south capitol street project public hearing presentation - january 22, 2015

Upload: anacostiawaterfront

Post on 01-Jun-2018

219 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    1/41

    South Capitol Street ProjectPublic Hearing

    January 22, 2015

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    2/41

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    3/41

    3

    Tonights Agenda

    6:30 p.m. Sign-In and Open House

    7:00 p.m. Presentation

    7:30 p.m. Public Comment8:30 p.m. Adjournment

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    4/41

    4

    Public Hearing Presentation

    I. Public Hearing Purpose Delmar Lytle, P.E.

    II. Reasons for Design Changes Delmar Lytle,P.E.

    III. Proposed Project Design Delmar Lytle,P.E.

    IV. Environmental Review Process Brian

    McMahonV. Staying Involved Delmar Lytle, P.E.

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    5/41

    5

    I. Public Hearing Purpose

    Delmar Lytle, P.E.AWI Program Manager

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    6/41

    6

    NEPA Studies and Planning

    Final Environmental ImpactStatement (FEIS) signed March22, 2011

    Hearings April 26 and 28, 2011

    Revised Preferred Alternative

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    7/41

    7

    NEPA Studies and Planning

    Supplemental DraftEnvironmental ImpactStatement (SDEIS)

    Same Purposeand Need

    Notice of Availability publishedDecember 19, 2014

    45-Day Public Comment PeriodEnding February 2, 2015

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    8/41

    8

    II. Reasons for Design Changes

    Delmar Lytle, P.E.AWI Program Manager

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    9/41

    9

    Reasons for Design Changes

    Acquisition of 5.2acres ofat the JBAB.

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    10/41

    10

    Reasons for Design Changes

    Realignment of a privately-operated helipad

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    11/41

    11

    Reasons for Design Changes

    Reconstruction of a 65-year-old levee

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    12/41

    12

    Reasons for Design Changes

    Relocation of two fiberoptic cables and a 69-kilovolt PEPCO power

    cable

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    13/41

    13

    Reasons for Design Changes

    Remediation ofcontaminated soils

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    14/41

    14

    Reasons for Design Changes

    Investigation of navigationrequirements for movablebridge

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    15/41

    15

    Reasons for Design Changes

    Substantial cost savings

    Revised Preferred Alternative

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    16/41

    16

    III. Project Design

    Delmar Lytle, P.E.AWI Program Manager

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    17/41

    17

    South Capitol Street Improvements New Frederick Douglass

    Memorial Bridge (FDMB)

    Demolition of existing FDMB

    New traffic ovals at west and eastends of FDMB

    Upgraded I-295 and SuitlandParkway, I-695 and South CapitolStreet and MLK Boulevard, SE andSuitland Parkway interchanges

    Improved bikeway and pedestrianfacilities

    New drainage and stormwatermanagement

    Significant landscaping andstreetscape

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    18/41

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    19/41

    19

    New Frederick Douglass Memorial(FDMB)

    Existing bridge Movable (swing) Needs replacement Remain open To be demolished

    Proposed bridge Fixed (not movable)

    42foot clearance Parallel alignment

    30 south of existingbridge

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    20/41

    20

    Key Differences

    FEISAlignment

    New Alignment

    SDEISAlignment

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    21/41

    21

    Key Differences

    FEISAlignment

    East Traffic Oval

    SDEISAlignment

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    22/41

    22

    Key Differences

    FEISAlignment

    No impact on JBAB

    SDEISAlignment

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    23/41

    23

    Benefits

    Enhanced corridor appearance

    Improved pedestrian and bike access

    and trail connections Reduced bridge construction cost,

    maintenance and operating costs

    Less property acquisition

    Fewer anticipated impacts

    Reduced risks to schedule

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    24/41

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    25/41

    25

    Supplemental EIS DDOT is applicant and FHWA is lead Federal agency

    Supplements most recently distributed version of thedraft or final EIS

    Prepared for changes, new information, or furtherdevelopments on a project which result in newsignificant environmental impacts and newalternative

