sor-5: pipeline & terminal piping works (amendment … · page 1 of 16 sor-5: pipeline &...
TRANSCRIPT
Page 1 of 16
SOR-5: PIPELINE & TERMINAL PIPING WORKS (Amendment-2)
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
PIPELINE ENGINEERING
1 P010.01.00 PIPELINE LAYING / INSTALLATION
PIPELINE LAYING/ INSTALLATION Supply of Coated/
Bare linepipes as per Specifications, Laying/installation of coated/ bare line
pipe as required , associated fittings and accessories, etc. as per
specifications, drawings, other provisions of Contract and instructions of
Engineer-in- Charge, including but not limited to carrying out the following:
handling, loading, transportation and unloading of externally corrosion
coated and bare line pipes to Contractor's own stock-yard(s)/ workshop(s)/
work-site(s) including stringing on the pipeline Right-of- Use (ROU)/ Right of
way (ROW); Arrangement of all additional land required for Contractor's
storage, fabrication, access for construction (other than Owner provided
ROU/ROW); supply of all materials, consumables, equipment, labour, etc;
Staking and installation of construction markers, clearing, grubbing, grading
(as required) of Right of Use/ Right of Way; Counting the number and type
of trees cut in presence of DFO /concerned authorities and keeping record
thereof; Trenching to all depths and to a width to accommodate the pipeline
and/ or optical fiber cable/cable conduit as specified in scope document
and as per the relevant standards, specifications, etc. by excavation in all
types of soils(including soft/hard rock), including blasting, chiseling or
otherwise cutting etc.; providing trench padding as required with sand/
graded earth approved by Engineer-in-Charge; Carrying out repairs of
line pipe and coating as required, thorough internal cleaning of all pipes
by suitable methods to remove debris, shots, grits etc. to the satisfaction of
Page 2 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
Engineer-in-Charge; Stringing of line pipes along ROU/ROW including
providing straw bags, soft padding/sand padding; Aligning, bending,
cutting and beveling (as required) of pipes for welding and field
adjustments, NDT of re-beveled area, welding, carrying out destructive/
non-destructive testing of welds as required including radiography and
providing all requisite equipment, labor, supervision, materials, films,
consumables, all facilities and personnel to process, develop, examine
and interpret radiographs and other tests, as required; carrying out
repairs of weld joints found defective by Engineer-In-Charge, carrying out
re-radiography and other nondestructive tests as required on repaired joints,
etc.; Installation of carrier pipe at all crossings including roads/canals/
nala/ water crossings etc. (except at major water and other crossings that
are specifically covered separately in this document) by open cut or
Jacking/boring method including pre-testing as required; Carrying out
installation of carrier pipe in the casing pipe at cased crossings (excluding
supply and installation of casing pipes covered separately); Coating of all
field weld joints, long radius bends, buried fittings, valves etc.; Lowering
the pipelines in trench including providing sand bag separators for
parallel pipelines at the specified spacing(when applicable), providing
required padding over and around the pipeline with sand/graded
material approved by Engineer-In Charge (in rocky areas), backfilling with
available, approved excavated material and/or other suitable soil approved
by Engineer-In-Charge; Supply and installation of slope breaker as
per specifications and drawings in steep slope areas, wherever required;
Carrying out hydrostatic testing including air cleaning, flushing, filling,
gauging, pressurization of complete pipeline in various test sections as
approved by Engineer-In- Charge to the specified test pressure, providing
all equipment, pumps, fittings, instruments, dead weight tester, all types of
pigs etc., and services, supervision, labour, consumables, water including
supply of corrosion inhibitor, air, etc. as required, locating of leaks and
rectification of defects attributable to Contractor, retesting after rectification,
Page 3 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
successful completion of Hydrotesting of pipeline (De-watering etc.
covered elsewhere in the SOR); All tie-ins, including the tie-in(s) with
the pipeline /piping installed by others including cutting of test header, re-
beveling as required; Carrying out all temporary, ancillary, auxiliary
works and all incidental works required to make the pipeline ready for
pre-commissioning; Repair of defects recorded during EGP/gauge plate run
or otherwise including cutting, beveling, welding, radiography, field joint
coating etc; as applicable, Final clean-up and restoration of right of way/right
of use including obtaining work permits from respective statutory
authorities as required and disposal of debris and returning all surplus
material to designated disposal areas/storage yard, as directed by
Engineer- In Charge; Restoration of land, facilities and boundary wall etc.
