sonic thermal (p) limitedenvironmentclearance.nic.in/writereaddata/online/eds/0_0...elcb/rccb of 30...

47
Point Wise Compliance for Modification of Product Mix of Existing Ferroalloy Plant: 4 X 7.5 MVA and 1 X 5 MVA for production of Ferro-chrome in addition to existing product mix of Ferro-manganese, Silico-manganese and by-product Ferro-manganese Slag by M/s. Sonic Thermal Private Limited located at Village- Namobandh- Sitarampur Panchayat/P.O.: Ghutgoria, PS: Barjora Zilla Parishad – Bankura, District – Bankura, West Bengal. Sl. No. Compliance Reply 1 Scheme to meet Stack emissions from all units at less than 30 mg/Nm 3 should be furnished Scheme for meet Stack Emission norms from all units at less than 30 mg/Nm 3 is enclosed in Annexure-1. 2 Proper HIRA should be done and presented Detail Hazard Identification & Risk Assessment (HIRA) Study is given in Annexure-2. 3 Fourth hole extraction system should be provided as per TOR. -1. Possibility of providing fourth -hole extraction of the fumes from the furnace to pre-heat the charge shall be prepared and given in the EIA/EMP report We are in the process to providing Fourth Hole Extraction System for the fumes from the furnace. 4 AAQ values are as high as 95.30 µg/Nm 3 at certain places. No explanation is available. Reasons for the higher values be given along with mitigation plan shall be furnished Detail explanation & mitigation measures for AAQ values are as high as 95.30 µg/Nm 3 at certain places are given in Annexuere-3. 5 In Bankura area Soil carbon is 0.3 %. Moisture in soil sample taken up to 50 cm depth, as reported needs to be justified The organic carbon is an indicator of the fertility of soil. The organic carbon content have been checked at 8 points located in the vicinity of the plant. Out of eight points, the one at Barjora has come as 0.3 %. The location of the sampling point is found to be

Upload: others

Post on 01-Feb-2021

7 views

Category:

Documents


0 download

TRANSCRIPT

  • Point Wise Compliance for Modification of Product Mix of Existing Ferroalloy Plant: 4 X 7.5 MVA and 1 X 5 MVA for production of Ferro-chrome in addition to existing product mix of Ferro-manganese, Silico-manganese and by-product Ferro-manganese Slag by M/s. Sonic Thermal Private Limited located at Village- Namobandh-Sitarampur Panchayat/P.O.: Ghutgoria, PS: Barjora Zilla Parishad – Bankura, District – Bankura, West Bengal.

    Sl. No.

    Compliance Reply

    1 Scheme to meet Stack emissions from all units at less than 30 mg/Nm3 should be furnished

    Scheme for meet Stack Emission norms from

    all units at less than 30 mg/Nm3 is enclosed

    in Annexure-1.

    2 Proper HIRA should be done and

    presented

    Detail Hazard Identification & Risk

    Assessment (HIRA) Study is given in

    Annexure-2.

    3 Fourth hole extraction system should be

    provided as per TOR. -1. Possibility of

    providing fourth -hole extraction of the

    fumes from the furnace to pre-heat the

    charge shall be prepared and given in the

    EIA/EMP report

    We are in the process to providing Fourth

    Hole Extraction System for the fumes from

    the furnace.

    4 AAQ values are as high as 95.30 µg/Nm3 at

    certain places. No explanation is available.

    Reasons for the higher values be given

    along with mitigation plan shall be

    furnished

    Detail explanation & mitigation measures

    for AAQ values are as high as 95.30

    µg/Nm3 at certain places are given in

    Annexuere-3.

    5 In Bankura area Soil carbon is 0.3 %.

    Moisture in soil sample taken up to 50 cm

    depth, as reported needs to be justified

    The organic carbon is an indicator of the

    fertility of soil. The organic carbon content

    have been checked at 8 points located in the

    vicinity of the plant. Out of eight points, the

    one at Barjora has come as 0.3 %. The

    location of the sampling point is found to be

  • a patch of up land devoid of any vegetative

    growth. This may be the reason for low

    organic carbon.

    Except for this location other locations the

    OC % is higher varying from 0.9 to 1.3.

    Another point at Tickergram shows 0.4 %

    probably because it is a reclaimed area filled

    with bottom soil.

    6 CER Activities have not been taken from

    public consultation proceeds and SIA out

    comes. CER calculations need to be revised.

    Action plan for CER shall be submitted as

    per the Ministry’s O.M. dated 1/05/2018.

    Corporate Environment Responsibility

    (CER) has been taken from Public

    Consultation proceeding and Action Plan

    for CER as per the Ministry’s O.M. dated

    1/05/2018 is attached in Annexure-4.

    7 Action plan for RWH more than 100% of

    annual water consumption shall be

    submitted.

    We have recharge more than 100% of annual

    water consumption. Action Plan is given is

    attached in Annexure-5.

    8 CEMS shall be installed in next three

    months and a completion report shall be

    made available to MoEF&CC.

    We have already installed CEMS and the

    details are attached in Annexure-6.

    9 Scheme to manage chromium bearing waste shall be submitted.

    Scheme for manage chromium bearing

    waste is enclosed in Annexure-7.

    10 Scheme for strengthening of green belt shall

    be submitted.

    Action Plan for Green Belt development is

    attached in Annexure-8.

  • Annexure-1

    SONIC THERMAL (P) LIMITED

    Scheme to meet stack emissions standard (< 30 mg/nm3) from all units

    Following modification to be done-

    1. Bag-house chamber to be increase by 25% for better dust collection.

    2. Bag house operating system to be changed from online to offline by partition

    of chamber.

    3. Bag house outlet duct line to be installed and connected to each chamber

    through pneumatic damper.

    4. New heat-exchanger (air cooler) to be installed for increase cooling surface

    area.

    5. New inter connected duct to be fitted at heat-exchangers.

    6. New ID. FAN to be installed for increase suction volume.

    7. Electrical work to be done as per modification.

    8. New dust collecting bags to be installed at each bag house.

    9. New screw compressor (450 CFM) to be installed for better pressure

    maintains and dust cleaning.

    10. Man power required as per organization chart.

    It will be done by phase manner and completed end of December 2020.

  • SL NO.

    ACTIVITY HAZARDHAZARDOUS

    EVENTPOSSIBLE OUTCOME

    POPULATION AT RISK

    EXISTING CONTROL MEASURE PROBABILITY SEVERITY RISK ADDITIONAL CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY

    HAZARD IDENTIFICATION & RISK ASSESSMENT

    Ref:HSE/AMA/STPL/8/20 TROPIC : ELECTRICAL SAFETY HIRA - 01

    1

    working on HT power lines,

    transformers,control pannel, installation,

    maintenance, repair or using

    electrical equipments.

    Electricity

    Contact with

    electricity or electric shock due to lekage

    current

    ElectrocutionElectrician,Equipment operator

    1. Log Out - Tag Out system shall be strickly maintained during any non-routine maintenance job.2. Provision of body earthing is mandatory for all electrical equioment.3. Only use three core double insulated cables for portable tools.4. All electrical connections, fittings, appliances shall comply with International Protection Rating(IP) such as IP44, IP54, IP64 etc for protection against the solid object(including body parts and fingers), dust, accidental contact and water . Only industrial standard plugs and sockets shall be used 5. Connection of all low voltage installations shall be taken through ELCB/RCCB of 30 mA sensitivity. Record of their periodic testing shall be ensured.6. using Full Body Safety Harness and Non - metallic Ladder while working for any electrical works at height.

    2

    2 2*2=4(L)Electrician, person in

    charge

    Electrician, person in

    charge

    Fire due to short-

    circuit/overloading of

    circuit

    Electrical Fire

    All workmen

    at worksite, property damage

    1.Earth-pits and the earthling connections shall be periodically maintained to have effective earthling system on all electrical equipment & installations. All non-current carrying metal parts of high & extra high voltage installations should be earthed. 2. Ensure effective earthling and insulation at the joints if any in the cables connected with Electrical power driven tools, mobile - equipment. 3.Fire buckets filled with clean & dry sand, portable fire extinguishers (Carbon di-Oxide & D.C.P. types) should be provided for extinguishing electrical fire occurrences.

