Solenoid Status

Paul Brindza

Dec. 12, 2003

Page 2: Solenoid Status
Page 3: Solenoid Status

Status of work at IUCF

 

• Solenoid R&R is based on a MOU between JLAB and IUCF

• The MOU divides the work into three Phases and a pause.

 

• Phase zero is measurement and investigation.

• This includes electrical measurements on each coil, instrumentation checkout, leak testing and pressure testing and mechanical measurements of the shields in coils 1 and 4.

Page 4: Solenoid Status

Status of work at IUCF

• Phase one includes the rework of all four coils and final testing and evacuation.

• This includes replacement of the LN2 shields, repair of instrumentation and other internal work

 

• The pause is to allow time for getting the Model 2800 Helium refrigerator operational

 

• Phase two includes the replacement of "puffing billy" and the reassembly of the solenoid, new controls and instrumentaion and mating with the new power supply.

 

• At present Phase zero is near completion.

Page 5: Solenoid Status

Phase zero measurements and results 

Coil electrical measurements

Coil #Across

CoilLH Lead - Ground

RH Lead - Ground

1 4.9 O 2.2 O 6.4 O

2 3.2 O OPEN OPEN

3 2.7 O 2.6 O 0.2 O

4 5.2 O OPEN OPEN

Page 6: Solenoid Status

Coil Inductances

•  

• Coil 1 Coil 2 Coil 3 Coil 4

•  

• 372 mH 244 mH 172 mH 763 mH

Page 7: Solenoid Status

Internal instrumentation and voltage taps

• Each coil has voltage taps (VT) and Carbon Resistance Thermometers (CRT) in the Helium vessel and Thermalcouples (TC) on the N2 shield and strain gauges (SG) on the support posts.

Coil 1 Coil 2 Coil 3 Coil 4

 

VT OK OK OK OK

 

CRT 7 of 8 OK OK OK 4 of 7 OK

 

TC OK OK OK OK

 

SG 3 of 6 OK 2 of 6 OK OK 3 of 6 OK

Note: coil 4 has some extra CRT’s in unknown locations.

Page 8: Solenoid Status

Leak testing and pressure testing

 

N2 Shield He Vessel External Pressure tests

Coil one 5 x 10 ^ -5 OK 12 inch bellows OK

 

Coil two OK 2 x 10 ^ -6 OK OK

 

Coil three 4 x 10 ^ -5 OK 12 inch bellows OK

 

Coil four 4 x 10 ^ -6 OK OK OK

Leak rates in torr-liter per second

Page 9: Solenoid Status
Page 10: Solenoid Status
Page 11: Solenoid Status
Page 12: Solenoid Status

Ongoing work for Phase zero

 • Coils 1, 3 and 4 have been evacuated , backfilled dry and sealed.

 

• A search is on for the Helium leak in coil 2

• The N2 shield has been removed to provide access

• The He vessel has been pumped to reduce background

• The He vessel will also be pressurized and "sniffed"

• The leak will be repaired by welding when found

• During the leak investigation further tests to locate the probblems with the strain gauges have been performed

Page 13: Solenoid Status

Ongoing work for Phase zero

• All four coils have had conflat flanges added to all internal connections to permit high quality leak testing and to permit future connections without "cut and weld".

 

• The two damaged and leaky 12 inch bellows will be replaced.

• Attempts to repair have proven to be temporary

 

• The model 2800 helium refrigerator is indoors and is being prepped for shipment to JLAB

• The JLAB cryo group will perofrm a thorough checkout , some updating and a dry run

• To test the turbines.

 

• The new N2 shield design based on field measurements of coils 1 and 4 and original drawings is being finalized at JLAB in consultation with the manufacturer.

• The N2 coolant flow for the new shields has been evaluated.

• Potential modification to the "cake pan" coil covers is being evaluated with IUCF to provide better clearance for assembly and insulation

Page 14: Solenoid Status

Cake Pan ModificationsCake Pan Modifications

Cross section of coil 2,3,4

Page 15: Solenoid Status

Status of Phase one

 • A Scope of Work (SOW) and Purchase Requisition (PR) have been prepared

• The SOW and PR have been circulated at JLAB for signature

• Final approval is awaiting CD-0

• The SOW has been sent to IUCF for comment.

 

• The Scope of Work includes the complete R&R of all four coils.

• This includes replacement of the LN2 shields, repair of any leaks, repair (if possible) of instrumentation, final evacuation and leak test, pressure test and dry storage until Phase two

Page 16: Solenoid Status

Magnetic simulations of the upstream hole and an iron plug with varying gaps

• .

Page 17: Solenoid Status

Bmod over a patch (-5 < Z < 80 , 10 < R < 80 inches)4 inch gap , max field .208 T , Integral B.dA = 132 Tesla inch^2

Page 18: Solenoid Status

Bmod max on patch upstream

Bmod max on an upstream patch

0

500

1000

1500

2000

2500

3000

3500

0 1 2 3 4 5 6 7 8

gap inches

ga

us

s Bmod max thick plug

Bmod max Big Hole

Bmod max Thin plug

Page 19: Solenoid Status

Integral Bmod over patch upstream

Integral Bmod.dA over an upstreampacth

0

50

100

150

200

250

0 1 2 3 4 5 6 7 8

gapinches

Tesl

a in

ch^2 Int Bmod.da thick plug

Bmod.dA Big hole

Int Bmod thin plug

Page 20: Solenoid Status

Bmod on patch with big hole

Page 21: Solenoid Status

Bmod on upstream patch 4 inch gap with thin plug