at associated facilities dismantled/damaged by the Contractor during
construction; Obtaining work permits from various statutory authorities
having jurisdiction, before execution of the work, and complying with all
stipulation/ conditions/ recommendation of the said authorities; Preparation
of as-built drawings, pipe-book and other records. SOR shall be read in
conjunction with scope of work, job specific requirements, specifications,
standards, drawings and other provision of contract document. All above
works for buried pipeline as per following details:
1.1
P010.01.01
Supply of Coated Line Pipes (without OFC/OFC conduit) as
per following details: ( Pipe OD – 219.1 mm, Wall Thickness –
7.1 mm, Pipe Grade - API 5L Gr. X-52 PSL 2 , Coating - 3LPE ) Note:
Rate of laying of OFC and conduit shall be quoted in relevant Schedule
of Rate (SOR) of Telecom works hence not to be included in pipeline
laying works.
m 11650
1.2
P010.01.02
Supply of Bare Line Pipes (without OFC/OFC conduit) as per
following details: ( Pipe OD – 219.1 mm, Wall Thickness – 7.1
mm, Pipe Grade - API 5L Gr. X-52 PSL 2 , Bare) Note: Rate
of laying of OFC and conduit shall be quoted in relevant Schedule of
m 500
Page 4 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
Rate (SOR) of Telecom works hence not to be included in pipeline
laying works.
1.3
P010.01.03
Installation of Coated Line Pipes (without OFC/OFC conduit) as
per following details: ( Pipe OD – 219.1 mm, Wall Thickness –
7.1 mm, Pipe Grade - API 5L Gr. X-52 PSL 2 , Coating - 3LPE ) Note:
Rate of laying of OFC and conduit shall be quoted in relevant Schedule
of Rate (SOR) of Telecom works hence not to be included in pipeline
laying works.
m 10738
2 P010.02.00 GEO TEXTILE BAGS FOR ANTI-BUOYANCY
2.1 Additional works over and above item no. P010.01.00 for design,
manufacture and supply of Non- biodegradable geo-textile bags (made
of polypropylene fabric) materials and installation of geo- textile bags duly
filled with gravel/ stone ballast on pipelines of all wall thicknesses for anti-
buoyancy, drawings, and instructions of Engineer-in-Charge and other
provisions of the Contract document. Note: This item shall be
applicable for Marshy areas as per instructions of Engineer-in-Charge.
m 100
3 P010.03.00 BACKFILLING WITH SELECT SOIL
3.1
P010.03.01
BACKFILLING WITH SELECT SOIL (For Station
Approach)
Unit rate over and above item no. P010.01.00 for supply of specified
and approved quality of sand including supply of sand in place of
available excavated material and/ or other suitable soil as per applicable
standards/ specifications, including backfilling of excavated trench for
specified length after laying of pipeline, including transportation of backfill
material over all distances and disposal of surplus excavated soil, complete.
m 200
3.2 P010.03.02 BACKFILLING WITH SELECT SOIL (For Seismic
Areas) m 100
Page 5 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
Providing specified and approved quality of backfill material as defined in
contract document at seismic zone along pipeline route as per
standards/ specifications over and above item P010.01.00, including
supply of select backfill in place of available excavated material and/or other
suitable soil including backfilling of excavated trench for specified length
after laying of pipeline including transportation of such special backfill
material over all distances and disposal of surplus excavated soil, complete.
4 P010.04.00 PERMANENT MARKERS
Supply, fabrication and installation of following types of permanent markers
along the route including all associated civil works such as excavation in all
types of soil, construction of pedestals and grouting with concrete, clearing,
supply and application of approved colour and quality of primer and
paint, stencil letter cutting for numbers, direction, chainage, etc.,
restoration of area to original condition and performing all works as per
drawings, specifications and instructions of
Engineer-in-Charge. Note: The painting of all markers shall conform to
Industrial Marine environment of spec. 6-79-0020 irrespective of whatever
shown on respective standards.
