and
explained to the aggrieved AHs to resolve the issues in a satisfactory manner to the AHs. To
date, there is no outstanding complaint.
o Magnitude of impacts on occupations, livelihoods, and income sources of AHs
Table 9. Type and magnitude of impacts on occupations and livelihoods
TypeMagnitude of impacts
TotalSevere Insignificant
Relocated13 0 13
39.4% 0.0% 39.4%
Relocating and losing 10% or more than 10%of productive landholdings
2 0 2
6.1% 0.0% 6.1%
Impacts on residential land/structures 8 2 10
22
TypeMagnitude of impacts
TotalSevere Insignificant
(relocation is not required) 24.2% 6.1% 30.3%
Losing 10% or more of their productivelandholdings
4 1 5
12.1% 3.0% 15.2%
Losing less than 10% of their productivelandholdings
0 2 2
0.0% 6.1% 6.1%
Impacts on residential land/structure(relocation is not required) and losing 10% ormore of their productive landholdings.
0 1 1
0.0% 3.0% 3.0%
Total27 6 33
81.8% 18.2% 100.0%
The survey result shows that out of the total 33 households, 27 are severely affected.
Out of which, 15 households have to relocate, including two relocated households who lost 10%
or more of their productive landholdings. The severely affected households had to find new jobs
as well as livelihood sources, accounting for 81.8%. 15 households have to relocate, making up
45.5%; eight AHs whose residential land/structures are affected but do not have to relocate,
representing 24.2%; the number of AHs losing more than 10% of productive landholdings
occupies 12.1% while two (02) AHs, or 6.1%, have to relocate and at the same time lose more
than 10% of their productive landholdings. The slightly affected households who are able to
maintain their current jobs and income sources accounted for 18.2%.
Table10. Types and magnitude of impacts on incomes
Type
Magnitude of impacts
TotalLost 50-100%of income
level
Lost 10-50%of income
level
Lost <10%of income
level
Relocated13 0 0 13
39.4% 0.0% 0.0% 39.4%
Relocating and losing 10% or morethan 10% of productive landholdings
2 0 0 2
6.1% 0.0% 0.0% 6.1%
Impacts on residential land/structures(relocation is not required)
7 3 0 10
21.2% 9.1% 0.0% 30.3%
Losing 10% or more of their productivelandholdings
4 1 0 5
12.1% 3.0% 0.0% 15.2%
Losing less than 10% of theirproductive landholdings
0 0 2 2
0.0% 0.0% 6.1% 6.1%
Impacts on residential land/structure(relocation is not required) and losing10% or more of their productivelandholdings.
0 1 0 1
0.0% 3.0% 0.0% 3.0%
Total 26 5 2 33
23
Type
Magnitude of impacts
TotalLost 50-100%of income
level
Lost 10-50%of income
level
Lost <10%of income
level78.8% 15.2% 6.1% 100.0%
Of the total 33 surveyed households, 78.8% said that they have lost 50% to100% income; most
of whom are severely affected households who have to relocate and at the same time lose
more than 10% of their agricultural landholdings. Those losing from 10% to 50% of their income
levels accounted for 15.2%, most of whom are AHs affected on residential land/structures but
do not have to relocate (9.1%). The remaining 6.1% are slightly AHs who lost less than 10% of
productive landholdings as well as less than 10% of their income levels. Compensation and
assistance for affected households
According to data provided by the TPPMB1 and from the previous monitoring batches
for 40 AHs in the main plant area, the total acquired area is 1,196,995.80 (m2) equivalent to the
amount of VND 67,181,575,600D. In which the compensation cost for lands is VND
15,448,934,800.
Total11: Types of acquired land and compensation amount
Type of land Number of HHs Amount (VND
Residential land 17 1,740,165,000
Garden land 16 3,395,473,900
Agricultural land 11 1,023,264,100
Forestry land 12 2,156,303,100
Aquacultural land 9 2,559,341,500
Others 11 4,574,387,200
Total 76 15,448,934,800
Total compensation amount for affected houses, structures, and other assets of AHs is
VND 50,463,640,800.
Table 12: Types of assets and compensation amount
Assets Number of AHs Amount (VND)
Structure 39 41,840,742,468
House 25 1,790,078,232
Other assets 39 6,832,820,100
Total 103 50,463,640,800
Total assistance amount for 15 relocated HHs is VND 1,270,000,000 including life
stability supports, rental allowances, relocation allowances, and other supports.
Table 13: Type of assistances
Assistance Number of AHs Amount (VND)
24
Assistance Number of AHs Amount (VND)
Life stability 15 52,950,000
Rental allowance 15 98,800,000
Relocation allowance 15 45,750,000
Assistance for beneficiary HHs of social policies 0 0
Bonus for timely handing over site 0 0
Others 15 1,072,500,000
Total 60 1,270,000,000
After receiving compensation, 39.4% of the surveyedHHs decided to invest but the
others (60.6%) did not. In which, 27.3% of the HHs invested in business establishment and
business expansion; 9.1% depositedtheir savings in bank, and 3.0% invested in other sectors.
