speedup your data conversion process while ensuring quality with a pre-configured data conversion...
TRANSCRIPT
A collaboration between:
• Headquarters: Denver, CO
• Products & Services: Oil & Natural Gas exploration and production
• Major Areas of Eagle Ford, Williston Basin
Operations: & Midland Basin
• Enterprise Value*: ~$5.0 billion
• Employees: ~900
• Solution: SAP ERP w/ IS Oil (FICO, FA, PRA, JVA, & PS) & SAP Data Services
*As of August 12, 2015
Overview
Best Practices for Oil & Gas 2015| 3
• Transition P2 Excalibur System to SAP ERP with IS Oil plus the implementation of Quorum Land, WellMaster, & the integration of 30+ applications.
• Started the SAP Implementation project in April 2013.
Project Start
Best Practices for Oil & Gas 2015| 5
Realization Support
Blueprint Realization Support
Initial Plan
Extend Blueprint
Prep FinalPrep
FinalPrep
BlueprintPrep
• After completing an 8 month design and blueprint, SM Energy received an updated plan from their integrator to complete the project.
Project Adjustment
Best Practices for Oil & Gas 2015| 6
Blueprint Realization SupportSI’s Updated Plan
FinalPrep
Prep
• SM Energy asked Akili for a project review and recommendation to ensure delivery success by January 2015.
• The outcome of the recommendations was for Akili to provide Project Management Leadership, to complete the Data Conversion, and to provide some individual consultants to augment the team.
Project Review
Best Practices for Oil & Gas 2015| 7
• Akili’s recommendation:
– Adjust the plan for a more agile implementation approach which leverages the release of high value functionality first.
– Connect the configuration, the development, the data conversion, and the test scenarios to ensure each Release drives business value.
– Continually evaluate the project scope based upon actual results using customer converted data in the testing.
Project Review & Recommendation
Best Practices for Oil & Gas 2015| 9
Project Methodology
Best Practices for Oil & Gas 2015| 10
Blueprint Realization SupportSI’s Updated Plan
Detailed Design Build Test
Releases
Detailed Design
Build
TestLessons Learned
Blueprint SupportAkili’s Plan
Requirements
Requirements
Requirements
Prep
Prep
FinalPrep
FinalPrep
Release 1
Release 2
Release 3
Release 4
• The traditional approach to work streams during realization.
• Iterative approach to an integrated work plan for realization
Project Methodology
Best Practices for Oil & Gas 2015| 11
Realization
Functional Activity
Test
Release 1
Technical Activity
Data Activity
Functional Activity
TestTechnical Activity
Data Activity
Release N
Functional Activity
TestTechnical Activity
Data Activity
Issue: Upstream Oil & Gas is different from many industries in that key processes such as Revenue and JIB are run in monthly batch cycles. As a result it is very difficult to fix issues with data on a transaction by transaction level in the normal business cycle. Accurate master data is critical!
Resolution: Testing is only valid on business processes in which the business test is being completed on converted data from the source systems.
Data Conversion in Oil & Gas
Best Practices for Oil & Gas 2015 | 12
Iterative Approach to Data Conversion
Best Practices for Oil & Gas 2015 | 13
Release 1 –Baseline
• Baseline the process
• Process a small set of data
• Core Conversions only
• Validating the environment & core process
• No data validation
Release 2 –Assess the Data
• Assess the Data Quality
• Complete all high priority conversions
• Assess Data Quality
• Confirm conversion mapping and rules
Release 3 –Test 1
• Full data load –Ready for System Testing
• All Conversions Complete
• Validate load plan
• Identify data issues
Release 4 –Test n
• Final validation
• No new conversions
• Final data cleanup
• Repeat cycle until target data quality achieved
Cutover
• Cutover controls in place
• All data validations in place
Over 70 pre built SAP Load Objects are delivered in our pre-configured solution
Pre-Configured Migration Content
Best Practices for Oil & Gas 2015 | 14
AKILI DATA
MIGRATION
SAP Data Services
• Well Data• Delivery Networks• Division Order
• Business Associates• Joint Operating Agreements• WBS Elements
Data Conversion
• Initial baseline data load started within 60 days
• Identified additional business scenarios not identified in the blueprint that needed to be addressed
• Met Go Live requirement of January 2015
• Converted 98% of all data
– Remaining 2% was the combination of unnecessary records and incomplete records that need further research
Business
• By the first close on SAP, SM Energy was able to decrease closing timeline from 13 days to 7 days with a higher level of accuracy.
Outcomes
Best Practices for Oil & Gas 2015 | 16
• Start data conversion and cleansing as early as possible in the project
• Controls must be included in each data conversion test.
• It will take several (3-5) iterations of data conversion for functional tests to ensure a high level of data accuracy at Go-Live.
• All functional testing must be done on converted data from the source systems.
Lessons Learned
Best Practices for Oil & Gas 2015 | 17
Q&A
Best Practices for Oil & Gas 2015| 19