4.1 P010.04.01 Kilometer Posts No. 6
4.2 P010.04.02 Pipeline Warning Signs No. 80
4.3 P010.04.03 Right of use Boundary Markers No. 100
4.4 P010.04.04 Aerial Markers No. 2
4.5 P010.04.05 Direction Markers No. 50
5 P010.05.00 INSTALLATION OF CASING PIPE: Supply and installation of casing pipe/
CS conduit for OFC by jacking/ boring or open cut for rail, road or
Page 6 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
canal crossings wherever required in all types of soils and terrain separately
for carrier pipes and fiber optic cable/cable conduit, supply of casing pipe
and all other Contractor supplied materials viz. casing insulators and
casing end seals as per enclosed drawing, materials for casing vents
and drains, etc. including transportation, supply of all other materials,
equipments, consumables, man-power, welding including visual inspection
of all weld joints, installation of casing insulators, end seals, vents and
drain- off pipes, backfilling and restoration as original of the facility
crossed and performing all works as per drawings, specifications
and instructions of Engineer- in- Charge and provisions of Contract
document.
5.1 P010.05.01 Installation of Casing Pipe
By Jacking/ boring
(Size :- 356 mm, Material : - API 5L GR.B/IS3589 Gr. FE 410, Wall
thickness : - 6.4 mm )
m 366
5.2 P010.05.02 Installation of CS Conduit for OFC
By Jacking/ boring
(Size : -168.3 mm, Material - API 5L GR.B/IS3589 Gr. FE 410 , Wall
thickness - 6.4 mm )
m 366
6 P010.06.00 IDLE TIME PRESERVATION OF PIPELINE
Preservation of complete pipeline as per Bid document and its
maintenance including supply of all consumables, all equipment, man-
power, etc., complete as per the requirements of specifications, other
provisions of Contract document and instructions of
Page 7 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
Engineer-in-Charge Note: Owner reserves the right to exercise either or
none of the rates below.
6.1
P010.06.01
By filling and pressurizing with nitrogen to a pressure of 2 bar (g) for
a period of 2 months ( Pipeline size – 219.1 mm, Nitrogen
Pressure in bar(g) - 2 , Specified period - 2 month )
LS 1
6.2 P010.06.02 For additional period of Two months or part thereof LS 1
6.3
P010.06.03
By filling and pressurising with corrosion inhibited water including
supply and maintenance of water with regular dosing of inhibitor to maintain
the effectiveness of the inhibitor water for the following details: (
Pipeline size – 219.1 mm, Nitrogen Pressure in bar(g) - 2 , Specified
period -2 month )
LS 1
7 P010.07.00
Supply including procurement and transportation to worksite(s)/workshop(s)
including loading, unloading and handling for the following materials to be
supplied by Contractor (except items as detailed elsewhere in the SOR
document) as per the requirement of PMS, specifications, data-sheets,
standards, instructions of Owner/ Engineer-In-Charge and other provisions
of Contract.
7.1
P010.07.01
INSULATING JOINTS
Supply of Insulating Joints as per following details:
(Size - 8 INCH, Rating - 300, Data Sheet No. - 6987-
01- 010-83-41-DS-0005)
Note: One (01) nos. each at GCPTCL DT & OPaL RT
No. 2
(Size - 4 INCH, Rating - 300, Data Sheet No. - 6987-
01- 010-83-41-DS-0005)
Note: One (01) nos. each at GCPTCL DT & OPaL RT
No. 2
Page 8 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
7.2
P010.07.02
FLOW TEES
Supply of Flow Tees as per following details:
(Size – 8x8x8 INCH, Rating - 300, Data Sheet No. -
6987-01- 010-83-41-DS-0006)
Note: One (01) nos. each at GCPTCL DT & OPaL RT
No. 2
(Size – 8x8x4 INCH, Rating - 300, Data Sheet No. -
6987-01- 010-83-41-DS-0007)
Note: Three (03) nos. each at GCPTCL DT & OPaL RT
No. 6
7.3
P010.07.02
SCRAPER TRAPS & PIG SIGNALERS
Supply of Scraper Traps & Pig Signalers as per following details:
Scraper Launcher: Size – Major Barrel: 12 Inch, Minor
Barrel: 8 Inch, Rating - 300, Data Sheet No. - 6987-01-
010-83-41-DS-0001)
Note: Tag No. 009-ML-00-101 at GCPTCL DT
Nos. 1
Scraper Receiver: Size – Major Barrel: 14 Inch, Minor
Barrel: 8 Inch, Rating - 300, Data Sheet No. - 6987-01-
010-83-41-DS-0002)
Note: Tag No. 011-MR-00-101 at OPaL RT
Nos. 1
Pig Signaler as per Data Sheet No. - 6987-01- 010-83-
41-DS-0003
Note: Tag No. 009-XXIS-1202 at GCPTCL DT & 011- XXS-1402 at OPaL
RT
Nos. 2
Pig Signaler as per Data Sheet No. - 6987-01- 010-83-
41-DS-0004 Nos. 2
Page 9 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
Note: Tag No. 009-XXIS-1201 at GCPTCL DT & 011- XXS-1401 at OPaL
RT
8 P010.08.00 LONG RADIUS (R=6D) BENDS
8.1
P010.08.01
Fabrication & Supply of Long Radius (R=6D) Bends from line pipe as
defined in scope of work. (Size - 8
INCH, Angle 30 to 45 , Pipe thickness – 7.1 mm, Material API 5L GR.
X-52 PSL 2)
No. 8
8.2
P010.08.02
Fabrication & Supply of Long Radius (R=6D) Bends from line pipe as
defined in scope of work. (Size - 8
INCH, Angle 46 to 60 degree, Pipe thickness – 7.1 mm, Material API 5L GR.
X-52 PSL 2).
No. 8
8.3
P010.08.03
Fabrication & Supply of Long Radius (R=6D) Bends from line pipe as
defined in scope of work. (Size - 12
INCH, Angle 61 to 90 degree, Pipe thickness – 7.1
mm, Material API 5L GR. X-52 PSL 2).
No.
15
9 P010.09.00
PIPELINE INSTALLATION BY HDD TECHNIQUE: Installation of 3 Layer
PE coated/ Bare linepipes of size 8", W.T. 7.1 mm and API 5L Gr. X-52
grade by HDD Method. For complete works for the crossing by horizontal
drilling method (HDD) including all additional drilled lengths necessitated by
Contractor's design of water crossings, carrying out all topographical
and geo-technical surveys required for design and construction of crossing,
preparation of all necessary design & construction drawings and procedures
for Owner's approval, mobilization and demobilization at site(s), supply of
all materials as per "Contractor's scope of supply" including 6" size, 6.4
mm API 5L Gr. B /IS:3589 Fe 410 CS conduit pipe for OFC in required
lengths, all consumables, equipments, manpower and other resources and
acquiring the required land for site preparations, and execution of, but not
limited to, the following works in accordance with specifications, drawings,
L.S 1
Page 10 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
and as per provisions of the Contract document and instructions of
the Owner/Engineer-in- Charge. Strings preparation including welding, NDT
of welds and re-beveled areas, radiography, pre-testing of completed
string, corrosion coating of field joints with HDD sleeves, inspection of
corrosion coating and repair of defects, Preconstruction surveys,
Installation of pipeline and CS
conduit/optical fiber cable conduit by horizontal directional drilling to the
correct profile as per approved drawings and specification, Strapping of
CS conduit with main pipeline, Pulling of optical fiber cable in inter- duct of
flexible HDPE tubing in the conduit mentioned above, Post-installation
hydrotest including leaks and repair of defects and retesting, etc. for
defects attributed to Contractor's faulty work, Supply, fabrication and
construction of protective fencing as required, Supply fabrication and
erection of pipeline markers, Restoration and clean-up etc., Preparation of
as-built drawings and other records etc., All other works not specifically
listed herein, but required as per specifications, drawings, provision of
contract document, calculations, and construction method statements,
leading to successful completion of works as per details below.