Among these households, business investment broughtthe highest average profits while those
who deposited their compensation at the bank as savings expected to get monthly interest that
enough for them ensure their lives. The remaining AHs did not invest but used the
compensation to build and repair houses, pay debts, spend on daily expenses, buy essential
furniture, and especially, several HHs use the compensation money to spend on their children’s
education.
Table 14. Investment and using the compensation amount of affected households
Purpose
The average
investment
amount/month
(VND)
Percentage of
respondents
(%)
The average
profit/month
(VND)
Transferring money to relatives or lending
money to fiends0 0 0
Bank savings 14,485,000 9.1 1,267,000
Opening/expanding business 320,000,000 27.3 9,500,000
Other investment sectors 4,500,000 3.0 0
Paying debt 90,424,000 42.4
Spending on daily needs (food, clothes,
building and repairing house...)
8,700,000 12.1
o Resettlement and livelihood restoration
Among 33 surveyed AHs, 15 relocated households have received compensation and
moved to new places. Out of which, 13 households have relocated within the area of Mong
Duong Ward whereas two (02) AHs relocated out of the ward. Among these 15 households,
four (04) built houses on their land plots outside the affected area and eight (08) AHs bought
new land to build houses, and three (03) households have been given land by their relatives.
25
Among the surveyed AHs, 53.3% have received advices and assistances in relocation
and information regarding LRP activities. Out of which, 75% of the respondents have received
advices and supports from the ward/city authorities while 25% from
relatives/neighborhoods/friends.
For HHs that their lands have been acquired, they have received assistances in order to
restore income and create favorable conditions for them to settle down, develop production and
improve living standards after the project. 87.2% of the respondents said that they have not been
provided with assistances while 3.9% assessed that the assistance programs were not effective,
especially the seedling supply program. 8.3% of the respondents assessed that the vocational
training program and employment program of project or credit andloan supports were relatively
effective; only 0.6% of them said that these program werevery useful as they have received
information and placement of available jobs. There are 2/33 respondents got help from friends for
vocational training, job seeking, and income restoration.
Table 15. Overall evaluation of livelihood restoration assistances
Type of impact
Overall evaluation of assistances
TotalVery
usefulUseful
Not
useful
Not
receiving
assistance
Resettlement 0.0% 3.3% 0.0% 40.0% 43.3%
Partial impacts on lands/structures 0.6% 0.0% 3.3% 29.4% 33.3%
Losing more than 10% of agricultural
landholdings0.0% 5.0% 0.6% 11.1% 16.7%
Losing less than 10% of agricultural
landholdings0.0% 0.0% 0.0% 6.7% 6.7%
Total 0.6% 8.3% 3.9% 87.2% 100.0%
After compensation payment, in order to ensure income and living conditions, many HHs
have found jobs/income sourceswithin 1-3 months (60.6%) and 4-6 months (18.18%); while
percentage of HHs whotookone year or more was 9.09%, and 3.03% of the respondents are
still looking for a replacement job/income.
After handing over the land, due to lack of skills, many HHs have to work as seasonal
labour or do simple works that require good health. Many people assessed that due to difficult
economy in general, it was hard to find a job. Difficulties in employment lead to unstable
income, expense and education for their children. Recommendations are often directed to
training and resolving employment issues for their children.
26
III.1.4. COMPARISON BEFORE AND AFTER LAND ACQUISITION AND RESETTLEMENT
The analytical results show that the number of HHs doing agriculture have no
significant change during pre-project and post-project because they still have land area for
agriculture, forest, aquaculture and fishing. However, their average incomes changed
substantially. For HHs growing rice and vegetables, their current income level equals 3% to pre-
project income. Similarly, income level of HHs doing aquaculture and fishing equals 14% to pre-
project one and income of HHs doing livestock husbandry is reduced by more than30%. In
contrast, income from forestry has increased slightly (by 30%). The number of HHs who shifted to
businessand services is boosted from 6 to 8 HHs with the income raising from VND 10 million to
140 million. Similarly, the income from other sources isalso increased by 5 times. The AHs
haveshifted to investment and diversified their livelihoods in order to obtain better incomes.
Many households said that their income are enough for living expenses (69.6%). In
contrast, 15.2% of respondents have income level higher than the expense level. 15.2 %
respondents have difficulty in cover living costs, thus, have tocut downtheir spending and borrow
money.
Table 16: Comparison of income before and after land acquisition and resettlement
Income sources
Pre-project (2007 and
earlier)Present (from 2012 to 2013)
Number
of HHs
Average household
income/year (VND)
Number
of HHs
Average household
income/year (VND)
1.Growing rice, vegetable 11 14,545,454.55 11 454,545.45
2.Planting flowers, ornamental trees 3 13,333,333.33 4 13,750,000.00
3.Livestock husbandry (chicken, pig,
cow, buffalo…)14 14,928,571.43 12 9,166,666.67
4.Aquacuture and fishing 6 29,166,666.67 3 4,000,000.00
5.Forestry 7 9,714,285.71 6 14,500,000.00
6.Business, trading and service 6 10,333,333.33 8 140,000,000.00
7.Salary/ benefits 15 23,400,000.00 14 45,714,285.71
When being asked about the living standards of the households before and after the project,
42.4% of the respondents said that the living standards were better, 33.3% assessed that it was
the same, while 18.2% thought that their living standards were worse. The remaining 6.1% said
that it was hard to evaluate.Regarding theirevaluation and comparison of availability and
reliability of utilities, public services, and market that HHs access toat present, 45.5% said that it
27
was better, 39% assessed that such services were the same, 13.3% considered it washard to
evaluate while 2.3% answered that it was worse.
