southern regional power committee - … line was declared faulty by kptcl, ict-1 synchronized on 400...
TRANSCRIPT
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Southern Regional Power Committee Bengaluru
Agenda for the 142nd OCC Meeting of Operation Coordination Committee
to be held on 10.04.2018 at SRPC Bangalore
1 Confirmation of the Minutes of the 141st Meeting of OCC of SRPC held on 09th March 2018
at Hyderabad.
2 Monthly Outage Plan/ Annual Outage Plan
2.1 ISGS/CGS: Generating Units
a) Shut Down Proposals for April/May 2018
b) Shut Down carried out during March 2018 along with reason for deviation, if any.
2.2 ISTS/State Sector Transmission Lines and Elements
All utilities are to submit the S/D proposals for the subsequent month by 3rd of the current
month. Shutdown requests for the same month needed to be avoided. An outage
coordination group had been created ([email protected]) for
review of the previous OCC approved shut downs (construction/critical).
In the 140th OCC Meeting after deliberations, it was decided that proposals received
after 3rd of each month would not be considered. Any deferment or changes in the
schedule needed to be communicated in the mid review and before D-3 in the WBOCS
system.
In the 141st OCC Meeting it was decided that Mid review outages would be approved
only after confirmation from SLDCs of AP, KAR, KER, TN & TS. Proposals will be
sent to outage group and after confirmation from states the approved shutdowns
will be uploaded in SRPC website.
SRLDC to conduct a workshop through VC regarding LC importance, implications
on ATC/TTC/grid, IEGC provisions and issues in postponement, deferment etc.
Non-availing the OCC approved shut downs
SRLDC to furnish the approved vs availed percentage of shut down approved for March
2018. States/Utilities to furnish the reasons for non-availing the shutdown.
SR I was requested to furnish the list of shut downs carried out vs approved w.r.t Annual
Outage Plan for the previous month. The format had been communicated already.
MEL request for outages for MEL-NPS line for 3 days
MEL vide E-mail dated 02.03.2018 had requested outages for MEL-NPS line for 3
days (from 28th to 30th March-18) to carry out 400kV line diversion work from Phase-1
to Phase-2 to meet CERC Order. As per CERC orders, MEL had to change line
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
diversion from Phase-1 to phase-2 to facilitate evacuation of full quantum capacity of
MEL/SEL power.
In the 141st OCC Meeting after deliberations it was decided that keeping in view CTU
approved connectivity, CEA energisation certificate and Hon’ble CERC Order, MEL
shutdown was approved for shifting from 2,000 amp to 3,000 amp switchgear
(28.03.2018 to 30.03.2018). Commercial issues between SEL & MEL were beyond
the scope of OCC.
Subsequently SEL vide letter dated 22.03.2018(Annexure-2A) had informed that
SEL have not agreed for anything being done over their property and premises.
SRPC vide letter dated 27.03.2018(Annexure-2B) had forwarded SEL’s letter to
MEL.
3 LGBR for upcoming five months
3.1 The following details to be furnished for discussion: Schedule of Hydro, Thermal Generation, RES, Purchases, Anticipated Consumption etc.
Shortfall/Surplus, if any and how the same is proposed to be met.
Arrangements to meet the Demand and Energy surplus/deficit.
Status review of Development of State of the Art load forecasting tools as per clause
5.4.2 of IEGC.
Load Generation Balance in real time.
3.2 LGBR for upcoming five months & TTC/ATC computations
3.2.1 All states were requested to furnish PSSE base case for August 2018.
The following details are to be updated:
State 5 months LGB
Converged PSSE Base case
ATC/TTC Computation furnished to SRLDC
ATC/TTC Computation posted on SLDC website
Nodal Officer details
AP Being Furnished
TS
KAR
TN
KER
4 Review of Power Supply Position /Inflows
Constituents/ Generators to furnish the reasons for deviation:
a) Actual with respect to anticipated (MW & MU) for availability and requirement.
b) Generation variation category wise with respect to MoP targets/LGBR figures.
c) Inflows (MU) to major reservoirs: Actual w.r.t. 10 year moving average and w.r.t.
same month last year.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
d) Reasons for demand -supply gap and its variation
5 MAJOR ISSUES
5.1 Projection of likely availability figures from CGS Stations
In the 141st OCC Meeting it was observed that in the present surplus scenario,
preparation of LGBR needed to be discussed/reviewed. Likely DC can be given by
generator, however requisition is under the purview of states, factoring in a number of
consideration (mainly MOD). The actual generation schedule would be restricted based
on the requisition. There is a need for clear methodology to reach at a decision like which
units to be backed down, to be taken out under RSD, outage planning etc,
The following was noted:
LGBR preparation in surplus scenario- While DC would be as per generator, scheduling would naturally be only as per merit order. Constituents were therefore requested to revert back with observation/comments in this regard which would be discussed in the 142nd OCC.
5.2 Outage of ICT-2 at Narendra
KPTCL vide letter dated 07.03.2018 had intimated that ICT-2 at Narendra was taken out
from the grid on 05.03.2018 at 13:42 hrs. KPTCL had suggested that the outage may
please be approved in the month of May 2018 and arrange the availability of the ICT-2 at
Narendra by restoring it immediately.
After deliberations the following were concluded:
SR-II would take the commissioning of new Narendra ICT (500 MVA) on priority.
Though the S/D is up to 31st March 2018, KPTCL/OCC advised SR-II to bring the
ICT by 23rd March 2018.
SR-II assured that works would be taken on priority and new 500 MVA ICT
would be commissioned by 31.03.2018.
SR-II would provide 8 SEMs on urgent basis for 220 kV lines at Kudgi-NTPC
and render assistance in commissioning. The lines would be closed at the
earliest to relieve the loading. KPTCL, Kudgi-NTPC & SR-II would coordinate.
KPTCL would work out possibility of any SPS (like tripping of Mahalingapur
feeder etc) to restrict loading on existing Narendra ICT. SR-II/KPTCL would
expedite the commissioning.
KPTCL would expedite revival of Kaiga-Guttur line. Patrolling/ maintenance
would be taken up lines in Nagjheri complex.
Subsequently it was noted that SR-II have requested for extension of additional 10
days of shutdown from 01.04.2018 to 10.04.2018. SRPC vide letter dated 27.03.2018
(Annexure-5A) had informed that this matter is of serious concern and PGCIL,
SR-II has not yet brought back the new 500 MVA ICT, instead have requested for
extension of additional 10 days of shutdown. Considering the serious constraints in
Karnataka System, the new 500 MVA ICT needs to be commissioned at the
earliest.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5.3 Enhancement of net exportable quantum for SEIL(2x660MW)
SEIL vide letter dated 22.03.2018(Annexure-5B) had submitted the following:
Sembcorp Energy India Ltd. – SEIL (formerly Thermal Powertech Corporation India
Ltd (TPCIL) was granted Connectivity by CTU for 1320 MW. Subsequently after trial
run for Unit 1&2 and declaration of commercial operation, the net exportable quantum
is considered 1240 MW (620 MW from each unit) from SEIL station and NOC is also
getting issued based on the same.
SEIL station is comfortably able to maintain net export of 1254 MW within gross
generation of 1320 MW due to reduced auxiliary consumption and other site
conditions. The same can be confirmed from the generation and export data for the
month of January to March 2018.
Net Exportable Capacity Quantum for SEIL Unit(s) may please be updated and
recorded as 1254 MW (627 MW each unit) (connectivity granted by CTU) as well.
SEIL requested that SRPC may kindly do the needful to notify the proposed increase in
the Net Exportable for SEIL Unit-1&2,
5.4 Availing shutdown of Grid element without SRLDC approval / Opening code.
SRLDC vide message dated 19.03.2018(Annexure-5C) had informed SR-II that SR II has
availed 403 Main bay at Hassan S/D at 10:19 hrs on 19.03.2018 without any intimation to
SRLDC. The above S/D was known to SRLDC only after the tripping of 400 kV Hassan –
Nelamangala-1 & ICT-1 at Hassan at 12:27 hrs. on 19.03.2018. It was noted that there
was no shutdown code issued by SRLDC for the said S/D and it is a clear violation of
IEGC 5.2(c). SRLDC requested SR II to give explanation under IEGC 5.9.5(2) to office to
avail initiating any Grid violation for the above incident.
SR II vide letter dated 19.03.2018(Annexure-5D) had intimated that SRLDC code
is obtained for the following important Transmission elements.
I. All 400 kV/230 kV ISTS lines
II. All 400 kV Transformers/Reactors
III. 765 kV and above bays, lines, Transformers and Reactors
IV. All Bus shutdowns above 220 kV and above.
Reproducing the IEGC Clause 5.2.(c) as below SR II clarified that the same is applicable
on those list of elements which has been prepared by RLDC in consultation with the
concerned users, CTU and STUs. Presently the code is taken only for i,ii,iii and iv
(c) No important elements of the National/Regional grid shall be deliberately opened or
removed from service at any time, except clearance of RLDC or with specific and prior clearance of RLDC. The list of such important grid elements on which the above stipulations apply shall be prepared by the RLDC in consultation with the concerned users. CTU and STUs, and be available at the websites of NLDC/RLDC/SLDCs. In
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
case of opening / removal of any important element of the grid under an emergency situation, the same shall be communicated to RLDC at the earliest possible time after the event. RLDC shall inform the opening/removal of the important elements of the regional grid to be affected by it) as specified in the detailed operation procedure by NLDC.
Since the 400 kV bays are not specifically meant to be included in the list of important
elements required as per IEGC 5.2(c), the code is not being asked for bay shut activities.
Hassan ICT-1 Main bay was availed by issuing CPCC code for AMP works. Due to fault
in Hassan – Nelamangala-1, the Main line breaker and Tie Breaker (Tie of ICT-1-
Nelamangala-1) got tripped. This led to disruption of power flow from in ICT-1, which got
shifted immediately to ICT-2 and no system disruption has occurred. Since Hassan –
Nelamangala-1 line was declared faulty by KPTCL, ICT-1 synchronized on 400 kV side
by opening line isolator of above line, after getting code from SRLDC and no violation of
IEGC 5.2.(c) occurred in this case.
5.5 Charging of 400 kV Tuticorin – Tirunelveli Line along with 400 kV Tuticorin GIS – reg.
SR II vide letter dated 26.02.2018 (Annexure-5E) had informed that the construction
works of 400/220 kV Tuticorin GIS along with 2 X D/C 400 kV Tuticorin – Tirunelveli Line
are in advance stage of completion and the same is scheduled for commissioning by
20.03.2018(Eestablishment of 400/220 kV Tuticorin GIS along with 2 X D/C 400 kV
Tuticorin – Tirunelveli Line under Green Energy Corridor – Part A.)
PGCIL requested M/s Mytrah Techno Electrical & Engineering Co Ltd to communicate the
readiness of associated Transmission system to be connected at 400/220 kV Tuticorin
GIS.