9.1 P010.09.01 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 0.272 km
9.2 P010.09.02 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 0.500 km
9.3 P010.09.03 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 1.000 km
9.4 P010.09.04 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 1.600 km
Page 11 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
9.5 P010.09.05 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 2.830 km
9.6 P010.09.06 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 4.000 km
9.7 P010.09.07 Reliance Corridor & RCC Roads/ Asphalt
Roads/ Drains/ Utilities at Ch. 4.750 km
9.8 P010.09.08 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 9.300 km
9.9 P010.09.09 RCC Roads/ Asphalt Roads/ Drains/ Utilities at
Ch. 9.600 km
9.10 P010.09.10 Any other location as per direction of Engineer
In Charge
10 P010.10.00 PIPING WORKS FOR STATION ISOLATION VALVES (SIV)
All works for installation of all pipeline/piping above ground at all elevations
and below ground at all depths for Station Isolation Ball Valve (8" NB,
300#, BW, Buried, Stem Extended, MOV on departing & receiving pipeline)
at Despatch & Receiving Terminal as per P&ID in all type of terrains
and soils including supply of all Contractor supplied materials to work site;
supply of all consumables, materials, manpower and carrying out all
mechanical works of underground and above ground piping, welding,
non destructive testing of welds, weld repairs/retesting,
cleaning/flushing, functional testing, cutting of mainline and beveling, tie- in
of isolation/block valve & actuators, installation of various valves, insulating
flange kits, piping including stand pipes for instrument tappings, flanges,
fittings, tapping for density meter & sulphur analyser (wherever required)
Page 12 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
etc. including radiography of tie-in joints, corrosion coating and external
painting as required, installation of instruments like pressure/ temperature
instruments/ gauges/ transmitters etc., obtaining all statutory clearances,
approvals and permissions for the works (wherever required),excavation
and filling in all types of soils including soft/hard rock for installation of
piping/pipe/valve supports, providing pipe/valve supports including all
associated civil and structural works; painting, finishing, clean-up and
restoration of site; preparation of as-built drawings, documents and project
records and performing all works as per drawings, specifications,
other provisions of Contract document and instructions of Engineer-in-
charge.
Note:
1. All Civil/ structural works including pipe supports will be paid separately
as per rate provided elsewhere in the Contract
document.
2. The quoted rate is applicable only for isolation/block
valve including nearby tappings inside terminal.
3. Supply of all relevant valves, pipe, fitting etc. will be paid separately as
per rates covered elsewhere.
10.1
P010.10.01
All works as stated in item no. P010.10.00 for 1 No. Station Isolation/Block
Ball Valves (8" NB, 300#, BW, Buried, Stem Extended, MOV) at GCPTCL
Despatch Terminal as per P&ID.
LS 1
10.2
P010.10.02
All works as stated in item no. P010.10.00 for 1 No. Station Isolation/Block
Ball Valves (8" NB, 300#, BW, Buried, Stem Extended, MOV) at Opal
Dahej Receiving Terminal as per P&ID.
LS 1
11 P010.11.00 PRE-COMMISSIONING AND COMMISSIONING ASSISTANCE
PRE-COMMISSIONING AND COMMISSIONING ASSISTANCE FOR
LIQUID HYDROCARBON PIPELINES (EXCEPT HVP) : Carrying out pre-
Page 13 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
commissioning activities and pre-commissioning checks to the specified
acceptance criteria, providing assistance during the complete duration of
commissioning operations and making the entire pipeline system ready for
commissioning, supply of all equipment, manpower, consumables including
pigs, materials for all temporary works and performing all associated works,
complete as per the relevant specifications, other provisions of Contract
document and instructions of Engineer-in- Charge.
11.1
P010.11.01
Pre-Commissioning Checks
Note:- Pre- Commissioning of GCPTCL to Opal Dahej
LPG Pipeline
LS 1
11.2 P010.11.02 Dewatering
Note:- Dewatering of GCPTCL to Opal Dahej LPG Pipeline
LS 1
11.3 P010.11.03
Swabbing
Note:- Swabbing of GCPTCL to Opal Dahej LPG Pipeline LS 1
11.4
P010.11.04
Commissioning Assistance
Note:- Commissioning Assistance of GCPTCL to Opal
Dahej LPG Pipeline
LS 1
12 P010.12.00 PIPING WORKS FOR DESPATCH/RECEIPT STATIONS
All works for installation of piping above ground at all for all facilities at
GCPTCL Despatch Terminal & OPaL Dahej Receipt Terminal indicated in
Scope of work and applicable P&IDs including procurement & supply of all
equipment and materials to work sites as applicable, survey/ soil
investigation, all mechanical works of above ground piping/pipeline
including fabrication, welding, installation of all piping items, pipes, edge
preparation (inclusive of grinding the edges of pipes, fittings, flanges etc. to