In general, HHs in project area said that their current living conditions werebetter than
the pre-project level (45.5%), 30.3% assessedthat their living standards were the same while
24.2% of them evaluated it was worse. Explaining for better living standards, the surveyed AHs
said that they have used their compensation and assistance to invest in business and thereby
increasing their income. On the contrary, HHs assessed that their living conditions were worse
because they did not have enough money to start a business, were unable to find jobs, and lost
productive land for farming. In addition, environmental pollution, unemployment, and increase in
social evils are most concerned by the interviewed AHs. When being asked about their
satisfaction towards their current jobs and living conditions, 70% of the respondents said that
they weresatisfied while 30% of them assessed otherwise.
III.1.5. LIVELIHOOD RESTORATION MODELS/PROGRAMS
Models of LRP: TPMB1has organized LRP for AHs in main plant area such as:
organizing Agricultural and forestry extension programs by invitingagricultural and economic
specialists to provide training in cultivation and livestock husbandry techniques as well
astraining materialsfor 40 participants. In addition, veterinary training course for 2
representatives of Aps were also conducted. However, there was no AP registered for this
course as most of the Aps havechanged to business by using compensation for opening shops
and small businesses to serve residents and workers in the project area. Some APs are
workers responsible to planting and taking care of industrial crops for Cam Duong Forestry
Company. Some APs also bought trucks for transporting materials and suppliers for residents in
the area.LRP for AHs in main plant area have been implemented and achieved certain results.
However, most of severely AHs did not have access to or were not interested in the LRP
activities. However, most of them have actively changedtheir production model, services and
business to be suitable to their current conditions. In general, their living standardsare better
after land acquisition. Relocated HHs have settled down and Improved their living conditions.
III.2. ASSESSMENT OF LIVELIHOOD RESTORATION PROGRAM FOR
FRESHWATER COMPONENT (phase 2).
III.2.1. SURVEY METHODOLOGY
III.2.1.1. Identification of affected households
Of the total 192 households affected by the FWC, 127 are affected by the reservoir
whereas 65 households are affected by the pipeline. Among 127 households and organization
(Cam Pha Forest Plantation) affected by the reservoir in Quarter 10 of Mong Duong Ward, 37
28
have to relocate. All of these households are insignificantly affected by the water pipeline in
Mong Duong Ward and Cong Hoa Commune as none of them lost more than 10% of their
productive landholdings or had to relocate. Regarding 37 relocated households of the reservoir
subcomponent, a resettlement site is not needed as all of them opted to self-relocation in the
area of Quarter 10, Mong Duong Ward.
During the site visit, the EMA have worked with TPMB1, cadastral officials, the authorities
of Mong Duong Ward and Cong Hoa Commune, in cooperation with and village and residential
group leaders in the affected area to make a check list of AHs. This list has been served as the
basis for the survey of HHs with the focus on the severely AHs and relocated households. At
the survey time, there were 28 out of 37 relocated HHs living in Quarter 10 ofMong Duong Ward
while nine (09) AHs have moved to other places (including 7 AHs moved to Dam Ha District and
2 AHs to Tien Yen District).
III.1.1.2. Survey Methodology
The survey was conducted usingsociological survey method with sample size of100% of
the relocated AHs (37 HHs). However, 9HHs have displaced to other places so the selected
samples were all of the relocated AHs living in Mong Duong Ward (28 HHs, or76%).
III.1.2. DEMOGRAPHIC AND OCCUPATIONAL STRUCTURE OF AFFECTED
HOUSEHOLDS
o The number of persons and household size
The livelihood restoration survey for the second phase was conducted at Quarter 10,
Mong Duong Ward of28 HHs losing houses, lands, and structures due to land acquisition for the
construction of FWC.
28 AHs were made up of 116 persons with average household size of 4.14 persons. In
which, 2 HHs had smallest scale with 2 persons/HH (7.1%), 9HHs with 4 persons/HH accounting
for 32.1%. Finally, the HHs with 5 persons, 6 persons and 7 personsaccounted for 21.5% (6
HHs), 10.7% (3 HHs), and 3.6% (1 HH), respectively.
Table17: Persons and Household size
Number of persons Number of HHs Percentage (%) Average
2 2 7,1
4.14
3 7 25,0
4 9 32,1
5 6 21,5
6 3 10,7
7 1 3,6
29
Number of persons Number of HHs Percentage (%) Average
Total: 116 28 100.0
o The population structure by age, ethnic minority and gender
Age structure of APs in survey sample is presented in Table 18. The results of data
processing showed that household members were classified in age groups. In which, the
majority of the APs are in the working age (15-60 years old), representing 64.6%. The
difference in proportions of males and females was not significant,at52.6% and 47.4%,
respectively. There was no person belonging to the mainstream Kinh group, butTay and Dao
ethnic minority groups. 24 out of 28 surveyed households were Dao people made up of 98
persons (84.5%) and 4 TayEM households with 18 persons (15.5%).
