sound chemicals mangement mainstreaming and …
TRANSCRIPT
SOUND CHEMICALS MANGEMENT MAINSTREAMING AND UPOPS REDUCTION IN
KENYA
2017 Quarterly Progress Report
(April- June 2017)
Project Summary
Country: Kenya
Project Duration:May 2016 – May 2021
Project Budget: US$4,515,000.00
Annual Budget: US$ 1,424,497.50
Donor Annual budget US$
Donor GEF 1,424,497.50
Cumulative expenditure: US$ 123,395.90
Contact Persons: David Githaiga
Team Leader
Email: [email protected]
Mayiani Saino
Project Manager,
Email: [email protected]
Implementing Partner: Ministry of Environment and Natural Resources (MENR)
Responsible Parties:Ministry of Health, Green Belt Movement, Kenya Disaster Concern, Kenya Association of
Manufacturers, University of Nairobi.
Table of Contents
1. Executive Summary .......................................................................................................................................... 5
2. Progress towards development results ............................................................................................................ 8
3. Gender Development Results ......................................................................................................................... 19
4. Targeting, sustainability of results, strengthening national capacities and South-South and Triangular
Cooperation ......................................................................................................................................................... 19
5. Partnerships .................................................................................................................................................... 20
6. Monitoring and Evaluation ............................................................................................................................ 21
7. Knowledge management ................................................................................................................................ 21
8. Challenges/Issues ............................................................................................................................................ 22
9. Lessons Learnt and Way Forward ................................................................................................................ 22
10. Risks and Mitigation Measures ................................................................................................................... 23
11. Financial Summary ...................................................................................................................................... 24
Acronyms
BAT Best Available Technology
BEP Best Environmental Practices
HCF Health Care facility
HCWM Health care Waste Management
MENR Ministry of Environment and Natural Resources
MOH Ministry of Health
NGOs Non-Governmental Organizations
NIP National Implementation Plan
PMU Project Management Unit
POPs Persistent Organic Pollutants
PRTR Pollutant Release Transfer Register
SC Stockholm Convention
UPOPs Unintended Persistent Organic Pollutants
WHO World Health organization
1. Executive Summary
Background
The project intends to protect human health and the environment by managing the risks posed by production, use, import and export of chemicals and reducing /
preventing the release of U-POPs and toxic compounds originating from the unsafe management of waste in two key sectors: Health Care Waste and Municipal Waste.
These sectors are among the highest priorities identified in the updated NIP. On the HCWM waste side, the project will adopt an integrated approach aimed at
increasing the proper management of waste within the hospital facilities (increasing segregation, reducing waste generation) and by replacing the dangerous disposal
waste modality currently adopted (open burning or burning in single chamber incinerators) by SC-compliant equipment. Training will be deliver both at HCF level and
in classroom training events, and will be based on the WHO bluebook guidance tailored to the country needs. On the municipal waste side, the project intends to
reinforce the 3R (Reduce, Reuse, Recycle) economy on two specific waste streams, by enhancing their upstream collection, ensuring the quality of recovered material,
and securing access to national market by promoting cooperation with domestic industries. This for providing a valid alternative to the dumpsite economy, and
preventing the release into the environment of U-POPs and toxic substances upon release by open burning of these waste streams. The project also includes a
component related to the sound management of chemicals, by implementing activities on U-POPs monitoring, upgrading of the relevant regulation on chemicals, and
establishing a PRTR database
Objectives
The project aims toreduce the release of UPOPs and other substances of concern and related health risks, through implementation of environmentally sound
management of municipal and healthcare wastes and of an integrated institution and regulatory framework covering management of and reporting on POPs. The project
outcomes are defined as:
1. Streamlining sound management of chemicals and waste into national and county development activities through capacity building of MENR, MOH, county
governments of Nairobi, Kisumu, Nakuru and Mombasa and the NGOs;
2. Introducing environmentally sound management of health care waste in selected healthcare facilities; policy and strategic plans to prepare them to adopt BAT and
BEP disposal;
3. Demonstration of sound healthcare waste disposal technologies in a selected number of healthcare facilities in each county;
4. Minimizing releases of unintentionally produced POPs from open burning of waste; and
5. Monitoring, learning, adaptive feedback, outreach and evaluations.
Results in the Quarter
Component Summary
Component 1: Policies and strategies on mainstreaming chemicals
Component 1 on the project is on target.