    2 3 2*3=6(M)

    1.Electrical cables and tools shall be regularly inspected. Any defective tool or damaged cables shall be replaced or rectified.2. Maintain good housekeeping in the generator rooms. 3. Create awareness of the workmen through tool-box-talk & other HSE-promotional training to avoid sleeping in/near the generator.

    2

    3 2*3=6 (M)

    1. Treat everything as live and ensure use of job specific PPE regarding electrical work.

    2. Display notice near medium, high voltage installations.

    1 3 1*3=3(L)

    userTypewritten TextAnnexure-2

    userTypewritten Text

    userTypewritten Text

  • Ref:HSE/AMA/STPL/8/20 MATERIAL HANDLING HIRA - 02

    SL NO.

    ACTIVITY HAZARDHAZARDOUS

    EVENTPOSSIBLE OUTCOME

    POPULATION

    AT RISKEXISTING CONTROL MEASURE PROBABILITY SEVERITY RISK ADDITIONAL CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY

    2*2=4(L)Men in charge,

    safety offier

    HAZARD IDENTIFICATION & RISK ASSESSMENT

    1

    Loading, unloading, shifting of

    material

    Manual handling

    Adopting poor/awkard posture

    orhandling excessive

    load repeatedly

    back injury, strain,

    MSD(Musculoskeletal Disorder)

    Rigger, Helper,

    workmen

    1.carrying of exessive load shall be avoided(25kg max each person). 2. awkward posture shall be avoided(twisting,turning, bending).

    3. use of cotton hand gloves & shoulder pad shall be ensure.

    4. Adopt 5 principle for manual handling(a> Assess the task b> plan c>position the feet d> take a secure grip e> keep the load close to the body f> use the leg muscle & back should be straight.

    5. Avoid lifting from floor level or above shoulder height, especially heavy loads.6. Consider how much minimise carrying distance.

    2 3

    2

    2*3=6(M)

    1. Safe lifting technique shall be trained to employees.

    2. If possible mechanical manual handling shall be done instead of manual handling.

    2 2

    Mechanical Handling

    using mobile

    crane,forklift etc

    fall of material,

    pinch point,

    struck by materials or lifting

    equipment

    fractures, bruies, cuts, LTI

    Rigger, Helper,

    workmen

    1. All the lifting tools & tackles shall be throughly visual examined before taken into use. Any damage or defected tools shall be rejected.2. All the lifting tools & tackles shall be examined by competent person & shall be certified as per section-28 of factories act( Third party certificate). This is legal requirement.3. Only authorized operator shall be deployed(HMV driving license & eye test report) for any kind of equipment operation.4. Guy rope shall be used from min 2 meter distance for balancing the material.5. Flagman/ signal man shall be engagged during material handling.6. Load chart shall be strickly followed.

    No overloadding shall be allowed.

    Men in charge,

    safety offier3 2*3=6(M)

    1. All the mandatory PPE'S( safety helmet, safety shoe, hand gloves, reflecting jacket) must be used during the material handling operation.2. The material shifting path shall be free from any kind of obstruction & ground shall be in even condition.3.The lifting/shifting/loading shall be cordoned to prevent unauthorized person entry.

    2 2 2*2=4(L)

  • SL NO.

    ACTIVITY HAZARDHAZARDOUS

    EVENTPOSSIBLE OUTCOME

    POPULATION

    AT RISKEXISTING CONTROL MEASURE PROBABILITY SEVERITY RISK ADDITIONAL CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY

    HAZARD IDENTIFICATION & RISK ASSESSMENT

    Ref:HSE/AMA/STPL/8/20 Work at Height HIRA - 03

    1

    working at elevated platform,

    scaffolding, pipeline,roof etc

    more than 2 mtr height

    Working at height

    Fall of person

    Parmanent disable

    injury, fatal

    person working at height

    1.Provide guard rail, mid rail and toe board in working platform in every elevated platform. 2. Ensure the scaffolding taging system. 3. vertical support, cross bracing shall be ensured on the scaffolding. 4. ladder shall be provided in4:1 ratio & 1 mtr extension from the working platform shall be ensured. 5. proper PPE's with double lanyard full body harness shall be use while working at height. 6.Fall arrestor & safety net must be use as second layer of protection.7. Every stairecase shall be free from dirt,oil & steps, railing shall be free from damage. 8.work at height permit system shall be implemented.

    2

    2 3 2*3=6(M)

    1. experienced worker shall be engagged while working at height.2. All mandatory PPE'S shall be used.

    3 2*3=6(M)

    1. All workmen working at height(more than 3 mtr) shall be go through vertigo test & certified fit by competent medical officer.2.Avoid movement on beam or any narrow structure.3. fall restraint system shall be used while working at fragile roof.4. job specific training shall be given to the workforce before working at height.

    Working at height

    Fall of material

    may injured the person working on

    ground level/lower

    level or struck by

    falling material cause to

    fatal

    Rigger, Helper,

    workmen

    1. working area shall be barricadded & cautionary board shall be displayed to alart people.2. double layer safety net shall be use. For catching person(45 mm each cell) & for material catching(25mm each cell) must be use.3. keep the workplace net & clean. any lose material shall be immidiately removed at elevated position.4.Remove the scarp immidiately.5. using hand to hand or using manila rope for shifting of small materials/equipment instead of throwing or droping from height.

    2 2 2*2=4(L)Men in charge,

    safety offier

    Men in charge,site engineer,

    safety offier

    2 2 2*2=4(L)

  • SL NO.

    ACTIVITY HAZARDHAZARDOUS

    EVENTPOSSIBLE OUTCOME

    POPULATION

    AT RISKEXISTING CONTROL MEASURE PROBABILITY SEVERITY RISK ADDITIONAL CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY

    HAZARD IDENTIFICATION & RISK ASSESSMENT

    Ref:HSE/AMA/STPL/8/20 HEAT STRESS HIRA - 04

    1

    Working on hot

    environment/hot

    work/Boiler/Furnace

    Unsuitable thermal

    environment, which leads

    to Hypothermia or Heat Stress

    Exposure to thermal extremes

    Heat Exhaustion

    orHeat Cramp

    orHeat Stoke

    peole working in Hot

    Environment

    1. Effective insulation of hot surface/equipment.2. Improved ventilation: A) General Ventilation; incoming cool air should be directed over personal before reaching hot equipment. B) Ventilation canopies over hot equipment to direct hot air away(fans may be required with canopies) c) Localised ventialtion over personal; incoming air must be cool.3. Shielding- one or more shields may be interposed between the source of heat radiation and the personal.4. protective clothing- reflective surface of polished metal or paint. ventilated suits for excessive radiant heat loads or excessively humid conditions.5.Painting surface of hot equipment or of sheild or clothing; a) white for short wave length radiation(solar). b) aluminium for infra-red radiation.

    3 3 3*3=9(M)

    Management of personal exposed to heat:1. provide ample supplies of cool water or flavoured drinks(provide extra salt where required).2.Ensure lightweighted, loose fitting clothing, if possible clothing should be white in high radiant heat load areas.3.Alternatively repaet rest periods of workers in cool surroundings.4.where possible do not employ men in hot condition if they are : a)Obese b)suffering from any cardiovascular disease. c) Over 45 yeras age. d) Physically unfit. e) Suffering from any skin disease or if they fail to sweat properly.

    Men in charge,site engineer,

    safety offier

    2 2 2*2=4(L)

  • SL NO.

    ACTIVITY HAZARDHAZARDOUS

    EVENTPOSSIBLE OUTCOME

    POPULATION AT RISK

    EXISTING CONTROL MEASURE PROBABILITY SEVERITY RISK ADDITIONAL CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY

    2 2*2=4(L)

    HAZARD IDENTIFICATION & RISK ASSESSMENT

    Ref:HSE/AMA/STPL/8/20 HOUSEKEEPING HIRA - 05

    1Stacking

    and movement of man and

    material/material storage

    slippery or uneven

    ground,storing

    combustable material/empty container and packing materials/accumulation of waste/dusty window &

    floor/ objects or

    equipments laying out of

    places.

    Trip,slip,fall,inadequate

    illumination,struck by objects,

    spontaneous combustionunhygenic condition

    LTI/Serious injury/Major

    fire/health risks due to unprotected exposure to chemicals.