Table18. Age structure by ethnic minority and gender
AgeGender Ethnic minority
Male Female Total Tay People Dao People Total
0-5 years old5 3 8 0 8 8
62,5% 37,5% 0% 100%
6-10 years old6 4 10 3 7 10
60,0% 40,0% 30,0% 70,0%
11-14 years old8 7 15 3 12 15
53,3% 46,7% 20,0% 80,0%
15-17 years old3 7 10 2 8 10
30,0% 70,0% 20,0% 80,0%
18-30 years old16 14 30 3 27 30
53.3% 46.7% 10,0% 90,0%
31-60 years old18 17 35 5 30 35
51,4% 48,6% 14,3% 85,7%
Over 60 years old5 3 8 2 6 8
62,5% 37,5% 25,0% 75,0%
Total61 55 116 18 98 116
52,6% 47,4% 100.0% 15,5% 84,5% 100.0%
o Education of AH members
The affected households living in the reservoir area mostly belong to the ethnic minority
groups; therefore, their educational attainment was limited. The survey results showed that the
majority of the APs, or 45%, had secondary education, followed by high school education with
26%, and primary school education with 25%. The number of APs who had college and
university education accounted for the small proportion, at 4%. The number of people without
schooling represented 1%; most of them were the elderly and students dropped out of schools.
30
o Occupational structure before and after the project
Land acquisition has directly affected the production activities and occupations of the
APs. At pre-project time, 50% of the APs have been dependent on agricultural production such
as cultivation and livestock husbandry. After land acquisition, the proportion of people engaged
in farming and livestock husbandry has reduced to 33.6%. On the other hand, the number of
APs shifted to business and services have increased significantly from 2.6% to 6.9% as well as
the number of workers have raised from 3.5% to 8.6%. Similarly, the proportion of
seasonallabours hasalso boosted from 2.6% to 10.3 % while unemployment rate has also
increased from 1.7% to 3.5%. Overall, the statistical indicators showed that this is inevitable
after land acquisition and resettlement. Due to significant decrease in agricultural land area, the
number of people engaged inagricultural activities have reduced substantially. Moreover, there
were other reasons as people had cash compensation to open small businesses or worked at
the forestry plantation, some chose to work as seasonal labours… However, this was positive
sign for EM AHs as they were only used to cultivation and livestock husbandry. Their current
jobs and activities have shown a transformation and more opportunities for the APscompared to
the pre-project time
Table19. Occupations of the APs before and after the project
Occupation
Members of AHs
Post-project Pre-project
Under working age 12 10,3% 16 13,8%
Cultivation and livestock husbandry 39 33,6% 58 50,0%
Business and services 8 6,9% 3 2,6%
Housewife 5 4,3% 4 3,5%
Pupil, student 16 13,8% 18 15,5%
Free/seasonallabour 12 10,3% 3 2,6%
Worker 10 8,6% 4 3,5%
Repairer 2 1,7% 2 1,7%
Retired 2 1,7% 2 1,7%
Loss of working capacity 3 2,6% 3 2,6%
Driver 3 2,6% 1 0,9%
Unemployed 4 3,5% 2 1,7%
Total 116 100% 116 100%
o Qualifications and working area
The survey results showed that 50% of HH members did not have skills as they have
not undergone any vocational training, their working area were mainly household economy and
31
seasonal labour. 15.5 % of them had elementary level while the percentage of members had
intermediate level/technical workers was 8.6%. Most of these APs have participated in the LRP
vocational training organized by the Project; some of them have worked as workers at the state
and private enterprises (coal mining, forest plantation)in Cam Pha City after taking part in the
training course. The percentage of APs with high professional skills was low, at only 1.7%.
Table20.Qualifications and working area of APs
Current working area Quantity Percentage Qualifications Quantity Percentage
Under working age &
students28 24,1%
Under working age &
students28 24,1%
State enterprise 8 6,9%Not receiving vocational
training58 50,0%
State agency 0 0,0% Elementary level 18 15,5%
Privtae company 9 7,8%Intermediate/Technical
worker10 8,6%
Cooperative 0 0,0% Advanced level 2 1,7%
Household 67 57,8%
Others 4 3,5%
Total 116 100.0% Total 116 100.0%
o Woman-headed household and poor household
At the monitoring time, the results showed that there were 4 woman-headed HHs but no
single women raising children. of the total28 surveyed HHs, there were no poor
households. These HHs are all ethnic minority HHs belonging toTay and Dao
groups(Dao EM people accounted for the majority).
o Land/House/Asset handing over time
When being asked about the time of site handing over, 80% of the respondents said that
it was between 2012 and 2013 while 20% of them did not remember the exact time.
