    South Eastern Power Networks plc

    Use of System Charging Statement

    FINAL NOTICEEffective from 1 Apr il 2014Version 2.1 

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    2/36

    Version Control  Version Publication

    DateDescription of version and any changes made

    1.0 24/12/2013 Indicative Charges Effective 1 April 2014 (form to be approvedby Ofgem)

    2.0 19/02/2014 Final Charges Effective 1 April 2014 (form still awaiting Ofgemapproval)

    Please note changes have been made to the following charges:-

     Annex 1:LV Medium Non-DomesticLV HH MeteredHV HH MeteredLV UMS (Pseudo HH Metered)LV Sub Generation Non-Intermittent

     Annex 4: All charges beginning with:LDNO LVLDNO HV

    2.1 20/02/2014 Form Approval received from Ofgem

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    3/36

    Contents

    1.  Introduction ........................................................................................................................................... 2 

    2.  Charge Application and Definitions ...................................................................................................... 3 

    Supercustomer Billing and Payment .................................................................................................... 3 Supercustomer Charges ...................................................................................................................... 3 Site-Specific Billing and Payment......................................................................................................... 4 

    Site-Specific Billed Charges ................................................................................................................. 4 

    Time Periods for Half-Hourly Metered Properties ................................................................................ 5 

    Time Periods for Half-Hourly Unmetered Properties............................................................................ 6  Application of Capacity Charges .......................................................................................................... 6 Chargeable Capacity ............................................................................................................................ 6 Exceeded Capacity .............................................................................................................................. 6 Demand Exceeded Capacity ................................................................................................................ 7 Generation Exceeded Capacity ............................................................................................................ 7 Standby Capacity for Additional Security on Site ................................................................................. 7 

    Minimum Capacity Levels .................................................................................................................... 7 

     Application of Charges for Excess Reactive Power ............................................................................. 8 

    Demand Chargeable Reactive Power .................................................................................................. 8 Generation Chargeable Reactive Power .............................................................................................. 8 Generation Charges for pre-2005 Designated EHV Properties ........................................................... 9 Provision of Billing Data ....................................................................................................................... 9 Out of Area Use of System Charges .................................................................................................. 10 Licensed Distribution Network Operator Charges .............................................................................. 10 Third Party Access from Exempt Distribution Networks .................................................................... 11 

    3 Schedule of Charges for Use of the Distribution System 12

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    4/36

    1. Introduction

    1.1. This statement has been prepared in order to discharge the obligation of South

    Eastern Power Networks plc, hereafter referred to as “UK Power Networks”, under

    standard licence condition 14 of its Electricity Distribution Licence. It contains

    information about our charges 1  and charging principles for use of our distribution

    system. It also contains information about our Line Loss Factors (LLFs).

    1.2. The charges in this statement are calculated using the Common DistributionCharging Methodology (CDCM) for Low Voltage and High Voltage (LV and HV)

    Designated Properties and the Extra-high Voltage Distribution Charging Methodology

    (EDCM) for Designated Extra-high Voltage (EHV) properties. The application of

    charges to premises can usually be referenced using the Line Loss Factor Class

    (LLFC) contained in the charge tables.

    1.3. All charges in this statement are shown exclusive of VAT. Invoices will include VAT at

    the current applicable rate.

    1.4. The annexes that form part of this statement are also provided for additional

    convenience in spreadsheet format. This spreadsheet also contains supplementary

    information used for charging purposes but which is not required to be provided in

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    5/36

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    6/36

    permitted in the Electricity (Unmetered Supply) Regulations 2001 2  and where

    operated in accordance with BSCP520 3 and traded as NHH.

    2.8. Identification of the appropriate charge can be made by cross-reference to the LLFC.

    2.9. Valid Settlement combinations 4 for these LLFCs are detailed in Market Domain Data

    (MDD).

    2.10. Where an MPAN has an invalid settlement combination, the ‘Domestic Unrestricted’

    fixed and unit charge will be applied as default until the invalid combination is

    corrected. Where there are multiple SSC/TPR combinations, the default ‘Domestic

    Unrestricted’ fixed and unit charge will be applied for each invalid TPR combination.

    2.11. The time periods for the charge rates are as specified by the SSC. To determine the

    appropriate charge rate for each SSC/TPR a lookup table is provided in the spread

    sheet that accompanies this statement.

    2.12. The ‘Domestic Off-Peak’ and ‘Small Non-Domestic Off-Peak’ charges are

    supplementary to either an Unrestricted or a Two Rate charge.

    Site-Specific Billing and Payment

    2.13. Site-specific billing and payment applies to metering points settled as Half Hourly

    (HH) t d Th it ifi billi d t h k f HH

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    7/36

    •  a fixed charge, pence/MPAN/day or pence/MSID/day;

    •  a capacity charge, pence/kVA/day, for Maximum Import Capacity (MIC) and/or

    Maximum Export Capacity (MEC);

    •  an excess capacity charge, pence/kVA/day, if a site exceeds its MIC and/or MEC;

    •  unit charges, pence/kWh; more than one unit charge may apply;

    and

      an excess reactive power charge, pence/kVArh, for each unit in excess of thereactive charge threshold.

    2.18. Users who wish to supply electricity to Customers whose Metering System is

    Measurement Class C, D, E within SVA or Users who trade their own electricity within

    CVA will be allocated the relevant charge structure dependent upon the voltage and

    location of the Metering Point.

    2.19. Measurement Class C, E or CVA charges apply to Exit/Entry Points where HH

    metering, or an equivalent meter, is used for Settlement purposes.

    2.20. Measurement Class D charges apply to Exit Points deemed to be suitable as

    Unmetered Supplies as permitted in the Electricity (Unmetered Supply) Regulations

    2001 d h t d i d ith BSCP520

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    8/36

    2.26. The time periods for the application of unit charges to Designated EHV Properties are

    detailed in Annex 2.

    UK Power Networks has not issued a notice to change the time bands.

    Time Periods for Half-Hourly Unmetered Properties

    2.27. The time periods for the application of unit charges to connections that are Pseudo

    HH metered are detailed in Annex 1.

    UK Power Networks has not issued a notice to change the time bands.

     Appl ication of Capaci ty Charges

    2.28. The following sections explain the application of Capacity Charges and Exceeded

    Capacity charges.