5.6 Low voltage at Somanahalli during morning hours
SRLDC vide letter dated 29.03.2018(Annexure-5F) had informed that on many days
during March 2018 it is observed that voltage at Somahalli bus was less than 380 kV for
significant duration. Somanahalli voltage touched as minimum as 369 kV (as per SRLDC
SCADA) on 07.03.2018. Such a continuous low voltage operation is detrimental to grid
security and Karnataka confirmed two stages (stage 1 for < 380 kV and stage 2 for < 371
kV) of under voltage relay implementation at Somanahalli, in OCC meetings. SRLDC
requested KPTCL to take necessary action at KPTCL end for maintaining the voltages
within IEGC band at all times for secure grid operation and also to send the details
of under voltage relay operations, on the above mentioned dates, with the details of
load relief obtained and improvement in voltage profile of Somanahalli.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5.7 Schedule of Kudgi Station during RSD of one unit
KSEBL vide letter dated 24.03.2018(Annexure-5G) had submitted the following as per
discussion held in Commercial Committee :
The schedule of Kerala from Kudgi STPS is getting revised even up to 50% of
entitlement without any request for surrender by KSEBL. The maximum reduction is
applied during morning and evening peak hours when power is required by KSEBL.
Since the on bar DC of the station remains the same, the reduction in schedule is
reflected as surrender. For instance on 06.03.18, from 06.30 Hrs to 09.30 Hrs
schedule got revised downward. Similarly on 07.03.19 reduction in schedule was
observed from 05.45 Hrs to 08.45 Hrs. Such reduction reflects as violation of merit
order by KSEBL as KSEBL is forced to schedule power from KDPP/purchase from
exchange at a higher rate compared to the VC of Kudgi. This is likely to be audit
query for this year.
Kudgi STPS was taken on RSD from 28.02.18. It is learnt that RSD has been given
on request of KPTCL who is having 53.92% share. However whenever they want
Karnataka is requesting share and is being allowed by SRLDC. This effectively
results in reduction of schedules to Kerala. KSEBLs apprehension regarding whether
this deemed surrender will be considered as contribution to RSD and liable to pay the
charges was raised in the Commercial Committee Meeting and the forum had agreed
to expedite and confirm. KSEBL desired that as the matter is of commercial
significance an early reply is solicited.
5.8 Outage of ICT for gasket replacement, and Frequent SPS operations at UPCL
UPCL vide letter dated 02.03.2018(Annexure-5H) submitted the following:
UPCL has 2x600 MW units of generation and outlets via two 400kV Lines to Hassan
and two 220kV Lines to Kemar via two ICTs of 315 MVA each.
Till end of Feb 2018, around 65% of the ex-bus generation at UPCL was off loaded
on 400kV Network to Hassan, and remaining 35% via 220kV lines to Kemar.
In March 2018, the loading on each Kemar line has crossed 270 MW, which is closely
reaching near to the thermal capacity of the 220 kV equipments. The SPS incorporates a
logic to prevent overloading of Kemar lines beyond 285 MWs persists for more than 5
seconds and triggers units to back down. Due to overloading in 220 kV network, the ICT
and line getting stressed, it is pertinent to mention here that ICT maintenance is overdue.
UPCL requested KPTCL to kindly reduce the loading in 220 kV network. Secondly
frequent unit back down are not advisable hence SPS has been kept bypassed to avoid
frequent unit back downs. There are 30 SPS operations observed in Mar 18 at UPCL, due
to Kemar line over loading, resulting in to unit back down has been observed. The system
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
is so designed that entire power can be evacuated through 400 kV network alone, hence
if SPS remains in service any unit back down due to SPS operation should not be covered
under DSM regime.
Since last 2 months UPCL have applied for the outage of ICT for maintenance purpose,
and UPCL have been asked to revise the DC due to system constraint at UPCL end, the
power could not be pushed on 400 kV network due to system constraint in the 400 kV
KPTCL network. However 400 kV single line capacity is 1500 MW. UPCL have again
applied the ICT outage for all gasket replacement in both ICT for the month of May 18.
UPCL requested that this outage may be approved for dates before monsoon
season. Present moisture contents are 10 PPM against 15 PPM recommended. The
system is so designed that entire power can be evacuated through 400 kV network, and
any outage of ICT, DC revision should not be asked from UPCL.
5.9 Change of the LTA quantum in respect of NTPC Kudgi STPS from 2,392.49 MW to 2,262
MW
Chairperson, SRPC vide letter dated 22.02.2018(Annexure-5I) had submitted the
issues regarding change of the LTA quantum in respect of NTPC Kudgi STPS from
2,392.49 MW to 2,262 MW to CMD, PGCIL.
5.10 Coal Stock position
Coal stock position as on 04.01.2018 as uploaded in the CEA website.
ISGS Stations: NTPC Simhadri: 3 days, Kudgi:12 days, Ramagundam : 15 days,
Talcher: 6 days, NTECL: 24 days & NTPL: 37 days
State Sector: AP: Krishnapatanam: 4 days, VTPS: 1 days, SGPL: 9 days, RTPP: 8
days & HNCPL: 19 days.
Telangana: KTPP: 35 days, Kakatiya TPS: 8 days & KTPS New:29 days
Karnataka: BTPS: 5 days & RTPS: 1 day.
Tamil Nadu: MTPS Stage I: 26 days, Stage II: 20 days, NCTPS: 2 days & TTPS: 6
days
5.11 Task Force Committee Report on Flexibilisation of Thermal Power Plants-Unit
identification for Pilot project demonstration
In the meeting in CEA held on 08.02.2018 it was decided six units, including two units of
NTPC and one unit each from DVC, GSECL, APGENCO, MSPGCL, would be taken up
for 55 % minimum load operation in line with the CERC notification.
In the 141st OCC Meeting APGENCO had informed that they were examining the unit
which could be identified for flexibility. APGENCO would get in touch with CEA in
this regard.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5.12 Overarching Agreement
It was noted that Overarching Agreement in SR had been signed by all states in SR
except Tamil Nadu. SRPC vide letter dated 24.01.2018 had requested Chairperson,
TNEB that necessary directions to TANGEDCO for signing the Overarching Agreement
may kindly be arranged be given. It was noted that in the Meeting of Southern Zonal
Council held on 28.11.2017 this was an agenda point relating to Optimum Harnessing of
Renewable Energy Integration in SR.
In the 141st OCC Meeting, constituents were requested to make use Overarching
Agreement. User name and password details were to be collected from SRLDC. Hands
on experience to process the application could be coordinated with SRLDC. TN was
requested to also kindly sign the Agreement.
5.13 TTC assessment considering temperature dependent rating of lines/terminal
equipment
Keeping in view the high demand approaching (Jan to Apr), coal shortages etc SRPC
vide letters dated 13.11.2017 and 20.11.2017 had requested NLDC to take up the issue
with the concerned entities. NPC had written letters to CTU on 21.112017 and
19.12.2017, 16.02.2018 & 13.03.2018 ..
NLDC had been requested to share the status/correspondence in respect of TTC
assessment considering temperature dependant rating of lines/terminal
equipment. NLDC was requested to pursue with CTU.
5.14 Certification of availability of Transmission system of Inter State/RPC certified feeders.
It was agreed that Intra-state / RPC certified lines outage procedure would be
followed (as circulated by SRLDC) for availability computations.
All states to furnish the outage data, element wise and availability computations
duly vetted by SLDC to SRLDC by 2nd of every month as per procedure.
5.15 Automatic Generation Control(AGC) (Refer Item No. 4 in the Minutes of 7th NPC
Meeting)
CERC in its Order dated 13.10.2015 in Petition No.11/SM/2015 had reiterated the need
for mandating Primary Reserves as well as AGC for enabling Secondary Reserves.
In the 7th NPC Meeting held on 8th September 2017 two aspects of AGC had been
deliberated
a) AGC is the requirement of system operation where in generators has to participate in
frequency regulation.
b) Ramifications of implementation of AGC on Tariff.
NPC had decided that AGC would be discussed in detail at RPC level in a Special
Meeting.
As decided in the 32nd TCC/33rd SRPC Meetings, a Special Meeting was convened
on 28.03.2018 at SRPC to deliberate on the AGC matter. Minutes of the Meeting are
awaited.
AGC implementation at Simhadri needed to be firmed up. AGC at N P Kunta was
needed to be pursued.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5.16 Issues related to NPS-Nellore 400 kV Transmission lines loading: implementation of
SPS
In the Meeting it was noted that in the 33rd SRPC Meeting it was agreed to have an
SPS,during any tripping of one of the lines of NPS-Nellore. SPS logic would be finalized in
consultation with SRLDC, PGCIL, SEL/MEL and SRPC Secretariat. During any outage of
the interconnector, the system operator would take appropriate decision regarding
curtailment of interregional ATC or curtailment of NPS connected generators etc as per
provisions of extant regulations. In case of tripping of one line, the other line also would be
tripped through an over current relay when ampere rating increases corresponding to
1700+170 MW(10 % of thermal limit). Time delay also will be incorporated in the logic.
Time delay proposed is 20 seconds.
After deliberations the following was noted:
SPS on 400 kV Nellore-NPS was agreed. The setting agreed was 105% of 1,700 MW
with 5 second delay (Over current on both the circuits). To be disabled during closing
(when both the circuits are out). MEL/SEL agreed for the settings. SR-I agreed to
implement these settings.
Subsequently SR I, PGCIL informed that with reference to 141st OCC meeting minutes, it
was proposed to implement the proposed SPS for 400kV NPS – Nellore D/C Lines using
definite time O/C protection feature available in Main – 1 protection:
The agreed Logic is as follows: MW: 105% of 1700 = 1785MW, Corresponding Current @ 400kV Voltage = 2576A The Setting Available (in steps of 10A) = 2580A, Timer = 5 Sec
It was requested that SRPC/SRLDC may please concur the same for implementation. M/s
MEPL/SEPL was requested to arrange for deputation of M/s ABB Service Engineer for
configuration for implementing in Main-2 protection
5.17 Operation of Hydro Power Projects in Peaking Mode
It had been desired by CEA that monthly analysis of performance of Hydro Stations in
OCC Meeting was needed to be done. SRPC had suggested that the analysis be
circulated to states before the OCC so that any discrepancy is resolved mutually. Except
KSEBL, no other states is furnishing the analysis/comments on SRLDC analysis. All
SLDCs are requested to revert back with comments since the performance is
A special Meeting in this regard is now scheduled to be convened at KSEBL, SLDC
under Chairmanship of NLDC on 13.04.2018 (Meeting Notice at Annexure-5J) with
participation from SLDCs and Gencos. SLDCs had been requested to ensure the
participation of State Hydro Gencos.
5.18 Outages of NPCIL Units in Peak Demand period
In the 141st OCC Meeting TSTRANSCO and TANTRANSCO had expressed difficulties faced by them in managing their LGB due to loss of generation from NPCIL units.
After deliberations KKNPP was suggested to revive the unit II only in September to avoid refueling/Shutdown in peak months of 2019.
It was agreed to take up the issue of outages of NPCIL units with higher management of NPCIL.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5.19 Implementation of PMUs
CEA vide letter dated 12.02.2018 had communicated to CTU regarding Implementation of PMUs and their analytics regarding. It is requested that the following may please be sent to NPC, CEA so that the same could be taken up with RPCs and NLDC/RLDCs for discussion and coordination:
Details of each Analytics i.e., the methodology, assumptions, inputs,
calculations etc developed / being developed by CTU.
Progress of their implementation in SLDC/RLDC/NLDC (It is understood that
some of the Analytics have been implemented at few places, these are at
testing stage or the task have been completed.
Difficulties, if any, being faced by CTU in their development/installation.
Any other information on the subject
5.20 Compliance of WTG models to applicable CEA Technical standards for Connectivity to
the Grid (as amended from time to time) as stipulated in the MNRE
Guidelines/procedure for Revised List of Models and Manufacturers (RLMM)
In the Meeting it was noted that MNRE Office Memorandum dated 01.03.2018 would
be discussed in a Special Meeting.