Table21.Types of Houses before and after the Project
Type
Pre-project Post-project
Percentag
e (%)
Averag
e area
(m2)
Constructionyea
r
Percentag
e (%)
Averag
e area
(m2)
Constructio
n year
Thatched
cottage
Temporar
y house
Wooden
6..8
3.7
10.2
21.3
50.0 1995-2006
8.2
80.0 2012-2014
32
house
Grade-IV
house
with steel
roof
Grade-IV
house
with tiled
roof
One-
storey
house
with flat
roof
Two-
storey
house
56.0
2.0
0
3.8
49.5
38.5
Compared to the pre-project time, the current houses of affected householdswere built
better and more stably. Prior to the Project, HHs located in reservoir area mostly lived in Grade-
IV houses with tiled (56%) and steel roof (21.3%). On the other hand, there were afew HHs
living in flat-roofed house (2%), and the number of temporary housesaccounted for 33.7%. The
proportions of thatched cottage and wooden house were 8.8% and 10.2%, respectively.
At present when the Project has been completed, most of HHs used their compensation to build
better houses. The survey data showed that 38.5% of theAHs have built two-story or more
storeys houses, 49.5% of theAHs have built one-storey house with flat roof while only 8.2% and
3.8% of the HHs lived in Grade-IV houses with steel and tiled roof, respectively. Thatched
cottages and temporary houses are no longer existed. Prior to the project, most of the AHs built
their housesbetween 1995 and 2006 with the average area of 50m2. After the project, their
houses were built in 2012-2014 with average area of80m2., which coincided with the site
handing over, compensation and assistance payment, and resettlement time.
III.1.3. COMPENSATION AND RESETTLEMENT
o Information disclosure
Prior to the project implementation, the project information has been disclosed to 100%
of the AHsvia the following forms: meetings, consultation, loudspeakers, leaflets, and notices
posted at public places, etc.
33
TPMB1 hascoordinated with CLDF of Cam Pha City and PCs of Mong Duong Ward,
Cong Hoa and Cam Hai communes to hold meetings with the APs to disseminate the project
information and policies. 85% of the surveyed evaluated that the information disclosure was
quite adequate, 13% assessed as very sufficient whileonly 2% said that the information
dissemination activities were inadequate. The project information disclosure activities have
helped people easily understandthe project impacts and their entitlements.
o Detailed measurement survey (DMS) and compensation plan preparation
As forDMS process, 100% of the respondents said that theyparticipated in DMS with the
CCARB and signed the DMS records. These HHs also confirmed that they have referred to the
compensation plan before receiving the money and the plan showed the exact amount
ofaffected assets and compensation rates. Also, such plan was posted publicly at
Commune/Ward PCs.Basically, DMS was conducted in accordance with the procedures and in
an accurate manner. However, due to looseland management mechanism of Vietnam in
general and of local authorities in particular, it took a lot of time for CCARB to identifyland
ownership records and legal basisfor compensation rate application in order to prevent
disadvantages for AHs.Additional DMS for some households have been conducted to ensure
the accuracy in preparation of compensation plan and compensation/assistance payment.
o Magnitude of impacts on occupations and livelihood sources of affected households
According to the survey results, in total of 28% interviewed HHs that affected severely
and resettled, there were 17HHs affected more than 10% of their agricultural
landholdings.Severely affected households who had to find new jobs and livelihood sources
accounted for 60.7% while 11 HHs who had to relocate but lost less than 10% of their
agricultural landholdings (39.3%) still cultivate on their remaining land area and maintain their
income from agriculture.
o Compensation and using compensation amount
According to the summarized data of TPMB1 andfrom the previous monitoring batches
for 195 households affected by the FWC total area of land acquisition is 526.84m2, which is
equivalent to the compensation/assistance amount of VND 263,496,220,342. After receiving
compensation, 36.2% of AHs decided to invest while 63.8% did not. In which, 18.5% have
invested to open or expand their business; 12.5% have deposited their savingsat the banks and
5.2% of them invested in other sectors. The small businesses have brought back big average
profits for those invested. On the other hand, the APs with savings expected to have monthly
interests to ensure their lifeand withdraw money when needed.63.8% of the AHs did not invest
but spent most of their compensation on building new houses while the others used
34
compensation to pay debts, cover daily expenses, buy furniture and utilities, and pay tuition
fees.
o Resettlement and livelihood restoration
Of the total 37 self-resettled HHs of the FWC, 9 HHs have moved to new areas outside
the Cam Pha City, including HHs of Ly Van Phuc, Ly Van Thang, Ly Van Binh, Ly Van Thien,
Phun A Hai, Phun A Phuc, Ho Van Ducwho are Dao people and have moved to Dam Ha
District, QuangNinh Province. The remaining 2 HHs whohave resettled in Tien Yen District are
Dang Xuan Ba (Dao people) and Nguyen Van Bay (Taypeople).
28 interviewed HHs are living in a close vicinity(about 2km from their former residences)
in Quarter 10, Mong Duong Ward. All the households used their compensation/assistance to
buy land and new house. None of them had land plot outside the affected area or been given
land by their relatives. Basically, the new houses of these AHs are considered as better and
more stable than before.
83.2% of the respondents said that they received advice and help regarding
resettlement and LRP information. Out of which, 85% received advices and assistances from
local authorities while 15% from their friends/neighbors.