The engagement of the national consultant for Institutional Needs Assessment has been completed.
The consultancy for Institutional Gap Analysis is to be re-advertised due to low application.
The following activities applied to mainstreaming chemicals management: Awareness on Minimising Emissions of Open Burning of Waste done in Kilgoris
covering the counties of Kisumu, Kisii, Migori, Narok, Bomet and Homabay; (Report 1.1), A second awareness building workshop was held in Mombasa
involving counties of Mombasa, Tana River, Lamu, Kwale and Kilifi (Report1.2), 2nd Chemicals Regulations Review (Report1.3). Inter-university workshop on
mainstreaming chemicals MEAs in the curricular (Report 1.4). Activity on Pollutant Release and Transfer Register (PRTR) was not done, to be done in quarter 3.
Component 2: Management of Health Care waste
Two (TOT) Training workshops were undertaken, in which a total 52 public health officers have been trained to deliver component 2 activities to national
stakeholders and in the selected counties of Nairobi, Nakuru, Kisumu and Mombasa (Report 2.1 and 2.2).
To address how the interventions will be carried in the selected health care facilities, facility baseline survey was done (Report 2.3), two (2) Health Care Waste
Management Planning meetings held (Report 2.4 and 2.5), and HCWM plans developed for target counties (to be reported in quarter 3). This component is
running on time except that the subsequent activities that heavily rely on consultants.
The two national consultants are now in place and have started work.
Component 3: Support to health Care Facilities.
This component mainly deals with procurement of commodities and equipment some of which require feasibility study by consultants yet to be procured. In this
regard, an initial health care facility assessment was done (Report 3.1)
Under Quarter two plan the plan was to procure medical waste vehicles. However, the specifications were to be developed by consultants who have just been
recruited. Therefore, for commodities and waste transportation vehicles there is good progress on specifications and required standards which will guide
procurement.
Component 4: Minimizing open burning from municipal waste
The project is behind schedule on most of the key entry point activities that relate to Component 4. However, mobilization and fundamentals’ measures for the
project uptake have been established with the Greenbelt Movement and Kenya Association of Manufacturers. The Implementing partners (GBM/KDC) have
mapped out key stakeholders and 3R communities that are involved in both plastic and organic wastes in Nairobi, Nakuru and Kisumu counties. Already the
awareness creation workshops are ongoing.
Component 5: Project Management
The component has met its objectives.
The Memorandum of Understanding between MENR and the partners has been completed with the Attorney General’s office and submitted to the partners for
their review.
Technical Committee meeting and 4th PSC meeting held (Report5.1).
Networking with partners, liaising with Basel, Rotterdam and Stockholm conventions Secretariat on behalf of MENR. (Report 5.2)
Support UNDP on Child Gold project on Artisanal Gold Mining project
Key lessons learned
Finances
As at June 2017, USD 162,691.25 had been utilized out of the total quarter budget of USD434,369. This is an implementation rate of 37.45%.
Progress towards development results
Country Programme Document (CPD)/UNDAF Outcome 4.1: Policy and Legal Frameworks: By 2017, Kenya has robust policies and legal frameworks linking issues
of Sound chemical and waste management, environmental sustainability, climate change and sustainable land management to human security and resilience therefore
requiring an integrated and coordinated response to all phases.
Relevant CPD Output 3.1: GoK has adequate capacity to develop evidence-based and coherent policy responses to the inter-linked challenges of environmental
sustainability, land and natural resource management and human security
Summary achievements based on CPD Outcome targets
The project implementation is still in the early stages. Most of the actions have been on mobilization of the stakeholders and beneficiaries to action; identification of
actual sites within the ecosystem where the intended action is to implemented; and baseline information collection and development of the requisite plans for the
delivery of the expected outcomes.