    All the employees

    1.BUILDING:# All wall, ledges,roofs shall be free from dust & cobwebs.#All windows, bulbs shall be cleaned in regualar basis.#Spitoons and toilets shall be adequately clean to maintain hygine.2.FLOORS/WORKING SURFACES:#Floor/working surfaces shall be even and free from dust,waste,spillages,loose objects,cables/hoses lying.#Floor opening shall be kept covered or guarded with rails.#Trenches/pits shall be free from accumulation of rubbish.#There shall be clear and safe access to switches, fire extinguishers and emergency exits.3.MATERIAL:#There shall be sufficient areas and containers alloted for raw material,work in progress & finish product.# Sharp Material shall not be in projected condition3.MACHINERY AND EQUIPMENT:#There should be adequate space between machinery, fixed objects or structure.#Drip tray shall be provided and regularly cleaned.#Surroundings of machinery & equipment shall be free from chips,scrap

    3

    all the departmental H.O.D, Safety

    officer, housekeeping

    in charge & his team.

    3 3*3=9(M)

    1. 5S methodology(sort,set in order,shine,standardize,sustain) shall be adopted & maintain in

    every workplace.

    2.Maintain a scheule for periodic house keeping &

    assigned manpower in daily basis for only housekeeping in

    entire plant.

    2

  • SL NO.

    ACTIVITY HAZARDHAZARDOUS

    EVENTPOSSIBLE OUTCOME

    POPULATION

    AT RISKEXISTING CONTROL MEASURE PROBABILITY SEVERITY RISK ADDITIONAL CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY

    HAZARD IDENTIFICATION & RISK ASSESSMENT

    Ref:HSE/AMA/STPL/8/20 Working at height HIRA 6

    1

    working at elevated platform,

    scaffolding, pipeline,roof etc

    more than 2 mtr height

    Working at height

    Fall of person

    Parmanent disable

    injury, fatal

    person working at height

    1.Provide guard rail, mid rail and toe board in working platform in every elevated platform. 2. Ensure the scaffolding taging system. 3. vertical support, cross bracing shall be ensured on the scaffolding. 4. ladder shall be provided in4:1 ratio & 1 mtr extension from the working platform shall be ensured. 5. proper PPE's with double lanyard full body harness shall be use while working at height. 6.Fall arrestor & safety net must be use as second layer of protection.7. Every stairecase shall be free from dirt,oil & steps, railing shall be free from damage. 8.work at height permit system shall be implemented.

    2

    2 3 2*3=6(M)

    1. experienced worker shall be engagged while working at height.2. All mandatory PPE'S shall be used.

    3 2*3=6(M)

    1. All workmen working at height(more than 3 mtr) shall be go through vertigo test & certified fit by competent medical officer.2.Avoid movement on beam or any narrow structure.3. fall restraint system shall be used while working at fragile roof.4. job specific training shall be given to the workforce before working at height.

    Working at height

    Fall of material

    may injured the person working on

    ground level/lower

    level or struck by

    falling material cause to

    fatal

    Rigger, Helper,

    workmen

    1. working area shall be barricadded & cautionary board shall be displayed to alart people.2. double layer safety net shall be use. For catching person(45 mm each cell) & for material catching(25mm each cell) must be use.3. keep the workplace net & clean. any lose material shall be immidiately removed at elevated position.4.Remove the scarp immidiately.5. using hand to hand or using manila rope for shifting of small materials/equipment instead of throwing or droping from height.

    2 2 2*2=4(L)Men in charge,

    safety offier

    Men in charge,site engineer,

    safety offier

    2 2 2*2=4(L)

  • Ref:HSE/AMA/STPL/8/20 Meterial Lifting HIRA-7

    Impact rating Probability

    Risk level

    Impact rating Probability Risk level

    1. Failure of equipment 2. Inexperienced operation. 3. Overload shifting

    Toppling of equipment, injury to person

    1. Tested equipments shall be used. 2. Trained operator shall be operate. 3. Suitable capacity of crane/hydra shall be used. SWL shall be mentioned all the tools and tackles, equipments.

    5 3 H

    1. Activity shall be done under competent supervision. 2. Proper access shall be

    provided.

    4 2 L

    high risk work HODs

    N

    1. Defective tools and tackles. 2. Inexperience operator. 3. Suspended load

    Fall of hot material, injury to person

    1. Tested tools & tackles shall be used for rigging. 2. Trained person shall be allowed. 3. Suitable capacity of tools & tackles shall be used. SWL shall be mentioned all the tools and tackles.

    5 3 H

    1. Activity shall be done under competent supervision. 2. Entry sould be restricted to under the suspended load.

    4 2 L

    activities to

    N

    carried out at

    N

    workplace

    N

    hazards arising

    Hot Work N

    from these

    Material Handling N

    &

    Machine Guarding L

    measures

    3

    Mec

    hani

    cal M

    aint

    enan

    ce

    1

    ladl

    e Li

    fting

    casting Meterial Handling and shifting

    2

    Mat

    eria

    l Pak

    agin

    g

    crushing , screening and Pakaging

    HAZARD IDENTIFICATION AND RISK ASSESSMENT

    Sl N

    o

    Act

    ivity

    Sub Activity

    L(Legal), N(Normal Condition), AB(Abnormal Condition), E(Emergency)

    Hazard Consequence Existing control measures

    Risk

    Additional Control Measures

    Risk

    Safe work method Action By

  • No medical treatment or measurable

    physical effects

    Illness requiring Medical treatment

    Illness requiring hospital admission

    Illness in permanent impairment

    Fatality

    First aid treatmentIllness requiring

    Medical treatment but not Lost time

    Lost time Accident Serious injury requiring hospitalization

    Single or multiple Fatality

    1 2 3 4 5

    Most Unlikely 1

    Unlikely 2 Low

    Likely 3 Medium

    Most likely 4 High

    Inevitable 5

    RISK MATRIX

    Severity

    Likelihood

  • Annexure-3

    AAQ values are as high as 95.30 µg/Nm3 at certain places. No explanation is available. Reasons for the higher values be given along with mitigation plan shall be furnished.

    a) The project site is located in an industrial estate locality namely the Plasto Steel Park, in

    Barjora block of Bankura which is well in the proximity of another industrial hub Durgapur.

    As per EIA report submitted the area is having as many as 24 numbers of industries in the

    vicinity i.e. within 10 Km of the radius of project location.

    b) Secondly there may be higher emission load of some of the industries due to process upsets

    which may be transient. But this would have resulted in showing higher AAQ level in

    ambient air.

    The above points clarify as to why the AAQ values have been high at certain places.

    Mitigation Measures:

    1. There are number of industries in the cluster which contribute to the ambient air quality.

    Many of the industries may be operating sticking to old emission standard of 150mg/m3.

    Upon enforcement of the standard emission limit of 30 mg/m3 the ambient air quality will

    improve shall significantly.

    2. M/s STPL on its part shall take up modification measures of its pollution control measures

    to reduce the stack emission of its Ferroalloy furnaces which has been deliberated in point

    No I. above. The scheme to meet 30 mg/m3 norm of stack emission shall be completed by

    December 2020.It will be done by phase manner and completed end of December 2020.

    3. Another point for increase in particulate concentration in the ambient air is fugitive

    emission. The movement of vehicular traffic in the arterial roads without black topping or

    concreting may be contributing for high particulate level in ambient air. Regular water

    sprinkling shall be done on road.

    4. Water spraying shall be done at unloading and loading point .In dry months water

    spraying shall be done on heaps of storage materials i.e. minerals and coal.

  • Annexure-4

    Corporate Environmental Responsibility (CER) Budget Allocation according to Activities

    (As per the provision of “OM No. F. No. 22-65/2017-IA-III dated 01 May 2018") The project cost for M/s. Sonic Thermal Private Limited, Village: Namabandha-Sitarampur, P.O: Ghutgoria, Block: Barjora, Dist.: Bankura, West Bengal was Rs. 80.00 crore at the time of construction in the year 2006. The current proposal is only for modification of product mix. There is no need of additional land, machinery or budget for it. However, being a brown field project, the Corporate Environment Responsibility (CER) programme as per the provision of OM No. F. No. 22-65/2017-IA-III dated 01 May 2018" attracts 1% of the project cost, which amount to Rs. 80.00 lakh (mentioned in the revised EIA & EMP - para 8.0 of Chapter – 8). As per the guideline no. (ii) of the above notification, M/s. Sonic Thermal Private Limited is committed to spend Rs. 80.00 lakhs based on public hearing demand conducted on 21.12.2018 at Barjora Panchayat Samity Meeting Hall in presence of ADM, Barjora and other concerned authorities. Public Hearing proceeding has been attached in Annexure IX.