    Chargeable Capacity

    2.29. The chargeable capacity is, for each billing period, the MIC/MEC, as detailed below.

    2.30. The MIC/MEC will be agreed with UK Power Networks at the time of connection or

    pursuant to a later change in requirements. Following such an agreement (be it at

    the time of connection or later) no reduction in MIC/MEC will be allowed for a period

    of 12 months. In the absence of an agreement the chargeable capacity, save for

    i i ill b b d th l t MIC d/ MEC i l d b th

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    9/36

    Demand Exceeded Capacity

    )0,),max(max(2capacityexceededDemand22

    MICRERI AI   −+×=  

    Where:

     AI = Active Import (kWh)

    RI = Reactive Import (kVArh)

    RE = Reactive Export (kVArh)

    MIC = Maximum Import Capacity (kVA)

    2.33. Only reactive import and reactive export values occurring at times of active import are

    used in the calculation. Where data for two or more MPANs is aggregated for billing

    purposes the HH consumption values are summated prior to the calculation above.

    2.34. This calculation is completed for every half hour and the maximum value from the

    billing period is applied.

    Generation Exceeded Capacity

    )0,),max(max(2capacityexceededGeneration 22 MECRERI AE   −+×=  

    Where:

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    10/36

     Appl ication of Charges for Excess Reacti ve Power

    2.39. When an individual HH metered MPAN’s reactive power (measured in kVArh) at LV

    and HV Designated Properties exceeds 33% of total active power (measured in

    kWh), excess reactive power charges will apply. This threshold is equivalent to an

    average power factor of 0.95 during the period. Any reactive units in excess of the

    33% threshold are charged at the rate appropriate to the particular charge.

    2.40. Power Factor is calculated as follows:

    Cos θ = Power Factor

    2.41. The chargeable reactive power is calculated as follows:

    Demand Chargeable Reactive Power

    ( )

     

     

     

     

     

     

    011

    AIRI REkVA hh blD d

    kWh

    kVArh

    θ 

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    11/36

    Where:

     AE = Active Export (kWh)

    RI = Reactive Import (kVArh)

    RE = Reactive Export (kVArh)

    2.45. Only reactive import and reactive export values occurring at times of active export are

    used in the calculation. Where data for two or more MPANs is aggregated for billing

    purposes the HH consumption values are summated prior to the calculation above.

    2.46. The square root calculation will be to two decimal places.

    2.47. This calculation is completed for every half hour and the values summated over the

    billing period.

    Generation Charges for pre-2005 Designated EHV Properties

    2.48. Designated EHV Properties that were connected to the distribution system under a

    pre-2005 connection charging policy are eligible for exemption from Generation Use

    of System charges unless one of the following criteria has been met:

    •  25 years have passed since their first energisation/connection date, i.e.

    Designated EHV Properties with energisation/connection agreements dated prior

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    12/36

    amount consumed and/or produced in each half hour of each day and shall

    separately identify active and reactive import and export. Metering data provided to

    UK Power Networks shall be consistent with that received through the metering

    equipment installed. Metering data shall be provided in an electronic format specified

    by UK Power Networks from time to time and, in the absence of such specification,

    metering data shall be provided in a comma-separated text file in the format of D0036

    MRA data flow (as agreed with UK Power Networks). The data shall be emailed

    to [email protected].

    2.51. UK Power Networks requires details of reactive power consumed or produced to be

    provided for all Measurement Class C (mandatory HH metered) sites and for

    Measurement Class E (elective HH metered) sites. It is also required for CVA sites

    and Exempt Distribution Network boundaries with Difference Metering. UK Power

    Networks reserves the right to levy a charge on Users who fail to provide suchreactive data. In order to estimate missing reactive data, a power factor of 0.9 lag will

    be applied to the active consumption in any half hour.

    Out of Area Use of System Charges

    2.52. UK Power Networks does not operate networks outside its distribution service area.

    Li d Di ib i N k O Ch

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    13/36

    2.57. For nested networks the relevant charging principles set out in DCUSA Schedule 21

    will apply.

    Third Party Access from Exempt Distr ibution Networks

    2.58. Where one of our MPANs is embedded within an Exempt Distribution Network

    connected to one of UK Power Networks’ distribution systems, and a Difference

    Metering scheme is in place for settlement purposes, we will continue to charge the

    Supplier of the boundary MPAN of the connection, based on gross measurement for

    distribution use of system. No charges will be levied directly to the Customer or

    Supplier of the embedded MPAN(s) connected within the Exempt Distribution

    Network.

    2.59. UK Power Networks requires that gross metered data for the boundary of the

    connection is provided to them. Until a new flow is introduced for the sending of such

    gross data, gross metered data shall:

    •  be sent using the D0036 MRA data flow; and

    •  the D0036 shall contain the metering reference specified by UK Power Networks

    in place of the boundary settlements MPAN.

    2.60. For the avoidance of doubt the reduced Difference Metered measurement data for

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    14/36

    3. Schedule of Charges for Use of the Distr ibut ion System

    3.1. Tables listing the distribution use of system charges are published in the annexes tothis document.

    3.2. These charges are also listed in a spreadsheet which is published with this statement

    and can be downloaded from www.ukpowernetworks.co.uk. 

    3.3. Annex 1 contains charges to LV and HV Designated Properties.

    3.4. Annex 2 contains the charges to Designated EHV Properties and charges applied to

    LDNOs with Designated EHV Properties embedded in networks within UK Power

    Networks’ area.

    3.5. Annex 3 contains details of any preserved and additional charges that are valid at this

    time. Preserved charges are mapped to an appropriate charge and are closed to

    new customers.

    3.6. Annex 4 contains the charges applied to LDNOs in respect of LV and HV Designated

    Properties embedded in networks within UK Power Networks’ distribution services

    area.

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    15/36

    4. Schedule of Line Loss Factors

    Role of Line Loss Factors in the Supply of Electricity4.1. Electricity entering or exiting the DNOs’ networks is adjusted to take account of

    energy that is lost5 as it is distributed through the network.

    4.2. This adjustment is made to ensure that energy bought or sold by a User, from/to a

    Customer, accounts for energy lost as part of distributing energy to and from the

    Customer’s premises.

    4.3. DNOs are responsible for calculating the LLFs and providing these factors to Elexon.

    Elexon manage the Balancing and Settlement Code (BSC). The code covers the

    governance and rules for the balancing and settlement arrangements.

    4.4. Annex 5 provides the LLFs which must be used to adjust the metering system

    volumes to take account of losses on the distribution network.

    Calculation of Line Loss Factors

    4.5. LLFs are calculated in accordance with BSC Procedure (BSCP) 128, which

    determines the principles that DNOs must comply with when calculating LLFs.

    4.6. LLFs are calculated using either a generic method or a site-specific method. The

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    16/36

    4.10. The Elexon portal website, www.elexonportal.co.uk, contains the LLFs in standard

    industry data format (D0265). A user guide with details on registering and using the

    portal can be downloaded from www.elexonportal.co.uk/userguide .

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    17/36

    5. Notes for Designated EHV Properties

    EDCM Nodal/Network Group Costs5.1. A table is provided in the accompanying spreadsheet which shows the unscaled LRIC

    nodal costs used to calculate the current EDCM charges. These charges are

    published on our website www.ukpowernetworks.co.uk.

