Southern Dallas County Infrastructure Analysis
Planning Project
Pre-Proposal ConferenceFebruary 12, 2010
North Central Texas Council of Governments
NCTCOG Staff
Michael Morris – Director of Transportation
Natalie Bettger – Senior Program Manager
Ken Kirkpatrick – Procurement/Contract Oversight
Marian Pardue – Contracts & Grants Manager
Karla Weaver – Project Manager
Patrick Mandapaka – Project Coordination/Review
Emily Beckham – Grants Coordinator/Contract Coordination
North Central Texas Council of Governments
Project Goal
• To perform an infrastructure and needs assessment of the identified area, which will facilitate long range planning and sound development for the region.
• The analysis will focus on infrastructure related to transportation, potable water, storm water, sewer, and utilities.
North Central Texas Council of Governments
Project LocationA planning area defined as I.H. 35E on the west, Loop 12 on the north, the general Dallas County/Ellis County line on the south, including the City of Ferris, and the Trinity River on the east.
North Central Texas Council of Governments
Request for ProposalsTo create a Southern Dallas County
Infrastructure Analysis
North Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis Scope of Services
Task 1 Public Involvement and Outreach (Phase 1 & 2)
Development of a Public Involvement and Outreach Plan to include:• Media plan
• Agency coordination
• Key stakeholder interviews
• Focus groups
• Appropriate government agency (councils/boards) briefings
• Public meetings
• NCTCOG web site information content
North Central Texas Council of Governments
Task 2 Historic Review/Inventory (Phase 1). Examples:
• ULI Southern Dallas County TX – A strategy for developing the southern Dallas County logistics hub
• ForwardDallas! Comp plan
• Trinity River corridor rezoning
• UNT Dallas Campus master plan
• Southern Lancaster opportunity area study
• Industrial area redevelopment plan
• DART 2030 plan
• 2005 update long range water supply plan, Dallas water utilitiesNorth Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis Scope of Services
Task 3Technical Analysis/Data Collection (Phase 2)
• Population and employment projections by type (basic, retail, and service)
• Housing study
• Labor study
• Employment/housing balance
North Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis Scope of Services
Task 4Infrastructure Capacity and Needs Assessment (Phase 2)
Perform an infrastructure capacity and needs assessment for the study area focusing on transportation, potable water, sewer, storm water, and utility needs for the area.• Provide current transportation infrastructure inventory• Provide current water, sewer, utility, and other public infrastructure
analysis
• Projections of need for 2030 infrastructure needs
• Provide funding strategies for infrastructure investment
• Create a Phased Implementation Plan for improvements
North Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis Scope of Services
Task 5Creation of Infrastructure and Site Analysis (Final Report)
• To summarize the Phase 1 and 2 analysis
• Creating the final report and merging all information produced
North Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis Scope of Services
Issue RFP – January 22, 2010
Proposals Due – February 19, 2010 by 5 p.m. CST
Consultant Selection Committee – March 2, 2010
Interviews (if needed) – March 12, 2010
Executive Board – March 25, 2010
Estimated Start Date – April 5, 2010
Contract Length – Approximately 18 months
North Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis Schedule
Project Understanding 30 percent
Scope of Services 25 percent
Project Manager/Staff Qualifications 20 percent
Knowledge of Dallas-Fort Worth Area 10 percent
Firm Qualifications/Consultant References 10 percent
Study Schedule 5 percent
North Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis Project Selection Method
Questions and Answers
North Central Texas Council of Governments
Southern Dallas County Infrastructure Analysis
North Central Texas Council of Governments
Karla Weaver, AICPPrincipal Transportation Planner
[email protected](817) 608-2376
www.nctcog.org/trans/sustdev
For More Information: