    South Carolina Furniture Inc. produces all types of office furniture. The executive

    secretary is a chair that has been designed using ergonomics to provide comfort during

    long work hours. The chair sells for $ 130. There are 480 minutes available during the

    day, and the average daily demand has been 50 chairs. There are eight tasks:

    TaskPerformance time

    (min)

    Task must follow

    task listed below

    A 4 -

    B 7 -

    C 6 A,B

    D 5 C

    E 6 DF 7 E

    G 8 E

    H 6 F,G

    a) Draw a precedence diagram of this operation

    b) What is the cycle time for this operation

    c) What is theoretical minimum number of workstationsd) Assign tasks to workstations

    e) How much total idle time is present each day

    f) What is the overall efficiency of the assembly line

    Solution

    a) Precedence diagram

  • 8/3/2019 South Carolina Furniture Inc

    2/11

    b) Cycle time = Production time available per day

    Unit required per day

    = 480 minutes

    50 chairs

    = 9.6 ~ 10 min/chair

    c) Total task time = 4 + 7 + 6 + 5 + 6 + 7 + 8 + 6

    = 49 min

    Minimum number of workstations = Total task time = 49 min

    Cycle time 10 min

    = 4.9 ~ 5 workstations

    d) Tasks to workstation

    Since the tasks time in workstation must be not exceeding the cycle time. Then,

    total workstation is 7.

    A

    B

    C

    D E

    F

    G

    Station 1

    4 min 6 min Station 3

    5 min

    Station 4

    6 min

    Station 5

    7 minH

    Station 7

    6 min

    Station 2

    7 min

    Station 6

    8 min

  • 8/3/2019 South Carolina Furniture Inc

    3/11

    e) Idle time

    Idle times are in workstation 2 = 3 min, workstation 3 = 5 min, workstation 4 =

    4min, workstation 5 = 3min, workstation 6 = 2 min, workstation 7 = 4 min and

    total idle time is 21 minutes

    f) Efficiency

    Efficiency = (4 + 7 + 6 + 5 + 6 + 7 + 8 + 6) min = 49

    (7 workstations) x (10min) 16

    = 70%

  • 8/3/2019 South Carolina Furniture Inc

    4/11

    Mach 10 is a one person sailboat designed to be used in ocean. Manufactured by

    Creative Leisure, Mach 10 can handle 40 mph winds seas over 10 feet. The final

    assembly plant is in Cupertino, California. At this time, 200 minutes are available each

    day to manufacture Mach 10. The daily demand is 60 boats. Given the following

    information,

    a) Draw the precedence diagram and assign tasks to the fewest workstations

    possible.

    b) What is the efficiency of the assembly line

    c) What is the theoretical minimum number of workstations

    d) What is the idle time

    Solution

    a) Precedence diagram and fewest workstation

    Cycle time = Production time available per day

    Unit required per day

    = 200 minutes

    60 chairs

    = 3.33 ~ 4 min/chair

    Task Performance TimeTask must follow Task

    listed below

    A 1 -

    B 1 A

    C 2 A

    D 1 C

    E 3 C

    F 1 CG 1 D,E,F

    H 2 B

    I 1 G,H

  • 8/3/2019 South Carolina Furniture Inc

    5/11

    b) Efficiency of assembly line

    Efficiency = (1 + 1 + 2 + 1 + 3 + 1 + 1 + 2 + 1) min = 13

    (4 workstations) x (4 min) 16

    = 81.25%

    c) Theoretical minimum number of workstation

    No of workstation = total task time = 13

    Cycle time 4

    = 3.25 or 4 workstations

    A

    C

    B

    D

    EF

    G

    I

    H

    Station 2

    Station 1

    Station 3 Station 4

  • 8/3/2019 South Carolina Furniture Inc

    6/11

  • 8/3/2019 South Carolina Furniture Inc

    7/11

    Dr. Lori Baker, operation manager at Nesa Electronics, prides herself on excellent

    assembly line balancing. She has been told that the firm needs to complete 96

    instruments per 24 hour day. The assembly line activities are:

    Task Time (min) Predecessors

    A 3 -

    B 6 -

    C 7 A

    D 5 A,B

    E 2 B

    F 4 C

    G 5 FH 7 D,E

    I 1 H

    J 6 E

    K 4 G,I,J

    a) Draw precedence diagram

    b) If the daily (24- hour) production rate is 96 units, what is the highest allowablecycle time

    c) If the cycle time after allowances is given as 10 minutes, what is the daily (24

    hour) production rate

    d) What a 10 minute cycle time, what is the theoretical minimum number of station

    with which the line can be balanced

    e) What a 10 minutes cycle time and six workstations, what is the efficiency

    f) What is the total idle time per cycle with a 10 minute cycle time and six

    workstations

    g) What is the best workstation assignment you can make without exceeding a 10

    minute cycle time and what is its efficiency

  • 8/3/2019 South Carolina Furniture Inc

    8/11

    Solution:

    a)

    b) Cycle time

    Cycle time = (24 hours) (60 minutes/ hours)

    96 units

    = 15 minutes/unit

    c) Production rates

    Production rates = cycle time x production units

    = (10 min/unit) (96 units)

    = 960 minutes

    A

    D

    C

    B

    F

    H

    J

    G

    E

    KI

  • 8/3/2019 South Carolina Furniture Inc

    9/11

    d) Minimum workstations

    No of workstation = Total time

    Cycle time

    = (3 + 6 + 7 + 5 + 2 + 4 + 5 + 7 + 1 + 6 + 4) min

    10 min

    = 5 workstations

    e) Efficiency

    Efficiency = 50 min

    (6 workstations) (10 min/units)

    = 83.33%

  • 8/3/2019 South Carolina Furniture Inc

    10/11

    f) Workstations

    Idle times are in workstation1 = 1 min, workstation 2 = 3 min, workstation 3 = 1

    min, workstation 4 = 1 min, workstation 5 = 3 min, workstation 6 = 1 min and total

    idle time is 10 minutes

    A

    B

    C

    D

    F

    K

    H

    G

    I

    E J

    Station 1

    3 min

    6 min

    Station 2

    7 min

    Station 3

    4 min

    5 min

    Station 4

    7 min

    2 min

    Station 5

    1 min

    6 min

    Station 6

    5 min

    4 min

  • 8/3/2019 South Carolina Furniture Inc

    11/11

    g) the best workstation assignment you can make without exceeding a 10 minute

    cycle time and its efficiency

    Efficiency = 50 min

    (6 workstations) (9 min/units)

    = 92.6%

    A

    B

    C

    D

    F

    KH

    G

    I

    E J

    Station 1

    3 min

    6 min

    Station 2

    7 min

    Station 3

    4 min

    5 min

    Station 4

    7 min 1 min

    Station 5

    2 min 6 min

    Station 6

    5 min