Project Output 1: Streamlining Sound Management of Chemicals and Waste into National and County Development activities through Capacity Building of
MENR, MOH, County Governments of Nairobi, Kisumu, Nakuru and Mombasa and the NGOs-CBOs.
Output 1.1: Policies, strategies regulatory and policy framework integrating the provisions of streamlining chemicals management into development activities
(specifically those of the Stockholm convention and the SAICM recommendations) adopted and institutional capacity.
Summary achievements based on CPD output targets
CPD output targets Summary achievement to date Status
Meeting on Draft Regulations and
TOR for Gap Analysis
30 participants attended workshop in Naivasha. It was
organized by NEMA
Suggestions made to Director general on revisions to be made to
ensure MEAs provisionsare included in the Draft Chemical
Regulations 2017.
Recommendations were made to accelerate Kenyas pace to ratify
the Minamata Convention on mercury
Engage local consultant to draft
gap analysis
TOR developed, consultancy advertised. Only one
response received.
Applicant did not meet selection criteria
It will be advertised. In the meantime astakeholder’s workshop
will be held to identify the gaps. It will use the UNDP toolkit
Draft chemical
regulations/guidance
MEAS provisions for Stockholm, Minamata, and
Rotterdam considers.
Basel Convention guideline discussed
To be held in Quarter 3
Workshop to Review and adopt
draft gaps analysis report by 1st
week of February.
Not held To be held in Quarter3
Meeting 4: Identify institutions in
charge of chemical management
and develop TORs for needs
assessments expert
Scheduled for q3
Consultant of Chemical, Health
and Development
Consultant hires Awaiting inception report
Meeting of national Chemicals
coordination committee
Held in Q1
Overall status Ongoing
Activity 1.1.1: Overall policy framework and specific regulatory measures covering environmentally sound management of chemicals in general and POPs in
particular through chemicals life cycle management developed and implemented.
This is hasbeen addressed in the following ways.
i. National Government institutions starting with the project partners have held inception workshops and activity based meetings and for a to address policy
framework and regulatory framework starting with the understanding of the objectives of Basel Rotterdam and Stockholm Convention objectives and
obligations toKenya. The next is how to domesticate them in Kenya laws and regulations. In this regard,a draft chemical regulation.
ii. The new draft regulations on e-waste, waste regulations and air quality regulations have been discussed. It is now up to NEMA and the Solicitor General’s
office to prepare to gazette them.
iii. PMU supported a large Kenya delegation to the BRS COPs held in Geneva on 24th April to 6th May 2017. Because of this participation, the key institutions are
now more aware and coordinated on the urgent emerging issues and need to comply with deadlines set by the BRS COPs as well as SAICM.
iv. In addition, the Kenya Government network with Intergovernmental Organizations of Chemicals Management (IOMC) was strengthened and progress made
on resource mobilization.
v. Project helped to kick start the GEF Project on the National Action Plan for the artisanal Gold Mining in Kenya
Activity 1.1.2: Key institutions have knowledge and skills to formulate and implement necessary chemicals and waste environmental policies, consistent with
sound chemicals management principles and obligations under international agreements.
From 1.1.1 above, preliminary discussions have been held on the Terms of reference for inter- ministerialcoordination. The inter- ministerial committee is intended to
be made a permanent feature. It will:
Coordinating the active participation by Kenya in the international agenda on in the field of chemicals and wastes management;
Coordinating activities on chemicals and wastes management such as the classification of chemicals and industrial wastes generated in the country, regularly
and rationally
Being focal point for the chemicals and wastes Multilateral Environmental Agreements. By ensuring timely actions that the MEA may require as guided by the
respective conference of parties for each MEA.
