socio-environmental impacts of mining · overview of the ok tedi mine ¾ large copper/gold project...

38
© MEA 2006 V 1.0 08/2006 Socio-Environmental Impacts of Mining Social Impact Key Issues David Brereton

Upload: others

Post on 04-Feb-2021

0 views

Category:

Documents


0 download

TRANSCRIPT

  • © MEA 2006 V 1.0 08/2006

    Socio-Environmental

    Impacts of MiningSocial Impact – Key Issues

    David Brereton

  • July 16, 2015 © MEA 2006

    Social Impact – Key Issues

  • July 16, 2015 © MEA 2006

    What are social impacts?

    The term ‘social impacts’ refers to the

    effects – positive as well as negative – that

    mineral operations can have on individuals

    and communities.

  • July 16, 2015 © MEA 2006

    Social impacts that can result from large-scale

    minerals developments

    Loss of amenity due to traffic, noise, dust, visual impacts,

    etc.

    Public concern about health risks

    Relocation

    Demographic changes – population growth; change in

    community composition

    Cultural changes – introduction of new influences; erosion of

    traditional values & identity

    Changes in wealth distribution and forms of income

    generation

    Increased social strains in communities

    Improved services.

  • July 16, 2015 © MEA 2006

    Why do project planners need to take account of

    social impacts?

    Legal requirements - SIA now required as part of

    the EIS for major projects; native title & cultural

    heritage

    The ‘social license to operate’ – failure to take

    account of, and respond to community concerns,

    can lead to conflict with community, damage to

    corporate reputation, etc.

    Obligations created by company and industry

    policies and codes.

  • July 16, 2015 © MEA 2006

    Identifying potential social impacts

    Characteristics of the operation

    Where will the operation be located?

    What will it produce and what inputs will it

    require?

    How will materials be transported to and from the

    operation?

    How many people will it employ?

    Where will employees come from and where will

    they live?

  • July 16, 2015 © MEA 2006

    Identifying potential social impacts, cont’d

    Community characteristics

    What is the size, economic base, demographic composition,

    etc. of nearby communities?

    How might the proposed development alter the make-up of

    these communities?

    What concerns, expectations, perceptions etc. do

    community members have about the proposed operation?

    How much community support is there for the development?

    Who are the likely winners and losers?

    Are there any Indigenous communities likely to be affected?

  • July 16, 2015 © MEA 2006

    Managing Social Impacts: General Principles

    Design projects to minimise potential adverse

    social impacts

    Implement mitigating strategies where impacts

    cannot be avoided

    Inform, consult and engage with affected

    communities and groups.

    Monitor impacts and adjust strategies as required.

    Need to manage the impacts of closure, as well

    as start-up impacts.

  • July 16, 2015 © MEA 2006

    Discussion points

    1. Why do mining companies need to be concerned

    about their social impacts?

    2. Are the issues different in Australia than in the

    developing world?

    3. To what extent should the management of social

    impacts associated with large resource

    developments be a government, rather than

    company, responsibility?

  • July 16, 2015 © MEA 2006

    Week 12 presentation

    Social Impact – Tools

    and frameworks

  • July 16, 2015 © MEA 2006

    What is Social Impact Assessment?

    A process of systematic social inquiry that focuses on

    the consequences for people’s well-being of proposed,

    current and/or past actions.

  • July 16, 2015 © MEA 2006

    SIAs: Key Points

    An SIA can be initiated at any time during the life-cycle of a mining project.

    SIAs can be backward-looking (what happened & why) as well as forward-looking (what is expected to happen).

    An SIA should be regarded as an iterative process, rather than a one-off activity.

    SIAs should be focused on how to deliver positive outcomes for communities, rather than just on how to mitigate negative impacts.

  • July 16, 2015 © MEA 2006

    Why do SIAs?

    To comply with regulatory requirements & secure project approval

    To plan for social & physical infrastructure

    To identify and help manage social risks and opportunities

    To inform internal and external stakeholders about project impacts and benefits.