For HHs that their land has been acquired, they have received assistances in order to
restore income and create favorable conditions for them to settle down, develop production and
improve living standards after the project. 78% of the respondents said that they haveparticipated
in these programs while 28% did not. Out of which, 8.5% assessed that the assistance programs
were not effective, especially the cooking trainingprogram. 78.5% of the respondents assessed
that the vocational training program and employment program of project or credit andloan
supports were relatively effective; whereas 13% of them said that these program were very useful
as they have received information and placement of available jobs and helps from friends and
relatives.
After compensation for site clearance, in order to ensure their income and living
standards, some members from these HHs have found new jobs/income sourceswithin 1-3
months (70.3%). The percentages of members who have found new jobswithin 4-6 months and
one year were 21.7% and 8.0%, respectively.
In general, the difficulties of these HHs after land acquisition and resettlement are due
to their lack of trained skills; therefore, it is hard for them to find new jobs. As they worked as
seasonal labors with unstable wages, it was difficult to maintain their incomes and to spend on
their living costs and children’s study. However, the interviewed AHs assessed that they
overcame all of these initial difficulties as they were active in changing their jobs and adapting
35
to the new conditions together with assistances from the local authorities. In addition, the
TPMB1 has provided advisory as well as training and support programs including vocational
training and job placement. Therefore, at the monitoring and evaluation time, the APs have
stable jobs and better incomes compared to the pre-project time.
III.1.4. COMPARISION BEFORE AND AFTER LAND ACQUISITION AND RESETTLEMENT
The survey data showed that there was no significant change in the number of HHs
engaged inagricultural activities (cultivation/livestock husbandry) before and after the project as
the APs still have enough remaining land for farming, forestry, livestock husbandry, and
aquaculture. However, the number of householdmembers not involved in agricultural production
activities reduced substantially. For HHs growing rice and rain-fed crops, their current
incomelevelis equal to 75% of the pre-project level while income from livestock husbandry also
fell by 20%. It is worth noting that the number of HHs conversing to business and servicehave
increased from 2 to 8HHs with average income raised by 29%. Average income from salary and
allowances (from those who work at private/state company and production facilities…) increased
to 69.5%. The households affected by the project has conversed the investment model and
diversified their livelihoods to obtain better incomes.
Table 22: Comparison before and after land acquisition and resettlement
Income sources
Pre-project (2011 and
earlier)Present (2012-2015)
Number
of HHs
Average
income/year
(VND)
Number
of HHs
Average
income/year (VND)
1.Growing rice and crops 28 12,525,650 24 9,450,634
2.Planting flowers, ornamental
plants0 0 0 0
3.Livestock husbandry (pig,
chicken, cow, buffalo,…)28 15,658,423 26 12,147,312
4.Aquaculture and fishing 6 5,142,690 2 4,634,798
5.Forestry 18 7,314,237 15 6,213,980
6.Trading, business, services 2 12,192,354 8 42,678,950
7.Salary/Allowances 4 25,500,000 11 36,450,500
The survey and interview showed a positive outcome with 45.6% of the respondents
assessed that the living standards were better than before while 35.4% assessed as the same
and only 15% thought that it was worse. The remaining 4% said that it was difficult to assess.
Evaluating and comparing of the availability and the reliability of utilities, and accessibility to
36
public services and market of the AHs, 68.5% said that such services were better, 23.5%
assessed the same while 8% considered it was hard to evaluate. None of these AHs assessed
that it was worse. In general, HHs in the project area said that their current living conditions
are better than before (62.6%), 31.2% of them believed that it is the same while 6.2% evaluated it
was worse. The reason for better conditions is they received the compensation/assistance then
invest in business and build bigger house and resettlement site is in the center leads to
convenient in traffic and public services…...In contrast, those who said it is worse as they used up
compensation to build house and buy furniture while the area of production land was reduced and
they have no job. When asked about satisfactory level of current job and living standards, more
than 80% said that they are satisfied, below 20% of respondents is not happy with their current
jobs and living standards.
In general, HHs in project area said that their current living conditions were better than the pre-
project level (62.6%), 31.2% assessed that their living standards were the same while 6.2% of
them evaluated it was worse. Explaining for better living standards, the surveyed AHs said that
they have used their compensation and assistance to invest in business and thereby increasing
their income. Their houses were also improved. The relocation area is also the center in the
area; therefore, it is convenient for transportation and accessibility to public services. On the
contrary, HHs assessed that their living conditions were worse because they did not have
enough money to start a business as they have used up their compensation for building houses
and purchasing furniture. In addition, due to decrease in productive landholdings and inability to
find new jobs, they found their living conditions worse.When being asked about their satisfaction
towards their current jobs and living conditions, more than 80% of the respondents said that
they were satisfied while less than 20% of them assessed otherwise.
III.1.5. LIVELIHOOD RESTORATION PROGRAM/MODEL
“Implementation of site clearance and resettlement has been completed and achieved good
results. LRP implementation has been finished. In 2014, TPMB1 hascoordinated with local
authorities, consulting agencies, and contractorsto carry out LRP for AHs of the FWC, which have
achieved good results. The training courses such as motorbike repairing, agricultural/forestry
extension, cooking, small credit/loan access support… have been supported and participated by
local people.” (Mr.Nguyen Cong Chi – Representative of TPMB1)
LRP models and activities: TPMB1 implemented LRP for AHs of the FWC.Specifically,in
2004, TPMB1 held training coursesincluding agricultural extension (cultivation and livestock
husbandry), elementary vocational training incooking and motorbike repairing for officials of
communes/wards. In addition, they alsocarried out small credit/loan access support program
37
(Company will pay interest). However, as the loan size of the Social Policy Bank is small, none of
the AHs has accessed to this program.