Id. Activity Planned delivery
date
Actual delivery date Completion status Budget
Allocation
Actual Budget Expense
1 Recruitment of National
Consultant for Institutional Needs
April 2017 June 2017 Completed UNDP
2 Chemicals Awareness workshop
for minimizing emissions of open
burning of waste, Kilgoris
May 2017 23 - 25 May 2017 Completed - 2,126,500
3 Chemicals Awareness workshop
for minimizing emissions of open
burning of waste, Coastal Zone
/Mombasa counties
June 2017 6 - 8 June 2017 Completed - 2,104,600
4 Chemicals Regulations Review June 2017 26 - 29 June 2017 Completed 800,000 2,615,000
5 Inter-university workshop on
mainstreaming chemicals MEAs in
the curricular
July 2017 4 -5 July 2017 Completed 2,500,000 934,000
Activity 1.1.3: Key institutions have incorporated sound management of chemicals and wastes, including POPs, in their activities.
This componentis awaiting report of the national consultant on institutions.
Meeting held in the counties of Kisumu, Nairobi, Mombasa and Nakuru to promote sound chemicals management and to initiate institutional policies that
promote activities that minimize open burning of waste.
A second awareness building workshop was held in Mombasa involving counties of Mombasa, Tana River, Lamu, Kwale and Kilifi. Activity on Pollutant
Release and Transfer Register (PRTR) was not done, rescheduled for quarter 3.
1.4: National coordinating meetings on POPs held regularly without GEF financial support.
The PMU coordinated the following meetings
i. Review of the draft Action Plan on the Minamata convention on mercury
ii. A review meeting on the phasedown approach for mercury use in dental amalgam
Output1.2: Monitoring activities intensified and strengthened and PRTR database in place
Summary achievements based on CPD output targets
CPD output targets Summary achievement to date Status
International consultant TOR Developed Consultancy to be advertised in August
National report
PRTR network
TOR for national consultant developed National consultant to be in place in September
Status Overall Ongoing
Activity 1.2.1: At least 70% of laboratory analysis in research and monitoring institutions required to monitor the implementation of national policy on
hazardous chemicals and wastes being carried on a cost recovery basis
A workshop meeting of institutions carrying out monitoring is planned for September to cover water quality analysis, product analysis and how to roll out the Global
Programme on monitoring of POPS
Activity 1.2.2: 70% of universities nationwide include issues of hazardous chemicals and wastes, risks and legislation in curriculum.
The University of Nairobi, Chemistry Department is the lead partner for this activity because it is the regional coordination institutions for the UNEP/GEF Project on
Global Monitoring of POPS. It organized a workshop for other universities and research institutions to address the issue of integrating MEAs issue into university
curriculum and address how parameters addressing MEAs can be monitored in a routine way
i. Workshop on integrating MEAS in university curricular held
ii. Roadmap for promoting and selecting MEA material that can be a good basis for university curricular culminating a in a bigger conference that will articulate
the MEA article in education, public information and research
Activity 1.2.3: PRTR Database and reporting system in place
Project Output 2: Introducing environmentally sound management of health care waste in selected healthcare facilities; policy and strategic plans to prepare
them to adopt BAT and BEP disposal
Output2.1: Personnel of hospital facilities and control authorities at central and county levels have enough capacity guidance and equipment to manage healthcare
waste in an Environmental Sound Manner.
CPD output targets Summary achievement to
date
Status
Hold 3-day meeting to develop TORs to engage international & local
consultants for training & review of guidelines in line with I-Rat tool
& WHO blue book
Held
International
Review HCWM guidelines/SOPs & Injection Safety/Waste disposal
communication strategy to align to I-Rat tool & WHO blue book
Held County Health Care teams formed for Kisumu, Mombasa,
Nakuru and Nairobi
Training of health personnel on I-Rat tool & WHO blue book by
international consultant
Held See Report
Undertake training needs assessment for all the 13 facilities Held See Report
Train 80 TOT for all the 4 counties on HCWM in 2 groups of 40 Held See report
Train 60 facility managers & CHMTs on HCWM planning for 3
days
Held See Report
StatusOverall Ongoing
Activity 2.1.1: Procedures and guidelines for the assessment and implementation of hazardous waste management at healthcare facilities built on lessons and
examples from the application of the I-RAT tool under the GEF4 /UNDP Global projects and on the WHO bluebook “Safe Management of Wastes from
Health-care Activities” developed and adopted
This activity has not been implemented
Activity 2.1.2: A national healthcare waste handbook containing guidelines for HCWM drafted and adopted by the MOH, including introduction of non-
mercury devices in the HCFs
Output 2.2: Implementation of BAT/BEP at selected hospital facilities successfully demonstrated and measured against the baseline.