    5.2. These are illustrative of the modelled costs at the time that this statement was

    published. A new connection will result in changes to current network utilisations,

    which will then form the basis of future prices: the charge determined in this

    statement will not necessarily be the charge in subsequent years because of the

    interaction between new and existing network connections and any other changes

    made to UK Power Networks’ distribution system which may affect charges.

    Charges for New Designated EHV Properties

    5.3. Charges for any new Designated EHV Properties calculated after publication of the

    current statement will be published in an addendum to that statement as and when

    necessary.

    5.4. The form of the addendum is detailed in Annex 6 to this statement.

    5.5. The addendum will be sent to relevant DCUSA parties and published as a revised

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    18/36

    5.9. Several options exist in which UK Power Networks may agree for some or the entire

    MIC to be interruptible. Under the EDCM the applicable demand capacity costs would

    be based on the MIC minus the capacity subject to interruption.

    5.10. An EDCM customer interested in making part or all of its MIC interruptible as an

    integral irrevocable feature of a new connection or modification to their existing

    connection should in the first instance contact UK Power Networks’ connections

    function;

    •  By emailing [email protected] 

    •  By telephone to 08701 964 599

    •  By writing to UK Power Networks, Projects Gateway, Metropolitan House, Darkes

    Lane, Potters Bar, EN6 1AG

    The customer must make an express statement in their application that they have an

    interest in some or all of the import capacity being interruptible for active network

    management purposes.

    5.11. An EDCM customer who is proactively interested in voluntarily but revocably offering

    to make some or all of their existing connection’s MIC interruptible should in the first

    instance contact UK Power Networks’ Agreement Manager at the address in

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    19/36

    6. Electrici ty Distribution Rebates

    6.1. UK Power Networks has neither given nor formally announced any Use of System

    rebates to Users in the 12 months preceding the date of publication of this revision of

    the statement.

    7. Accounting and Administ ration Services

    7.1. UK Power Networks reserves the right to impose payment default remedies. The

    remedies are as set out in DCUSA where applicable or else as detailed in the

    following paragraph.

    7.2. If any invoices that are not subject to a valid dispute remain unpaid on the due date,

    late payment interest (calculated at base rate plus 8%) and administration charges

    will be imposed.

    7.3. Our administration charges will be set at a level which is in line with the Late Payment

    of Commercial Debts Regulations 2002;

    Size of Unpaid Debt Late Payment Fee

    Up to £999.99 £40.00

    £1,000 to £9,999.99 £70.00

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    20/36

    9. Glossary of Terms

    9.1. The following definitions, which can extend to grammatical variations and cognateexpressions, are included to aid understanding:

    Term Definition

     All-the-way Charge A tariff applicable to an end User rather than an LDNO.

    Balancing and Settlement Code(BSC)

    The BSC contains the governance arrangements forelectricity balancing and settlement in Great Britain. Anoverview document is available at:

    www.elexon.co.uk/ELEXONDocuments/trading_arrangements.pdf .

    CDCM

    The common distribution charging methodology used forcalculating charges to Designated Properties as required bystandard licence condition 13A of the Electricity Distribution

    Licence.

    Central Volume Allocation (CVA) As defined in the BSC.

     A person to whom a User proposers to supply, or for thetime being supplies, electricity through an exit point, or fromwho, a User or any relevant exempt supplier, is entitled torecover charges, compensation or an account of profits inrespect of electricity supplied though an Exit Point.

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    21/36

    Term Definition

    Distribution Connection and Useof System Agreement (DCUSA)

    The DCUSA is a multi-party contract between the licensedelectricity distributors, suppliers, generators and OffshoreTransmission Owners (OFTOs) of Great Britain.

    It is a requirement that all licensed electricity distributorsand suppliers become parties to the DCUSA.

    Distribution Network Operator(DNO)

     An electricity distributor who operates one of the 14distribution services areas and in whose ElectricityDistribution Licence the requirements of Section B of the

    standard conditions of that licence have effect.

    Distribution Services AreaThe area specified by the authority within which each DNOmust provide specified distribution services.

    Distribution System

    The system consisting (wholly or mainly) of:

    •  electric lines owned or operated by an authoriseddistributor that is used for the distribution ofelectricity from grid supply points or generation sets

    or other entry points to the points of delivery tocustomers or users; or

    •  any transmission licensee in its capacity asoperator of that licensee’s transmission system orthe Great Britain (GB) transmission system

    and includes any remote transmission assets (owned by atransmission licensee within England and Wales) that areoperated by that authorised distributor and any electricalplant, electricity meters, and metering equipment owned or

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    22/36

    Term Definition

    Entry Point

     A boundary point at which electricity is exported onto adistribution system from a connected installation or fromanother distribution system, not forming part of the totalsystem (boundary point and total system having themeaning given to those terms in the BSC).

    Exempt Distributor

     A person who is an operator of an electricity distributionsystem intended for the conveyance of electricity to or fromusers connected to that electricity distribution system for

    which a specific exemption to hold a distribution licencepursuant to the Electricity Act has been granted to thatoperator or the operator is entitled to not hold a distributionlicence consequent to a class exemption from the holding ofa distribution licence also issued pursuant to section 5 ofthe Electricity Act as amended.

    Exempt Distribution Network

     Any structures, equipment, lines, appliances or devicesused, or to be used, at a Premises, that constitutes an

    electricity distribution system under the control if not theownership of the Exempt Distributor.

    Exit Point

     A Point of Connection at which a supply of electricity mayflow from the Distribution System to the Customer’sinstallation or User’s installation or the Distribution Systemof another person.

    Extra-High Voltage (EHV) Nominal voltages of 22kV and above.

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    23/36

    Term Definition

    Invalid Settlement Combination  A Settlement Combination that is not recognised as a validcombination in Market Domain Data –see: https://www.elexonportal.co.uk/MDDVIEWER 

    kVA Kilovolt Amperes.

    kVArh Kilovolt Ampere reactive hour.

    kW Kilowatt.

    kWh Kilowatt hour (equivalent to one “unit” of electricity).

    Licensed Distribution NetworkOperator (LDNO)

    The holder of a licence in respect of distribution activities inGreat Britain.

    Line Loss Factor (LLF)The factor used in Settlement to adjust the metering systemvolumes to take account of losses on the DistributionSystem.

    Line Loss Factor Class (LLFC) An identifier assigned to an SVA metering system which isused to assign the LLF and Use of System charges.

    Low Voltage (LV) Nominal voltages below 1kV.

    Market Domain Data (MDD)Market domain data is a central repository of reference dataused by all users involved in settlement. It is essential tothe operation of SVA trading arrangements.