    Table No. 1: Activities considered to implement under CER taken from Public Hearing or Social-Economic impacts input

    Sl. No.

    Activities under CER Proposal Issue raised by/ during or taken from

    1. Organizing Health camp with free distribution of medicines

    Sri Jagjiban Achaya and Sri Shyamal Raj of village Ghutgoria, Sri Tapas Ghosh of Hetukdanga and Sri Ajoy Rakshit of Barjora village requested in the Public Hearing meeting.

    2. Providing ambulance to address the emergency need

    3. Repairing of Boundary Walls and /or Toilets of School & Colleges

    Sri Kartik Ghosh, Sri Kartik Dey of Metali, Sri Partha Guin, Sri Ajoy Rakshit of Barjora, Sri Dilip Pal, Sri Gunomoy Ghosh, Sri Rammohan Pal and Sri Bhairab Ghosh, Sri Jagjiban Achaya, Sri Shyamal Raj and Sri Arun Sil Pradhan of village Ghutgoria, Sri Tapas Ghosh of Hetukdanga village, requested in the Public Hearing meeting.

    4. Setting up library in the schools

    5. Training program for development of self sustainable/ job oriented professional skill

    6. Construction of Borewell with overhead tank to supply drinking water Sri Kartik Dey of Metali, Sri Partha Guin of

    Barjora, Sri Rammohan Pal and Sri Bhairab Ghosh of Village Ghutgoria requested during the Public Hearing Meeting.

    7. Repairing of Village Roads

    8.

    Installation of solar lights on the village roads to provide alternative source of energy to the villages

  • Annexure-4

    Table No. 2: Time Bound Budget of Welfare Expenditure based on Public Hearing & Socio-economic needs

    Sl. No.

    Issues raised by Public & Necessities in Peripheral Areas

    1st Year 2nd Year

    3rd Year 4th Year

    5th Year Total

    1. Infrastructure Development Health

    i) Organising Health camp with free distribution of medicines

    ii) Providing ambulance to address the emergency need

    Education

    i) Repairing of Boundary Walls and /or Toilets

    ii) Setting up library in the schools

    Professional Skill Development

    i) Training program for development of self sustainable/ job oriented professional skill

    Drinking Water Facility

    i) Construction of Borewell with overhead tank to supply drinking water

    Village Road

    i) Repairing of Village Roads ii) Installation of solar lights on

    the village roads to provide alternative source of energy to the villages

    Rs 2 lakhs

    Rs 9 lakhs

    Rs 2.5 lakhs

    Rs 2.5 lakh

    Rs 4 lakhs

    Rs 2.5 lakhs

    Rs 3 lakhs

    Rs 1.5 lakhs

    Rs 2 lakhs

    0

    0

    0

    Rs 4 lakhs

    Rs 2.5 lakhs

    Rs 3 lakhs

    Rs 1.5 lakhs

    Rs 2 lakhs

    0

    0

    0

    Rs 4 lakhs

    Rs 2.5 lakhs

    Rs 3 lakhs

    Rs 1.5 lakhs

    Rs 2 lakhs 0

    Rs 2.5 lakhs

    Rs 2.5 lakh

    Rs 2 lakhs

    Rs 2.5 lakhs

    Rs 3 lakhs

    Rs 1.5 lakhs

    Rs 2 lakhs

    0

    0

    0

    Rs 2 lakhs

    Rs 2.5 lakhs

    Rs 3 lakhs

    Rs 1.5 lakhs

    Rs 10 lakhs

    Rs 9 lakhs

    Rs 5 lakhs

    Rs 5 lakhs

    Rs 16 lakhs

    Rs 12.50 lakhs

    Rs 15 lakhs

    Rs 7.5 lakhs

    Total Expenditure towards CER in 5 years is Rs 80 lakhs.

  • Annexure-4

    Budget of Village wise Welfare Expenditure based on Public Hearing & Socio-economic needs

    Table No. 3: Health Care Facilities Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for 5

    years

    1. Anandapur Organising Health camp with free distribution of medicines

    Nityanandpur Rs 2 lakhs

    2. Lagardanga Ghutgoria

    Rs 2 lakhs

    3. Tikar Gram Rs 2 lakhs

    4. Barjora Barjora Rs 2 lakhs

    5. Saharjora Saharjora Rs 2 lakhs

    Sub. Total Rs 10 lakhs

    Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for 5

    years

    1. Anandapur Providing ambulance to address the emergency need

    Nityanandpur

    Rs 9 lakhs

    2. Lagardanga Ghutgoria

    3. Tikar Gram

    4. Barjora Barjora

    5. Saharjora Saharjora

    Sub. Total Rs 9 lakhs

    Table No. 4: Education Facilities Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for 5years

    1. Saharjora Repairing of School Boundary Walls and /or Toilets

    Saharjora Rs 1 lakhs

    2. Tikar Gram Ghutgoria

    Rs 1 lakhs

    3. Gutgoria Rs 1 lakhs

    4. Kadsol (Barjora College)

    Barjora Rs 1 lakhs

    5. Anandpur Nityanandpur Rs 1 lakhs

    Total Rs 5 lakhs

    Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for 5years

    1. Saharjora Setting up library with study facility

    Saharjora Rs 1 lakhs

    2. Tikar Gram Ghutgoria Rs 1 lakhs

  • Annexure-4

    3. Gutgoria Rs 1 lakhs

    4. Kadsol (Barjora College)

    Barjora Rs 1 lakh

    5. Anandpur Nityanandpur Rs 1 lakhs

    Total Rs 5 lakhs

    Table No. 5: Professional Skill Development Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for 5

    years

    1. Anandapur Training program for development of self

    sustainable/ job oriented professional skill

    Nityanandpur Rs 4 lakhs 2. Chaitnyapur

    3. Lagardanga Ghutgoria Rs 4 lakhs

    4. Tikar Gram

    5. Barjora Barjora Rs 4 lakhs

    6. Kadsol

    7. Saharjora Saharjora Rs 4 lakhs

    8. Muktatore

    Total Rs 16 lakhs

    Table No. 6: Drinking Water Facilities Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for 5

    years

    1. Chaitnyapur Construction of Bore well with overhead tank to supply drinking water

    Nityanandpur Rs 2.5 lakhs

    2. Gutgoria Ghutgoria Rs 2.5 lakhs

    3. Tikar Gram Ghutgoria Rs 2.5 lakhs

    4. Saharjora Saharjora Rs 2.5 lakhs

    5. Muktatore Saharjora Rs 2.5 lakhs

    Total Rs 12.5 lakhs

    Table No. 7: Village Road Development Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for

    5years

    1. Muktatore Repairing of Village Roads

    Saharjora Rs 3 lakhs

    2. Kadsol Barjora Rs 3 lakhs

    3. Lagardanga Ghutgoria Rs 3 lakhs

  • Annexure-4

    4. Gutgoria Rs 3 lakhs

    5. Chaitnyapur Nityanandpur Rs 3 lakhs

    Total Rs 15 lakhs

    Sl. No.

    Name of Village

    Particulars of the Project

    Under G.P. Assessment Amount for 5years

    1. Muktatore Installation of solar lights on the village

    roads to provide alternative source of energy to the villages

    Saharjora Rs 1.5 lakh

    2. Kadsol Barjora Rs 1.5 lakh

    3. Lagardanga Ghutgoria

    Rs 1.5 lakh

    4. Ghutgoria Rs 1.5 lakh

    5. Chaitnyapur Nityanandpur Rs 1.5 lakh

    Total Rs 7.5 lakhs

    Action Plan There is a specific time bound action plan has been suggested below for monitoring of proposed CER activities to ensure its due time completion as well as its effective implementation. Under the direct supervision of Plant Head, one employee should be given responsibility to conduct regular monitoring process and for reporting in regular interval (i.e. either monthly or quarterly basis) to send the half yearly progress report to the Regional office and to the district collector, which will be uploaded on the company/ plant’s own website. The activities considered under CER proposal which has been requested by the public during Public Hearing will be implemented in a Time bound manner after fund allocation on different activities head.

    The concerned responsible person from STPL will ensure implementation of aforesaid CER activities in a well coordinated need based manner in consultation with local administration and concerned line departments, public representatives and local youth.