CPD output targets Summary achievement to date Status
Overall status Ongoing
Activity 2.2.1: Hospital personnel at all level trained on implementation of the above procedures
Activity Planned delivery date Actual delivery
date
Completion status Budget Allocation Actual Budget Expense
1st Train the Trainer(ToT) training 12 -17 June 2017 12 -17 June 2017 Completed 7,214,400 3,107,450
2nd TOT training 3- 8t July 2017 3 - 8 July 2017 Completed -
3rd TOT training 24- 29th July 2017 Not yet done
Activity Planned delivery date Actual delivery
date
Completion status Budget Allocation Actual Budget Expense
Activity 2.2.2:Baseline assessment of each healthcare facility based on the assessment procedures developed in 2.1.1 carried out, and waste management plans
based on the baseline assessment level drafted and implemented
A baseline assessment has been carried out
Activity 2.2.3:
1st Planning and budgeting training for CHMTs and
Facility managers
20 – 22 June 2017 20 – 22 June 2017 Completed 4,778,400 1,760,048
2nd Planning and budgeting training for CHMTs and
Facility managers
11- 13 July 2017 11 - 13July 2017 Completed
ESM management of healthcare waste (based on WHO bluebook) implemented in 4 facilities in each county (12 facilities) including replacement of mercury
devices with non-mercury
Activity Planned delivery
date
Actual delivery date Completion status Budget Allocation Actual Budget
Expense
Facility baseline survey for 12 HCF
carried out by MOH
3- 9 May 2017 3 – 9 May 2017 Completed 809,500 926,600
Activity 2.2.4: Final assessment of the healthcare facility to measure results achieved with the implementation of ESM management against baseline is carried
out and estimate amount of U-POP release avoided.
Project Output 3: Demonstration of sound healthcare waste disposal technologies in a selected number of healthcare facilities in each county
Output 3.1: Feasibility analysis and procurement of ESM technologies for healthcare waste disposal completed.
CPD output targets Summary achievement to date Status
Status Overall Ongoing
Activity 3.1.1: Feasibility study and term of reference for non-combustion or low-U-POPs emission technologies for healthcare waste disposal in selected
hospitals or waste management facilities.
Not started
Output 3.2: BAT/BEP technologies for the disposal of healthcare waste successfully established and demonstrated, with a potential reduction of U-POPs emission in
the order of 19Teq/year.
Summary achievements based on CPD output targets
CPD output targets Summary achievement to date Status
Status Overall Ongoing
Activity 3.2.2: Waste disposal activities of hospital facilities/programs are documented and their performance is evaluated to exemplify best practices in
healthcare waste management.
Belgian Grant on microwaves for medical waste sterilization
i. A total of 10 microwave equipment together with shredders were expected in the country. So far a total of 3 microwaves have been received in the country and
taken to Kisii level 5 hospitals, JaramogiOgingaOdinga Teaching and Referral Hospital in Kisumu and Moi Teaching and Referral Hospital in Eldoret.
ii. Kisii Hospital, Moi Teaching and Referral Hospital and Nakuru County Referral Hospital have already finished construction of housing for the microwave and
shredders. JaramogiOgingaOdinga Teaching and Referral hospital is still waiting for the allocation from the County health department to begin its
constructions but they have already secured building drawings and bill of quantities and
iii. In this 3rd quarter we expect to have two or three microwaves installed and operationalized.
Not started
Activity 3.2.3: Useful replication toolkits on how to implement best practices and techniques are developed.
Not started
Project Output 4: Minimizing releases of unintentionally produced POPs from open burning of waste
Output 4.1: Awareness raising and capacity strengthening on ESM of solid waste ensured.