5.21 Utilization of RE Generators for Reactive Compensation & High Voltage
In the earlier OCC Meetings, it had been noted that even though Solar / Wind generators had very controllable reactive injection / absorption capability, they were not being utilized on account of PPA commitment / penalties. It had been suggested that SLDCs / STUs may approach their Regulator for flexible set points as per direction of SLDCs. The direction of SLDCs could be based on voltage level on single basis or on solar / non-solar hours on daily basis. SRLDC had agreed to take up the issue in the FOR forum.
In the TCC Meeting held on 16.02.2018 it was noted that certain provisions of PPA of
solar generators may not be as per the grid operational requirements and therefore this
aspect needs to be looked into. Hence, Reactive support/management of RE generators
needs to be examined and revisited keeping in view higher RE penetration. The
recommendation in this regard could be referred to FOR. CEA had stated that in draft
Amendment of CEA Connectivity Regulations, provision of voltage set point and control
of VAR interchange had also been proposed. It was opined that details could be shared
by the states and the matter could be examined to arrive at commonality in SR.
5.22 Common Transmission System Data Base (Refer Item No. 5 in the Minutes of 7th NPC
Meeting )
In the 7th NPC Meeting held on 8th September 2017, NPC had emphasized the need for
having an accurate All India power system data base for carrying out accurate power
system studies for operational and planning horizons. It was observed that data mining
needed to be carried out for this purpose. It was accepted that POSOCO may prepare
requires formats and circulate to all RPCs and in turn RPCs may obtain data from their
constituents. POSOCO was requested to circulate the format in this regard to be used by
all RPCs.
In the 139th /140th /141st OCC Meetings, NLDC had been requested to circulate the
Formats.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5.23 State-wise allocation of 540 MW power from RGPPL to Railways
540 MW power from Ratnagiri Gas and Power Private Limited (RGPPL) has been allocated
to Indian Railways. Allocation to SR States (out of 540 MW) would be as under:
State Nodal Railway Maximum load in MW after availability of corridor between NEW Grid and SR
Telangana SCR 50
Tamil Nadu SR 100
Karnataka SR 35
35 MW MoP allocation to Railways (Karnataka) from RGPPL was operational from 25th
October 2017.
TSTRANSCO had informed that meters/communication equipment’s are being
procured.
TANTRANSCO had informed that TANGEDCO was to enter into the Agreement.
TSTRANSCO and TANTRANSCO to be ready with the infrastructure since it was
MOP allocation and was being monitored by higher bodies. At short notice, this may be
required to be operationalized.
5.24 Compliance of CEA Regulations for Grid connectivity of Renewable Energy Sources
CEA vide letter dated 12.04.2017 & 08.05.2017 (enclosing MoP letter 06.04.2017) and in
Special Meeting on 28.06.2017 & 11.09.2017 had observed that it was obligatory for all
the grid connected renewable generators to provide necessary facilities for data-
communication and data-storage and other parameters as may be stipulated. It was
decided by CEA that the respective states will submit weekly reports of data
communication status to CEA as well as to respective RPC/RLDC and NLDC.
Compliance of CEA Regulations was further discussed in 4th Meeting on LVRT for
compliance of Orders of Hon’ble CERC in respect of Petition No. 420/MP/2014 &
provisions of CEA/CERC Regulations and other RE issues held on 25.10.2017 at SRPC,
Bengaluru.
The following was the updated status on RE SCADA availability as noted in the 141st
OCC Meeting:
SCADA availability as on 28.02.2017 Mapped I/C
Remarks
AP Wind: 3751/3835.77 MW (97.79%) Solar: 1911/2144.88 MW (89.10%) Total: 5662/5980.55 MW (94.67%)
Pending SCADA availability was for RE connected distribution level and for which action had been taken for compliance.
TS Wind: 100.8/100.8 MW (100%) Solar: 3008.32/3246.42 MW (92.67%) Total: 3109.12/3347.22 MW (92.89%)
Action for balance SCADA availability at 33 kV and below was being followed up and notices had been issued.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
KAR Wind: 3633.68/3633.68 MW (100%) Solar: 3764.37/3764.37 MW (100%) Total: 7398.05/7398.05 MW (100%)
KER Wind: 16/59.3 MW (26.99%) Solar: 71.18/90.858 MW (78.34%) Total: 87.18/150133 MW (58.07%)
TN Wind: 6342/7909.9 MW (80.18%) Solar: 648/1950 MW (33.23%) Total: 6990/9859.9 MW (70.89%)
Notices had been issued for SS under 10(1) for SCADA availability. 100% SCADA availability of wind was likely to be ensured by December 2017. TANTRANSCO (Communication) and TANGEDCO (Metering) had jointly initiated action for Solar SCADA availability and was targeted to be completed by March 2018.
The following had been noted in the RE/LVRT Meeting:
SRPC had pointed out that 100 % RE visibility was required to be ensured and the issue
was being viewed by MoP / CEA. Weekly status reports were to be furnished to CEA.
SRPC & SRLDC had requested the SLDCs that pending SCADA availability of RE was
to be completed sincerely with concerted efforts for compliance of CEA / CERC
Regulations.
In the Meeting it was also noted that TANTRANSCO solar SCADA monitoring
percentage is very less. TANTRANSCO informed that they are addressing the issue..
Subsequently it was informed by TSTRANSCO that wind SCADA monitoring would
achieve 100 % by June 2018. For Solar, action had been initiated to procure meters and
will require some more time.
5.25 Monitoring of scheme funded from PSDF
In the 7th NPC Meeting was conducted on 08.09.2017 RPCs were further requested to
examine the implementation of schemes in OCC & TCC meetings and intimate NPC
about any bottlenecks.
In the 6th Meeting of the Monitoring Group of PSDF held on 05.01.2018 at Kochi, Kerala.
It was emphasized in the meeting that better utilization was very essential, especially
since the progress is also being monitored by MoP. SRPC vide letter dated 11.01.2018
had addressed this issue SRPC constituent states.
The minutes of the 6th Meeting of the Monitoring Group of PSDF held on 05.01.2018 at
Kochi, Kerala was issued by POSOCO/NLDC letter dated 23.02.2018.
All the states/entities to kindly furnish the updated status.
5.26 Daily Load Forecasting by SLDCs/RLDCS/NLDC
SRLDC to present the error (forecast Vs actual demand) for the month of March 2018.
5.27 PSS Tuning of generators
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5th Meeting to review the status of PSS tuning of the generators had been convened on
26th July 2017 and minutes of the Meeting are available at SRPC website. All the
generators need to follow the action plan finalized in the 5th PSS meeting
5.28 RGMO margin during scheduling
SRPC had pointed out that necessary checks / interlocks needed to be in place so as to
ensure that RGMO margin is available in all the generators under SRLDC control area.
Regulation 5.2(h) of IEGC states, ‘…………….For the purpose of ensuring primary
response, RLDCs/SLDCs shall not schedule the generating station or unit (s) thereof
beyond exbus generation corresponding to 100 % of the Installed capacity of the
generating station or unit (s) thereof.’
SRLDC vide letter dated 07.02.2018 had taken up the issue with IPPs/MPPs
All IPPs / MPPs to ensure RGMO margin (ensure that total schedules of LTA,
MTOA, STOA and PX are not more than the NOC (normative ex bus)).
SRPC vide E-mail dated 27.02.2018 had requested that the Auxiliary Energy
Consumption (percentage value) considered by IPPs vis-a-vis for keeping margin
for RGMO compliance may please be shared.
5.29 Prolonged Outage
KKNPP Second reactor: Update .
6. High Frequency
6.1 High frequency at Load Change Over.
a) Status review of implementation of staggered load change over within the constituents
as per the decision of 23rd SRPC meeting, moderating own generation, surrendering of
ISGS power in advance and other actions by Regional Entities to avert high frequency
excursion.
6.2 Low Frequency
a) Summary statement of different violation messages issued by SRLDC to each constituent as per new IEGC Amendment.
b) In the 124th OCC Meeting it was suggested that SRLDC may identify incidents of UD/OD for Analysis by States. SRLDC to furnish the incidence for analysis, if any.
7. VOLTAGE PROFILE
7.1 Low voltage
a) Details of Capacitors installed during March 2018 and during April 2017 to March 2018.
Details of the healthy/faulty capacitors to be furnished.
7.2 High Voltage
High Voltage at 400 kV and 765 kV nodes
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
7.2.1 Status review of GT Tap positions
GT tap Positions - GT taps yet to change as per recommendation (Refer Table-III)
GT taps of all new units getting synchronized to grid should be kept at the nominal grid
voltage level of 400 kV or 220/230 kV. SRLDC would ensure the requirement for ISTS
connected generators while SLDCs should ensure it for their embedded generators.
7.2.2 MVAR Interchange/MVAR capability testing
Nodal Officers may kindly ensure that the data reaches SRLDC/SRPC in time (by
fourth of every month) so that SRLDC can correlate it with SCADA data and analysis
could be done facilitating actions for further improvement.
Recommendations finalized in the Special Meetings were required to be implemented.
All the SLDCs to kindly monitor VAR absorption/injection of generating units in their respective control areas in real-time.
In the 141st OCC Meeting it was noted that number of MVAR Testing had been
undertaken and review of recommendation of MVAR testing would be taken up in
the 142nd OCC- SRLDC would compile and furnish these details.
High Voltage and MVAR Injection
Details of nodes of high voltage coupled with MVAR injection during October 2017 to
January 2018 is given below:
Nodes with MVAR injection during V > 103%
AP KAR KER TN TS
Cuddapah Bidadi Kochi Alamathy Gajwel
Chittoor Munirabad Trivandrum Kalavinthapattu Hyderabad
Gazuwaka Mysore
Karaikudi Khammam
Kurnool Madhugiri
Pugalur Mehaboobnagar
Nellore PG Nelamangala
S V Chatram Malkaram
NP Kunta Pavagada
Trichy Warangal
Vijayawada Raichur
Dichipally
Maheshwaram
In the 141st OCC Meeting it was noted that the entities would furnish an action taken report to control over voltage and avoid MVAR injection at high voltage before 142ndOCCM.
7.2.3 Status review of Bus/Line Reactors, Line Reactors and STATCOM
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Status of implementation of Bus / Line Reactors approved in the Standing Committee /
SRPC pending for commissioning by the SR constituents.(Refer table-IV)
7.2.4 Reactive Power Planning
Status update on capacitor installation. (Refer table-V)
8 Network Protection/Security issues
8.1 U/F & df/dt Relays Schemes
Implementation of SRPC recommended quantum
SCADA mapping of feeders of AUFR & df/dt schemes
The status update as per SRLDC after validation of all the States is as follows:
State SCADA
mapped %
Status
AP 65.49 One RTU to be commissioned. Balance RTUs are covered under OPGW scheme approved through PSDF.
TS 79 6 RTUs had been provided for Solar Generators and for 17 RTUs, procurement was being taken up and it could take 4-5 months. There were 18 RTUs for Interstate feeders and some would provide UFR and df/dt relief quantum also. With this they were likely to achieve 100% mapping.
KAR 100
KER 100
TN 94 Additional RTUs needed to be procured for 100% SCADA mapping. Transducers to be procured.
Pudu 92
SR 88
All the States were requested to kindly initiate the action to achieve 100 % SCADA visibility.
In the 141st OCC Meeting the following was noted:
UFR & df/dt relief quantum and visibility was to be informed by TS
(within a week). It would be jointly vetted by SRLDC & TS. A report
would be prepared in this regard.