  • July 16, 2015 © MEA 2006

    Overview of the SIA Process

    BaselineStudies

    Risk & opportunity Analysis

    InitialScoping

    Implemen-tation

    MonitoringEvaluation& Review

    Reporting

  • July 16, 2015 © MEA 2006

    The SIA Process

    1.Scoping

    Aim:

    Determine the scale, timing and focus of the SIA

    Tasks include:

    Ascertain who is likely to be impacted on by, or have an interest in, the project (stakeholder analysis)

    Consult with potentially affected groups and those who are knowledgeable about the ‘impact communities’

    Review available information sources

    Identify key knowledge gaps

  • July 16, 2015 © MEA 2006

    The SIA Process

    2. Establishing a social baseline

    Aim:

    Profile the ‘impact communities’ and assess how people are

    likely to respond to anticipated changes

    Tasks include:

    Analysis of demographic patterns & trends

    Socio-economic analysis

    Community needs analysis

    Social mapping

    Engagement with community stakeholders

  • July 16, 2015 © MEA 2006

    The SIA Process

    3. Analysing risks and opportunities

    Aim:

    Ensure that key social risks and opportunities have been identified and appropriate management strategies developed.

    Tasks include:

    Identification and assessment of potential impacts, including indirect & cumulative impacts

    Alternatives analysis

    Prioritising of risks and opportunities

    Selection & evaluation of possible ‘controls’

  • July 16, 2015 © MEA 2006

    The SIA Process

    4. Implementation

    Aim:

    Ensure that there is follow through on the outcomes of the risk & opportunity assessment

    Tasks include:

    Developing a risk and opportunity register with designated responsibilities and time lines

    Formulating a community development plan linked to this

    Ensuring that strategies are also linked to other planning and management processes (e.g. HR planning, purchasing policy).

  • July 16, 2015 © MEA 2006

    The SIA Process

    5. Monitoring

    Aim:

    Ensure that desired SD outcomes are being achieved.

    Tasks include:

    Identifying priority areas for monitoring

    Defining ‘lead’ and ‘lag’ indicators

    Setting up data collection processes

    Reporting: internally and externally

  • July 16, 2015 © MEA 2006

    Good practice in SIA

    The earlier the better – but it is never too late to get started!

    SIAs should be linked to other management and planning processes, rather than being approached as stand-alone exercises.

    Community engagement should be seen as an integral part of the SIA process.

    SIAs need to be reviewed and updated regularly, on the basis of monitoring data.

  • July 16, 2015 © MEA 2006

    SIAs will be most useful when:

    They are linked to an ongoing monitoring

    program.

    They are part of an engagement strategy.

    They link back into mainstream management

    processes, such as risk management frameworks.

  • July 16, 2015 © MEA 2006

    Discussion points

    1. Should there be a requirement placed on mining

    operations to undertake some form of social

    impact assessment as part of closure planning?

    2. What information would you need to be able to

    assess the likely social and economic impacts of

    closing a mine?

    3. What use should a mine make of this

    information?

  • July 16, 2015 © MEA 2006

    Week 12 presentation

    Ok Tedi Case Study

  • July 16, 2015 © MEA 2006

    Overview of the Ok Tedi Mine

    Large copper/gold project in Western Province, PNG– 1968 Mt. Fubilan deposit discovered

    – 1984 Gold production begins

    – 1987 Copper production begins

    – 2010 Planned closure

    Project shareholders– PNG Sustainable Development Program

    Company - 52%

    – GoPNG - 30%

    – Inmet Mining - 18%

    OTML contributes approx 10% of PNG GDP and 20% export earnings

    Workforce of 2,000– 1850 PNG National

    – 800 Preferred Area

    – 1500 Contractors

    Diverse population in mine-impact area of 60,000+

    Papua New Guinea

    Tabubil

    Western

    Province

    Ningerum

    Kiunga

    Daru

    Lake Murray

    Stricklan

    d

    Riv

    er

    Fly RiverO

    k T

    edi R

    iver

    Telefomin

    Obo

    Oksapmin

    Balimo

    Morehead

    OK Tedi Case Study

  • July 16, 2015 © MEA 2006

    Ok Tedi Overview

    Large copper and gold mine in remote area of PNG. High rainfall area

    – 11m p.a.