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    24/36

    Term Definition

    Metering Point

    The point at which electricity that is exported to or importedfrom the Licensee’s Distribution System is measured, isdeemed to be measured, or is intended to be measuredand which is registered pursuant to the provisions of theMRA. For the purposes of this statement, GSPs are not‘metering points’.

    Metering SystemParticular commissioned metering equipment installed forthe purposes of measuring the quantities of exports and/or

    imports at the Exit or Entry point.

    Metering Point AdministrationNumber (MPAN)

     A number relating to a metering point under the MRA.

    Meter Timeswitch Code (MTC)

    MTCs are three digit codes allowing Suppliers to identifythe metering installed in Customers’ premises. Theyindicate whether the meter is single or multi-rate, pre-payment or credit, or whether it is ‘related’ to another meter.

    MRA The Master Registration Agreement.

    Nested LDNO A Distribution System Operator that is responsible for aNested Network.

    Nested Networks

    This refers to a situation where there is more than one levelof Embedded Network and therefore Nested DistributionSystems between LDNOs (e.g. host DNOintermediate

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    25/36

    Term Definition

    Supplier  An organisation with a supply licence which can registeritself as being responsible for electricity supplied to and/orexported from a metering point.

    Supplier Volume Allocation(SVA)

     As defined in the BSC.

    Time Pattern Regime (TPR)The pattern of switching behaviour through time that one ormore meter registers follow.

    Use of System ChargesCharges applicable to Demand and Generation connectionswhich are connected to and utilise the Distribution Network.

    UserSomeone that has a Use of System agreement with theDNO e.g. a Supplier, Generator or other DNO.

    Unmetered SuppliesExit points deemed to be suitable as unmetered supplies aspermitted in the Electricity (Unmetered Supply) Regulations

    2001 and where operated in accordance with BSCP520.

    10. Annexes 1 to 6

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    26/36

     Annex 1 - Schedule of Charges for use of the Distribution System by LV and HV Designated Properties

    Time periods Red Time Band Green Time Band Black Time Band Yellow Time Band Green Time Band

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    16.00 - 19.00 16.00 - 19.0007:00 - 16.00

    19.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    07.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    00.00 - 07.00

    23.00 - 24.00

    00.00 - 07.00

    23.00 - 24.00

    Saturday and Sunday

     All Year 00.00 - 24.00 00.00 - 24.00

    Notes

    Open LLFCs PCs

    Unit rate 1

    p/kWh

    (red/black)

    Unit rate 2

    p/kWh

    (amber/yellow)

    Unit rate 3

    p/kWh

    (green)

    Fixed charge

    p/MPAN/day

    Capacity charge

    p/kVA/day

    Reactive power

    charge

    p/kVArh

    Excess capacity

    charge

    p/kVA/day

    Closed LLFCs

    Domestic Unrestricted 300, 301 1 2.617 3.99

    Domestic Two Rate 100, 101, 250 2 3.252 0.073 3.99

    Domestic Off Peak (related MPAN) 251, 283, 296 2 0.372

    Small Non Domestic Unrestricted 320, 324 3 1.531 4.29

    Small Non Domestic Two Rate 120, 124, 270, 274 4 1.926 0.042 4.29

    Small Non Domestic Off Peak (related MPAN) 10, 287, 297 4 0.344

    LV Medium Non-Domestic 480, 484 5-8 1.908 0.038 30.86

    LV Sub Medium Non-Domestic

    HV Medium Non-Domestic

    LV HH Metered 550 0 12.509 0.181 0.026 12.47 3.11 0.353 3.11

    LV Sub HH Metered 11 774 0 114 0 021 8 55 5 41 0 298 5 41

    South Eastern Power Networks - Effective from 1st April 2014 - Final LV and HV charges

     Amber Tim e Band

    07.00 - 16.00

    19.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

    November to February

    Inclusive

    Monday to Friday

    (Including Bank Holidays)

    March to October Inclusive

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    Notes

    Time Bands for Half Hourly Unmetered PropertiesTime Bands for Half Hourly Metered Properties

     All tim es are in UK Clock time

    Saturday and Sunday

     All Year 

     All tim es are in UK Clock time

     Annex 2 - Schedule of Charges for use of the Distribution System by Designated EHV Properties (including LDNOs with Designated EHV Properties/end-users).

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    27/36

    Note: The list of MPANs / MSIDs provided may be incomplete; the DNO reserves the right to apply the listed charges to any other MPANs / MSIDs associated with the site. 1 of 2

    ImportUnique Identifier 

    LLFC ImportMPANs/MSIDs

    Export UniqueIdentifier 

    LLFC ExportMPANs/MSIDs

    Name

    Import

    Super Redunit rate

    (p/kWh)

     Import

    fixed charge

    (p/day)

    Import

    capacity rate

    (p/kVA/day)

    Import

    exceededcapacity rate

    (p/kVA/day)

    Export

    Super Redunit rate

    (p/kWh)

     Export

    fixed charge

    (p/day)

    Export

    capacity rate

    (p/kVA/day)

    Export

    exceededcapacity rate

    (p/kVA/day)

     ASHGEN 796 1900090978866 ASHGEN 797 1900090978875 BREHON PROPERTY UNIT TRUST (EUROPA NURSERIES) 0.564 46.54 1.64 1.64 -0.931 1,396.08 0.05 0.05

     AYLESF 868 1900060216613 AYLESF 725 1900060436880 NPOWER COGEN LTD 1.032 198.67 1.08 1.08

    B&RLTD 7711900035000482,

    1900035425153BROWN AND ROOT LTD 0.691 138.50 4.09 4.09

    BEDDIN 771

    1900070745640,

    1900070745650,

    1900070745669,

    1900070745678

    MORGAN STANLEY & CO 1,922.22 1.24 1.24

    BP_OIL 7711900017426438,

    1900017426447BP OIL UK LIMITED 0.182 138.50 2.49 2.49

    BRETSH 8711900090466576,

    1900061003393BRETSH 726

    1900060866064,

    1900060866082NFPA 0.554 8.16 2.31 2.31

    BRKHST 796 1900090834409 BRKHST 797 1900090834418 BIFFA WASTE SERVICES LTD 1.157 76.83 1.74 1.74 -1.737 3,937.63 0.05 0.05