CPD output targets Summary achievement to date Status
Develop sensitization materials adaptive to grassroot
communities training
Done Materials have been developed but not tested
Material awaiting printing
Preparatory meetingwith all the stakeholders in waste
management (consultation forum, mapping key partners)
e.g county government, , chiefs, community groups
representatives, KAM, NEMA ( Nairobi, Nakuru and
Kisumu)
Held in 3rd quarter Report to be in 3rd quarters
Public awareness on waste menace, effects and potential
solutions in 3 counites (Nairobi, Nakuru and Kisumu)
@ least 300 participants
Hels in 3rd Quarter Await report of 3rd Quarter
Policy gap analysis and regulations on communities for
integrated waste management and entrepreneurships
Capacity Building for 100TOTs - creating a pool of local
trainers on UPOPs-Equip the CTOTs with skills &
Knowledge in intergrated waste management-value
chain, market development, value chain, legal
framework support, record keeping, leadership
Overall status Ongoing
Activity 4.1.1: Awareness raising activities for the communities and the municipalities aimed at enhancing 3Rs of waste
Activity Planned delivery date Actual delivery date Completion status Budget Allocation Actual Budget Expense
1 Develop and design sensitization
materials
18th – 19th June 5th – 6th July Completed 1,398,000 0
2 Stakeholders Workshop on
Promoting 3Rs
26th- 28th June 2017 24th -26th July 2017 Deferred to quarter 3 827,000 UNDP Direct Payment
Activity 4.1.2: Regulatory framework for the recovery of waste material (glass, organic, plastic) and for licensing of the recovery activity at county and central
level improved to integrate SC requirements
Not started
Activity 4.1.3: Counties provided with training, manual, and technical assistance for the management of solid wastes.
Not started
Output 4.2: Sound Management of solid waste in targeted municipalities implemented with the support of NGOs, with a reduction of unintentionally produced POPs
from the burning of solid waste of 23 g I-TEQ/year (20 % of the current estimate of 247 g I-TEQ/year).
CPD output targets Summary achievement to date Status
Development of training module on composting (popular
version or simplified materials
Done Done
Periodic monitoring of waste recycling activities,
documentation of success and challenges in 3 counties 2
weeks per year
Done
Development of training module on plastic wastes recycling
and UPOPS
Done
Program CBO capacity development Officer offering day to
day implementation, monitoring, Evaluation and
documentation of impact and lesson learnt, expertise and
professional support during the project cycle in Nakuru and
Nairobi
Ongoing
Support for GIS/IT support, finance management at
organization level, administration, project office
management costs and office services not covered in the co-
financing commitments
Ongoing
Overall status Ongoing
Activity 4.2.1: Communities selected for demonstrating plans of actions for the reduction of solid waste open burning by increasing 3Rs of waste.
Training held
i. County CSO based in Nakuru County under the GBM its normal activities now sensitized on minimization of open burning
ii. Plastics Ban- Manufacture, Sale, and importation of Carrier bags of all types banned with effect from 1st September, 2017. Awareness campaigns and
done with GOK funds.
iii. NEMA carried out control environmental audits and inspections at the licensed facilities criteria developed selection to start in Q3
Activity 4.2.2: Initiatives for reduce reuse and recycle of waste and for composting, collection of compostable municipal waste for communities in three
counties of Nairobi, Mombasa and Nakuru implemented with a PPP approach and supervised with the support of NGOs.
Not started
Activity 4.2.3: Local initiative for the re-use/recycling of other non-hazardous waste streams (i.e. plastics).
Not started
Output 4.3: Municipal waste disposal sites with adequate management practices (non-burn).
CPD output targets Summary achievement to date Status
Status Overall Ongoing
Activity 4.3.1: Prioritization of open-burning landfills to be closed and cleaned up, emergency plans including social and resettlement issues and clean-up
plans for at least 3 landfills drafted.
Not started
Activity 4.3.2: Emergency measures for reducing release of contaminant in the environment and the exposure of the population implemented in one high
priority site.