  • Annexure-4

    Table No. 8: Time Bound Action Plan for Implementation of CER Activities

    Sl. No.

    CER Activities Name of Village

    Under G.P. Time Bound Half Yearly Progress of Activities (in %) Total

    1 2 3 4 5 6 7 8 9 10

    Rs. 2,00,000/- to each village for 5 years plan period (Total allocated budget Rs. 10,00,000/-)

    1. Organising Health camp with free distribution of medicines

    Anandapur Nityanandpur 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 100%

    2. Lagardanga Ghutgoria

    10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 100%

    3. Tikar Gram 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 100%

    4. Barjora Barjora 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 100%

    5. Saharjora Saharjora 10% 10% 10% 10% 10% 10% 10% 10% 10% 10% 100%

    Rs. 9,00,000/- for 5 years plan period (Total allocated budget Rs. 9,00,000/-) 1. Providing

    ambulance to address the emergency need

    Anandapur Nityanandpur

    100%

    100%

    2. Lagardanga Ghutgoria

    3. Tikar Gram

    4. Barjora Barjora

    5. Saharjora Saharjora

    Rs. 1,00,000/- for to each village in 2 equal installments for the 5 years plan period (Total allocated budget Rs. 5,00,000/-)

    1. Repairing of Boundary Walls and /or Toilets

    Anandapur Nityanandpur 50% 50% 100%

    2. Ghutgoria Ghutgoria

    50% 50% 100%

    3. Tikar Gram 50% 50% 100%

    4. Kadsol Barjora 50% 50% 100%

    5. Saharjora Saharjora 50% 50% 100%

    Rs. 1,00,000/- for to each village in 2 equal installments for the 5 years plan period (Total allocated budget Rs. 5,00,000/-)

  • Annexure-4

    Sl. No.

    CER Activities Name of Village

    Under G.P. Time Bound Half Yearly Progress of Activities (in %) Total

    1 2 3 4 5 6 7 8 9 10

    1. Setting up library in the schools

    Anandapur Nityanandpur 50% 50% 100%

    2. Ghutgoria Ghutgoria

    50% 50% 100%

    3. Tikar Gram 50% 50% 100%

    4. Kadsol Barjora 50% 50% 100%

    5. Saharjora Saharjora 50% 50% 100%

    Rs. 2,00,000/- for each village for the 5 years plan period (Total allocated budget Rs. 16,00,000/-)

    1. Training program for development of self sustainable/ job oriented professional skill

    Anandapur Nityanandpur

    25% 25% 25% 12.5% 12.5% 100%

    2. Chaitnyapur 25% 25% 25% 12.5% 12.5% 100%

    3. Lagardanga Ghutgoria

    25% 25% 25% 12.5% 12.5% 100%

    4. Tikar Gram 25% 25% 25% 12.5% 12.5% 100%

    5. Barjora Barjora

    25% 25% 25% 12.5% 12.5% 100%

    6. Kadsol 25% 25% 25% 12.5% 12.5% 100%

    7. Saharjora Saharjora

    25% 25% 25% 12.5% 12.5% 100%

    8. Muktatore 25% 25% 25% 12.5% 12.5% 100%

    Rs. 2,50,000/- to each village in 2 equal installments for the 5 years plan period each village for 5 years plan period (Total allocated budget Rs. 12,50,000/-) 1. Construction of

    Borewell with overhead tank to

    Chaitnyapur Nityanandpur 50% 50% 100%

    2. Ghutgoria Ghutgoria

    50% 50% 100%

    3. Tikar Gram 50% 50% 100%

  • Annexure-4

    Sl. No.

    CER Activities Name of Village

    Under G.P. Time Bound Half Yearly Progress of Activities (in %) Total

    1 2 3 4 5 6 7 8 9 10

    4. supply drinking water

    Saharjora Saharjora

    50% 50% 100%

    5. Muktatore 50% 50% 100%

    Rs. 3,00,000/- to each village in 2 equal installments for the 5 years plan period (Total allocated budget Rs. 15,00,000/-)

    1. Repairing of Village Roads

    Chaitnyapur Nityanandpur 50% 50% 100%

    2. Lagardanga Ghutgoria

    50% 50% 100%

    3. Ghutgoria 50% 50% 100%

    4. Kadsol Barjora 50% 50% 100%

    5. Muktatore Saharjora 50% 50% 100%

    Rs. 1,50,000/- to each village in 2 equal installments for the 5 years plan period (Total allocated budget Rs. 7,50,000/-) 1. Installation of

    solar lights on the village roads to provide alternative source of energy to the villages

    Chaitnyapur Nityanandpur 50% 50% 100%

    2. Lagardanga Ghutgoria

    50% 50% 100%

    3. Ghutgoria 50% 50% 100%

    4. Kadsol Barjora 50% 50% 100%

    5. Muktatore Saharjora 50% 50% 100%

  • Annexure-5

    DETAILS OF ROOF TOP RAINWATER HARVESTING WITHIN PREMISES

    AND ARTIFICIAL RECHARGE MEASURES OUT SIDE THE PREMISES

    In compliance to the query raised by Ministry of Environment, Forest & Climate Change,

    Delhi details of roof top rainwater harvesting and artificial recharge measures by adopting

    village pond have been furnished herewith.

    ROOFTOP RAINWATER HARVESTING

    Rainwater harvesting is the technique of collection and storage of rainwater at surface or in

    sub-surface reservoir before it is lost as surface run-off. The augmented resource can be

    harvested in the time of need. Artificial recharge to groundwater is a process by which the

    groundwater reservoir is augmented at rate exceeding the one under natural conditions of

    replenishment

    Rooftop rainwater harvesting structures are to be constructed in the premises of M/S Sonic

    Thermal Pvt. Ltd. The collected rainfall at first is to be passed through a filter so that the water

    can be drained into suitable structures. A provision to drain out portion of the first rainfall has

    been designed, as it would flush out the dirt.

    Rain water harvesting is an important activity to conserve the rainwater for reuse and thus

    reducing the overall raw water consumption for domestic requirements.

    In the project area, the rainwater available from roof tops of buildings that goes as waste

    can be utilized gainfully at the time of need by way of surface storage. The rainwater

    harvesting system has been designed in such a way that it does not occupy large space for

    collection.

    In order to harvest the rain water within the project premises it is recommended to harvest

    roof top rain water from buildings. For this purpose quantity of rain water that could be

    generated is calculated below.

    Runoff = Rainfall X Catchment area X Runoff coefficient

    Annual Rainfall = 1.19 m

    Total Run-off: Roof Top

    Intensity of rainfall = 1.19 m

    Drainage area in sqm = 11207.0 m2

    Coefficient of run-off = 0.85

    Therefore, runoff = 0.85 x 1.19 x 11207.0 = 11335.88 m3

  • Annexure-5

    Total Run-off: Road Area

    Intensity of rainfall = 1.19 m

    Drainage area in sqm = 5684.00 m2

    Coefficient of run-off = 0.70

    Therefore, runoff = 0.70 x 1.19 x 5684.00 = 4734.77 m3

    Total Run-off: Open Area

    Intensity of rainfall = 1.19 m

    Drainage area in sqm = 23811.00 m2

    Coefficient of run-off = 0.60

    Therefore, runoff = 0.60 x 1.19 x 23811 = 17001.05 m3

    Total Runoff Load = (11335.88 +4734.77 +17001.05) m3

    = 33071.7 m3/annum

    From the above computation, it is evident that a total quantum nearly about 33071.7 m3 of

    rain water can be fruitfully harvested annually by constructing storage tank in the premises

    & recharge pits.

    DESIGN OF THE STORAGE TANK

    The storage capacity of the tank is considered to store rainwater available from rooftop of the

    buildings. The capacity of the storage tanks has been designed to accommodate rainfall from

    the roof area.

    The size of the storage tank is suggested to be 30 m (length) x 10 m (breadth) x 2.5 m depth).

    Artificial Recharge of Ground Water through the Village Pond:

    It is noteworthy that, the Total Fresh Water Requirement of the project is 166980 m3 per

    annum. So, in order to ensure the enhanced quantum of recharge, the plant authority has

    planned to renovate and maintain 1 no. of private pond existing nearby with due consent of

    villager. The pond is in Saharjora mauza the consent agreement is also attached.