UFR & df/dt relief quantum and visibility of TN would be jointly vetted by
SRLDC & TN, and a report would be prepared. TN would furnish a
report with time lines on the activities identified.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
8.2 RGMO/FGMO
RGMO response had been deliberated in various Special/OCC/TCC/SRPC meetings.
Inadequate response was an area of serious concern and there was no noticeable
improvement. SRPC had stated that the recommendations finalized in the special
RGMO/MVAR interchange meeting should be complied by all the utilities.
RGMO implementation/ Extension of RGMO status point to SLDC (Refer Table-VI of
Appendix).
As per 5th Amendment to IEGC, gas stations above 50 MW Installed Capacity were also
to come under RGMO/FGMO Operation w.e.f. 1st October 2017. SLDCs were requested
to follow up for compliance of the Amendment. AP, TN and NTPC (Kayamkulam) were
requested to ensure compliance.
SRLDC had requested that the list of all hydro stations and gas stations which are
covered under FGMO/RGMO response along with the status clearly mentioning the
CERC order in case exemption/extension is received from Commission may be
furnished.
In the 141st OCC Meeting SRLDC presented the RGMO response for the incident on
30.01.2018 at 10:46 hours. During 1,250 MW generation loss at Koderma, frequency dip
was 0.07 Hz. (49.89 Hz to 49.82 Hz.) 3 % of generation was considered as expected
response (5 % corresponds to 1.25 Hz).
After deliberations, it was decided that SRLDC would post the RGMO
analysis for 30.01.2018. All the ISGS and SLDCs would furnish the reasons for
limited response and also action envisaged for non performing units (approaching
SERC, RGMO meeting etc) within 10 days.
SRLDC had furnished the analysis(Annexure-8A)
8.3 Special Protection Systems
In the 140th OCC Meeting it was felt that SPS of 400kV Nunna-Vemagiri(PG) line could be
retained from security point of view, while the settings can be fixed after studies.
SR I was requested to give details like Thermal limit etc and additional margin may be
incorporated as per Planning Criteria.
8.4 Automatic Demand Side Management Scheme (Petition No. 250/MP/2012) & GSES
(Petition No. 265/MP/2012)
SRLDC had pointed out that similar to existing ADMS logic (O/D), backing down of
generation during the sustained U/Ds during high grid frequency may be required. It was
observed that KSEBL and KPTCL were having provisions of tripping/backing down of the
generators in case of U/Ds during high frequency. Other states were requested to examine
the technical feasibility/provision for backing down of generators and revert back.
8.5 Grouping of loads (IEGC clause 5.4.2 (e))
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
As per IEGC, to maintain the frequency within stipulated band and also to ensure network
security, the interruptible loads were to be arranged in four groups of loads, This was for
the purpose of scheduled power cuts/load shedding, loads for unscheduled load
shedding, loads to be shed through UF relays, df/dt relays and loads to be shed under
any SPS scheme. These loads are to be grouped in such a manner that there is no
overlapping between different groups of loads.
The issue was noted for compliance by the concerned utilities. SRLDC requested all the
states to kindly furnish the updated details in this regard.
9 LVRT Implementation
Hon’ble CERC has passed Order in respect of Petition No. 420/MP/2014 on 05.01.2016.
The Order directs a number of actionable points by various utilities for compliance of
LVRT, CEA & CERC Regulations etc. Four Special Meeting were conducted at SRPC on
05.02.2016, 18.04.2016, 05.07.2016 & 25.10.2017 (Meeting minutes are available at
SRPC website).
Number of actionable points had been finalized in the 4th Meeting on LVRT / RE issues.
SRLDC vide letter dated 29.11.2017 had requested the entities to take necessary action
and resolve the issues within the time line mentioned.
Submission of WTG data by all states as per the format circulated by SRPC / SRLDC
within one week.
Inclusion of suitable clause in the bidding documents (Solar) to ensure LVRT
compliance and provide details of NITs issued after the date of CERC Order.
Identification of optimal location for installing PMUs for LVRT analysis purposes.
Conducting capacity building workshop regarding forecasting and scheduling of RE.
STUs had been requested to study the line loading in the systems for M-1 compliance
and submit report to CEA.
Identify and implement ‘Contingency Demand Disconnection Scheme’ for locations
having large chunk of RE generation to the tune of 1000 MW and above.
All states were requested to analyze Solar generation ramp-up / ramp down based on
the capacity and identify the measures for compensating the same.
States were requested to take up the issue of PPA provision related to MVAR
interchange with respective SERCs for modifying the same to mitigate high voltage
scenario in the grid.
In the 141st OCC Meeting, SRLDC was requested to again take up the issue with
the concerned. It was felt that Special Meeting may be convened to discuss the
issues in which the concerned wing officials of the states may be called.
10 Emergency Restoration System (ERS)
As per ERS requirement outlined in MoP letter dated 05.12.2014, status update on ERS
is given at Table VI of Appendix.
In the Meeting held under the Chairmanship of Secretary (Security) on 28th June 2017 it
was noted that ERS were in procurement stage in most of the states and the response
from the states was not very encouraging.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
11 SCADA AND COMMUNICATION
A Special Meeting was held on 13,03.2018 to deliberate on pending
SCADA/Communication issues. Minutes of the Meeting is uploaded on SRPC website.
The status of pending Items as deliberated in the Special Meeting is at Table VIII of
Appendix.
SRLDC had invited attention of the forum that CERC had brought out Order on Suo moto
Petition 007/SM/2014 dated 29.01.2016 regarding SCADA. SRLDC had started posting
this information from February 2016 on their website.
12 TRANSMISSION NETWORK ISSUES AND SYSTEM OPERATION ISSUES
Load ability of ICTs and revisit of the associated protection settings to prevent cascade
tripping of ICTs/high loading of transmission lines. Insufficient action in controlling the
loading of ICTs leads to N-1 criteria violation in compliance of Regulation 3.1 f(8) of
CEA(Grid Standards) Regulations 2010 and Regulation 3.5 a(i) of CERC Indian
Electricity Grid Code Regulations 2010.
Over loading of ICTs and N-1 violation at Hoody, Vemagiri, Gazuwaka & Nellore was
being observed.
13 Black Start Procedure
Status needs to be furnished in the following format :
State BSRP reports for January 2018 to June 2018
BSRP schedule for July 2018 – December 2018
Point to point mock exercise report being furnished
Updated list of Nodal Officer
Workshop Schedule
Development of mock exercise procedure for Individual Stations / Systems.
Point to point mock exercise for black start by all constituents
Development of Procedure for restoring Metro Operation in case of Black out.
KAR SLDC/SRLDC to review the BSRP in respect of Nagjheri to BTPS and Jurala to
Raichur by month end.
TS to update on DG set capacity enhancement /availability at Jurala
14 Upcoming Generating Stations
Status update of Central sector and State Sector Upcoming generating stations are at
Table VII of Appendix.
SRPC had stated that declaration of COD letter from SLDC was required to be
submitted to CEA, Fuel Management Division for purpose of coal linkages etc.
SRLDC had pointed out those new ISTS connected units should come out with detailed
metering scheme for various units commissioning schedule at least one year prior to
synchronization. The scheme needed to be discussed and finalized in the Meeting of
Commercial Sub Committee.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
15 Any other point with the permission of the Chair.
16 Date and Venue of the next Meeting
Appendix Follow up Issues
1
ROW issue of 400 kV Nelamangala-
Hoody Line/ commissioning of 400 kV
Yelahanka substation/220 kV
evacuation system of KPTCL at
Yelahanka substation
PGCIL: Substation commissioned on 22.03.2018 by PGCIL, SR II KPTCL:6/16 sections(2.2 kM) cable
laying completed from Yelahanka
station end. 7th section excavation is
under progress. 3/16 cable jointing
work completed and cable trench and
joint bay excavation commenced from
PGCIL end. RCC duct from JB1 to JB 2
at PGCIL end has been completed.
2
REMC Project
(GOI) sanction had been received in
Sep 2017
First kick off Meeting for REMC project
implementation conducted on
01.11.2017
Site survey for SRLDC is carried out.
Implementation schedule was of 14
months.
3 VC facility Puducherry to take up VC requirement
in 2017-18
5 Completion of Kamudhi bays at
Karaikudi by PGCIL
First bay completed.
Second bay completed by mid of
February 2018 and planning to
commission the 400 kV DC line from
Kamuthi to Karaikkudi.
TANTRANSCO end taken up the LC
works on 16.02.2018 to 18.02.2018
(TANTRANSCO was of the opinion that
both the bays would be connected
simultaneously).
6 Operation of Nagarjunasagar /
Srisailam / Kadamparai units in pump
mode
Srisailam, two units were operating in
Pump operation during high frequency
period from 8th November 2017.
Maximum 4 Units are being put in
pump mode operation simultaneously.
Since there is some pressure issue
more than four at a time is not possible
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
at present even though all the 6 units
are capable of operating in pump
mode.
During 09.01.2018 to 01,02,2018
NSHES / TSGENCO Units 2 to 8 were
tested successfully in pump mode
operation.
During this season only 3 units can be
operated simultaneously due to some
constraints in suction side of the water
conducting system.
7 Condenser mode of operation of
Nagarjunasagar and Srisailam LB
All the 6 units at Srisailam operated in
condenser mode at different times.
During day time four units together also
had been operated in condenser mode.
At Nagarjunasagar all the units except
Unit IV and VI put in condenser mode
and four units simultaneously also
being operated at condenser mode.
8 Closing of 220 kV Upper Sileru-
Balimela line
Idle charged from 8th January 2015
from Upper Sileru end.
9
PMU Status
All the States were requested to give
the requirements for Second Phase to
CTU. KSEBL & APTRANSCO had
submitted the requirement.
10 Priority for Railways/Metros in the
matter of Restoration of Supply
TSTRANSCO had informed that
meters/communication equipment’s are
being procured.
TANTRANSCO had informed that
TANGEDCO was to enter into the
Agreement.
TABLE I
PSS TUNING
SRT of following units had been analyzed upto 5th Meeting of PSS and necessary
action had to be taken as per Recommendations
Entity Generating Stations/Units
APGENCO Rayalaseema TPS U1 to U5; VTPS U1 to U4 & U7; SDSPP U1&U2; Srisailam RB HEP U1 to U7; Lower Sileru HEP U1
AP IPP HNPCL U1 & U2
TSGENCO Nagarjunasagar HEP U1 to U8; Srisailam LB HEP U1 to U6;
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Kakatiya TPS U1 & U2; Kothagudem TPS U 7&8(Report to be analysed) U10 & U11; Singareni Collieries U1 &U2 (Reports to be analyzed)
KPCL Raichur TPS U1,2,3,5,6,7& 8; BTPS U1 to U3; Varahi UGPH HEP U1 to U4; Nagjheri HEP U1 to U6 (U6 report to be analyzed); Sharavathy HEP U1,2,3,4,5,6,7,9, 10 & 8 (Report to be analyzed), Raichur TPS U4 (Report to be analyzed)
KAR IPPs UPCL U1 & U2; JSWEL U1 to U3
KSEBL
TANGEDCO MTPS-I U1 to U4 (U1 Report to be analyzed); NCTPS St-I U1 to U3; Tuticorin TPS UI(Report to be analysed)U2 to U5; NCTPS St-II U1; Kadamparai HEP U1 & U2, Mettur-II (Report to be analyzed).