Not started
Project Output 5: Monitoring, learning, adaptive feedback, outreach and evaluation
Output 5.1: Project monitoring, including PTR, Annual and Quarterly Progress reports.
CPD output targets Summary achievement to date Status
Technical Committee Meetings to monitor and develop
workplans and report (2)
Held
PMU staff induction workshop Done
Meetings of PSC (4) Held
Meetings of National Chemicals Coordinating
committee
1st Meeting Held
Develop M & E Framework On-going
Status Overall Ongoing
Activity 5.1.1: Project Steering Committee.
Activity 5.1.2: Operations of the PMU.
2. Gender Development Results
Gender results Evidence
Gender result 1:During all the workshops there has been a gender
balance but because traditionally the nursing sector has been tilted
towards women, there has been more women
Evidence 1:Evidence of women attendance to training and
quarterly meetings can be obtained in photographic and
attendance sheet evidence compiled during work.
3. Targeting, sustainability of results, strengthening national capacities and South-South and Triangular Cooperation
3.1. Targeting
Target groups
Needs addressed Evidence
3.2. Sustainability
Results achieved Sustainability
1. Partners in MENR,MOH, NEMA, UON, GBM, KAM, now have
fully owned the project and have started to incorporate the project
activities in the day to day activities
2. Project has sensitized over 300 experts who will institutionalize the
project
The partners are the best to ensure sustainability of the project outputs and the
project objectives
3.3. Strengthening national capacity
Results achieved Institution National capacity strengthened
1) 10 three-day workshops facilitated by PMU in
order to begin the process of environmentally
sound management of chemicals and wastes.
MOH Headquarters
County health care facilities
Green Belt Movement
CEJAD, WARMA, NEMA, PCPB, Treasury, Judiciary
This will create, in the long run,
informed supportive Government
institutions
5. Partnerships
The Project has strengthened the sector of health and that of environment, and by extension the Ministry of Health and that of environment and Natural resources. The
more partnership the more it is easy to implement the project. This cooperation is reflected in the following ways
Development of joint projects for funding by GEF and bilateral programmes
Promoting the non-burn technologies which will be used as financing this will be quantified during the assessment
Support to action plans on Minamata Convention on Mercury
Entry into the counties
The other partnership is with the universities, starting with the University of Nairobi, other post-secondary institutions will be made partners. The project has also
smoothened thepartnership with non-governmentalorganizations and community groups through the greenbelt movement,
A clear set up of partnership has been made with a formal memorandum of understanding.
6. Monitoring and Evaluation
M&E activities have not been conducted during the quarter:
7. Knowledge management
Knowledge products completed/published during the reporting period:
Title, author, date Link Evidence (why they were useful?)
Title, author, date Link Explain how you used the product
Title, author, date Link
Title, author, date Link
Title, author, date
8. Challenges/Issues
The Government financial year closed on 31st June 2017, ordinarily the new financial year starts by mid/end of July. However, Kenya is slated to hold the general
elections on 8th August 2017. New parliament may seat in September to approve the financial budget for 2018/2019, this will affect the project delivery on advanced
payment mode. It is therefore critical that UNDP Country Office supports the funds disbursement for that period.
Id. Description Mitigation plan ( what is being
done to prevent the risk)
Contingency plan (what will
be done if the risk occurs)
Likelihood of risk
occurring
Potential Impact
(financial/schedule/quality
etc.)
1 Funds Disbursement modalities MoU/ Agreement developed and
finalized
Direct Payment Low High
2 Difficulties in the promotion of
upstream waste segregation
Awareness creation Regulations and policy
enforcement
Low Medium
3. Start-up activities for
demonstration of plans for
reduction of waste for communities
not done due to lack of funds and
also capacity at the NGO
MOU finalized.
Technical meeting to thrash out
the roadblocks and barriers held
with the NGO
Direct payment/ refunds for
project activities carried out.
Medium Medium
9. Lessons Learnt and Way Forward
The fund transfer is a challenge, the lack of synchronization of UNDP financial guidelines and GOK guidelines. Hence the need to develop and adopt the memorandum.