According to Training Contract No.105/HDDT-2014/ADN1 on 7 July 2014 between
TPMB1U and Cam PhaVocational Training Centre, vocational training courses have been
organized for APs of the FWC in Quarter 10, Mong Duong Ward starting from July/2014,
including:
(i) Training courses for cultivation-livestock husbandry techniques had 80 participants
(ii) Elementary course for cooking techniques with 11 participants
(iii) Elementary course for motorbike repairing services with 10 participants
These training courses were organized for two (02) months with the total cost of VND
143,770,000 includingsalaries of the trainers, costs for training materials, tools and equipment
for practice, and classrooms, and lunch allowances for trainers and participants.
LRP for AHs of the FWC have been implemented and achieved certain results.
According to evaluation of TPMB1 representative- andMr. Nguyen Van Nuc, Secretary of Party
Cells of Quarter 10, Mong Duong Ward, vocational training courses have partly helped young
members of AHs finding suitable jobs such as: for motorbike repairing services, most of the
participants haveopened or worked at motorbike repairing shops in the area; for training
courses in cultivation and livestock husbandry techniques, majority of the participants
haveworked for Cam Pha forestry plantation while those who learned cooking have worked at
restaurants and hotels in Cam Pha city and the vicinity.
In general, for livelihood restoration of AHs of the FWC, basically all of the HHs,
especially severelyand relocated AHs have built new houses and settled down. The interview
results showed that after land acquisition, the area of productive landholdings has been
reduced. However, prior to land acquisition, incomes from agricultural and forestry production
were not high; therefore, the living standards were difficult. When receiving compensation, the
AHs had capital to invest in business, and a part of the compensation was used to build and
repair houses. The remaining was used to invest in livestock husbandry and businesses (some
AHs also bought trucks to transport goods). Some HHs deposited residual compensation to the
bank for interest. In addition, there are few interviewed HHs have concerns that, although
their current lives are better than before with improved houses and better living standards, they
are still worried about their unstable and unsafe future since the AH members had to work as
hired labours and did not participate in production activities as the productive landholdings were
reduced. Generally, the LRP of the Project has been implemented and achieved certain
results. However, most of the severelyAHs said that they participated in some models while the
38
others did not have access to or are not interested in LRP that has been implemented as they
have taken initiative in changingproduction and business models to be suitable to the current
conditions. Thus, their living standards have been improved after land acquisition. Relocated
HHs lived in this area have built new houses and settled down.
“Most of severelyand relocated AHs built new houses and settled down in Quarter 10, Mong
Duong Ward, 2km from the place they used to live (reservoir area), except for about 10HHs
who have already moved to other places. In general, HHs have a better life after resettlement.
However, the area of productive land was reduced, so HHs have conversed to business,
services, trading, or working at the companies, … In 2014, the Project organized vocational
training courses in Mong Duong Ward for young members of AHs. After finishing the course,
some of them work at motorbike repairing shopswhile the others work at Cam Pha forestry
plantation and other enterprises which help them have better income after the training”.
(Mr.Nguyen Van Nuc – Secretary of Party Cells in Quarter 10, Mong Duong Ward).
39
PART IV
CONCLUSIONS, RECOMMENDATIONS VÀ LESSONS LEARNED
(i)During final M&E, site clearance-phase 1 for main plant area and auxiliary
components have been completed and achieved good results. LRP has also been
implemented. However, there are many AHs did not participate in this program due to different
reasons. In addition, some phases in theland acquisition and resettlement processare not fully
complied with the RP regulations (these issues were presented in 10th M&E report)
(ii)Site clearance – phase 2 (RP for freshwater component including pipeline and
reservoir) has also beencompleted in 2014 and achieved good results. However, in the process of
implementation, there were some shortcomings in DMS, which were presented in previous
monitoring, some HHs did not receive compensation as they were not satisfied with the
compensation payment (price was applied incorrectly, identificationof land ownership records has
not been carried out…). These shortcomings were checked and reviewed promptly by TPMB1
and Cam Pha City CLDF in order to supplement and pay compensation for HHs, address totally
these shortcomings so AHs were not disadvantaged.
(iii) TPMB1 and consulting agency should strengthen supervision during
construction/operation/environment processes of components to ensure that DMS and
compensation are implemented for any adverse impacts on local people in accordance with the
project policies.
(iv) Cam Pha City CARB is directly responsible for implementing site clearance and
compensation payment; therefore,close coordination with stakeholders is needed,
particularlyproviding documents and data related to site clearance and resettlement for
TPMB1in a regular and timely manner, better coordinating with consultingagencies and
stakeholders to help them fulfill their duties.
(v) Stakeholders should pay attention to sustainable livelihood restoration program for
AHs, especially vulnerable and poor groups. They also need long-term strategies to help these
AHs have a better living standards after resettlement. Livelihood strategies of each
severely/relocated AH are needed to identifyproject impacts on HHs and members of HHs.
