US Army Corps of Engineers Sacramento District BUILDING STRONG ® SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE Marshall Marik Project Manager South Sacramento Streams Group Sacramento District May 19, 2011

Upload: aletta

Post on 26-Feb-2016

25 views

Category:

Documents


0 download

DESCRIPTION

Marshall Marik Project Manager South Sacramento Streams Group Sacramento District May 19, 2011. SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE. Morrison Creek Construction Along Union Pacific Railroad. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

US Army Corps of EngineersSacramento DistrictBUILDING STRONG®

SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATEMarshall MarikProject Manager

South Sacramento Streams Group

Sacramento District

May 19, 2011

Page 2: SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

BUILDING STRONG®

Page 3: SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

BUILDING STRONG®

Morrison Creek Construction Along Union Pacific Railroad

Current schedule is to award end of this year, pending real estate rights from Union Pacific Railroad (UPRR).

Received tentative approval from UPRR for design at March 30th meeting.

Construction will not start until May 1, 2012 due to Endangered Species Act compliance.

Page 4: SOUTH SACRAMENTO COUNTY STREAMS GROUP UPDATE

BUILDING STRONG®

Post Authorization Change Report (PACR)

Sacramento City/County completed providing all existing hydrology on April 14th. Reviewing County General Plan with County staff to determine future hydrology.

Corps to complete hydrology review and start floodplain determinations next month.

Delay in receiving hydrology has caused PACR schedule to slip from completion in January 2014 to July 2014.