match with the matching edges of uneven/ different thickness wherever
required), valves (manual & actuated), fittings, flanges, bending, pre-
Page 14 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
heating, threading wherever required, branch connections/ tappings,
painting and supporting works; Erection of pipes of all types and
thickness over sleepers, overhead on racks and at all elevations; hook-
up with equipment nozzles; installation of all type of valves, all types of
inline and online instruments such as pressure/ thermal safety valves
Non- destructive testing of welds, weld repairs/re-testing, hydrostatic testing,
dewatering, cleaning, functional testing, any other testing as specified,
cutting of terminal piping and beveling, if required, tie-in of valve assembly
including radiography of tie in joints, radiography, corrosion coating and
external painting as required; excavation in all types of soils for installation
of piping, piping supports, gravel filling wherever required, finishing,
clean-up and restoration of site; preparation of as-built drawings,
documents and project records and completing all works in all
respects as per AFC drawings, specifications, standards, other
provisions of Contract document and instructions of Engineer-in-charge
12.1
P010.12.01
At GCPTCL Dahej Despatch Terminal
(As detailed in Item no. P010.12.00)
(Refer Annexure I for detailed break up of Quantities of item)
LS 1
12.2
P010.12.02
At OPaL Dahej Receipt Terminal
(As detailed in Item no. P010.12.00)
(Refer Annexure III for detailed break up of Quantities of item)
LS 1
13 P010.13.00 PIPING WORKS FOR INSTALLATION OF NEW NAPHTHA PUMPS
All works for installation of piping above ground at GCPTCL Despatch
Terminal indicated in Scope of work (6987-01-010-83-41-SOW-9502) and
applicable P&IDs including procurement & supply of all materials to work
sites as applicable, survey/ soil investigation, all mechanical works of above
ground piping including fabrication, welding, installation of all piping
items, pipes, edge preparation (inclusive of grinding the edges of
Page 15 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
pipes, fittings, flanges etc. to match with the matching edges of uneven/
different thickness wherever required), valves (manual & actuated),
fittings, flanges, bending, pre-heating, threading wherever required,
branch connections/ tappings, painting and supporting works; Erection of
pipes of all types and thickness over sleepers, overhead on racks and at all
elevations; hook-up with equipment nozzles
& existing piping hook up as per P&IDs; installation of all type of valves,
all types of inline and online instruments such as pressure/ thermal
safety valves Non-destructive testing of welds, weld repairs/re-
testing, hydrostatic testing, dewatering, cleaning, functional testing, any
other testing as specified, cutting of terminal piping and beveling, if
required, tie- in of valve assembly including radiography of tie in joints,
radiography, corrosion coating/ painting and external painting as required;
excavation in all types of soils for installation of piping, piping supports,
gravel filling wherever required, finishing, clean-up and restoration of
site; preparation of as-built drawings, documents and project records
and completing all works in all respects as per AFC drawings,
specifications, standards, other provisions of Contract document and
instructions of Engineer-in-charge
13.1
P010.13.01
At GCPTCL Dahej Despatch Terminal Piping Installation of Naphtha
Pumps & Associated Piping Works
(As detailed in Item no. P010.13.00)
(Refer Annexure I for detailed break up of Quantities of item)
LS 1
14 P010.14.00 SUPPLY OF PIPING MATERIALS:
Supply of piping items shall be as per Schedule of
Quantity
14.1 P010.14.01 All procurement quantities as detailed in Annexure II attached with this SOR
for GCPTCL Dahej Despatch Terminal LS 1
14.2 P010.14.02 All procurement works as detailed in Annexure IV attached with this
SOR for OPaL Dahej Receipt Terminal LS 1
Page 16 of 16
S.
No. Item No. Description of Items Unit Quantity
Unit
Rate Amount
15 P010.15.00 PRE-COMMISSIONING AND COMMISSIONING ASSISTANCE:
15.1
P010.15.01
Providing Pre-Commissioning and Commissioning assistance of Skilled/
Semi Skilled/ unskilled workers as per the direction of Engineer In charge
with hand tools (including consumables). Pre-commissioning and
commissioning requirements over & above that already described
elsewhere in the SOR. The man day is 12 Hrs. duties
Note: All works at GCPTCL Dahej Despatch Terminal
LS 1
15.2
P010.15.02
Providing Pre-Commissioning and Commissioning assistance of Skilled/
Semi Skilled/ unskilled workers as per the direction of Engineer In charge
with hand tools (including consumables). Pre-commissioning and
commissioning requirements over & above that already described
elsewhere in the SOR. The man day is 12 Hrs. duties
Note: All works at OPaL Dahej Receipt Terminal
LS 1
Sub-Total SOR 5