    Pre-mine subsistence economy. Virtually no infrastructure or services,

    no towns of any size.

  • July 16, 2015 © MEA 2006

    Ok Tedi Timeline1981 – construction commences; approvals require stable

    waste dumps and tailings storage facility

    1984 – mining starts; landslide destroys tailings facility; PNG

    Government approves riverine disposal on an

    interim basis

    1990 – PNG Govt reaches further agreement with OTML to

    allow riverine disposal of all tailings and much of the

    waste rock

    early 90’s – downstream landowners bring legal action against

    BHP

    1997 – BHP agrees to pay damages

  • July 16, 2015 © MEA 2006

    Time Line cont’d

    1999 – OTML and PNG Government initiate consultations with

    communities affected by mine

    2000 – BHP announces intention to exit from OK Tedi, possible

    closure

    2001 – PNG Govt announces it wants the mine to remain open

    and that the local community supports this

    2002 – BHPBilliton transfers shares to a Program Company

    2010 – Expected mine closure

  • July 16, 2015 © MEA 2006

    Environmental Impacts 90 million tonnes of tailings & overburden discharged

    annually into Ok Tedi river – 50 million tonnes reaches Fly River.

    Increased flooding, leading to dieback

    Currently 1 300 sq km affected

    Predicted 2 040 sq km

    Loss of land for growing food, reduced fish catch.

    No evidence of poisoning, some capacity for environmental recovery once mining ceases.

  • July 16, 2015 © MEA 2006

  • July 16, 2015 © MEA 2006

    Environmental impacts cont.

  • July 16, 2015 © MEA 2006

    Environment: Dredging

    Photo

    Sand piles rehab (aerial)

    Photo

    Unassisted dieback recovery

  • July 16, 2015 © MEA 2006

    Economic Impacts

    Mine provides direct and indirect employment for 3,500 people – 90% PNG citizens.

    Accounts for 10% of PNG’s GNP and 18 % of foreign exchange earnings.

    OTML has constructed most of the infrastructure in the area.

    Estimated benefit to Western Province 2002-2010: K 1.35 billion.

  • July 16, 2015 © MEA 2006

    Health Benefits Incidence of malaria in a 40 km radius has fallen

    by 80%.

    Infant mortality down from 300 per 1,000 to 15 per 1,000.

    Life expectancy of men increased from 30 years to 50+ years.

    Better nutrition and better services.

  • July 16, 2015 © MEA 2006

    Social Impacts Disruption of traditional lifestyles

    Creation of new settlements, including squatter

    settlements

    Increased social mobility

    What happens when the mine closes?

  • July 16, 2015 © MEA 2006

    Closure issues Tabubil township and attendant facilities – office,

    workshops and accommodation buildings

    Transport infrastructure – roads, bridges, airstrips, wharves, shipping

    Utilities – hydro, diesel power, telecommunications, banks, shopping centres

    Education and health services

    Rehabilitation of the mine pit

    Squatters

    Livelihoods

  • Sustainability Objectives Community participation in the development process

    Ensuring a food secure population

    Developing a sustainable economic base – focus on primary sector

    Ensuring effective governance for the future

    Mitigating environmental impacts

    Ensuring a skilled labor force

    Continued access to health and education services

    Gender equity i.e. including women in all programs

    Integrated development and mine closure planning –community, company and government

  • July 16, 2015 © MEA 2006

    Overcoming Dependencies

    Alternate sources of protein – rabbits,

    poultry, goats, ducks, fish farming

    Community forestry

    New food crops – rice, African yams,

    taro

    STAND (Skills Transfer and No

    Dependency)

  • July 16, 2015 © MEA 2006

    Issues for Discussion

    1. Should Ok Tedi have ever been built?

    2. Should the mine have been shut down by now?

    3. Should BHPBilliton have stayed?

    4. What should OTML be doing to manage for post-

    closure?