Spectrometer SolenoidSchedule
MICE Schedule Review
May 23rd 2011
Roy Preece (STFC RAL, LBNL)
![Page 2: Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)](https://reader036.vdocument.in/reader036/viewer/2022081813/5697bfab1a28abf838c9ab6d/html5/thumbnails/2.jpg)
Sections– Construction
• Cold Mass – Reworking for the additional cryo coolers, resistor conduction, fill / vent tubes.
• Cooler Towers – Reworking for the additional cryo coolers, flanges and access ports.
• Instrumentation – New sensors, harness and feedthroughs. External cabling and hardware.
• MLI – Focus on each part to be insulated.– Assembly
• Sequential process for assembly with control points for quality checking.– Testing
• Cool down, instrumentation, magnetic training and mapping.– Shipping / Integration
• Method of packing and shipping to RAL.
![Page 3: Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)](https://reader036.vdocument.in/reader036/viewer/2022081813/5697bfab1a28abf838c9ab6d/html5/thumbnails/3.jpg)
Construction• Conservative estimates for timescales
– Estimate from previous experience of the construction– Slack included in the estimate.
• Risk– Quality checks – MLI, instrumentation...etc– Periodic review – MICO, Collaboration Meetings, MAP PMG, in
house meetings– Documentation / Drawings / Models / Pictures
• Parallel work– Personnel and work space an issue.– Instrumentation, MLI, documentation, models and drawings.– Vacuum Vessel and Radiation shield
![Page 4: Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)](https://reader036.vdocument.in/reader036/viewer/2022081813/5697bfab1a28abf838c9ab6d/html5/thumbnails/4.jpg)
Assembly / Test• Sequence of assembly
– Utilising the crane structure and support beam.– Working space.– Only one magnet at a time.
• Cool down and Test– Initial cooldown – semi automated LN2 cooling– He fill– Run the cryo coolers and stabilise – Allow for 2 weeks– Limit to 1 quench / day and then stabilise again– Continue until stable running of coils and cryo coolers – at least 24h
continuous running– Characterise under various operation modes
• Magnet mapping– Can be carried out when stable operations can be replicated.
![Page 5: Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)](https://reader036.vdocument.in/reader036/viewer/2022081813/5697bfab1a28abf838c9ab6d/html5/thumbnails/5.jpg)
Shipping / Integration• Shipping / Integration
– Pack into standard / open topped / High ball shipping container, 20’ or 40’.
– Lift in and out from top – Advantage of open topped container– Truck overland to New York / Ship to Folkestone
• 1 week truck• 4 weeks shipping (including truck Folkstone – RAL ~ 1 day)
– Ship without the stand welded to the vacuum vessel• Reduces height• Possibly eases integration issues – weld into position at RAL
– Discussions with RAL team.
![Page 6: Spectrometer Solenoid Schedule MICE Schedule Review May 23 rd 2011 Roy Preece (STFC RAL, LBNL)](https://reader036.vdocument.in/reader036/viewer/2022081813/5697bfab1a28abf838c9ab6d/html5/thumbnails/6.jpg)
Milestones• Major milestones taken from current schedule
– Upstream Spectrometer Solenoid• Cold Mass ready for assembly – 7th July• Upstream and Downstream Radiation Shields ready for installation – 22nd July• Assembly starts – 25th July• Cold Mass Aligned to Vacuum Vessel – 22nd August• Vacuum Vessel closed – 12th October• Ready for pump down, cooling and training – 27th October• Ready for Magnetic measurements – 25th January• Ready to Ship – 22nd February• Arrival at RAL – 26th March
– Downstream Spectrometer Solenoid• Cold Mass lifted onto beam – 19th August• Assembly starts – 10th October• Cold Mass Aligned to Vacuum Vessel – 29th November• Vacuum Vessel closed – 21st December• Ready for pump down, cooling and training – 2nd February• Ready for Magnetic measurements – 24h April• Ready to Ship – 25th May• Arrival at RAL – 3rd July