The selection of consultants needs to be streamlined if the project is to meet its timelines.
For the project so far Kenya will be able to
Promote better access of chemical safety data, environmentally sound practices and techniques needs through the cooperation of the partner institutions
Ensureit protects itself from the dumping of obsolete and internationally rejected chemicals
Data is key to precautionary and reactive measures to chemical and waste disposal.
From the workshops and training forums, there were a few observations;-
The number of days for the training was found to be inadequate; - For HCW, the training period should be increased to seven days for the participants to be
effectively trained and also for them to fully assimilate what is taught.
Improvement on time management.
In respect to the participants’ jobs, the training was found to be very useful.
The participants noted that they received a lot of new information from the training course. The new information will be useful in changing perception and
mind set.
The participants found the trainers to be knowledgeable and very good.
Printed and electronic information provided was found to be very useful. The information will be used as reference material.
The overall opinion of the participants was that the training was stimulating and practical to them.
10. Risks and Mitigation Measures
Risks Mitigation Measures
Funds are delivered on time It is critical that funds disbursement issue be addressed in a holistic sense especially when MENR
started to disburse funds to partners.
Financial - MENR the Implementing Partner, was required to
pre-finance its lead activities as part of the HACT compliance.
Given the huge amounts of financial resources required for delivery of the routine project activities,
the PSC recommend that UNDP signs Letters of Agreement (LOA) with the threenon-
governmental Responsible Parties (KAM, GBM, KDC and other NGO for direct funds channeling
to them for the activities they were directly responsible for delivery. This enabled the start of
implementation in August 2017 and continued delivery over January to June 2017.
Operation - Under the re-imbursement financing modality to the
IP and direct cash transfer to the RPs, there have time lags in the
flow of resources and reporting.
The PMU continue to work towards shorter approval and reporting frameworks, that is supported
with enhanced M&E and tracking of delivery.
11. Financial Summary
Outputs / Activity Result
Current Quarter Budget
(KES)
(Jan – March 2017)
Total Expenditure
(Reporting Period)
Skip this column for
annual reporting
Cumulative
Expenditures
% Expenditure
(Cumulative)
A B D D/A*100
Output 1: Streamlining sound management of chemicals and waste into national and county development activities through capacity building of MENR, MOH, county
governments of Nairobi, Kisumu, Nakuru and Mombasa and the NGOs
Output 1 Sub-total 5,570,000.00 2,339,777.00 2,339,777.00 86.04%
Output 2: Introducing environmentally sound management of health care waste in selected healthcare facilities; policy and strategic plans to prepare them to adopt
BAT and BEP disposal
Output 2 Sub-total 21,400,000.00 4,983,210.00 4,983,210.00 69.19%
Output 3: Demonstration of sound healthcare waste disposal technologies in a selected number of healthcare facilities in each county
Output 3 Sub-total 0 0 0 100.00%
Output 4: Minimizing releases of unintentionally produced POPs from open burning of waste
Output 4 Sub-total 15,080,792.00 31,709.00 31,709.00 21.49%
Output 5: Monitoring, learning, adaptive feedback, outreach and evaluations
Output 5 Sub-total 7,550.000.00 31,709.00 31,709.00 21.49%
Grand total 49,600,793.00 10,000,000.00 10,000,000.00 80.00%
List of attached reports.
1.1 Chemicals Awareness workshops for minimizing emissions of open burning of waste, Kilgoris
1.2 Chemicals Awareness workshops for minimizing emissions of open burning of waste, Coastal Zone /Mombasa counties
1.3 Chemicals Regulations Review
1.4 Inter-university workshop on mainstreaming chemicals MEAs in the curricular
2.1 1st Train the Trainer (ToT) training
2.2 2nd Train the Trainer (ToT) training
2.3 Facility Baseline survey
2.4 Survey findings - kisumu
2.5 HCWM planning and budgeting
2.6 HCWM planning and budgeting
5.1 PSC minutes
5.2 BRS minutes