Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 2 of 14
Cosmic Origins Spectrograph
Synopsis
• Role: STScI supports COS science operations by leading development of “front-end” (operations) and “back-end” (OPUS/MAST/calibration) ground system.
• COS project is led by NISD, and presently consists of 8 people (5.15 FTE) drawn from NISD, SISD, and ESS.
• The project is on track (green)– most recent report: 19 June 2001
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 3 of 14
Cosmic Origins Spectrograph
Health Chart
Subproject Staffing
Schedule Technical
Instrument Development OK (g) ongoing (g) • IDT/STScI MOU (g)• FUV I & T CU/UCB (g)• NUV Grating reflectivity (y)
Commanding and RPS2 OK (g) ongoing (g) • OP-01 (g)• Alignment development (g)
Pipeline and Calibration OK (g) ongoing (g) • keyword development (g)• pipeline design (g) • CDRs (g)
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 4 of 14
Cosmic Origins Spectrograph
Accomplishments
• SI News: – Flight detectors are available for both FUV and NUV that meet or exceed
performance requirements– FUV flight spare detector integration continuing at UCB– backup door-opening mechanism repair and recovery plan implemented– NUV grating reflectivity below specification (continues yellow)
• G185M below spec; G225M can be used – lower resolution; vendor working• G225M below spec; primary vendor evaluating fix; different vendor selected for
mechanically-ruled alternate• G285M OK• G230L in fabrication; looks good
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 5 of 14
Cosmic Origins Spectrograph
Accomplishments (cont.)
• STScI pipeline systems– OPUS/HDA and calcos CDRs: held at STScI on 23 and 24 July,
respectively• Formal review panel: STScI and IDT representation• 12 Requests for Action (RFAs) submitted
– All reviewed and Actionees assigned
• CDR presentations and RFA status at:
http://www.stsci.edu/instruments/cos/devel/coscalwg.htmlhttp://www.stsci.edu/instruments/cos/devel/coscalwg.html
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 6 of 14
Cosmic Origins SpectrographCOS Pipeline CDR Review Panel
• Ray Kutina (STScI) – Chair• Tom Brown (STScI)• Ken Brownsberger (CU/IDT)• Paul Goudfrooij (STScI)• Richard Shaw (NOAO)
Send mail to Review Panel: [email protected]
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 7 of 14
Cosmic Origins Spectrograph
COS Pipeline CDR Agenda• Introduction M. McGrath• Data system environment @ SM4 D. Swade• COS File Structure Overview T. Keyes
• COS Keywords & Associations D. Swade • Science Data Processing J. Rose• DADS ingest and distribution A. Farris• On-the-Fly-Reprocessing (OTFR) M. Swam• COS and StarView N. Gaffney• Thermal Vac support R. Henry• Coding Environment P. Greenfield• Coordination with IDT T. Keyes• CALCOS P. Hodge• Schedule & resources M. McGrath
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 8 of 14
Cosmic Origins Spectrograph
Accomplishments (cont.)
• STScI scheduling system– Phase 3 development completed and tested at STScI
• Ops bench testing at Ball per FSW availability timeline– Initiated mechanism alignment mode development (phase 4) on schedule
• requirements analysis and proposal instructions completed; OPRs filed• TRANS development underway
– STScI FSW-timing tests on ops bench - 40% complete
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 9 of 14
Cosmic Origins SpectrographCOS Phase Development Plan (rev 5, 6/1/01)
Phase 1 (1/1/00 – 6/30/00)
1. Macro Development
2. Reconfigurations
Phase 2 (7/1/00 – 12/31/00)
3. NUV Timetag Mode + Darks
4. FUV Timetag Mode + Darks
Phase 3 (1/1/01 – 6/30/01)
5. FUV & NUV Accumulation Science Exposures
6. FUV & NUV Target Acquisition Exposures
7. FUV & NUV Target Peakup Exposures
Phase 4 (7/1/01 – 12/31/01)
8. Aperture Alignment Exposures
9. OSM1 Focus Alignment Exposures
10.OSM1 Rotation Alignment Exposures
11.OSM2 Rotation Alignment Exposures
12. FUV & NUV FP-Split Exposures
Phase 5 (1/1/02 – 6/30/02)
13. FUV & NUV GO Wavelength Calibration Exposures
14. FUV & NUV Automatic Wavelength Calibration Exposures
15. FUV & NUV Flat Field Lamp Calibration Exposures
16. SAA Contours
Phase 6 (7/1/02 – 12/31/02)
17. SMGT Preparations
18. SMOV Special Commanding
19. FUV & NUV Anomalous Recovery
20. FUV & NUV Initial Turn-on
21. FUV & NUV BOP Target Screening
Phase 7 (1/1/03 – 6/30/03)
22. FUV & NUV Lifetime Adjustments
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 10 of 14
Cosmic Origins Spectrograph
Plans
Planned Activities and Future Milestones:
• Evaluate and respond to OPUS/HDA and calcos CDR RFAs• Continue Phase 4 ALIGN mode exposure development• Conduct Phase 4 requirements review and initiate development for
FP-SPLIT exposures• Commence training new IS• Commence ETC requirements definition
• Milepost Dates:– COS ops bench test data to STScI: 1 Dec 2001 (no change)– COS integrated SI test data to STScI: 1 April 2002 (no change)– SI delivery to GSFC: 11 Sep 2002 (+2 weeks) {+ ==> later than last report} – Launch: January 2004
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 11 of 14
Cosmic Origins Spectrograph
Detailed Schedule
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 12 of 14
Cosmic Origins Spectrograph
Resource Summary• Current COS Resources (FY 01)
– NISD• 2 Scientists (1.5 FTE); new hire (K. Sembach) Sep 01
– SISD• 1 Data Analyst (0.5 FTE)
– ESS• 1 System Engineer (0.5 FTE)• 1 Command Development System Engineer (1.0 FTE)• 1 Instrument Engineer (0.4 FTE)• 2 Developers (1.25 FTE)
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 13 of 14
Cosmic Origins Spectrograph
Metrics
• Progress versus Planned Milestones and Requirements:– 2 of 2 planned activities completed within reporting period
• COS Pipeline PDR Requests for Action (RFA) Items :– 5 (all remaining) closed during review period
• COS Pipeline CDR Requests for Action (RFA) Items:– 12 opened (actionees assigned; all open at present)
Monthly Status Review 21 August 2001
Charles D.(Tony) Keyes
Page 14 of 14
Cosmic Origins Spectrograph
Issues
Note: Arrows indicate trend (same, better, worse) by direction (right, up, down), and current impact (resolved/no issue, medium, severe) by color (green, yellow, red).
Title Issue Impact Action Status
FSW Status at Ball
Delay of FSW implementation for output of SI data and target acq
Delays timeframe for testing our acq commanding and delays availability of hardware-generated test image data
Delay testing; delay development of OPUS/HDA features and beta to be consistent with Ball capability
STScI front and back end development proceeding; remains on-sched this period; ops bench timing tests proceeding
Instrument Development
NUV grating reflectivity
None to STScI short-term; IDT long-term schedule impacts possible
IDT continue consult with vendor; contract with 2nd vendor (Hitachi) for G225M