    Reviewed and distributed same as a draft and finalEIS

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    26/41

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    27/41

    27

    Affected EnvironmentNo Change for:

    Air Quality

    Economy and Emp loyment

    Geology, Topography, and Soil s

    Noise

    Water Quali ty

    Wil dl ife and Habitat

    Visual Quali ty

    Change for:

    Communi ty Cohesion and Facili ties

    Cultural Resources

    Environmental Justice

    Floodplains

    Hazardous Mater ials

    Land Use

    Pedestr ian and Bicycl e Facili ties

    Threatened and Endangered Spec ies

    Traffic and Transpor tation

    Wetlands

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    28/41

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    29/41

    29

    Parkland

    Improve access road toAnacostia Park

    Demolish existing ramps

    Create contiguous parkspace

    Enhance landscaping andsignage

    Reduce impervious area

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    30/41

    30

    Additional ImpactsWater Quality Construction of bridge piers

    Land Use Acquisition of Right of Way Operations of Fuel Pier

    Hazardous Materials Contaminated soils and groundwater Unexploded ordinances

    Traffic Multimodal during construction

    Wetlands Small wetland along I-295

    Wildlife and Habitats Peregrine Falcon and Osprey nests

    Image source: Washington Post

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    31/41

    31

    Improved Pedestrian and

    Bicycle FacilitiesSeparate sidewalks and bikepaths on both sides of FDMB

    Grade separated access underInterstate 295 Ramp D

    Pedestrian bridge over SuitlandParkway

    Firth Sterling Trail connectingSouth Capitol Street and

    Anacostia Metrorail Station

    Pedestrian staircases fromFDMB to Anacostia Riverwalk

    Trail

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    32/41

    32

    Improved Visual Quality

    Significantlandscaping andstreetscapeimprovements

    Visual quality

    criteria and manualfor design

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    33/41

    33

    Good Decision

    Elimination or minimization of risks

    Reduced environmental impacts

    Substantial costs savings

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    34/41

    34

    Key Stakeholders

    Local communities andresidents

    Businesses

    Motorists, bicyclists

    and pedestrians

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    35/41

    35

    Key Agencies

    U.S. Coast Guard* U.S. Navy*

    Army Corps of Engineers*

    National Park Service*

    District Department of theEnvironment*

    National Capital PlanningCommission*

    * Cooperating Agency

    State Historic PreservationOffice

    NOAA National MarineFisheries Service

    U.S. Fish and WildlifeService

    Washington MetropolitanArea Transit Authority

    DC Water

    Commission on Fine Arts

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    36/41

    36

    Next Steps

    FHWA and DDOT considerpublic comments PreparesSupplemental FinalEnvironmental Impact

    Statement (SFEIS)

    FHWA decision on reviseddesign - Publishes Record ofDecision (ROD)

    DDOT proceeds withpermitting, design andconstruction

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    37/41

    37

    V. Stay Involved

    Delmar Lytle, P.E.AWI Program Manager

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    38/41

    38

    Staying Involved

    Provide verbal comments tonight

    Fill out comment cards and returnby February 2, 2015.

    For more information, visitwww.southcapitoleis.com

    orwww.anacostiawaterfront.org/SouthCapitolStreetCorridor

    Receive project updates, askquestions or comment:

    o Sign up tonight for the projectemail list

    o Email: [email protected]

    o Call: 202-741-8528

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    39/41

    39

    Public Hearing

    Delmar Lytle, P.E.AWI Program Manager

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    40/41

    40

    Public Hearing

    Sign-in

    3 minute time limit

    All comments recorded Questions answered in SFEIS

    Comment cards

    8:30 adjournment

  • 8/9/2019 South Capitol Street Project Public Hearing Presentation - January 22, 2015

    41/41

    41

    Thank You

    Delmar Lytle, P.E.AWI Program Manager