    CHESDC 7961999000002228,

    1999000002237SOUTHERN ELECTRIC POWER DISTRIBUTION 198.67 1.25 1.25

    CRYENG 872 1900060831692 CRYENG 730 1900060831708 ROLLS ROYCE-CROYDON ENERGY 0.099 70.97 1.38 1.38

    DSCPRK 796 1900091057568 DSCPRK 797 1900091057559 DISCOVERY PARK, KENT 1.058 69.67 2.51 2.51 -1.065 1,072.90 0.05 0.05

    E_SHOS-1 7104 MSID: 7104 E_SHOS-1 7104 MSID: 7104 SHOREHAM POWER STATION 0.018 146.50 1.30 1.30

    EMR_RD 873 1900060413234 EUROPEAN METAL RECYCLING LTD 3,207.61 0.51 0.51

    EUROTU 874 1900060219605 EUROTUNNEL 57,191.74 0.53 0.53

    GAT_AF 869

    1900017427938,

    1900017427947,

    1900060576620

    GATWICK AIRPORT LTD 1.324 2,281.37 6.09 6.09

    GAT_BF 8701900060690231,

    1900060690240GATWICK AIRPORT LTD 1.107 397.33 4.86 4.86

    GROVEH 875 1900060225185 GROVEH 727 1900060225194 ST REGIS PAPER COMPANY LIMITED 260.54 1.04 1.04

    HANSTA 8761900031426056,

    1900004383769HANSTA 728

    1900060442174,

    1900060512032NFPA 3.628 1.14 1.15 1.15

    KENTIS 877 1900070122273 KENTIS 722 1900070122343 KENTISH FLATS WINDFARM PROJECT 0.589 8.64 0.86 0.86

    KINGSTON DNET MSID: 1027 UKPN 972.50 1.19 1.19

    LCHEYI 878 1900090194653 LCHEYI 721 1900090194644 LITTLE CHEYNE COURT WIND FARM LIMITED 2.199 1.52 1.22 1.22 197.15 0.05 0.05

    NEWHVN 800 1900090585014 NEWHVN 700 1900090585005 VEOLIA ES SOUTH DOWNS LTD 2.104 31.61 1.54 1.54 -2.482 221.28 0.05 0.05

    NP_LAB 771 1900047386380 SERCO LTD 2.388 277.00 4.80 4.80

    NR_3BR 866 1900060219145 NETWORK RAIL INFRASTRUCTURE LTD 1.130 596.00 4.11 4.11

    NR_AFD 851 1900060219377 NETWORK RAIL INFRASTRUCTURE LTD 2.822 397.33 2.69 2.69

    NR_ASH 879 1900070068129 NETWORK RAIL INFRASTRUCTURE LTD 0.041 397.33 3.58 3.58

    NR_BRI 852 1900060218675 NETWORK RAIL INFRASTRUCTURE LTD 397.33 2.34 2.34

    NR_BYF 853 1900060218727 NETWORK RAIL INFRASTRUCTURE LTD 0.309 596.00 2.40 2.40

    NR_CAN 854 1900060218790 NETWORK RAIL INFRASTRUCTURE LTD 397.33 2.36 2.36

    NR_CRO 855 1900060218815 NETWORK RAIL INFRASTRUCTURE LTD 397.33 1.98 1.98

    Time Periods for Designated EHV Properties

    Super Red Time Band

    South Eastern Power Networks - Effective from 1st April 2014 - Final EDCM charges

    16:00 - 19:00

     All t imes are in UK Cl ock ti me

    Time periods

    Monday to Friday

    (Including Bank Holidays)

    November to February Inclusive

    Notes

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    28/36

    Note: The list of MPANs / MSIDs provided may be incomplete; the DNO reserves the right to apply the listed charges to any other MPANs / MSIDs associated with the site. 2 of 2

    ImportUnique Identifier 

    LLFC ImportMPANs/MSIDs

    Export UniqueIdentifier 

    LLFC ExportMPANs/MSIDs

    Name

    Import

    Super Redunit rate

    (p/kWh)

     Import

    fixed charge

    (p/day)

    Import

    capacity rate

    (p/kVA/day)

    Import

    exceededcapacity rate

    (p/kVA/day)

    Export

    Super Redunit rate

    (p/kWh)

     Export

    fixed charge

    (p/day)

    Export

    capacity rate

    (p/kVA/day)

    Export

    exceededcapacity rate

    (p/kVA/day)

    Time Periods for Designated EHV Properties

    Super Red Time Band

    South Eastern Power Networks - Effective from 1st April 2014 - Final EDCM charges

    16:00 - 19:00

     All t imes are in UK Cl ock ti me

    Time periods

    Monday to Friday

    (Including Bank Holidays)

    November to February Inclusive

    Notes

    NR_DOR 856 1900060219303 NETWORK RAIL INFRASTRUCTURE LTD 2.371 397.33 2.59 2.59

    NR_EAS 857 1900060218912 NETWORK RAIL INFRASTRUCTURE LTD 0.274 397.33 3.62 3.62

    NR_FOK 858 1900060218959 NETWORK RAIL INFRASTRUCTURE LTD 1.378 397.33 3.19 3.19

    NR_HAS 859 1900060218986 NETWORK RAIL INFRASTRUCTURE LTD 0.340 2,667.35 2.45 2.45

    NR_LEA 860 1900060219001 NETWORK RAIL INFRASTRUCTURE LTD 0.194 397.33 2.44 2.44

    NR_MAI 861 1900060219535 NETWORK RAIL INFRASTRUCTURE LTD 2.433 397.33 2.37 2.37

    NR_NOR 862 1900060219891 NETWORK RAIL INFRASTRUCTURE LTD 794.66 1.82 1.82

    NR_QUE 863 1900060219084 NETWORK RAIL INFRASTRUCTURE LTD 198.67 2.73 2.73

    NR_SIT 864

    1900060219819,

    1900060219855,

    1900060492477

    NETWORK RAIL INFRASTRUCTURE LTD 0.019 397.33 2.03 2.03

    NR_THA 865

    1900060219720,

    1900060219794,1900060492430

    NETWORK RAIL INFRASTRUCTURE LTD 3.319 397.33 3.78 3.78

    NR_TUN 867 1900060219206 NETWORK RAIL INFRASTRUCTURE LTD 8.169 397.33 6.76 6.76

    OLDRSF 796 1900091024517 OLDRSF 797 1900091024526 OLD RIDES SOLAR FARM 0.288 4.58 20.13 20.13 392.75 0.05 0.05

    PFIZER 881 1900060219544 PFIZER 724 1900060858356 PFIZER LIMITED 1.058 2,166.58 2.51 2.51

    SENTIV 888

    1900090497281,

    1900090497290,

    1900090497306,

    1900090497315

    SENTRUM SERVICE LTD 43,456.94 1.07 1.07

    SEVIND 7160 MSID: 7160 SEVIND 7160 MSID: 7160 UKPN RESERVE 10.479 0.85 1.91 1.91 -11.081 68.40 0.05 0.05

    SMURFI 882 1900060219952 SMURFI 723 1900060554947 TOWNSEND HOOK LTD 3.431 70.49 1.16 1.16

    STAREN 883 1900060830217 STAREN 729 1900060830226 STAR ENERGY 0.155 822.33 11.47 11.47

    THAEAR 850

    1900090417081,

    1900090417090,

    1900090417115,

    1900090417124,

    1900090417151

    THAEAR 733

    1900090417170,

    1900090417198,

    1900090417203,

    1900090417230

    THANET EARTH CUSTOMERS

    (charge divided by number of customers)386.67

    THAEARD 8501998000000015,

    1998000000024THAEARD 733

    1998000000033,

    1998000000042THANET ENERGY LIMITED (Distributor) 2.434 64.83 1.16 1.16 1,998.18 0.05 0.05