(vi) Develop specific and suitable LRP for each district;
(vii) Design livelihood models or intervention activities for severelyAHs by type of
occupations that they are working and their expectations to suit each area and farming
practices of people;
40
(viii) A better coordination is needed among the authorities at different levels,
projectstakeholders, and HHs in LRP implementation in order to facilitate the livelihood
restoration of severely affected households in a prompt and effective manner.
41
APPENDIX
Appendix 1: List of interviewees
No. Full name Address Note
1 Nguyen Cong Chi TPMB1
In charge of the site
clearance for Mong
Duong Thermal Power
1 project.
2 Vu Tuan HungOfficial of Finance and Planning
Department of TPMB1
4 Pham Van Chien Vice president of Mong Duong Ward PC
5 Tran DucChuyen Cadastral official of Mong Duong Ward
6 Dinh Van Luc Vice president of Cong Hoa Commune PC
7 Bui Thi Suu President of Cong Hoa Commune PC
8 Pham Van Tan Quarter 8, Mong Duong Ward
9 Vu ThiLanh Cam Y Quarter, Mong Duong Ward
10 Vu Thi Chap Group 148, Quarter 9, Mong Duong Ward
11 Pham Van Quy Group 148, Quarter 8, Mong Duong Ward
12 Le Anh Dung Group 148, Quarter 8, Mong Duong Ward
13 Doan Van Xuong Group 148, Quarter 8, Mong Duong Ward
14 Hoang Van Kim Group 148, Quarter 8, Mong Duong Ward
15 Nguyen DinhVinh Group 148, Quarter 8, Mong Duong Ward
16 Pham QuangHoan Group 148, Quarter 8, Mong Duong Ward
17 Nguyen Trung Lap Group 148, Quarter 8, Mong Duong Ward
18 Tran DuyThien Group 148, Quarter 8, Mong Duong Ward
19 Pham Van Thuy Group 148, Quarter 8, Mong Duong Ward
20 Ngo Ngoc Thuy Quarter 8, Mong Duong Ward
21 Nguyen Thi Ban Quarter 8, Mong Duong Ward
22 Doan Van Son Quarter 8, Mong Duong Ward
23 Doan Van Phuong Quarter 8, Mong Duong Ward
24 Doan Van Quy Quarter 8, Mong Duong Ward
25 Nguyen Thi Ha Quarter 8, Mong Duong Ward
26 Khong Van Quyet Group 148, Quarter 8, Mong Duong Ward
27 Dang QuangTrung Group 148, Quarter 8, Mong Duong Ward
28 LuuDucCuong Group 148, Quarter 8, Mong Duong Ward
42
No. Full name Address Note
29 Truong Van Tro Village 4, Cam Hai Commune
30 Bui DinhKhe Village 3, Cam Hai Commune
31 Ha Thi Tieu Village 5, Cam Hai Commune
32 Nguyen Van NucSecretary of Party cells in Quarter 10,
Mong Duong Ward
33 Nguyen Thi Dang Chief of Quarter 10, Mong Duong Ward,
34 Ly Van Phuc Quarter 10, Mong Duong Ward
35 Ly Van Tu Quarter 10, Mong Duong Ward
36 Ly Van Hai Quarter 10, Mong Duong Ward
37 Dang A Ung Quarter 10, Mong Duong Ward
37 Luu Van Co Quarter 10, Mong Duong Ward
39 Loan Van Quang Quarter 10, Mong Duong Ward
40 Ngoc Van Bay Quarter 10, Mong Duong Ward
41 Ly Thi Hai Quarter 10, Mong Duong Ward
42 Ly Van Minh Quarter 10, Mong Duong Ward
43 Dang Xuan Minh Quarter 10, Mong Duong Ward
44 Ngoc Van Trieu Quarter 10, Mong Duong Ward
45 Hoang Xuan Doan Quarter 10, Mong Duong Ward
46 Trieu QuyBinh Quarter 10, Mong Duong Ward
47 Luong Van Yen Quarter 10, Mong Duong Ward
48 Dang A Sut Quarter 10, Mong Duong Ward
49 Ban Van Nam Quarter 10, Mong Duong Ward
50 Ho Quang Sang Quarter 10, Mong Duong Ward
51 Ho Van Thanh Quarter 10, Mong Duong Ward
_____________
43
Appendix 2: Some images of the field trip
Mong Duong Thermal Power Center completed,
contributed electric into National power grid
Thermal power plant 1 &2
Interview AH- Mr.Nuc- Secretary of Party cells in
Quarter 10, Mong Duong Ward
Interview HH in reservoir area, Quarter 10,
Mong Duong Ward
44
Kindergarten was built in resettlement site,
reservoir area, Quarter 10, Mong Duong Ward
A spacious house of the resettled
household was built in reservoir area,
Quarter 10, Mong Duong Ward
Cooling water discharge cannel, Mong Duong
Thermal Plant
A spacious house of the resettled household
was built in Quarter 10, Mong Duong Ward
Interview affected household Freshwater reservoir, supply water for
Thermal Power Plant
45