    The industry has adopted pond near the industrial complex in order to recharge the rain

    water. It is proposed to adopt the village pond to take-up recharge to ground water of the

    pond water, which is overflowing to adjacent areas during monsoon period. The recharge to

    ground water in the pond area via pond cleaning and desilting will result into rise in water

    levels in the village tube-wells and increase the supply of water to the lands adjacent for

    irrigation purposes. Thus recharge schemes in the pond will benefit the area.

  • Annexure-5

    POND RECHARGE CALCULATION Sl No

    Village Name

    Khata No

    Area (in Hectare)

    Area (m2)

    Existing Depth (m) after Desilting

    Volume of water stored in pond/ Storage Capacity (cum)

    Water available in Pond for recharge in 1 season (cum)

    Total annual Filling (no.)

    Quantity of water to be recharge (cum)

    No. of Recharge Shaft @15 m3/hour

    1 Saharjora 26 1.56 15600 3 46800 46800 3 140400 2 So we have to recharge 100% of the total withdrawal amount of water.

    Annual Water requirement = 166980 m3/annum

    Recharge Requirement = 100% of the Ground water withdrawal

    i.e. 166980 m3/annum.

    Recharge through pond = 140400 m3/annum

    RWH within premises = 33071.7 m3/annum

    Total rain water harvesting and ground water recharge = (140400+33071.7) m3/annum

    = 1,73,471.7 m3/annum

    Thus the proposed rain water harvesting within premises and ground water recharge through

    pond will be 1,73,471.7 m3/annum and it is higher than the required quantity of 166980

    m3/annum.

  • userTypewritten TextAnnexure-5

  • userTypewritten TextAnnexure-5

  • userTypewritten TextAnnexure-6

  • Page : 1 Of 2

    TAX INVOICE (Rule 46, Section 31 of The Central Goods and Services Act, 2017)

    ORIGINAL FOR RECIPIENT

    Seller: Forbes Marshall Pvt. Ltd. Buyer: 63049B-85, PHASE-II,Chakan Industrial Area,Sawardari , ChakanTal : Khed , Dist : PuneCHAKAN 410501Maharashtra,India

    SONIC THERMAL PVT LTD37 SHAKESPEARE SARANIKOLKATA 700017West BengalIndia

    KIND ATTENTION :PAN No : AAJCS1195G

    GSTIN : 19AAJCS1195G1Z2GSTIN. : 27AAACF2630E1Z5 PLACE OF SUPPLY : West BengalSTATE CODE : 27 STATE CODE : 19OUR PAN. : AAACF2630EBANK NAME : HDFC BANK LTD.(KANJUR MARG BRANCH)BANK ACCOUNT NO : FMPL66063049BANK ADDRESS : I - THINK TECHNO CAMPUS,OPP CROMPTON GREAVES,

    NEAR KANJUR MARG RLY STATION, , MUMBAI-400002,MAHARASHTRA

    IFSC CODE : HDFC0004989 Above mentioned HDFC Bank details are for NEFT / RTGS only & Cheque deposition is not allowed

    TAX INVOICE NO. : 551502222 DATED : 22-JUL-2020 CHK- Std InvoiceOUR OA NO. : 550110516 DATED : 21-JUL-2020 C4N StandardYOUR PO NO. : PO DATED : 01-OCT-2019DELIVERY NO. : 6164860SHIP TO

    PAN No :SONIC THERMAL (P) LIMITED GSTIN :VILL . NAMOBANDH- SITARAMPUR STATE : West BengalP.O. GHUTGORIA, P.S. BARJORABANKURA 722168West BengalIndia(A/C : SONIC THERMAL PVT LTD)

    STATE CODE :

    PAYMENT TERM : PROFORMA70% ADVANCE30%All payment advices / intimations should be sent to [email protected] :BRANCH :ADDRESS :SHIPPING INSTRUCTIONS : DOOR DELIVERY THROUGH TCI FREIGHT . Advance recd vide Ra-550811660// amt-531000.00,

    balance payment recd vide Ra-550812940// amt-623040 (Ship set Nos. 1, 2 & 3)Balance payment received vide RA 551802646 18-JUL-20 for Rs.934560/-

    TRANSPORTER : TRANSPORT CORPORATION OF INDIA LTDLR/DOCKET NO. : 653891475 DATED : 2020/07/23 00:00:00FREIGHT TERM : To payINSURANCE BY : By Us INSURANCE POLICY

    DETAILS:Transit Policy number 0830015522 valid from 1 April 2020 to 31 March 2021, TATA AIG General Insurance Company Limited

    EWAYBILL :CORRESPONDENCE ADDRESS

    :

    DOCUMENTATION DETAILS

    :

    PACKING DETAILS : 3 WCNET WEIGHT : 150 GROSS WEIGHT : 270

    **** BALANCE SUPPLY ****INV SR NO DESCRIPTION OF GOODS/SERVICES UOM QTY Price

    Rs.Amount

    Rs.PO SR NO1 C4N-DCEM2100PLUS-I-485

    EMISSION MONITORING EQUIPMENTS,DUAL BEAM CROSS DUCT OPACITY MONITOR WITH LOCAL DISPLAY, CONTROL

    EA 3 354,000.00 1,062,000.00

    mailto:[email protected]

  • Page : 2 Of 2

    TAX INVOICE (Rule 46, Section 31 of The Central Goods and Services Act, 2017)

    TAX INVOICE NO. : 551502222 DATED : 22-JUL-2020 CHK- Std InvoiceOUR OA NO. : 550110516 DATED : 21-JUL-2020 C4N StandardYOUR PO NO. : PO DATED : 01-OCT-2019DELIVERY NO. : 6164860

    1 UNIT & RS485 OUTPUT, AIR PURGE BY PLANT INSTRUMENT AIR, MODEL DCEM2100 PLUSTAG No. : IBR SERIAL NO. : IBR CERT. NO. : PRODUCT SERIAL NO : DCEM 20072, DCEM 20087, DCEM-20074HSN No: 90271000

    2 C4N-ENVCONNECT-SP14

    EMISSION MONITORING EQUIPMENTS,ENVIROCONNECT SOFTWARE FOR CPCB/SPCB/LOCAL VIEW/ ETS CONNECTIVITY, COMBINED CD, SP14TAG No. : IBR SERIAL NO. : IBR CERT. NO. : PRODUCT SERIAL NO : SP-12352,SP-12350,SP-12351HSN No: 90278090

    EA 3 0.00 0.003

    Net Sales 1,062,000.00

    Tax Type Taxable Amount Rs.

    Rate(%) Tax AmountRs.

    IGST 1,062,000 18% 191,160

    GROSS AMOUNT 1,253,160AMOUNT (IN WORDS) Indian Rupees Twelve Lakh Fifty Three Thousand One Hundred Sixty Only

    LESS RECEIPTS -ADVANCE 934,560

    ALLAR52020031212178025 12-MAR-2020ALLAR52020071813064872 18-JUL-2020

    NET AMOUNT 318,600AMOUNT (IN WORDS) Indian Rupees Three Lakh Eighteen Thousand Six Hundred Only

    Payment Schedule Amount Rs.

    Amount Due (Inclusive of Taxes) 318,600Total : 318,600

    TERMS AND CONDITIONS:

    This Invoice shall be construed and governed in accordance with the "Standard Terms and Conditions of Sale of Goods / Services" annexed with the above referred Sales Order Acceptance (Our OA No. 550110516 dated 21-JUL-2020)

    GST Declaration : We hereby confirm that the particulars given in this Tax Invoice are true and that the amount mentioned in this Tax Invoice represent the price actually charged to the Buyer and that there is no flow of additional consideration, directly or indirectly, from the Buyer.

    For Forbes Marshall Pvt. Ltd.