TN IPPs
CGS NTPC- Ramagundam U7 & U4 (reFport to be analyzed); NTPC-Simhadri U1 to U4; NTPC-Talcher STPS St-II U3 to U6; NTECL-Vallur TPS U1 to U3; NLC-Neyveli TPS II U4 to U7; NLC-Neyveli TPS II U1 to U3; KGS U2 (Report to be analyzed); NPCIL-KKNPP U1 & U2 (Report to be analyzed) ;NLC-Neyveli TPS II Exp. U1 & U2; (NLC & TN JV) NTPL U1; NTPC-Kudgi U1
ISTS connected IPPs
TPCIL U1 & U2 (U2 Report to be analyzed); Coastal Energen U2; IL & FS U1 & U2
For the following Units, PSS is to be tuned and SRT to be carried out / information not available.
Entity Generating Stations/Units
APGENCO VTPS U5 & U6; Lower Sileru HEP U2 to U4
AP IPPs
KPCL Yeramarus TPP
KAR IPPs JSWEL U4
KSEBL Idukki HEP U1 to U6
TANGEDCO NCTPS St-II U2; Kadamparai HEP U3 & U4
TN IPPs STCMS
CGS NTPC-Ramagundam U1, U2, U3, U5 to U6; NTPC-Kudgi U2; NLC-Neyveli TPS I Exp. U1 & U2 (SRT reports not submitted); NPCIL- KGS U1, U3 & U4 ( Full Report not submitted for U4); NPCIL-MAPS U1 & U2;
ISTS connected IPPs
Coastal Energen U1; Lanco Stage II & III; SGPL-Nellore; SEL U1 to U4; MEL U1 & U4
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Table IV- URTDSM UPDATES
Status as on 13.03.2018 Meeting Remarks
URTDSM Status Region: Approved/Installed/Integrated/Validated SR I SS 27/25/24 SR I PMU 113/104/98 SR II SS 41/40/38 SR II PMU 142/140/135
SR-I - 9 PMU –Chittor (5) and Srikakulam (4) installation works under progress. SR-I - 5 PMU -Srisailam (4) and Kurnool (1) data validation is not completed. SR-I - 1 PMU -Simhadri (1) - SRLDC requested SR-1 to co-ordinate with NTPC Simhadri to complete the pending installation works. SR-II -2 PMU -Kaiga (2) installation works under progress. SR-II -5 PMU -Arasur (2) and Kalpakkam (3) data validation is not completed.
Supply and installation of APS- Auxiliary power supply system as part of URTDSM project
SR-II had intimated that the Auxiliary
Power Supply System is under
manufacturing and is expected to reach
site by 20thApril 2018 and commissioning
will be completed by 15th May 2018
AP and TS had expressed concern
regarding delay in supply of Auxiliary
power supply system. SR-I confirmed that
the APS System is expected to reach site in
April 2018 and commissioning was
expected by May 2018.
Status of SAT and SAVT of URTDSM project in SR
SRLDC - SAT completed and SAVT is yet to commence. KSEBL - SAT and SAVT completed. KPTCL - SAT and SAVT completed.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
TNEB - SAT completed and SAVT is yet to commence TSTRANSCO - SAT completed and SAVT has commenced from 1st March 2018 APTRANSCO - Commissioning works under progress expected to be completed by 31st March 2018.
Powergrid Analytical Application installed as part of URTDSM
All the control centers were requested to use the software and report the deficiencies.
PGCIL had agreed to make a Web group of all the Control Centers, LD&C, IIT Mumbai, SR-I/SR-II etc for exchanging the information/usage and for deficiencies / rectification etc.
PGCIL requested all constituents to submit revised PMU requirement, if any, for Phase-II considering availability of Wide Band nodes.
Table-III - GT Tap: Recommended/Implemented
Station
Unit Present Tap And Corresponding Voltage(In kV)
Recommended Tap And Corresponding Voltage(In kV)
Remarks
ISTS connected Generators:
Kaiga I 1 & 2 6 & 229.125 7 & 223.25 MVAR interchange as per Special Meeting to be ensured. Kaiga II 3 & 4 3 & 409.5 4 & 399
APGENCO/APSLDC
IPPs of AP It is recommended that all IPPS under APSLDC could be advised to change their Tap position corresponding to voltage level of 400 kV / 220 kV.
KPCL/KAR SLDC
Sharavathi 9 & 10 2 & 231 4 & 220 First GT (9) reached during October 2017. Second GT reached during December 2017. Unit 10 GT erection works completed. Tap change would be carried out after receiving the ICTs.
UPCL 1 & 2 4 & 409.5 5 & 400 Observed rotor teeth temperature issues. 2 x 125 MVAR reactors agreed in 39th SCPSPSR. It was suggested that their MVAR absorption should be around 50-60 MVAR in case they are not able to change Tap.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
TANGEDCO/TN SLDC
Tuticorin TPS 1,2,3,4 5
8 & 243 230 All the GTs in TTPS are kept in Tap No. 10.
MTPS St.III 1 6 & 409.5 7 & 399 Provision of Bus Reactor is being carried out by GCC/TANTRANSCO, Salem. After the provision of Bus Reactor the GT Tap will be increased to 7(399 kV) from Tap- Reactor bay works were completed at present and allotment of reactor is awaited.
Table –IV- Reactor Installation Status
Entity Bus Name Status REMARKS
KPTCL Hoody Reactor erected on platform. March 2018
Nelamangala Reactor erected on platform March 2018
Entity Bus Name Capacity in MVAR
Approved in
Type Remarks
PGCIL Yelahanka 2x63 Bus
Deferred as per 40th SCPSSR. When Madhugiri line will come it will be expedited.
Cuddapah 50 to 125 39th SC Yet to be awarded
APTRANSCO
Vemagiri 125 36th SC
Bus Vemagiri and Kurnool is expected by December 2017. LoA issued on 18.06.2017. Kalpakka – will be completed by March 2018 Awaiting for APERC approval for Chittoor Reactor. Commissioning by March 2018.
Kurnool 125 Bus
Kalpaka 125 Bus
Chittoor 125 39th SC
Vijayawada 125 39th SC
It was noted that a separate reactor at Vijayawada in scope of AP had been identified. The exact location could be firmed up by APTRANSCO.
APTRANSCO/ APGENCO
VTPS Stage IV
125 39th SC
APGENCO informed that reactor enquiry was being taken up. It was noted that this reactor was different from the APTRANSCO reactor.
KPTCL
Davangere 125 39th SC 41st SCSPSRR: Members agreed with already approved additional reactors of 1x125 MVAR (400kV) each at
Talguppa 125 39th SC
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Talaguppa and Davangere 400/220kV Substations.
TANTRANSCO
Almathy 125 39th SC Specification Under Process
Manali 125 39th SC
Kayathar 125 39th SC
TANTRANSCO/ TANGEDCO
Mettur 125 39th SC To be diverted from Palavadi and works to be taken up.
TSTRANSCO Mamidipalli 125 36th SC
Bus
Commissioned on 23.02.2018 at 14:31 hours
TSTRANSCO/ TSGENCO
Srisailam LB 125
39th SC
41st SCPSPSR: After deliberations, it was agreed that TSTRANSCO will submit the requisite data for system study to CTU. The CTU, after carrying out studies will forward the results to CEA and TSTRANSCO. The requirement will be further discussed and finalized in a Joint Meeting.
NPCIL Kaiga 2 x 125
Bus
One reactor by December 2019. Financial approval had been received. They were in the process of floating the tender.
UPCL Udupi 2 x 125
39th SC
41st SCPSPSR: It was informed that the requirement was assessed based on system studies, therefore, it was decided that the the decision taken in 39th SC Meeting may be implemented.
Table V- Reactive Power Planning
Utility Reactive Power Planning Voltage level
Remarks
APTRANSC
O
Kadapa: 273.6 MVAR
Vijayawada: 144 MVAR
Visakhapatanam:175 MVAR
On 33 kV side
28.8 MVAR commissioned
0 MVAR commissioned
16.6 MVAR commissioned
APSPDCL 802 MVAR 154 MVAR commissioned
APEPDCL 276 MVAR 115 MVAR commissioned.
KPTCL Bengaluru Tr. Zone:784 MVAR
12.1 kV LOA issued. 30 MVAR Installed
Bagalkot Tr. Zone :258.1 12.1 kV Material supplied. Erection
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
MVAR completed/under progress. 78.3
MVAR Installed
Hassan Tr. Zone 150.8 MVAR
Material supplied. Erection
completed/under progress. 43.5
MVAR Installed
Mysore Tr. Zone :60.9 MVAR
60.9 MVAR commissioned
Gulbarga Tr. Zone :98.60 MVAR
Installed Nil
Tumkur Tr. Zone :281.3 MVAR
12.1 kV 46.4 MVAR commissioned. 34.8 MVAR EI approval awaited.
Telangana TSNPDCL:288x2 MVAR 110x1 MVAR
190 x 2 MVAR commissioned 69 x 1 MVAR commissioned.
KSEBL
360 MVAR
66 kV Works will be taken up after
approval. 11kV
TANGEDCO 34 x 2.4 MVAR 11 kV
16 x 2.4 MVAR 22 kV 16 x 2.4 commissioned
59 x 2.4 MVAR 11 kV IPDS tender to be opened on
30.11.2017
19x2.4. MVAR 22 kV IPDS tender to be opened on
30.11.2017
13 x 2.4 MAVR 110 kV PO placed on M/s Shreem
Electric Limited.
53 x 2.4 MVAR 11/22
kV
RAPDRP tender to be floated
101 x 2.4 MVAR 11/22
kV
Erode region: Tender to be
floated
32 x 2.4 MVAR 11/22
kV
Vellore Region: Tender to be
floated
82 sets of 11 kV, 2.4 MVAR
Capacitor Banks in
Coimbatore Region
11 kV BLTC note for price bid opening
to be submitted.
822 MVAR capacitors at
Distribution level had been
commissioned out of 931
MVAR capacitors planned.
Balance 109 MVAR to be
commissioned. However, for
further enhancement of
Reactive Power, Capacitor bank
provisions have to be arranged
by Planning/Transmission
wings.
SR I
NGR bypass
400 kV Nellore-Thiruvalam
line I & II ,Thiruvalam-
Kurnool I & II, Kozhikode-
Mysore I & II line reactors
November 2017
SR I informed that Thiruvalam
end works are over. SRLDC
informed that some voltage
issues are observed at
Thruvalam end and desired to
know the status. SR I agreed to
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
furnish the details.
Table –VI- ERS status
Transmission Utility
Requirement as per MoP
Existing Status/Remarks
APTRANSCO 3 2 PSDF funding proposal was rejected and AP will carry out the works unde O & Works
TSTRANSCO 1 Being retendered. Subsequently, it would be taken up for PSDF funding.
KPTCL 2 2
KSEBL 1 Tenders to be floated. Being followed up.