    THAMEM 7711900090872672,

    1900090872681THAMEM 792

    1900090876979,

    1900090876988THAMES WATER LTD 2.724 2,430.17 1.80 1.80 1,822.63 0.05 0.05

    THAMES 884 1900016424857 THAMES 732 1900060576611 THAMES WATER UTILITIES LTD (IMPORT) 2.598 4,651.68 7.28 7.28

    THANET 7230 MSID: 7230 THANET 7230 MSID: 7230 VATTENFALL 0.042 9.15 1.62 1.62 963.35 0.05 0.05

    TS__33 886 1900060216622 THAMESTEEL LTD 397.33 2.32 2.32

    TS_132 885 1900060225282 THAMESTEEL 3,155.68 0.52 0.52

    WRGALL 887 1900070394457 WRGALL 731 1900070394466 KEL LTD 3.512 491.45 0.81 0.81

    Annex 3 Schedule of Charges for use of the Distribution System to Preserved/Additional LLFC Classes

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    29/36

     Annex 3 - Schedule of Charges for use of the Distribution System to Preserved/Additional LLFC Classes

    1 of 1

    Closed

    LLFCsPCs

    Unit rate 1

    p/kWh

    Unit rate 2

    p/kWh

    Unit rate 3

    p/kWh

    Fixed charge

    p/MPAN/day

    290 2 0.622

    Closed

    LLFCs PCs

    Unit rate 1

    p/kWh(red/black)

    Unit rate 2

    p/kWh(amber /yellow)

    Unit rate 3

    p/kWh(green)

    Fixed charge

    p/MPAN/day

    Capacity charge

    p/kVA/day

    Reactive power

    chargep/kVArh

    Excess Capacity

    chargep/kVA

    .

    The Budgetwarmth Unit Rate is based on the Domestic Off Peak charge with 0.250p/kWh added for equipment rental

    South Eastern Power Networks has no Preserved NHH Tariffs/Additional LLFC classes

    South Eastern Power Networks - Effective from 1st April 2014 - Final LV and HV tariffs

    NHH preserved charges/additional L LFCs

    Notes:

    HH preserved charges/additional L LFCs

    Notes:

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    30/36

     Annex 4 - Charges applied to LDNOs with HV/LV end users

    Time periods Red Time Band  Amber Time Ban d Green Time Band Black Time Band Yellow Time Band Green Time Band

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    16.00 - 19.00 16.00 - 19.0007:00 - 16.00

    19.00 - 23.00

    Monday to Friday(Including Bank Holidays)

     All Year 

    07.00 - 16.0019.00 - 23.00

    07.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    00.00 - 07.00

    23.00 - 24.00

    00.00 - 07.00

    23.00 - 24.00

    Saturday and Sunday

     All Year 00.00 - 24.00 00.00 - 24.00

    Notes

    Unique billingidentifier 

    PCs

    Unit rate 1

    p/kWh

    (red/black)

    Unit rate 2

    p/kWh

    (amber/yellow)

    Unit rate 3

    p/kWh

    (green)

    Fixed chargep/MPAN/day

    Capacity chargep/kVA/day

    Reactive power

    charge

    p/kVArh

    Excess capacity

    charge

    p/kVA

    LDNO LV: Domestic Unrestricted 1 1.838 2.80

    LDNO LV: Domestic Two Rate 2 2.284 0.051 2.80

    LDNO LV: Domestic Off Peak (related MPAN) 2 0.261

    LDNO LV: Small Non Domestic Unrestricted 3 1.075 3.01

    LDNO LV: Small Non Domestic Two Rate 4 1.353 0.030 3.01

    LDNO LV: Small Non Domes tic Off Peak (related MPAN) 4 0.242

    LDNO LV: LV Medium Non-Domestic 5-8 1.340 0.027 21.68

    LDNO LV: LV HH Metered 0 8.787 0.127 0.018 8.76 2.18 0.248 2.18

    LDNO LV: NHH UMS category A 8 1.094

    LDNO LV: NHH UMS category B 1 1.560

    LDNO LV: NHH UMS category C 1 2.699

    LDNO LV: NHH UMS category D 1 0.801

    LDNO LV: LV UMS (Pseudo HH Metered) 0 24.338 0.456 0.331

    LDNO LV: LV Generation NHH 8 -0.903

    LDNO LV: LV Generation Intermittent 0 -0.903 0.257

    LDNO LV: LV Generation Non-Intermittent 0 -9.109 -0.197 -0.024 0.257

    LDNO HV: Domestic Unrestricted 1 1.186 1.81

    LDNO HV: Domestic Two Rate 2 1.474 0.033 1.81

    South Eastern Power Networks - Effective from 1st April 2014 - Final LDNO tariffs

    Time Bands for Half Hourly Unmetered Properties

     All tim es are i n UK Clo ck ti me

    Time Bands for Half Hourly Metered Properties

    Monday to Friday

    (Including Bank Holidays)

    November to February Inclusive

    Notes All times are in UK Clock time

    Monday to Friday(Including Bank Holidays)

    March to October Inclusive

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    Saturday and Sunday

     All Year 

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    31/36

    Time periods Red Time Band  Amber Time Ban d Green Time Band Black Time Band Yellow Time Band Green Time Band

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    16.00 - 19.00 16.00 - 19.0007:00 - 16.00

    19.00 - 23.00

    Monday to Friday(Including Bank Holidays)

     All Year 

    07.00 - 16.0019.00 - 23.00

    07.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    00.00 - 07.00

    23.00 - 24.00

    00.00 - 07.00

    23.00 - 24.00

    Saturday and Sunday

     All Year 00.00 - 24.00 00.00 - 24.00

    Notes

    Unique billingidentifier 

    PCs

    Unit rate 1

    p/kWh

    (red/black)

    Unit rate 2

    p/kWh

    (amber/yellow)

    Unit rate 3

    p/kWh

    (green)

    Fixed chargep/MPAN/day

    Capacity chargep/kVA/day

    Reactive power

    charge

    p/kVArh

    Excess capacity

    charge

    p/kVA

    South Eastern Power Networks - Effective from 1st April 2014 - Final LDNO tariffs