    AUTHORISED SIGNATORY

    SAVITHA SANATHKUMAR SALIGRAM

    Digitally signed by SAVITHA SANATHKUMAR SALIGRAM DN: c=IN, o=Personal, postalCode=410501, st=MAHARASHTRA, serialNumber=1d26578e801365b9d9b7efb4a1f72a10e3880792d2b0b197fd77e12d1a80d931, cn=SAVITHA SANATHKUMAR SALIGRAM Date: 2020.08.27 11:05:19 +05'30'

  • 8/27/2020 RTDMS

    cpcbrtdms.nic.in/cpcbIndustryRegistration/home 1/4

    Acknowledgement of submission of compliance information

    Central Pollution Control Board,

    Parivesh Bhawan, East Arjun Nagar,Delhi 110032, India

    Details submitted by Ujjwal Dey for SONIC THERMAL PVT. LIMITED falling under 17 categories or GPI units under Ganga Basin of Industries on 19 Aug2020 at 11:38 hrs

    on CPCB Portal www.cpcb.nic.in/17catindustriesinfo

    Industry Code -

    Industry Category Iron & Steel

    Falling under Ganga Basin No

    Industry Name SONIC THERMAL PVT. LIMITED

    Address WBIDC, Plasto Steel Park, Village Namabandh-Sitarampur & P.O. - Ghutgoria, P.S. Barjora, Bankura-722138, Durgapur, West Bengal-722138

    Name of Regional Office, SPCB Durgapur Regional Office

    Online Emission MonitoringSystem provided

    Yes

    Online Effluent MonitoringSystem provided

    No

    Online Data submitted to CPCB Yes

  • 8/27/2020 RTDMS

    cpcbrtdms.nic.in/cpcbIndustryRegistration/home 2/4

    Online Data submitted to SPCB No

    Industry Registered By Name Email Mobile

    Ujjwal Dey [email protected] 9748597975

    Industry’s Representatives Name Email Mobile Landline Plant/Process

    Rajesh Kumar [email protected] 8653544956 Manager - Mechanical

    Sovic Maji [email protected] 8926271732 Manager - Electrical

    Rajesh Kumar [email protected] 8653544956 Manager - Mechanical

    Souvik Maji [email protected] 8926271732 Manager - Electrical

    Bank Guarantee No

    Monitoringsystemattachedto

    Type ofMonitoringSystem

    ProcessesAttached

    Monitoring System Details

    FerroFurnaceStack 5(S5)

    Emission Furnace-5,Capacity7.5 MVA

    Parameter DeviceId

    DeviceMake

    DeviceVendor

    DeviceModel

    SystemCertified

    Certification CPCBURL

    PM 20072 ForbesMarshall

    ForbesMarshall

    DCEM21XX

    YES TUV

  • 8/27/2020 RTDMS

    cpcbrtdms.nic.in/cpcbIndustryRegistration/home 3/4

    Declaration:

    I Ujjwal Dey hereby declare that I am the representative of SONIC THERMAL PVT. LIMITED and I have registered my email id for any communication withCPCB with respect to any pollution control measures or administrative issues. I shall withdraw this registration if I do not represent this industry any more. Iwill furnish the correct information to the best of my knowledge.

    FerroFurnaceStack 2(S2)

    Emission Furnace-2,Capacity7.5 MVA

    Parameter DeviceId

    DeviceMake

    DeviceVendor

    DeviceModel

    SystemCertified

    Certification CPCBURL

    PM 20056 ForbesMarshall

    ForbesMarshall

    DCEM21XX

    YES TUV

    FerroFurnaceStack 1(S1)

    Emission Furnace-1,Capacity 5MVA

    Parameter DeviceId

    DeviceMake

    DeviceVendor

    DeviceModel

    SystemCertified

    Certification CPCBURL

    PM 20087 ForbesMarshall

    ForbesMarshall

    DCEM21XX

    YES TUV

    FerroFurnaceStack 4(S4)

    Emission Furnace-4,Capacity7.5 MVA

    Parameter DeviceId

    DeviceMake

    DeviceVendor

    DeviceModel

    SystemCertified

    Certification CPCBURL

    PM 20074 ForbesMarshall

    ForbesMarshall

    DCEM21XX

    YES TUV

    FerroFurnaceStack 3(S3)

    Emission Furnace-3,Capacity7.5 MVA

    Parameter DeviceId

    DeviceMake

    DeviceVendor

    DeviceModel

    SystemCertified

    Certification CPCBURL

    PM 20054 ForbesMarshall

    ForbesMarshall

    DCEM21XX

    YES TUV

  • 8/27/2020 RTDMS

    cpcbrtdms.nic.in/cpcbIndustryRegistration/home 4/4

    Ujjwal Dey

    For SONIC THERMAL PVT. LIMITED

    Kindly send this acknowledgement along with other relevant documents to CPCB.

  • Annexure-7

    Introduction

    Chromium is one of the most common toxic heavy metals found in the environment. It exists in the common oxidation states as hexavalent Cr (VI) and trivalent Cr (III). Chromium as Cr (III) is highly immobilised in the solid waste slag matrix and hence does not leach out. Moreover trivalent chromium is far less toxic than its hexavalent counterpart. On the other hand Cr (VI) is highly mobile under all environmental conditions and it causes all the toxic effect. As per Occupational Safety Health Administration (OSHA), USA, the major health effects associated with exposure to Cr (VI) include lung cancer, nasal septum ulcerations and perforations, skin ulcerations and allergic and irritant contact dermatitis. Toxicity of chromium ranges from pulmonary to dermatological problems. As per EPA (2000), it is a suspected carcinogen. That is why there is stringent USEPA Toxicity Characterising Leaching Study (TCLP) standard such as 0.1mg/l for Cr (VI) and 5.0 mg/l for total chromium (USEPA, 1990). There also exists stringent Indian discharge standard such as 2.0 mg/l for total chromium (total Cr) and 0.1 mg/l for Cr (VI)

    Ferrochrome is the most common alloying material for the production of different grades of stainless steel. Ferrochrome is manufactured through direct smelting in Sub-merged Arc Furnace (SAF) at a temperature above 1500 0C.The furnace has the suitable system for tapping heavier metal and lighter slag and their handling.

    In the ferrochrome manufacture the main contributor to solid waste is from the dust collected in in the bag filters and the Fe-Cr slag after the metal recovery section.

    Management of Bag Filter Dust

    The unit shall use Chromites ore dust. It has a briquette plant. The dust collected in the bag filter will therefore contain more of hexavalent chromium which is considered hazardous. Utmost care is to be exercised in handling the bag Filter dust. The company envisages to install a pneumatic conveying system for transfer of dust from the bag filters if each furnace to the silo. From the silo the dust is again conveyed to the briquetting plant by pneumatic conveying. The risk involved and the management plan to handle the risk is given in the table below

    The dust so collected is recycled back to the furnace through the briquetting plant. A description of briquetting plant has been given in Chapter II of EIA at Section 2.4.3iii. Proper care is exercised in handling the dust as per MSDS of Chromium.

    Management of Ferrochrome slag:

    Molten slag is lighter than the molten Fe-Cr alloy. It is tapped out through the tape holes in ladles and is allowed to cool. . Ferrochrome (FeCr) slag is found to consist of mainly silica, alumina and magnesia with significant amounts of chromium and iron oxides in the form of Partially Altered Chromite (PAC) and entrained ferrochrome alloy.

  • Annexure-7

    There is a generation of 1–1.2 MT of solid waste slag for each MT of ferrochrome product. The waste slag material can be made available in different sizes under different cooling conditions and after material recovery. It contains about 6–12% deleterious substances like chromium as chromium oxide and has the potentiality of releasing hazardous chromium compounds to the environment restricting its use and disposal. Chromium is one of the most common toxic heavy metal found in the environment. It exists in the common oxidation states of hexavalent chromium Cr (VI) and trivalent chromium Cr (III). While chromium as Cr (III) is less mobile and less harmful, Cr (VI) is highly leachable and extremely toxic under all environmental conditions. As per Occupational Safety Health Administration (OSHA), the major health effects associated with exposure to Cr (VI) include lung cancer, nasal septum ulcerations and perforations, skin ulcerations, and allergic and irritant contact dermatitis etc. Toxicity of chromium ranges from pulmonary to dermatological problems. As per US EPA, it is a suspected carcinogen. That is why there exists stringent Indian discharge standard such as 2.0 mg/l for total chromium (total Cr) and 0.1 mg/l for Cr (VI).

    Air cooled slag is crushed in order to extract any additional metal remaining in the slag by density separation or jigging process. Given below is a description of process jigging plant.

    Metal Recovery Plant:

    The ferroalloy slag consist some portion of valuable ferroalloy material which can be obtained in a directly saleable condition and can be sold at reasonably good market rates as compared to the main ferroalloy product. The Metal Recovery Plant is being used to recover this portion of metal from slag.