TANTRANSCO 2 As per Minutes of BLTC held on 03.01.2017, Procurement is put on hold
PED NIL NIL
PGCIL 4 (2 Nos. Additional)
4 (SR I & SR II is having 2 no. Each)
765 KV ERS (one each for SR-I and SR-II) tendering under progress.
Table –VII- Generating Units- Under Progress
Central Sector
Station Unit Installed Capacity
MW
Scheduled date of synchronizing / commissioning
Remarks
NTPC
Kudgi TPS Stage-I
I,II, III
3 x 800= 2400
Unit-I CoD from 31.07.2017 Unit-II. CoD from 31.12.2017 Unit–III : Synchronisation by February end, Trying to prepone COD to April 2018
Telangana STPP Phase I
2 x 800 U-I CoD May 2020 U-2 CoD December 2020
Pudimadaka AP 4 x 1000 52 Months from Zero Date
85% share to AP. Zero date yet to be finalized. AP requested NTPC to firm
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
up the zero date at the earliest. AP informed evacuation system would be developed by PGCIL
NLC
New Thermal Power Project
I 500 April 2018 CTU had informed that for evacuation LILO of Neyveli - Puducherry and 400 kV D/C to Araliyur lines are planned. NLC had applied for LTA of 340 MW which could be managed with the LILO of Neyveli – Puducherry. Balance 600 MW would be catered by 230 kV system of TANTRANSCO. Araliyur S/S was being developed by TANTRASCO and was expected by June 2018
II 500 April 2018
NPCIL
BHAVINI
Kalpakkam (PFBR)
I 500 Synchronization by 2017-18 COD by 2017-18 Synchronization by March 2017 COD by Sep 2017
KKNPP III & IV
2023 & 2024
UMPP
Krishnapatnam 3960 (6 x 660)
APEPDCL and PCKL had taken steps with their legal counsel to expedite the hearing before Honorable High Court of Delhi
Cheyyur 4000 New bids would be called
NEW PROJECTS OF STATE SECTOR & IPP
Sl No
Name of project Located in
Capacity in MW
Commissioning Schedule /Remarks
1 Rayalaseema TPS ST-IV
AP 1 x 600 2017-18
2 Dr. NTTPS, Vijayawada
AP 1 x 800 2017-18, June 2019
3 Krishnapatanam Stage II (U3)
AP 1 x 800
4 Polaki AP 4000 (5 x 800 MW)
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
5 Edlapur KAR 1 x 800
6 North Chennai Stage III TN 1 x 800 2019-20
7 North Chennai Stage IV
TN 2 x 800 Beyond 2019-20
8 Ennore TPS Exp TN 1 x 660 2018
9 Ennore replacement TN 1 x 660 2018
10 Udangudi Stage I TN 2 x 660 2019-20
11 Uppur TPP (TBCB) TN 2 x 800 2019-20
12 Manuguru PPP Telangana 4 x 270 U1 : March 2018 U2: June 2018 U3: Sep 2018 U4:Dec 2018
13 Kakatiya TPP Stage III Telangana 1 x 800 2017-18
14 Kothagudem TPS Phase VII
Telangana 1 x 800 December 2018
15 Damaracherla (Yadadri)
Telangana 5 x 800 U1 &2 Nov 2020 U3to5 20121
IPPs
Sl No.
Name of project Located in
Capacity in MW
Commissioning Schedule /Remarks
1 Meenakshi PH-II AP 2 x 350 2017-18 Untied: 640 MW
2 East Coast Energy Thermal
AP 2 x 660
2017-18 AP : 300 MW
3 Thermal Powertech (TPCIL) Unit-III
AP 1 x 660
2017-18
5 Godhna TPP, Janjir – Champa Dist, Chhattisgarh
For KAR 2 x 800 2017-18
Table VIII-SCADA/Communication
Update as per Meeting on 13.03.2017 Latest update
ICCP link failure/not stable
Expiry date of all licenses would be furnished by M/s GE to the respective Control Centers.
Respective Control Center would ensure that M/s GE take pro-active action to renew the licenses before the expiry.
There should not be any license renewal issues during the project cycle of the project and it needed to be ensured by Control Centers (through M/s GE).
License for external firewall is going to expire in three months. M/s GE has to update the certificates in ext
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
firewall of AP. M/s GE to take necessary action. M/s GE site engineer at respective Control Centers
to escalate the matter to BO-Noida, if they are unable the resolve the issue at their level. Further, inter-action between M/s GE site engineers at SLDCs and M/s GE site engineers at SRLDC needs to be strengthened.
Changeover to ICCP data communication through Backup SRLDC could be explored during such conditions which would reduce data outage duration.
All the ICCP links (Main/Back up CC of SLDCs to Main/Back up CC of SRLDC) to be checked daily to ensure healthiness.
All SLDCs to carry out HA test once in every month to a check SCADA/Communication system healthiness.
All states to actively raise all SCADA/communication related complain to M/s GE/CTU (M/s Tejas) /STU and not leaving the matter only to SRLDC for resolution.
It was noted there was no provision for DSM waiver during ICCP failure as per extant Regulations.
Updated communication network diagram to be submitted by SR-I and SR-II to all SLDCs & SRLDC. Further any changes done in the communication network needed to be informed to all.
Frequent data outage(State Sector/Central Sector)
PGCIL to share their observations for communication failure on the instances of data outage beyond 8 hrs put up by SRLDC.
PGCIL to share all fibre cut/equipment outage information in real time.
DCPC at Narendra is faulty which is being attended by GE(SRLDC to follow up)
Communication failure details as submitted by SRLDC for the period from 01.01.2018 to 12.03.2018 is at Annexure-I
Data outage after commissioning
Cross checking to be done with site daily values for newly commissioned elements for a period of two week duration from commissioning.
Data discrepancy
SRLDC to delete the points which are not feasible to be telemetered.
RTU/SAS Maintenance/Upgradation
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
All states/Powergrid/CGS to explore option of replacement of old RTUs and AMC for SAS, as getting spare is difficult for old RTU.
AMC need to be provided for all RTU/SAS gateways by CTU/STU.
A life/functional assessment report and action plan by PGCIL/ISGS on old RTUs would be prepared and submitted to SRLDC/SRPC.
Backup Control Centre
Backup SCADA functionality testing frequency needs to be done once in 6 months to ensure high availability of data/preparedness to operate from Back up CC in event of any contingency. Compliance report may be furnished to SRLDC.
Periodical testing was being carried out by SRLDC and KSEBL.
TN stated that communication network is being strengthened to Backup CC. Once same is completed, TN will do the testing.
APTRANSCO informed that communication link has to be established from AP CC at Vijaywada to Back Up CC of SRLDC at Delhi. Powergrid & AP confirmed to establish the same by 16.03.2018.
PGCIL would be floating new combined Open Tender for Backup SLDCs for AP (Tirupati), TS (Warangal) along-with few other states.
Backup control centre establishment for AP & TS need to be expedited.
ICCP with NTAMC
PGCIL had confirmed that due to cyber security concerns data would not be extended to SRLDC from NTAMC ICCP.
Functional requirement of the requisite data by SRLDC would remain, which needed to be ensured by PGCIL. SRLDC would furnish the list of telemetry points that have to be extended to PGCIL within 10 days, and within 1 month PGCIL would come out with a detailed plan to be completed within 6 months (October 2018)
Modification of EMS package TSTRANSCO had received estimate of Rs 47 lakhs and
the contract was being firmed up.
SRPC had requested that PGCIL to render assistance to
TSTRANSCO as requested by them if possible.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Status review of compliance of approved protocol of handling scada & communication issues (21.03.2016 communication meeting)
If the issue is not getting resolved within 8 hrs (3 hrs for ICCP) the following action would be taken:
Shri A P Gangadharan, GM(AM), SR-II and Shri S Ravi,
GM(AM), SR-I would be informed for necessary follow
up.
The issue would be escalated with M/s G E (both by
SLDCs and SRLDC) and with M/s Tejas (by SR-I & SR-
II).
In case the issue was as not resolved within 24 hrs
physical involvement of OEM (M/s GE and M/s Tejas)
would be ensured through effective coordination by user /
PGCIL/ SRLDC.
Sustained efforts/involvement of all the concerned entities
to be ensured till the issue is resolved
In case of hardware replacement / major rectification it
would be completed by 72 hrs.
No significant data outage for NCTPS stage 2, Sriperumbudur in last month
Sparing of Fibre in Central Sector Project
TANTRANSCO had again requested for sparing of fibre in
Central Sector Project. SR-II stated that request for
sparing of fibre in new FO links could be communicated
for consideration.
In 30th TCC/31st SRPC
meetings held on
24/25.02.2017 it was
noted that keeping in
view of the non
availability of spare
fibres in most of FO
links and the approved
MoU with M/s Powertel
the scheme of
allocation the fibres was
dropped.
VC issues
TSTRANSCO Video Conference issue at TSSLDC. There
was disturbance in Video Conference at TS end when
connected to SRLDC.
SRLDC confirmed as per AMC Engineer no issue was
observed at SRLDC end and software upgradation is
pending at TS end.
TSSLDC and SRLDC were requested to coordinate and
sort out the issue.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Talcher RTU
A meeting with NTPC Talcher, SR-II ULDC and SRLDC is
proposed in 3rd/4th week of March 2018.
SR-II was requested to address the communication issue
between Talcher-II & HVDC. NTPC as a User needed to
be proactive in this.
Table – IX FGMO/RGMO
Issues as per Special VC/Meeting
Commitment/suggestion Current Status
NTPC
Talcher RGMO status point yet to be provided, RGMO response of the station was very poor during the six incidents as per SRLDC analysis. Data not furnished by Talcher
NTPC agreed for providing the same by October end. RGMO needs to be implemented properly by the generator. Analysis to be submitted
In the 136th OCC Meeting it was informed that new RTU to be integrated to make available of status point. A Meeting is scheduled at SRLDC shortly with participation from NTPC Talcher and SR II
NLCTSII
Responding mostly frequency rise (unloading of machines) incidents.
Insufficient margin available may be issue for non-response during frequency dip incidents. If same status of response continues, further reduction in Normative DC may be considered by deducting mines share from the station.
Fine tuning had been carried out for all the unis.
NLCTSII EXP:
Performance was good during some of the incidents and it was not consistent. Generator explained that units are still facing stability issues as they are of new technology and all best efforts would be put for improving the performance.
Units are still facing stability issues as they are of new technology and all best efforts would be put for improving the performance.
NLC TS I Expansion Non-performance
Technical issues associated with Unit-1, the same needs to be
NLC informed that Powergrid is requested to help
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
addressed through OEM. RGMO status issue.
TANTRANSCO
List of Gas generating stations in TN control area for which RGMO implementation is mandated as per IEGC 5th Amendment w.e.f 01.10.2017.
To be submitted 136th OCC: TANTRANSCO have requested gas stations to give the action plan and it was informed that they are planning to approach CERC for exemption since gas availability is very less
Details of hydro generating stations exempted from RGMO/FGMO implementation by Hon’ble CERC along with relevant orders to be forwarded by TNSLDC.
To be submitted 136thOCC: Exemption has been received for all irrigation based hydro stations and others yet to be received.
NCTPS ST1 Performance was poor and it was informed by generator that logic error corrected last week, performance for future incidents needs to be observed. GPS synchronization facility not available
Would be completed in three months.
MTPS Stage 1 U-2 and MTPS Stage III
GPS synchronization not available
Agreed to complete GPS synchronization within two months.
Data to be submitted
Data to be furnished
By whom
To whom
Frequency
Comments
1 OCC approval requests for Generation Units Outages
Generators
SRPC/SRLDC
3rd of every month
It was emphasized that the maintenance schedule firmed up in OCC needed to be adhered by the
generators since it had LGB, commercial, ATC/TTC, market and grid security implications. All
generators needed to plan the maintenance and have periodic preliminary review meeting with the
OEM / Maintenance Agency to avoid any rescheduling. Any unilateral decision by the generator
could be considered as violation of IEGC.