    Time Bands for Half Hourly Unmetered Properties

     All tim es are i n UK Clo ck ti me

    Time Bands for Half Hourly Metered Properties

    Monday to Friday

    (Including Bank Holidays)

    November to February Inclusive

    Notes All times are in UK Clock time

    Monday to Friday(Including Bank Holidays)

    March to October Inclusive

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    Saturday and Sunday

     All Year 

    LDNO HVplus: NHH UMS category C 1 1.506

    LDNO HVplus: NHH UMS category D 1 0.447

    LDNO HVplus: LV UMS (Pseudo HH Metered) 0 13.581 0.254 0.185

    LDNO HVplus: LV Generation NHH 8 -0.515

    LDNO HVplus: LV Sub Generation NHH

    LDNO HVplus: LV Generation Intermittent 0 -0.515 0.146

    LDNO HVplus: LV Generation Non-Intermittent 0 -5.191 -0.112 -0.014 0.146

    LDNO HVplus: LV Sub Generation Intermittent 0 -0.513 0.151

    LDNO HVplus: LV Sub Generation Non-Intermittent0 -5.212 -0.104 -0.013 0.151

    LDNO HVplus: HV Generation Intermittent 0 -0.542 32.00 0.188

    LDNO HVplus: HV Generation Non-Intermittent 0 -5.706 -0.067 -0.012 32.00 0.188

    LDNO EHV: Domestic Unrestricted 1 0.837 1.28

    LDNO EHV: Domestic Two Rate 2 1.040 0.023 1.28

    LDNO EHV: Domestic Off Peak (related MPAN) 2 0.119

    LDNO EHV: Small Non Domestic Unrestricted 3 0.490 1.37

    LDNO EHV: Small Non Domestic Two Rate 4 0.616 0.013 1.37

    LDNO EHV: Small Non Domestic Off Peak (related MPAN) 4 0.110

    LDNO EHV: LV Medium Non-Domestic 5-8 0.610 0.012 9.87

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    32/36

    Time periods Red Time Band  Amber Time Ban d Green Time Band Black Time Band Yellow Time Band Green Time Band

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    16.00 - 19.00 16.00 - 19.0007:00 - 16.00

    19.00 - 23.00

    Monday to Friday(Including Bank Holidays)

     All Year 

    07.00 - 16.0019.00 - 23.00

    07.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    00.00 - 07.00

    23.00 - 24.00

    00.00 - 07.00

    23.00 - 24.00

    Saturday and Sunday

     All Year 00.00 - 24.00 00.00 - 24.00

    Notes

    Unique billingidentifier 

    PCs

    Unit rate 1

    p/kWh(red/black)

    Unit rate 2

    p/kWh(amber/yellow)

    Unit rate 3

    p/kWh(green)

    Fixed chargep/MPAN/day

    Capacity chargep/kVA/day

    Reactive power

    chargep/kVArh

    Excess capacity

    chargep/kVA

    South Eastern Power Networks - Effective from 1st April 2014 - Final LDNO tariffs

    Time Bands for Half Hourly Unmetered Properties

     All tim es are i n UK Clo ck ti me

    Time Bands for Half Hourly Metered Properties

    Monday to Friday

    (Including Bank Holidays)

    November to February Inclusive

    Notes All times are in UK Clock time

    Monday to Friday

    (Including Bank Holidays)

    March to October Inclusive

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    Saturday and Sunday

     All Year 

    LDNO 132kV/EHV: LV Sub Generation NHH

    LDNO 132kV/EHV: LV Generation Intermittent 0 -0.351 0.100

    LDNO 132kV/EHV: LV Generation Non-Intermittent 0 -3.537 -0.076 -0.009 0.100

    LDNO 132kV/EHV: LV Sub Generation Intermi ttent 0 -0.350 0.103

    LDNO 132kV/EHV: LV Sub Generation Non -Intermittent 0 -3.551 -0.071 -0.009 0.103

    LDNO 132kV/EHV: HV Generation Intermittent 0 -0.369 21.80 0.128

    LDNO 132kV/EHV: HV Generation Non-Intermittent 0 -3.888 -0.046 -0.008 21.80 0.128

    LDNO 132kV: Domestic Unrestricted 1 0.505 0.77

    LDNO 132kV: Domestic Two Rate 2 0.628 0.014 0.77

    LDNO 132kV: Domestic Off Peak (r elated MPAN) 2 0.072

    LDNO 132kV: Small Non Domestic Unrestricted 3 0.295 0.83

    LDNO 132kV: Small Non Domestic Two Rate 4 0.372 0.008 0.83

    LDNO 132kV: Small Non Domestic Off Peak (related MPAN) 4 0.066

    LDNO 132kV: LV Medium Non-Domestic 5-8 0.368 0.007 5.96

    LDNO 132kV: LV Sub Medium Non-Domestic 5-8 0.359 0.007 2.40

    LDNO 132kV: HV Medium Non-Domestic 5-8 0.275 0.004 20.88

    LDNO 132kV: LV HH Metered 0 2.414 0.035 0.005 2.41 0.60 0.068 0.60

    LDNO 132kV: LV Sub HH Metered 0 3.304 0.032 0.006 2.40 1.52 0.084 1.52

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    33/36

    Time periods Red Time Band  Amber Time Ban d Green Time Band Black Time Band Yellow Time Band Green Time Band

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    16.00 - 19.00 16.00 - 19.0007:00 - 16.00

    19.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    07.00 - 16.0019.00 - 23.00

    07.00 - 23.00

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    00.00 - 07.00

    23.00 - 24.00

    00.00 - 07.00

    23.00 - 24.00

    Saturday and Sunday

     All Year 00.00 - 24.00 00.00 - 24.00

    Notes

    Unique billingidentifier  PCs

    Unit rate 1

    p/kWh(red/black)

    Unit rate 2

    p/kWh(amber/yellow)

    Unit rate 3

    p/kWh(green)

    Fixed chargep/MPAN/day Capacity chargep/kVA/day

    Reactive power

    chargep/kVArh

    Excess capacity

    chargep/kVA

    South Eastern Power Networks - Effective from 1st April 2014 - Final LDNO tariffs

    Time Bands for Half Hourly Unmetered Properties

     All tim es are i n UK Clo ck ti me

    Time Bands for Half Hourly Metered Properties

    Monday to Friday

    (Including Bank Holidays)

    November to February Inclusive

    Notes All times are in UK Clock time

    Monday to Friday

    (Including Bank Holidays)

    March to October Inclusive

    Monday to Friday

    (Including Bank Holidays)

