soil improvement layer (a simple approach) by structural engineer ayyappadhas
TRANSCRIPT
-
7/31/2019 Soil Improvement Layer (A simple approach) By Structural Engineer Ayyappadhas
1/3
SOIL IMROVEMENT LAYER: A SIMPLE APPROACH
An Overview By: N.Ayyappadhas(Structural Engineer)
INTRODUCTION:
Most of the construction is done on soil, but the nature and properties of soil is not
always adequate for the desired construction. When such inadequacy occurs, the
engineer could redesign the structure according to the capacity of the soil - which is
generally not preferred, go for a very deep foundation depreciating the economy of the
project, or improve the properties of the ground before the commencement of
construction.
The most common and workable way to upgrade the ground is Densification. By
densification, not only can we achieve improvement in ground behavior such as
strength and stiffness, but we could also eliminate its vulnerability to volume
compression, even in the long run. In the construction of high raised structures with raft
foundations, one of the ways to achieve densification of the ground is to provide an
improvement layer on the ground before laying the foundation raft of the building.
Fig. 1: An image illustrating the ground improvement executed at site.
-
7/31/2019 Soil Improvement Layer (A simple approach) By Structural Engineer Ayyappadhas
2/3
METHODOLOGY:
The provision of the imprmethod of soil improveme
layer and replacing it with
done by laying an artificial
coarse aggregates. The c
cohesive soil, the rubber-ti
compaction.
The detailed procedure be
depth, considering a 1 m
foundation. The excavate
aggregates and the availab
layers of 15 cm or 30 cm d
Fig. 2: P
After each layer is sprea
rubber-filled roller or any
Compaction may be prolon
Site cleaning
Finalizing the levels
Excavating soil upto a
desired depth
Excavation
ovement layer is based on the removnt. This method involves removal of th
structural fill during grading operations.
cushion or a natural cushion formed u
shion layer requires adequate compact
red roller or the vibratory roller is most
ins with the excavation of the weak soil
hick improvement layer additional to th
area should be re-filled with a mix
le soil from the excavation. This re-fill s
pending upon the compaction effectiven
rocedure for laying the improvement laye
d, compaction should be implemented
suitable compaction machine for a co
ged in some cases in accordance with th
40 mm Course
Aggregates
Excavated Soil
Water if required
Material for
Re-fill In laAd
Total
afte
al and replacemente compressible soil
The grading can be
sing 40 mm granite
ion. In case of non-
commonly used for
own to the required
e desired depth the
of 40 mm course
ould be executed in
ess.
r.
using vibratory or
nsiderable duration.
e density of soil and
yers of 15 - 30 cm.
quate compaction
fter each layer
l achieved thickness
r compaction - 1m
Re-fill Process
-
7/31/2019 Soil Improvement Layer (A simple approach) By Structural Engineer Ayyappadhas
3/3
the required bearing capacity. If and when required, water can be used for compaction.
The process should continue until the total depth of the layer reaches 1 m. An engineer
at site is mandatorily required to monitor the whole process with caution.
CONCLUSION & RECOMMENDATION:
The introduction of the improvement layer below laying the foundation is gradually
gaining popularity in our country, even though it has been a popular practice in certain
other parts of the world for a long time now. In recent times, Indian engineers being very
open to the reception of innovative ideas and construction techniques, and more widely
accepting this method which is a very efficient alternative compared to providing
uneconomical foundation design or redesigning of the entire structure.
The improvement layer has additional advantages which are listed below:
Increases shear strength
Reduces permeability
Reduces compressibility
Cheap and easily achieved, when compared to other soil improvement methods.
IS 1893(Part1) recommends under section 6.5.3.2, that appropriate methods of
compaction is a possible alternative when the soil deposits consist of submerged loose
sand. Studies indicate that the primary settlement, which is a major concern in the case
of silty soil, can be resisted to a great extent by such densification methods. Hence, the
use of improvement layer is highly recommended, particularly in construction sites of
high raised structures having raft foundation.