2 ISTS/State Trans SRPC/ 3rd of Outage proposals for the months of April /May in
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
Sector Transmission Lines and Elements Outage Proposals
mission Licensees/Generators
SRLDC every month
respect of Central and State Transmission lines and elements are to be submitted
An outage coordination group had been created ([email protected]) for
review of the previous OCC approved shut downs (construction/critical).
3 Availed and non-availed transmission elements report
SRLDC
Requestors/SRPC
3rd of every month
4 Comments/Reasons for non-availing the shut down.
Transmission Licensees/Generators
SRPC/SRLDC
6th of every month
Power purchase by the states was also being planned based on these approved outages and any changes may affect their LGB and in some cases ATC/TTC was also getting affected. The issue should to percolate to the operating level/ working level it should be emphasized that they should not deviate from the approved schedule.
5 Annual Outage plan schedule vs Actual maintenance
All Generators
SRPC Monthly Information is required for the Annual Outage
Plan Deviation Report being submitted to
CERC. (CGS, State & IPPs) and Transmission
Licensees
6 Reasons for demand-supply gap and its variations
Constituents
SRPC for further communication to MoP/CEA
Every month along with PSP
MoP/CEA specifically needed the reasons for load shedding like transmission constraints, distribution constraints, regulatory constraints viz the power purchase not allowed beyond an agreed cost or quantum, natural calamities, tripping of some of major transmission lines etc. All the constituents to furnish the information in the specified format. Even if load shedding is zero a ‘Nil’ report needed to be furnished on monthly basis.
7 LS(In MU/MW)
States
SRPC/SRLDC
Monthly
8 Bilateral Purchases
states SRPC/SRLDC
Monthly
9 Installation/healthy capacitors
All Constituents
SRPC/SRLDC
Monthly Installation & ensuring healthiness of capacitor banks at distribution level should be ensured by all the constituents.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
10 MVAR Interchange/MVAR capability testing
All Generators/SLDCs
SRPC/SRLDC
4th of every month
All the SLDCs to kindly monitor VAR absorption/injection of generating units in their respective control areas in real-time.
Order of Hon’ble CERC dated 23.12.2009 merited attention in this regard. All agencies needed to provide required reactive compensation thus avoiding the need for exchange of reactive power to/from ISTS and maintain ISTS voltage within specific range.
11 AUFR & df/dt schemes
All constituents
SRPC/SRLDC
Updates if any changes
Details of the feeders implemented in AUFR & df/dt schemes along with the status of SCADA mapping as per the specified Formats.
12 detailed report of operation of AUFR
All constituents
SRPC/SRLDC
Daily basis
In accordance with clause 9 (2) of CEA (Grid Standards) Regulations, 2010. It was noted that only KSEBL and PED were submitting the daily report regarding operation of relays.
13 Upcoming Wind/Solar Projects
All Constituents
SRPC/SRLDC
Monthly Procedure for RE Frameworks had been notified and is available at NLDC website. Progress of works of RE Generators and evacuation system are available in the minutes of the LVRT/RE Meeting held on 25.10.2017.
14 Power Flow Analysis under high RE scenario
All Constituents
SRPC/SRLDC
Monthly A project has been undertaken jointly by POSOCO, USAID and NREL for power flow analysis under high RE scenario. APTRANSCO needed to furnish the data and requested them to furnish the details at the earliest.
14 Outage deviation report
All States/Entities
SRPC/SRLDC
Monthly Outage plan deviation Generating Units/Transmission Elements of Southern Region needed to be submitted by all the concerned which is to be communicated to Hon’ble CERC.
15 Power Supply to Rural Areas
All DISCOMS
SRPC first week of the month for previous month.
In the Meeting held at MoP on 09.04.2014 it had been decided to collect the data invariably from DISCOMs. It is requested that the data in this regard in the required format may please be arranged to be communicated to SRPC Secretariat at the following E-mail addresses: [email protected]/[email protected]
16 Status of implementation of the recommendations of the Enquiry Committee
3rd and 17th of every month
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
17 Energy Generation data Management from Renewable Energy Sources
All the states
To CEA with a copy to SRPC
Monthly
18 Power supply hours in various States/UTs (Rural and Urban areas)
All States
SRPC Monthly For Replying to Parliament Questions: CEA Requirement
19 Physical and Cyber Security/Crisis Management Plan/Black Start Procedure
CEA/SRPC Quarterly Cyber Security: To be furnished to Chief Engineer, DPD, CEA, Sewa Bhavan, New Delhi-110066. Physical Security, other Mock Drills for CMP, Mock Drill for Black Start Restoration: Chief Engineer, DMLF, CEA, Sewa Bhavan, New Delhi-110066. Information required by CEA (vide letter dated 26.11.2013) regarding Security of power installations was to be furnished to CEA.
20 Declaration of availability and healthiness of various protection / defense mechanism
All States
SRLDC/SRPC
Monthly Validated certificates needed to be communicated in a timely manner.
21 Tripping Details/Reports
All the concerned
SRLDC Within 24 hrs as per IEGC/CEA regulations.Para 29 of Hon’ble CERC Order dated 20.02.2014 in respect of Petition No.146/MP/2013 was brought to attention of the OCC.
22 Compiled Telemetry status
Utility wise
As directed by Hon’ble Commission Hon’ble Commission vide order dated 19.12.2013 on Suo-moto petition No. 56/SM/2013 had directed all the utilities to provide the required telemetry within six months of this order. It was requested that MAPS, KGS & KKNPP may please furnish the compliance status of pending SCADA inputs the earliest. Details in this regard were available on SRLDC web site.
Agenda for 142nd OCC Meeting to be held on 10.04.2018 at SRLDC ,Bangalore
For KKNPP only 2 points are pending w.r.t GT tap position. Re -tendering was going on and it will take 5 more months to complete the works.
23 Prolonged outage
States
SRPC/SRLDC
Monthly All constituents were requested to convey the schedule of revival for the elements under prolonged outage to SRPC, which was to be reported to Hon’ble CERC on monthly basis. (CERC Order on petition no 146/MP/2013).
24 Nodal Officer list : Disaster Management
All utilities
SRLDC Update The updated status as per the information available with SRLDC has already been shared.
25 Presentation on Operational issues
All States/ Entities
SRPC/ SRLDC
5th of every month
Additional Agenda for 142nd OCC
to be held on 10.04.2018 at SRPC Bangalore
1. APSPCL – Evacuation of power from Ananthapuramu Ultra Mega Solar Park (1500
MW)
APSPCL vide letter dated 04.04.2018(Annexure-I) has sought certain clarifications in
regard to evacuation of Solar Power generated from Ananthapuramu Ultra Mega
Solar Power Park (1500 MW). It was also requested that this issue may kindly be an
agenda item of next OCC/Special Meeting.
The following were submitted by APSPCL
Andhra Pradesh Solar Power Corporation Pvt Ltd (APSPCL) is a Joint Venture
Company formed between Solar Energy Corporation of India Limited (SECI),
Andhra Pradesh Solar Power Generation Corporation Ltd (APGENCO) and New
& Renewable Energy Development Corporation of Andhra Pradesh Ltd
(NREDCAP) for development of Solar Parks in the State of Andhra Pradesh.
Ananthapuram Ultra Mega Solar Park at N.P.Kunta Mandal of Ananthapuram
district is being developed by APSPCL to establish total 1500 MW capacity of
Solar projects by various Solar Power Developers under various MNRE schemes
as detailed below:
I. 250 MW Solar project was already commissioned by NTPC under EPC
mode in the year 2016
II. 500 MW proposed to be developed under VGF Scheme, SECI has already
selected SPDs through ICB to establish 400 MW Solar projects as flows:
a) M/s.ACME - 150 MW
b) M/s.Tata Power - 100 MW
c) M/s.FRV - 100 MW
d) M/s.Azure - 50 MW
SPDs for balance 100 MW yet to be identified by SECI.
III. For balance 750 MW capacity, NTPC has issued NIT on 09.03.2018 for
selection of Solar Power Developers and is likely to be commissioned by
June 2019
APSPCL is creating all infrastructure facilities including Internal Evacuation
system by establishing 220/33 kV Pooling substations of each 250 MW inside the
Solar Park to evacuate entire 1500 MW Solar Park.
External Power Evacuation system for evacuation of 1500 MW capacity from this
Solar Park was established by PGCIL ie., CTU by setting 400/220 kV grid
substation within the Solar Park at N.P.Kunta village. The necessary approvals
for LTA & Connectivity approvals from PGCIL (CTU) have already taken by
PGCIL.
In this connection, it is inform that the Interconnection point and tariff metering for
250 MW Solar project which was already commissioned by NTPC is on 33 kV
side of 220/33 kV Pooling Substation established by APSPCL as per the guide
lines/regulations prevailed at that time. Scheduling and forecasting for the power
generated from this project is being done by APSLDC since the power generated
from the project is purchased by APDISCOMs as per the PPA entered with
NTPC.
Out of 500 MW capacity proposed to be developed under VGF, 400 MW Solar
Projects are under development and are likely to be commissioned in the month
of April/May 2018. 3 Nos. of 220/33 Pooling Sub Stations of each 250 MW, 50
MW and 100 MW and its associated 2 Nos. 220 kV D/C lines connecting to
400/220 kV PGCIL grid substation are likely to be charged by end of April, 2018.
As per the revised guide lines/regulations the Interconnection point and tariff
metering is on 33 kV side of 220/33 kV grid substation of PGCIL ie., CTU at
N.P.Kunta site. Solar Energy Corporation of India Ltd (SECI) has entered Power
Sale Agreement (PSA) with APDISCOMS for sale of power generated from 400
MW Solar Projects. In turn, SECI has entered Power Purchase Agreement
(PPAs) with selected SPDs as above.
With the commissioning of 400 MW capacity at Galiveedu site, total capacity of
650 MW including existing 250 MW capacity will be evacuated through PGCIL
400/220 kV Grid Substation. Entire 650 MW capacity will be scheduled to
APDISCOMS as per the existing PPA/PSA.
Further to inform that minimum 10% of total 1500 MW solar power generated in
this park shall be given to out of the state.
A decision is to be taken on the following issues regarding evacuation of solar
power generated from Ananthapuram Ultra Mega Solar Park (1500 MW).
i. Whether 650 MW (250+400) capacity generated from the Solar Park is
scheduled by APSLDC or SRLDC since the entire 650 MW capacity is purchased
by APDISCOMS as per the existing PPA with NTPC for 250 MW and PSA with
SECI for 400 MW.
ii. Whether this Solar Park comes under SRLDC purview or APSLDC purview.
Presently, it is under the purview of APSLDC and tariff metering is at 33 kV side
of 220/32 kV Pooling substation.
iii. If scheduling is done by APSLDC, then the responsibility for down loading data
from tariff meters located at 220 kV side 400 kV Grid substation of PGCIL and
energy accounting is to be clarified.
iv. If scheduling is done by SRLDC, the responsibility the impact of Deviation
Settlement Mechanism on different entities may also be clarified.
v. Presently, the real time / SCADA data is being transmitted to APSLDC from
220/33 kV Pooling Substations of APSLDC through PGCIL 400/220 kV Grid
substation and SRLDC.
vi. Procedure to be followed for transmission of Data to APSLDC/SRLDC from
SCADA of 220/33 kV Pooling Substations may be clarified.
vii. PGCIL may be advised to install tariff meters at 220 kV side of 400 kV Grid
substation as per the CERC/APERC metering code.
viii. After the entire capacity of 1500 MW is commissioned and if there is any
interstate sale agreement for minimum capacity of 10% of total capacity, the
procedure to be followed may also be examined.