    Certain portion of slag is conveyed to Metal Recovery Plant (MRP) wherein it is crushed as to extract good quality Ferrochrome from the slag waste. This process involves the following :

    Crushing and screening of metal containing slag. Separation of metal from slag. Re-crushing of middling to realize additional metal

    The process flow of Metal Recovery Plant is given in Fig below.

  • Annexure-7

    Crushing and Screening:

    This circuit produces a crushed slag having a narrow size distribution, which would aid the metal liberation in further stages. Cone crushers are used to maximize shear at metal-slag interfaces. Wherever possible, the multiple cycles of crushing are maintained in a close circuit so that the minimum crushed size is achieved. To minimize fines, the reduction ratios are maintained as low as possible.

    Separation of Metal from Slag:

    This involves two – stage recovery jigging process; known as the ‘Coarse Jigging’ and ‘Fine Jigging’. During the course jigging stage, the cut density is set with an aim to recover clean metal and not with a focus on recovery. The coarse fraction is crushed to have an output in the form of saleable coarse alloy. An under-bed air pulsated jig with a float control system is on the discharge gates. A hydro-dynamically stable float is positioned in the jigging bed.

    Later during the Fine Jigging, the cut density is lowered to focus on recovery. Since the material is fine, a strongly pulsed Jig is not required here. Only a single stage is required to utilize ‘through the bed’ Jigging as the material quantity reaching this stage is only about 5% of the total feed. The output of this stage is in form of fine tailings and slimes.

    Slime Tailing

    Crush/Screen

    Coarse Jig Fine Jig

    Slime handling

    Fine Tailing

    To Furnace Coarse Tailings

    Feed Water

    Middling

    Fine

    Coarse Middling

    Saleable Coarse Product

    Process Flow diagram of Jigging Plant

  • Annexure-7

    The final disposed middling from coarse jigging and very fine metal from fine jigging are used for furnace feed.

    Re-crushing of Middling:

    The re-crushed middling are returned for re-jigging to recover additional material.

    The throughput material (slag) requirement in an MRP (Metal Recovery Plant) is 3 times of its output. i.e 3 MT of slag needs to be fed to achieve 1 MT of saleable ferrochrome. The feed size specifications shall be provided by the technology supplier based on the final equipment design parameters. The standard composition of High Carbon Ferro chrome (HCFC) is as given below:

    Chromium - 57% to 63% Carbon - 6-8% Silicon - 4% Phosphorus - 0.0025-0.03% Sulphur - 0.03% Max

    In STPL ferrochrome plant wet jigging process is adopted. The slag so separated in the process is carried to slag storage shed. The generated slag is then subjected to TCLP test and if the hexavalent chromate is found below the specified hazard limit of 5mg/L(US EPA) for total chromium , total chromium of 2 mg/l and o.1 mg/l for Cr-(VI) in the Indian discharge standard. It is stored in a separate heap.

    There are number of options for utilisation of non hazardous slag.

    It is used as road base material in road construction. It is used as a concrete aggregate. It can be used in the manufacture of Portland cement. It can be used in the manufacture of slag cement. It can be used for filling of the evacuated mines

    If the particular batch of slag is found to contain more than the specified limit in TCLP test, it is taken to storage shed where it is stored on impervious flooring. Normally many of the Fe-Cr factories operating in the eastern zone of India find that the TCLP test results are within the limit.

    The hazardous slag is transported by truck covered with suitable tarpaulin cover by authorised hazardous waste TSDF operator. The following risks are identified and Management Plan for handling of risk also mentioned below..

  • Annexure-7

    Risk Management Plan:

    Activity Risk description Action to minimise /manage risk

    Responsibility

    Transporting of slag Potential for slag to become airborne during transportation

    Make use of tarpaulin over slag during transportation if the slag is having to potential to cause dust or to be blown from the vehicle.

    Transporter

    Handling of slag Potential for slag to emit dust during loading and unloading

    Slag is a heavy and dense material. The potential to cause is low. Take precaution to minimise dust formation by wetting the slag when necessary.

    Operator

    Material storage. Potential of stockpiled material to enter the surrounding environment.

    The slag is stable in storage. Slag is usually consumed in large volumes for which packaging is impractical. Store in demarcated area under a shed and over impervious flooring. Avoid storage conditions that may generate dust.

    Operator.

    Material Handling and Processing

    Potential for slag to emit dust during handling, crushing and screening activities.

    The slag is a heavy and dense material. The potential to cause dust is low. Take precautions to minimise dust formation by wetting of the slag when necessary.

    operator

    Material Handling and Processing of slag.

    Potential for skin exposure of humans whilst working with slag.

    Special attention other than routine personal hygiene not required.ash hands with water and soap. Wear the

    operator

  • Annexure-7

    appropriate PPE, overalls and safety boots, gloves for hands where applicable.

    Material Handling and Processing of slag

    Potential for eye contact exposure of humans whilst working with slag.

    Eye protection equipment should be worn wrhe dust is a potential hazard. Safety goggles and faces shields if the potential exists for the generation of sharp small chips, sharp flakes or excess dust.

    Operator

    Material Handling and Processing of slag

    Potential for inhalation of dust exposure of humans working with slag.

    Take precaution to minimise dust formation by wetting of the product and use appropriate personal protective e equipment to prevent dust inhalation.

    Operator

    Material Handling and Processing of slag

    Potential for ingestion of slag dust by humans working with slag and not wearing PPE or washing hands.

    Washout mouth with water. Wash hands thoroughly after handling.

    operator

    Environmental spillage.

    Potential for accidental release of slag into the environment during transport and material handling

    Clean slag spills immediately and remove to suitable storage area.

    Transporter and operator

    The hazardous Ferrochrome slag is disposed to authorised Hazardous Waste TDSF operators.

    The hazardous waste i.e. the ferrochrome slag having hexavalent chromium is then disposed in

    the secured landfills by the TDSF operator.

  • Annexure-8

    Green Belt Development: The Ferroalloy plant is operating since 2006 with consent to operate from West Bengal

    Pollution control Board. Present Proposal is for modification of product mix. The plant is

    located over a plot of land allotted by the WBIDCL in the Barjora Plasto Steel Park. The

    facility is already having a developed green belt. However, in keeping with the specific ToR

    conditions the company will develop green belt on stipulated 40% land of plant area i.e.

    over 6 acres of land.

    The greenbelt development plan aims to overall improvement in the environmental

    conditions of the region. The plan with a five-fold objective addresses issues such as

    providing sink for air pollutants likely to emitted from the project; enhancing the forest

    cover for increasing the biodiversity of the region; providing aesthetic value to the project

    area enhancing the ecological equilibrium of the area; and to a large proportion in

    combating soil erosion.

    It is proposed to develop greenbelt around the periphery as well as along roadside/and sub-

    paths of project area totaling about 33% of land area in line with the National

    Environmental Policy 2006 of Government of India. STPL has developed green belt in and

    around plant premises and proposes further development the action plan for green belt

    development is given below.

    Criteria for selection of Species: 1. Tolerance to specific conditions or alternatively wide adaptability to Eco physiological

    conditions.

    2. Rapid growth

    3. Capacity to endure water stress and climate extremes after initial establishment.

    4. Differences in height and growth habits Pleasing appearances Providing shade

    5. Ability of fixing atmospheric Nitrogen

    6. Improving waste lands.

    With the above criteria in mind, green belt development work will be undertaken on area of 6 acres. About 600 saplings will be planted per acre. The details of existing Green Belt and Development of Green Belt Plan for the proposed project are given below. The existing plantation has been done alongside the boundary wall and in the vacant land earmarked for the purpose. The plants in the existing green belt include Devil Tree (Alstonia scholaris), Mahaneem (Melia azadiracta), Gulmohar (Delonix regia), Acasia (Acacia auriculiformis), Am (Mangifera indica), Silk Tree (Albizia procera) with survivility of 65%. The future development will also include above local species. The tentative implementation proposal for development of green belt and species to be planted is mentioned below.

  • Annexure-8

    The tentative implementation proposal for development of green belt Sl. No.

    Year of Plantation Area

    (in acres) No of

    Saplings Cumulative

    Area % of Total

    Area 1 Existing Plantation 2.00 1200 2.0 13.33 2 1st year of proposed

    Expansion 1.0 600 3.0 20

    3 2nd year 1.5 900 4.5 30 4 3rd year 1.5 900 6.0 40 Total 6.0 3600 40

    Green Belt Photograph:

  • Annexure-8

  • Annexure-8