     All Year 

    Saturday and Sunday

     All Year 

    LDNO 0000: LV Sub Generation Non-Intermittent 0 -0.961 -0.019 -0.002 0.028

    LDNO 0000: HV Generation Intermittent 0 -0.100 5.90 0.035

    LDNO 0000: HV Generation Non-Intermittent 0 -1.052 -0.012 -0.002 5.90 0.035

     Annex 5 – Schedule of Line Loss Factors

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    34/36

    Period 1 Period 2 Period 3 Period 4 Period 5

    Winter Peak Summer Peak Winter Shoulder Night Other  

    Monday to Friday

    November to February16:00 - 19:59 07:00 - 15:59

    Monday to Friday

    June to August07:00 - 19:59

    Monday to Friday

    March07:00 - 19:59

     All Year  00:00 - 06:59 All Other Times

    Notes

    Metered voltage Period 1 Period 2 Period 3 Period 4 Period 5 Associated LLFC

    Low-Voltage Network 1.099 1.076 1.085 1.063 1.077

    10, 100 ,101, 120, 124, 250,

    251, 270, 274, 283, 287,

    290, 296, 297, 300, 301,

    320, 324, 350, 351, 352,

    353, 354, 355, 356, 357,

    358, 359, 360, 361, 362,

    363, 364, 365, 366, 480,

    484, 550, 921, 922, 932,

    933, 935

    Low-Voltage Substation 1.080 1.062 1.069 1.052 1.063 756, 781, 782

    High-Voltage Network 1.057 1.044 1.049 1.034 1.044 650, 926, 937

    High-Voltage Substation 1.053 1.040 1.045 1.032 1.040 771, 791, 792

    33kV Generic 1.017 1.014 1.015 1.011 1.014 796, 797

    132kV Generic 1.004 1.003 1.004 1.003 1.003 798, 799

    EHV Site Specific LLFs

    Demand

    South Eastern Power Networks - Effective from 1st April 2014 - Final LLF Time Periods

     All t imes are in UK Clo ck t ime

    Time periods

    Generic Demand and Generation LLFs

    Metered voltage, respective periods and associated LLFCs

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    35/36

    Site Period 1 Period 2 Period 3 Period 4 Period 5 Associated LLFC/MSID

    EHV Site Specific LLFs

    Demand

    NR_DOR 1.032 1.022 1.026 1.017 1.025 856

    NR_EAS 1.018 1.014 1.015 1.008 1.015 857

    NR_FOK 1.014 1.011 1.013 1.008 1.011 858

    NR_HAS 1.013 1.012 1.013 1.010 1.012 859

    NR_LEA 1.006 1.006 1.006 1.006 1.006 860

    NR_MAI 1.019 1.013 1.015 1.011 1.013 861

    NR_NOR 1.010 1.008 1.009 1.006 1.008 862

    NR_QUE 1.185 1.172 1.173 1.172 1.164 863

    NR_SIT 1.014 1.010 1.013 1.009 1.011 864

    NR_THA 1.034 1.022 1.026 1.018 1.024 865

    NR_TUN 1.045 1.085 1.035 1.021 1.032 867

    OLDRSF 1.017 1.014 1.015 1.011 1.014 796

    PFIZER 1.029 1.022 1.028 1.021 1.026 881

    RINGSF 1.017 1.014 1.015 1.011 1.014 796

    SENTIV 1.007 1.007 1.007 1.007 1.008 888

    SEVIND 1.053 1.040 1.045 1.032 1.040 MSID: 7160

    SMURFI 1.024 1.025 1.024 1.025 1.025 882

    STAREN 1.045 1.033 1.042 1.032 1.040 883

    THAEAR 1.016 1.011 1.014 1.011 1.010 850

    THAMEM 1.053 1.040 1.045 1.032 1.040 771

    THAMES 1.017 1.014 1.015 1.012 1.015 884

    THANET 1.000 0.998 1.000 0.997 0.999 MSID: 7230

    TS__33 1.017 1.014 1.015 1.011 1.014 886

    TS_132 1.004 1.003 1.004 1.003 1.003 885

    WRGALL 1.061 1.037 1.063 1.040 1.047 887

    EHV Site Specific LLFs

    Generation

     Annex 6 - New Designated EHV Properties. Addendum to Schedule of Charges for use of the Distribution System by Designated EHV Properties (including LDNOs with

  • 8/9/2019 South Eastern Power Networks - Effective From 1st April 2014 - Final LV and HV Charges

    36/36

    Designated EHV Properties/end-users).

    Note: The list of MPANs / MSIDs provided may be incomplete; the DNO reserves the right to apply the listed charges to any other MPANs / MSIDs associated with the site. 1 of 1

    Import

    Unique Identifier 

    Import

    MPANs/MSIDs

    Import

    LLFC

    Export

    Unique Identifier 

    Export

    LLFC

    Export

    MPANs/MSIDsName

    Import

    super-red

    unit rate

    p/kWh

    Import fixed

    charge

    p/day

    Import

    capacity rate

    p/kVA/day

    Import

    exceeded

    capacity rate

    p/kVA/day

    Export

    super-red

    unit rate

    p/kWh

    Export fixed

    charge

    p/day

    Export

    capacity rate

    p/kVA/day

    Export

    exceeded

    capacity rate

    p/kVA/day

    EDCM import 1 EDCM export 1

    EDCM import 2 EDCM export 2

    EDCM import 3 EDCM export 3

    EDCM import 4 EDCM export 4

    EDCM import 5 EDCM export 5

    EDCM import 6 EDCM export 6

    EDCM import 7 EDCM export 7

    EDCM import 8 EDCM export 8

    EDCM import 9 EDCM export 9

    EDCM import 10 EDCM export 10

    Import

    Unique Identifier 

    Import

    MPANs/MSIDs

    Import

    LLFC

    Export

    Unique Identifier 

    Export

    LLFC

    Export

    MPANs/MSIDsName

    Import LLF

    period 1

    Import LLF

    period 2

    Import LLF

    period 3

    Import LLF

    period 4

    Import LLF

    period 5

    Export LLF

    period 1

    Export LLF

    period 2

    Export LLF

    period 3

    Export LLF

    period 4

    Export LLF

    period 5

    EDCM Import 1 EDCM Export 1

    EDCM Import 2 EDCM Export 2

    EDCM Import 3 EDCM Export 3

    EDCM Import 4 EDCM Export 4

    EDCM Import 5 EDCM Export 5

    EDCM Import 6 EDCM Export 6

    EDCM Import 7 EDCM Export 7

    EDCM Import 8 EDCM Export 8

    EDCM Import 9 EDCM Export 9

    EDCM Import 10 EDCM Export 10

    South Eastern Power Networks - Eff ective from 1st April 2014 - Final new designated EHV charges

     Annex 6 - Ad dendu m to Annex 2 EHV ch arges

    South Eastern Power Networks - Effective from 1st April 2014 - Final new designated EHV line loss factors