APSPCL requested to include the above points in the agenda of next OCC/special
meeting conducted by SRPC and desired that all related parties (NTPC, SECI,
PGCIL, APSLDC and APTRANSCO, APPCC) may also be invited to discuss the
operational/scheduling/metering/commercial at the meeting for taking decision.
Subsequently SRPC vide letter 06.04.2018 (Annexure-II) had requested SRLDC to
communicate their views/stand on the scheduling issues raised by APSPCL for
enabling SRPC to take further action in this regard. SRLDC letter dated 10.04.2017
observations of SRLDC regarding scheduling of Adani Solar Power Projects of
Kamuthi in Tamil Nadu) was also enclosed since it was felt that there may be similar
scheduling issues involved.
2. Low coal stock in Major generating stations – Action requested
SRLDC vide letter dated 03.04.2018(Annexure-III) addressed to all SLDCs and
Generators for their kind intervention at Senior management level (of respective
generating stations / ISGS) for war foot action for improving the coal stock
position and facilitate preparedness for impending summer months where the SR
demand is expected to reach new highs. With the expected supplementary increase
in the forthcoming summer coupled with low RE generation particularly wind
generation, the availability of thermal units are critical for the grid in the forthcoming
days. It is to be noted that the coal stock position in major generating stations are
running low and urgent action has to be taken in order for the improvement in the
status of coal stock and secured gird operation for the summer). In the meanwhile,
efforts may also be explored for harnessing the bottled up generation available
within Southern Region like IPPs etc who have fuel stock but less schedule. It
is also requested for suitable arrangements for procuring and movement of coal in
order to optimize their thermal generation and SLDCs have to ensure drawal from
grid to be strictly as per schedule in order to maintain the frequency within IEGC
band ensuring smooth grid operation.
3. Frequent tripping of Konaje – Manjeswaram line on overload–reg
KSEBL vide letter dated 04.04.2018(Annexure-IV) has expressed concern regarding
the frequent tripping of Konaje – Manjeswaram 110 kV feeder recently and
requested that the matter may please be included as an agenda for next OCC
meeting.
The following were observed:
The trippings were found to be associated with the sudden increase in railway
traction load on two phases. Railways are drawing power at Uppala traction from
110 kV Substation of KSEBL. At present, Kubanoor Substation cannot be fed
from 220 kV system of KSEBL at Mylatty due to the inadequacy of transmission
system.
The matter was discussed with SLDC, Karnataka on 03.04.2018. As the time at
which railways draw excess power cannot be determined, extreme corrective
action cannot be taken by KSEBL such as imposition of load shedding in the
area to allow the trains to pass. The matter has been taken up with Chief
Engineer (Transmission-North) for taking up with Railways. It is also learned that
the excessive drawal at Uppala traction station is due to the delay in
commissioning of traction station near Mangalore in Karnataka.
The matter may please be reviewed. As an interim measure, KPTCL may take
action to increase the relay setting at Konaje Substation to allow short time
loading of the feeder due to railway loading, limiting to the thermal rating of the
conductor. KSBEL can ensure that the average loading on the feeder always
remain below 22 MW as agreed in the SRPC forum.
4. Pending points regarding URTDSM project
SRLDC vide letter dated 03.04.2018(Annexure-V)had requested PGCIL, SR II to
update the current status of the UPS system under URTDSM project for SRLDC, like
whether it has been dispatched or yet to be and from where it is to be dispatched. It
was noted that in the Special Meeting held on 13.04.2018 at SR II, PGCIL it was
informed by PGCIL that the UPS will be supplied by 20th April 2018. It was also
requested to update the status of the following pending SAT deliverables from PGCIL
Communication link from SRLDC to NLDC
Internet connection for patch management of URTDSM systems.
5. Relocating the Identified loads for strengthening Raichur – Sholapur SPS of
Sothern Region
KSEBL vide letter dated 23.03.2018(Annexure-VI) had informed the following:
220 kV Kalamasseryand BrahmapuramS/Sswere identified for the reliable operation
of SPS and for the secure operation of All India grid. However, taking cognizance of
the changes in the network configuration, the stations for erection of new DTPC’s are
relocated to
1) 110 kV S/S Chalakudy
2) 220 kV S/S Shornur
The total load relief of 70 MW can be obtained from the following feeders:-
1. Chalakudy – Kodungaloor I & II (66 kV) – 20 MW
2. 11 kV load TR 110/11 # I & II Chalakudy – 14 MW
3. Shornur – Ottapalam (110 kV) – 28 MW
4. Shornur – Patharipala (110 kV) – 10 MW
A total load relief of 72 MW is identified. All these loads are visible.
The feeders Vadakara – Meppayur (110 kV) and Orakattery– Panoor (110 kV) identified
with a load relief of 70 MW now shall be disconnected on completing the DTPC
configuration work at 110 kV S/S Chalakudy and 220 kV S/S Shornur.
Subsequently SR II, Powergrid vide E-mail dated 03.04.2018 had informed SRLDC that DTPCs have been supplied at the respective identified locations and you are requested to confirm for any changes at the earliest as the agency is going to commence installation from 2nd week of April’18.
SRLDC vide E-mail dated 03.04.2018 had informed that the relocation of DTPC's for SPS proposed by KSEBL may be agreed upon. The above was also discussed with operations department of SRPC wherein it was agreed that formal concurrence for the same would be given in forthcoming SRPC OCC meeting (Apr 2018).
6. Ramp Rates
The ramp up and ramp down rates are assuming significance with higher RE
penetration, sudden changes in load, sudden PX schedules etc. The details of ramp
rates of RRAS stations are enclosed at Annexure-VII. There may be need for review of
ramp rates keeping in view the provisions in CEA Regulations. SLDCs may also review
the ramp rates of State Control Area generators.
7. SPS for 400kV Nellore - NPS D/C
SPS for 400kV Nellore - NPS D/C using O/C feature in Main - 1 Protection has been implemented at 400kV Nellore Substation today at 17:00Hrs on 08.04.2018. The adopted Setting is : 2640A, Timer = 5 Sec.
8. Revised Outage Plan and Annual Generation for 2018-19
NTECL vide letter dated 07.04.2018 (Annexure-VIII) had revised Outage Plan and
Annual Generation plan for the year 2018-19. It may be noted that as per MoP
approved target and earlier submitted data for outage/generation plan the
LGBR/Outage Plan has been sent to CEA for approval.
9. Withdrawal of Kudgi unit from RSD
SRLDC vide mail dated 07.04.2018 had informed that NLDC had asked to withdraw the
RRAS given for Unit-2 of Kudgi Unit-2 from 10:00 hrs on 07-04-2018 considering the
trend of load met by Southern region when compared to 06-04-2018. The
communication from NLDC was immediately forwarded to all the respective
beneficiaries and KUDGI Power station. The beneficiaries were also asked to take a
note of the above situation as both the Units at Kudgi were running nearly at Technical
minimum i.e. 420 MW each and there is a possibility of one Unit of going under RSD
upon removal of RRAS. However, there was no further requisition given by any of the
benficiairies.
Accordingly, Kudgi power station was asked to revise the 'OFF Bar' and 'ON Bar' DC of
Kudgi Units and come to schedule. Kudgi power station had requested for taking Unit-1
under RSD as the schedule was less than technical minimum. Hence RSD was
concurred for Kudgi Unit-1 based on the request on Kudgi station and seeing the
schedule pattern of Kudgi Units.
10. Scheduling of Kudgi Power during RSD
TSSLDC vide letter dated 06.04.2018 (Annexure- IX) had raised certain observations
on scheduling of power from Kudgi during RSD. The following were submitted:
The issue of non-scheduling of power from Kudgi particularly during peak
hours was intimated for deliberation in the OCC during one unit under RSD.
Accordingly the subject was discussed in the 141st OCC meeting and a
consensus was arrived that, as the KPTCL’s entire requisition from both the
units of Kudgi was considered for keeping the unit-2 under Reserve Shut
Down (RSD), they can give requisition only for the balance entitlement
quantum from Unit-1. Accordingly KPTCL has restricted their requisition from
11.03.2018 to 02.04.2018. Further, it was also informed that the matter will be
taken up with CERC for clarification on scheduling power from the unit under
RSD.
Even after consensus in OCC, it is observed that on 03.04.2018,
TSTRANSCO schedule was curtailed even though full requisition was made
during evening peak hours from Kudgi which is not in line with the decision
taken in OCC. The working arrangement which was agreed in 141st OCC may
be adhered to and the matter may be placed as agenda item in the 142nd
OCC.
It is desired that the matter may be discussed and finalized at the regional
level for smooth operation of the grid. Necessary clarification in the operation
of RSD procedure may be obtained by SRLDC from CERC. In the absence of
any concrete resolution in this regard from SRLDC, TSTRANSCO constrained
to take up the issue with Hon’ble CERC.
TSTRANSCO views on the subject are as follows:
1. Due to surrender of power by Karnataka from both units of Kudgi led to RSD of
one of the Unit as the sum of requisitions of all other beneficiaries can be
accommodated from one unit.
2. For any requisition of power from surrendered quantity which is led to RSD has
to be considered with 8 hours prior notice and with a minimum schedule for 8
hours as per clause Nos.7.1 & 7.2 of DoP on RSD.
3. The present procedure being implemented by SRLDC is impacting the Load
Generation balance of beneficiaries who are not given consent for RSD because
of the cherry picking requisition especially during peak hours by the beneficiary
who has led to RSD.
4. The present procedure being followed by SRLDC leading to payment of fixed
charges even without availing power even though full schedule is requisitioned.
5. Also forcing additional procurement of power at higher cost.
It was also stated that the scheduling was not as per consensus arrived in 141st OCC
Meeting
11. Discussion on RSD Procedure
NLDC vide letter dated (Annexure-X) has proposed discussion on RSD procedure in
each of the RPC as noted in approved RSD Procedure. WRPC secretariat has been
requested to circulate the latest Procedure.
The following were noted:
The detailed procedure for taking unit(s) under Reserve Shutdown and
Mechanism for Compensation for Degradation of Heat Rate, Aux Compensation
and Secondary Fuel Consumption, due to Part Load Operation and Multiple
Start/Stop of Units was approved by the Hon’ble Commission vide its order dated
05.05.2017.
In the same order, NLDC was also advised to deliberate the WRPC procedure in
the other RPC’s and submit its feasibility in 6 months from the date of issue of
the procedure. The relevant paras of the order are quoted below:
“6.There is already a procedure for RDS for a station in WRPC in vogue based on
principle of removal of costliest stations and also provide for adjustment of allocation of
power to other generating stations in the consent of beneficiaries. NLDC is of the view
that same needs deliberation. NLDC is advised to deliberate the WRPC procedure in
the other RPC’s and submit its feasibility in 6 months from the date of issue of the
procedure.”
With the implementation of 55% technical minimum wef 15.05.2017, the problem
of RSD has been relegated to the background for some time. Considering the
smooth operation, the issue did not generally come up for discussion in any of
the RPC forums.
Recently, Secretary, CERC vide letter dated 26.03.2018 has sought NLDC’s
feedback on the WRPC RSD procedure. It is requested that WRPC Secretariat
may kindly circulate a copy of the RDS procedure (latest) prepared by them
to all other RPCs & NLDC so that the same could be discussed in each
RPC. It would be beneficial if WRPC Secretariat could arrange a
presentation in each RPC on their RSD procedure.
**********************