SPD Mechanics and Cooling Status of the activity in Padova Rosario Turrisi. SPD Mechanics and Cooling Status of the activity in Padova Rosario Turrisi. Contents: News about mechanics components Report on first test of cooling plant. Mechanics: components production. CFSS - PowerPoint PPT PresentationTRANSCRIPT
SPD Mechanics and CoolingStatus of the activity in Padova
Rosario Turrisi
SPD Mechanics and CoolingStatus of the activity in Padova
Rosario Turrisi
Contents: • News about mechanics components • Report on first test of cooling plant
November 16, 2004 2
• CFSS• 16 components produced. • One CFSS has been geometrically
qualified.• Parilene evaporation done.
• CFSS holders• Tooling completed• Four samples machined
• HS springs • Design completed• Tooling production started
• Half Cylinder• Tooling completed• Prototype ready for Dec ‘04
• Half Cone• Design in progress
Mechanics: components production
November 16, 2004 3
Status of cooling components
• Received from Medelec:• Phynox tubes• CuNi capillaries
• Processing started: • Squeezing• Ni+Cu layer on tubes ends• Fittings procurement
November 16, 2004 4
Recent actions
• Realization with M. Pimenta dos Santos (TS-CV-DC CERN) accomplished
• First test performed in October
• Foreseen installation (temporary) in bld. 23 for qualification
November 16, 2004 5
First test of cooling plant
Two-days hands-on course c/o TS-CV-DC• Manual setting of parameters (no automatization)• Use of a two-sectors-like setup • A few sets of parameters have been exploited
• different power dissipations• variation of liquid/vapor pressure
A first contact: some impressions, extensive test in order…
November 16, 2004 6
Test setup
• Final compontens of freon circuitry• Dummy staves: resistors mounted on kapton• Mount on carbon fiber• Thermal contact is the main issue
November 16, 2004 7
Cooling plant
Control panelControl panel
Control software Control software includes some includes some emergencyemergency procedures procedures
November 16, 2004 8
Cooling circuit scheme
compressorcompressor
(in final setup)(in final setup)
November 16, 2004 9
40 W/stave – T vs. flow 140 W/stave – T vs. flow 1
Flow (l/min) 0.81Flow (l/min) 0.81P inp(bar) 3.8P inp(bar) 3.8
Flow (l/min) 0.6Flow (l/min) 0.6P inp(bar) 3.1P inp(bar) 3.1
Flow (l/min) 0.58Flow (l/min) 0.58P inp(bar) 3.0P inp(bar) 3.0
Flow (l/min) 0.54Flow (l/min) 0.54P inp(bar) 2.9P inp(bar) 2.9
Flow (l/min) 0.51Flow (l/min) 0.51P inp(bar) 2.7P inp(bar) 2.7
Flow (l/min) 0.65Flow (l/min) 0.65P inp(bar) 3.2P inp(bar) 3.2
November 16, 2004 10
40 W/stave – T vs. flow 240 W/stave – T vs. flow 2
Flow (l/min) 0.81Flow (l/min) 0.81P inp(bar) 3.8P inp(bar) 3.8
Flow (l/min) 0.6Flow (l/min) 0.6P inp(bar) 3.1P inp(bar) 3.1
Flow (l/min) 0.58Flow (l/min) 0.58P inp(bar) 3.0P inp(bar) 3.0
Flow (l/min) 0.54Flow (l/min) 0.54P inp(bar) 2.9P inp(bar) 2.9
Flow (l/min) 0.51Flow (l/min) 0.51P inp(bar) 2.7P inp(bar) 2.7
Flow (l/min) 0.65Flow (l/min) 0.65P inp(bar) 3.2P inp(bar) 3.2
November 16, 2004 11
20 and 50 W IR shots
November 16, 2004 12
Summary plots
40 40 WW
Flow variation w/ input pressureFlow variation w/ input pressure
Temperature (measured with IR camera) Temperature (measured with IR camera) vs. powervs. power
Good sensitivity, wider range of pressure/flow feasible:Good sensitivity, wider range of pressure/flow feasible:ready for extensive test!ready for extensive test!
20 W20 W(nominal)(nominal)
November 16, 2004 13
Integration
• A mock-up of half detector has been installed in Padova
• It is being upgraded as needed• First tests:
• near-detector cables integration• beam pipe support positioning
both on RB26 side
November 16, 2004 14
Cables layout
• MCM- and bus-extenders have to go around input (output) capillars being twisted ~90o
• Protection of capillars under study
November 16, 2004 15
Beam pipe support
November 16, 2004 16
Summary and plans• Cooling plant up and working
• First test has been encouraging:• ease of startup• seamless power absorption (in test setup)• wide range of parameters tuning• emergency procedures implemented
• Mock-up of SPD implemented• Effective for debugging of integration issues • RB26 side started
• NEXT• Planning of extensive test of cooling plant for tuning on
real conditions• Mock-up upgrade up to first patch panels and RB24 side